Sr.
Major Activities Instructions
No.
1 Coordination Projects will be seleted as per the directions of the higher
officials from the Punjab ADP List of for the relevant sector.
Key personnel of the projects will be contacted for getting the
Basic information such as the contact numbers, Project
location and general status of the project.
Letter will be dispatched for getting the relevant documents
for project review
2 Documents review Minutes of Meeting of PDWP/DDSC/DDWP/DDC
PCI, PC II & PC IV documents.
List of Procurement
List of hiring staff etc.
3 Approval of visit After the confirmation of Project details and status, the project
is approved by the higher officials.
Noting will be furnished by the Evaluator to higher authorities
for allocation of time, budget and transportation facility for
site visit.
After the directions of higher authorities the intimation letter
for visit along with accommodation request in government
residential premises is dispatched.
4 Tools/Apparatus Evaluator is required to be equipped with relevant tools/
for the Evaluator equipment for the site visit along with relevant documents.
5 Field Visit Meeting will be conducted with the concerned officials
before the start of visit and briefing is taken from them about
the project.
Perfomas will be filled for the required activities as per the
relevant drawings & specifications
Observations will be recorded and any information related to
project is noted.
Visual inspection & measurements of any dimension will be
taken.
Field testing will be required for any major activity for
finding the quality/quality of the material.
Sr.
Major Activities Instructions
No.
Samples of materials for any major activity may be collected
for Laboratory Tests.
Snaps/Photos will be taken for any major
Observation/evidence or any discrepancy noted.
Questionnaire will be drafted as per project requirements.
Interviews will be conducted with beneficiaries/Stakeholders
if required for getting the updates of the project.
6 Report Data will be complied after the visit and relevant information
& documents will be collected from relevant departments or
from any other major source.
Laboratory testing of any material will be conducted if
required.
Analysis of the data will be done based on given details and
in the light of project objectives.
Draft Report will be written having all major components of
the project.
Draft report will be submitted for review to the higher
officials.
Corrections or alterations in report will be done after the
given instructions
Presentation will be given to DG M&E and report will be
discussed in pre ECM meeting
Finalized report will be issued to the concerned departments
and project stakeholders
Fallow up will be taken from the concerned departments
related to the progress of the project.
1.2 Brief Instructions Related to Material used in construction
Note: Check the record of material supply order & record of tests conducted on site and in laboratory of
all materials before the start of material inspection.
Project Title
ADP No.
Sector
Project Location
Sponsoring Authority
Executing Agency
O & M Agency
Sr.
Description of Materials General Assessment of Material Remarks
No.
1. Specification of material as √
per approved provisions? Yes No
2. Quality of Subgrade Material Good Average √ Poor
Sr. Description of
Description of Sub Activities Observations Remarks
No. Major Activity
All surface objects like trees, stumps, roots
Earthworks and other protruding obstructions has been
removed.
Slush points or Places of over moisture to be
observed
Prior to commencing subgrade preparation,
all culverts, cross drains (including their fully
compacted backfill), ditches, drains and
drainage outlets must be done first.
Normally the maximum compacted thickness
is 150mm for each layer. If therequired
thickness is greater than 150mm, the
materials should be spread and compacted in
two or more layers of approximately equal
thickness.
Sub Base
Should be free of large rocks/stones,
The full width of the roadway should be
properly prepared/compacted.
Normally the maximum compacted thickness
is 150mm for each layer. If the required
thickness is greater than 150mm, the
materials should be spread and compacted in
two or more layers of approximately equal
thickness.
The road surface should be properly shaped
to prevent water accumulation within the
roadway.
Binding Material/ stone dust should be as per
specifications.
Use Straight Edge to measure unevenness of
Surface
Base course
Camber/Cross Slope is as per drawings
Straight edge (tolerance) is as per
specifications
Should be free of large rocks/stones,
The full width of the roadway should be
properly prepared/compacted.
Normally the maximum compacted
thickness is 150mm for each layer. If
therequired thickness is greater than 150mm,
the materials should be spread and
compacted in two or more layers of
approximately equal thickness.
The road surface should be properly shaped
to prevent water accumulation within the
roadway.
Binding Material/ stone dust should be as per
specifications.
Prime Coat & Loose stones, dust and foreign matter
Tack Coat removed
Bitumen properties are as specified
Spray is not more than 1m height
Correct temperature and weather conditions
prior to spraying
Correct temperature and weather conditions
Asphaltic Base
prior to laying of asphalt which is generally
Course
b/w 140 to 180
Roller type is correct
Riding quality is smooth and to specified
tolerances.
Triple Surface
Thickness of TST
Treatment
Riding quality
Concrete Rigid
Pavement
A. Pre-Construction
Prior to pouring of concrete, the road base
should be well-prepared.
Dowel and tie bars are present with their
specified size and spacing.
Dirty aggregates should not be used.
B. During Construction
Concrete vibrator or concrete screeder with
vibrator should be used during a spreading of
concrete to prevent honeycombs
Generally for every 4.50m length of the
pavement, a contraction joint or weakened
plane joint should be provided.
For every pouring of concrete, the end of the
pavement should be provided with dowel
bars spaced at 30 cm or 1 foot.
Too much water or too wet concrete mixture
will weaken the structure.
Bedding and Backfill is as specified.(Such as
Culverts
sand, gravels etc.)
There should be a covering/fill of 300mm or
deeper on the top of Slab so that above load
is dispersed.
Inlet and Outlet Of culvert must have proper
wing walls to accommodate surface water.
A Anti-Termite Treatment
2 Check packing material/bottle of
Chemicals
B Excavation
1 Are there any underground utilities like
sewers, water pipelines, cables?
2 Check whether the excavated pits are
adequately shored/ timbered?
3 Are the excavated areas provided with
fences/ barricades?
4 Are the excavated material kept from the
edge of the pit/ trench by at least 1m?
11 Check bottom of excavation (indicate
proposed GL/Basement level with respect
to existing road level)
C Concreting
Check for provision of vibrators?
Check the horizontal and vertical
levelling of formwork components
Placement Method (Pump, Tremie,
Chute,Other)
Reinforcement Cover Maintained During
Pour
Formwork Stable During Placing and
Vibration
Concrete Placed and Compacted Within
required temperature and time period
Provision for Closure of
Access/Openings
Forms Free of Foreign Matter Prior to
Pouring
Concrete Finished to Approved
Tolerances
D Masonry
5 Wetting of bricks
6 Door frames, if any, erected in position?
7 Line out rechecked? (Room dimension,
diagonals, alignment with one layer of
brick work, Door opening position &
verticality, etc.,
8 Check whether Mortar Preparation is
fresh & provision of platform
9 Check Mortar Thickness
10 Check Alignment & Straightness
17 Check for proper pointing, packing &
finishing
DPC Check whether horizontal dpc is
provided upto finish floor level to restrict
dampness
Where there is difference of level in the
floors,then the vertical dpc is to be
checked.
E PLASTERING
F Painting works
1 Check the material/paints as approved
make
2 Check color shade approved
3 Cleaning of walls to be checked
(Scrapping), Surface finishing
4 Cracks, Dampness, any leakages to be
identified and repaired.
7 Check others materials covered neatly
during the painting work with masking
tape (protection of other materials from
damage like Electrical switches plate,
door/window joints, glass partitions,
wardrobes)
H Shuttering
1 Shuttering Material is New/ Old?
3 Cleanliness of Shuttering?
4 Oiling of Shuttering?
6 Alignment/ Level/ Rigidity OK?
7 Check Props. Are they OK?
9 Check Braces. Are they OK?
I Granite/Marble works
1 Cleaning slab off loose mortar/ material.
3 Proper Stacking of Granite/Marble
1 No material stacked after fixing?
2 Finished surface cleaned properly before
polishing
4 Are there any Cracked, should be
replaced
5 Curing for at least four days after Laying
Check List No.1: Lists of Major Documents Required
Check List No.2: List of Salient Features Related to Health & Safety
Sr.
Description Details/Remarks
No.
1. Site office Conditions
9. Safety Gloves
1. Executive Engineer
3. Sub Engineer
1. Resident Engineer
3. Material Engineer
4. Quantity Surveyor
5. Site inspector
6. Laboratory Technician
7. Surveyor
List of Contractor Staff
1. Project Manager
3. Quantity Surveyors
4. Surveyors
5. Material Engineer
1. Vibrating Compactors
3. Excavator
4. Graders
5. Paver