Collection from FAS worldwide origins Name : Gas to Gasoline Project Axles utilized : 210 hydraulic
Direct FTL, LTL, rail and Airfreight shipments Site location : Ovadandepe, Turkmenistan Axle movements : 1,280 movements
Ocean carriage up to TS ports Volume : 154,110 CBM River vessels utilized : 36
Transhipment operations Overland distance: 645 km’s
River transportation up to Caspian port Heaviest unit 317 mt along with 23
Discharging to Caspian port & Storage units over 100 mt
Re-loading on trailers & transit clearance 77 OOG/HL units
Road permits, obstacle removals, civil works Ocean, river, air, truck transportation
from 27 different origins
Transportation up to site
Project is the largest gas to gasoline
Lifting & Erection works
plant ever built in the world!
Import customs clearance at final destination
11
CASE STUDY: KARBALA PROJECT– 2016 / 2017 IRAQ
Transportation from Umm Qasr port up to final Name : Karbala Refinery Axles utilized : 180 hydraulic & 52 SPMT axles
destination Site location : Karbala, Iraq 6 x 665 mt, 3 x 720 mt bullets
Storage Volume : 200,000 CBM Total 540 km’s overland distance
Civil works & by-pass constructions Heaviest ever cargo to be transported in Iraq!
Bridge and flyover constructions Extensive road improvement works:
Various engineering works Samawah Tubular Bridge Construction (150 m length)
Kofa Cement Factory Ramp (400 m L) & flyover bridge
(12m) construction.
350 km of road width extension (4 m extension) done
16 x bypass road construction avoiding the culverts.
12
CASE STUDY: TORE PROJECT– 2013 TURMENISTAN
● CHALLENGE ● ● SOLUTION ●
Passing the gas-line pipes on CJ-ICM designed & built a
Transshipment to river vessels Name : Turkmenbashi Oil Refineries ground and railway with hl fly-over bridge to eliminate
River vessel transportation Site location : Turkmenbashi, Turkmenistan unit the challenge.
Various HL engineering works Volume : 98,240 CBM
Discharging to Caspian port
Re-loading on trailers & transit clearance
Road permits, obstacle removals, civil works
Transportation up to site
17
CASE STUDY: YOLOTEN PROJECT– 2010/2013 TURKMENISTAN
Collection from FOB & EX-works worldwide origins Name : South Yoloten Gas Development Project Axles utilized : 270 hydraulic
Pre-carriage up to FOB load ports, airports Site location : Mary, Yoloten, Turkmenistan Axle movements : 2,068 movements
Direct FTL, LTL, rail and Airfreight shipments Volume : ~700,000 CBM River vessels utilized : 79
Ocean carriage up to TS ports 290 OOG/HL units
Transhipment operations Transported 100 KM (8,614 pieces) of
River transportation up to Caspian port 56” coated pipes from FOB Italy to
site with 24 ocean & 44 river vessels
Discharging to Caspian port & Storage
in 143 days
Re-loading on trailers & transit clearance Heaviest Unit
Road permits, obstacle removals, civil works
Transportation up to site
Import customs clearance at final destination
37 5.6 6.44 473
length Width height tons