“MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DEL CAMINO VECINAL OTUZCO – BARRO NEGRO, DISTRITO DE OTUZCO, AGALLPAMPA Y USQUIL, PROVINCIA DE O
LA LIBERTAD” - III ETAPA
1
Cliente: MUNICIPALIDAD PROVINCIAL DE OTUZCO PLAZO 150 D.C.
Lugar: DISTRITO DE OTUZCO, AGALLPAMPA Y USQUIL, PROVINCIA DE
Parcial AGOSTO (22 dias) SEPTIEMBRE (30 dias) OCTUBRE (31 dias) NOVIEMBRE (30 dias) DICIEMBRE (31 dias)
Item Descripción Dias
S/. Parcial % Parcial % Parcial % Parcial % Parcial
01 OBRAS PRELIMINARES 62,158.84
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 2.40 x 3.60 m 1 934.16 934.16 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIA 2 30,533.81 30,533.81 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
01.03 TOPOGRAFIA Y GEOREFERENCIACION 25 30,690.87 25,780.33 84.00% 4,910.54 16.00% 0.00 0.00% 0.00 0.00% 0.00
02 EXPLANACIONES 650,071.91
02.01.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA 39 102,640.94 55,268.20 53.85% 47,372.74 46.15% 0.00 0.00% 0.00 0.00% 0.00
02.01.02 CORTE ROCA SUELTA CON MAQUINARIA 6 16,262.35 0.00 0.00% 16,262.35 100.00% 0.00 0.00% 0.00 0.00% 0.00
02.01.03 CORTE EN ROCA FIJA (PERF. Y DISP.) CON MAQUINARIA 35 198,126.56 0.00 0.00% 67,929.11 34.29% 130,197.45 65.71% 0.00 0.00% 0.00
02.01.04 CONFORMACION DE TERRAPLENES CON MATERIAL PROPIO 3 13,897.25 13,897.25 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02.01.05 CONFORMACION DE TERRAPLENES CON MATERIAL DE PRESTAMO 3 16,916.08 16,916.08 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
02.01.06 PERFILADO Y COMPACTADO DE SUB-RASANTE 131 302,228.73 34,606.33 11.45% 69,212.69 22.90% 71,519.78 23.66% 69,212.69 22.90% 57,677.24
03 PLATAFORMA DE RODADURA 2,667,549.98
03.01.01 CORTE EN TERRENO PARA MEJORAMIENTO C/OVER 36 97,875.36 51,656.44 52.78% 46,218.92 47.22% 0.00 0.00% 0.00 0.00% 0.00
03.01.02 EXTRACCION Y ACUMULACION DE MATERIAL DE CANTERA 60 354,285.36 112,190.36 31.67% 177,142.68 50.00% 64,952.32 18.33% 0.00 0.00% 0.00
03.01.03 ZARANDEO MECANICO 60 188,571.24 59,714.23 31.67% 94,285.62 50.00% 34,571.39 18.33% 0.00 0.00% 0.00
03.01.04 CARGUIO DE MATERIAL DE CANTERA 33 79,365.00 33,670.00 42.42% 45,695.00 57.58% 0.00 0.00% 0.00 0.00% 0.00
03.01.05 EXTENDIDO Y COMPACTADO 10 39,560.40 27,692.28 70.00% 11,868.12 30.00% 0.00 0.00% 0.00 0.00% 0.00
03.02 PAVIMENTO (AFIRMADO) 1,907,892.62
03.02.01 EXTRACCION Y ACUMULACION DE MATERIAL DE CANTERA 110 835,783.68 53,186.24 6.36% 227,941.00 27.27% 235,539.04 28.18% 227,941.00 27.27% 91,176.40
03.02.02 ZARANDEO DE AFIRMADO (TM max=2") 110 284,618.22 12,937.19 4.55% 77,623.15 27.27% 80,210.59 28.18% 77,623.15 27.27% 36,224.14
03.02.03 CARGUIO DE MATERIAL DE CANTERA 105 294,124.32 0.00 0.00% 47,620.13 16.19% 86,836.70 29.52% 84,035.52 28.57% 75,631.97
03.02.04 EXTENDIDO Y COMPACTADO DE MATERIAL DE AFIRMADO 105 411,606.75 0.00 0.00% 27,440.45 6.67% 121,521.99 29.52% 117,601.93 28.57% 121,521.99
03.02.05 MEZCLADO DE MATERIAL GRANULAR DE CANTERA 01, 02 Y 03 33 81,759.65 0.00 0.00% 54,506.43 66.67% 27,253.22 33.33% 0.00 0.00% 0.00
04 TRANSPORTE 4,226,026.17
04.01 TRANSPORTE DE MATERIAL GRANULAR D<=1 kM 23 295,765.50 0.00 0.00% 154,312.43 52.17% 141,453.07 47.83% 0.00 0.00% 0.00
IDAD DEL CAMINO VECINAL OTUZCO
PROYECTO:
“MEJORAMIENTO
– BARRO NEGRO,
DEL SERVICIO
DISTRITODE
DETRANSITABILIDAD
OTUZCO, AGALLPAMPA
DEL CAMINO
Y USQUIL,
VECINAL
PROVINCIA
OTUZCO DE–OTUZCO
BARRO NEGRO,
– DISTRITO DE OTUZCO, AGALLPAMPA Y USQUIL, PROVINCIA DE OTU
LA LIBERTAD” - III ETAPA LA LIBERTAD” - III ETAPA
1
Cliente: MUNICIPALIDAD
PLAZO 150 D.C. PROVINCIAL DE OTUZCO
Lugar: DISTRITO DE OTUZCO, AGALLPAMPA Y USQUIL, PROVINCIA DE
CRONOGRAMA VALORIZADO DE AVANCE DE OBRA FECHADO CRONOGRAMA VALORIZADO DE AVANCE DE OBRA FECHADO
DICIEMBRE
Parcial (31 dias) ENERO (6 dias)
Item Descripción Dias
S/. % Parcial %
01 OBRAS PRELIMINARES 62,158.84
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 2.40 x 3.60 m 1 934.16 0.00% 0.00 0.00%
02 EXPLANACIONES 650,071.91
02.01.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA 39 102,640.94 0.00% 0.00 0.00%
02.01.02 CORTE ROCA SUELTA CON MAQUINARIA 6 16,262.35 0.00% 0.00 0.00%
02.01.03 CORTE EN ROCA FIJA (PERF. Y DISP.) CON MAQUINARIA 35 198,126.56 0.00% 0.00 0.00%
02.01.04 CONFORMACION DE TERRAPLENES CON MATERIAL PROPIO 3 13,897.25 0.00% 0.00 0.00%
02.01.05 CONFORMACION DE TERRAPLENES CON MATERIAL DE PRESTAMO 3 16,916.08 0.00% 0.00 0.00%
03.01.01 CORTE EN TERRENO PARA MEJORAMIENTO C/OVER 36 97,875.36 0.00% 0.00 0.00%
03.02.01 EXTRACCION Y ACUMULACION DE MATERIAL DE CANTERA 110 835,783.68 10.91% 0.00 0.00%
03.02.02 ZARANDEO DE AFIRMADO (TM max=2") 110 284,618.22 12.73% 0.00 0.00%
03.02.04 EXTENDIDO Y COMPACTADO DE MATERIAL DE AFIRMADO 105 411,606.75 29.52% 23,520.39 5.71%
03.02.05 MEZCLADO DE MATERIAL GRANULAR DE CANTERA 01, 02 Y 03 33 81,759.65 0.00% 0.00 0.00%
04 TRANSPORTE 4,226,026.17
Parcial AGOSTO (22 dias) SEPTIEMBRE (30 dias) OCTUBRE (31 dias) NOVIEMBRE (30 dias) DICIEMBRE (31 dias)
Item Descripción Dias
S/. Parcial % Parcial % Parcial % Parcial % Parcial
04.02 TRANSPORTE DE MATERIAL GRANULAR D > 1 kM 105 1,852,522.50 0.00 0.00% 123,501.50 6.67% 546,935.21 29.52% 529,292.15 28.57% 546,935.21
04.03 TRANSPORTE DE MATERIAL A ELIMINAR DIST<=1 kM 2 16,726.21 0.00 0.00% 16,726.21 100.00% 0.00 0.00% 0.00 0.00% 0.00
04.04 TRANSPORTE DE MATERIAL A ELIMINAR DIST > 1 kM 1 2,387.90 2,387.90 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
04.05 TRANSPORTE DE MATERIAL GRANULAR DE CANTERA 01 A CANTERA 02 100 1,099,977.82 54,998.89 5.00% 329,993.35 30.00% 340,993.12 31.00% 329,993.35 30.00% 43,999.11
04.06 TRANSPORTE DE MATERIAL GRANULAR DE CANTERA 03 A CANTERA 02 15 158,653.46 52,884.49 33.33% 105,768.97 66.67% 0.00 0.00% 0.00 0.00% 0.00
04.07 TRANSPORTE DE MATERIAL OVER 65 799,992.78 209,228.88 26.15% 369,227.44 46.15% 221,536.46 27.69% 0.00 0.00% 0.00
05 OBRAS DE ARTE Y DRENAJE 576,405.54
05.01.01 CONFORMACION Y PERFILADO DE CUNETAS EN MATERIAL SUELTO 45 100,557.23 46,926.71 46.67% 53,630.52 53.33% 0.00 0.00% 0.00 0.00% 0.00
05.01.02 CONFORMACION Y PERFILADO DE CUNETAS EN ROCA SUELTA 5 7,448.00 0.00 0.00% 7,448.00 100.00% 0.00 0.00% 0.00 0.00% 0.00
05.01.03 CONFORMACION Y PERFILADO DE CUNETAS EN ROCA FIJA 2 4,947.00 0.00 0.00% 4,947.00 100.00% 0.00 0.00% 0.00 0.00% 0.00
05.02 BADENES (5 UND) 91,112.15
05.02.01 TRAZO Y REPLANTEO EN ESTRUCTURAS 5 2,851.70 2,851.70 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05.02.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS 8 9,227.47 9,227.47 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05.02.03 ELIMINACION DE MATERIAL EXCEDENTE 2 734.09 734.09 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05.02.04 AFIRMADO e=0.20m 2 669.87 669.87 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
05.02.05 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS 12 8,558.90 2,852.97 33.33% 5,705.93 66.67% 0.00 0.00% 0.00 0.00% 0.00
05.02.06 CONCRETO F'C=210 KG/CM2 8 63,911.92 0.00 0.00% 63,911.92 100.00% 0.00 0.00% 0.00 0.00% 0.00
05.02.07 EMBOQUILLADO DE PIEDRA C/C F'C=140 KG/CM2 + 60% P.M. 8 4,556.74 0.00 0.00% 4,556.74 100.00% 0.00 0.00% 0.00 0.00% 0.00
05.02.08 JUNTAS ASFALTICAS e=1" 2 601.46 0.00 0.00% 601.46 100.00% 0.00 0.00% 0.00 0.00% 0.00
05.03 CUNETA BATEA 12,040.70
05.03.01 EXCAVACION MANUAL PARA ESTRUCTURAS 20 882.50 706.00 80.00% 176.50 20.00% 0.00 0.00% 0.00 0.00% 0.00
05.03.02 SUB BASE GRANULA e=0.15 m 2 1,279.49 0.00 0.00% 1,279.49 100.00% 0.00 0.00% 0.00 0.00% 0.00
05.03.03 ENCOFRADO Y DESENCOFRADO 2 1,118.12 0.00 0.00% 1,118.12 100.00% 0.00 0.00% 0.00 0.00% 0.00
05.03.04 CONCRETO f'c=175 kg/cm2 2 8,467.60 0.00 0.00% 8,467.60 100.00% 0.00 0.00% 0.00 0.00% 0.00
05.03.05 JUNTAS ASFALTICAS e=1" 2 292.99 0.00 0.00% 292.99 100.00% 0.00 0.00% 0.00 0.00% 0.00
05.04 MUROS DE CONTENCION 360,300.46
IDAD DEL CAMINO VECINAL OTUZCO
PROYECTO:
“MEJORAMIENTO
– BARRO NEGRO,
DEL SERVICIO
DISTRITODE
DETRANSITABILIDAD
OTUZCO, AGALLPAMPA
DEL CAMINO
Y USQUIL,
VECINAL
PROVINCIA
OTUZCO DE–OTUZCO
BARRO NEGRO,
– DISTRITO DE OTUZCO, AGALLPAMPA Y USQUIL, PROVINCIA DE OTU
LA LIBERTAD” - III ETAPA LA LIBERTAD” - III ETAPA
1
Cliente: MUNICIPALIDAD
PLAZO 150 D.C. PROVINCIAL DE OTUZCO
Lugar: DISTRITO DE OTUZCO, AGALLPAMPA Y USQUIL, PROVINCIA DE
CRONOGRAMA VALORIZADO DE AVANCE DE OBRA FECHADO CRONOGRAMA VALORIZADO DE AVANCE DE OBRA FECHADO
DICIEMBRE
Parcial (31 dias) ENERO (6 dias)
Item Descripción Dias
S/. % Parcial %
04.02 TRANSPORTE DE MATERIAL GRANULAR D > 1 kM 105 1,852,522.50 29.52% 105,858.43 5.71%
04.04 TRANSPORTE DE MATERIAL A ELIMINAR DIST > 1 kM 1 2,387.90 0.00% 0.00 0.00%
04.05 TRANSPORTE DE MATERIAL GRANULAR DE CANTERA 01 A CANTERA 02 100 1,099,977.82 4.00% 0.00 0.00%
04.06 TRANSPORTE DE MATERIAL GRANULAR DE CANTERA 03 A CANTERA 02 15 158,653.46 0.00% 0.00 0.00%
05.01.01 CONFORMACION Y PERFILADO DE CUNETAS EN MATERIAL SUELTO 45 100,557.23 0.00% 0.00 0.00%
05.01.02 CONFORMACION Y PERFILADO DE CUNETAS EN ROCA SUELTA 5 7,448.00 0.00% 0.00 0.00%
05.01.03 CONFORMACION Y PERFILADO DE CUNETAS EN ROCA FIJA 2 4,947.00 0.00% 0.00 0.00%
05.02.07 EMBOQUILLADO DE PIEDRA C/C F'C=140 KG/CM2 + 60% P.M. 8 4,556.74 0.00% 0.00 0.00%
Parcial AGOSTO (22 dias) SEPTIEMBRE (30 dias) OCTUBRE (31 dias) NOVIEMBRE (30 dias) DICIEMBRE (31 dias)
Item Descripción Dias
S/. Parcial % Parcial % Parcial % Parcial % Parcial
05.04.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS 20 22,920.78 0.00 0.00% 22,920.78 100.00% 0.00 0.00% 0.00 0.00% 0.00
05.04.02 RELLENO COMPACTADO CON MATERIAL PROPIO 25 9,242.95 0.00 0.00% 0.00 0.00% 3,327.46 36.00% 5,915.49 64.00% 0.00
05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL 20 72,789.65 0.00 0.00% 0.00 0.00% 0.00 0.00% 50,952.75 70.00% 21,836.90
05.04.04 ENCOFRADO Y DESENCOFRADO CARA VISTA 25 67,791.14 0.00 0.00% 0.00 0.00% 0.00 0.00% 37,963.04 56.00% 29,828.10
05.04.05 GEOTEXTIL 4 6,279.89 0.00 0.00% 0.00 0.00% 6,279.89 100.00% 0.00 0.00% 0.00
05.04.06 CONCRETO F'C=210 KG/CM2 6 63,899.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 63,899.80
05.04.07 CONCRETO f'c=175 kg/cm2 13 89,957.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 89,957.74
05.04.08 JUNTA DE DILATACION 3/4" 10 1,755.57 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,755.57 100.00% 0.00
05.04.09 TUBERIA DE PVC C-5 D=2" 6 5,399.20 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,399.20 100.00% 0.00
05.04.10 TUBERIA PERFORADA D=6" 9 20,263.74 0.00 0.00% 0.00 0.00% 20,263.74 100.00% 0.00 0.00% 0.00
06 FLETE TERRESTRE 20,524.85
06.01 FLETE TERRESTRE 2 20,524.85 20,524.85 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00
CRONOGRAMA VALORIZADO DE AVANCE DE OBRA FECHADO CRONOGRAMA VALORIZADO DE AVANCE DE OBRA FECHADO
DICIEMBRE
Parcial (31 dias) ENERO (6 dias)
Item Descripción Dias
S/. % Parcial %
05.04.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS 20 22,920.78 0.00% 0.00 0.00%
05.04.02 RELLENO COMPACTADO CON MATERIAL PROPIO 25 9,242.95 0.00% 0.00 0.00%
MANO DE OBRA
1.1 CAPATAZ 1 1 1 1
1.2 OPERARIO 1 1 1 1
1.3 OFICIAL 1 1 1 1
1.4 PEON 1 1 1 1
1.5 TOPOGRAFO 1 1 1 1 1
1.6 MANO DE OBRA - T 2 2 2 2 2
1.7 MANO DE OBRA - LT 1 1 1 1 1
1.8 MANO DE OBRA-A 1 1 1 1 1
1.9 MANO DE OBRA - SEÑALIZACION 2 2 2
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y
1.10 1 1 1 1 1
SALUD EN EL TRABAJO
1.11 MANO DE OBRA - PROTECCION COLECTIVA 1 1 1
1.12 CHARLAS DE CAPACITACION EN SEGURIDAD AL PERSONAL 1 1 1 1 1
1.13 MANO DE OBRA - CAPACITACION EN SEGURIDAD 1 1 1 1 1
MATERIALES
2.1 ALAMBRE NEGRO Nro. 8 1 1 1 1 1
2.2 ALAMBRE NEGRO Nro.16 1 1 1 1
2.3 CLAVOS CON CABEZA DE 2 1/2", 3", 4" 1 1 1 1 1
2.4 CLAVOS CON CABEZA DE 3" 1 1 1 1 1
2.5 CLAVOS CON CABEZA DE 4" 1 1 1
2.6 ACERO 1 1 1
2.7 ARENA GRUESA 1 1 1
2.8 ARENA FINA 1 1 1 1
2.9 PIEDRA CHANCADA DE 1/2” Y 3/4" 1 1 1
2.10 AGUA 1 1 1 1 1
2.11 AGUA 1 1 1 1
2.12 ASFALTO LIQUIDO RC-250 1 1 1 1
2.13 MEZCLA ASFALTICA EN CALIENTE 1 1 1
2.14 TRANSPORTE DE MEZCLA ASFALTICA C/VOLQUETE 10M3 1 1 1 1
2.15 LADRILLO KK TIPO IV 24X13X09 CM 1 1 1 1
2.16 CEMENTO PORTLAND TIPO I (42.5kg) 1 1 1 1
2.17 PEGAMENTO PARA TUBERIA PVC 1 1 1 1
2.18 CAL (BOLSA X 20 kg) 1 1 1 1
2.19 CORDEL 1 1 1 1
2.20 IMPERMEABILIZANTE LIQUIDO PARA CONCRETO 1 1 1 1
2.21 EXTINTOR DE POLVO SECO 1 1 1 1
2.22 DISCO DE CORTE DE 16" 1 1
2.23 CASCO DE PROTECCION 1 1
2.24 BOTINES DE CUERO 1 1
2.25 TAPONES AUDITIVOS 1 1
2.26 GUANTES DE CUERO 1 1
2.27 RESPIRADOR CONTRA POLVO 1 1
2.28 CHALECOS REFLECTIVOS 1 1
2.29 LENTES DE PROTECCION 1 1
2.30 MATERIALES - PROTECCION COLECTIVA 1 1
2.31 MATERIALES - SEÑALIZACION SEGURIDAD 1 1
2.32 CAMILLA 1 1
2.33 BOTIQUIN CON MEDICINA 1
2.34 CILINDRO VACIO 1
2.35 TAPA DE CONCRETO C/MARCO F°F PARA BUZON ø 0.60m 1
2.36 GASOLINA 95 OCTANOS 1
2.37 HORMIGON 1
2.38 AFIRMADO 1
2.39 MADERA TORNILLO 1
2.40 MADERA TORNILLO-A 1
2.41 KEROSENE INDUSTRIAL 1
2.42 TUBO PVC-SAP - 8" (5M) 1
2.43 TUBO PVC-SAP-4" (3M) 1
2.44 TUBO PVC-SAP - 6" (5M) 1
2.45 TAPON PVC SAL P/DESAGUE 08” 1
EQUIPOS 1
3.1 HERRAMIENTA 1
3.2 HERRAMIENTA-T 1
3.3 HERRAMIENTA - LT 1
3.4 COMP. NEUMATICA - 93 HP - 335/375 PCM 1
3.5 MARTILLO NEUMATICO - 25/29 KG 1
3.6 RETROEXCAVADORA S/LLANT. 62 HP -1 YD3 1
3.7 TRACTOR DE TIRO DE 60HP 1
3.8 PLANCHA COMPACTADORA VIBRAT. 4.0 HP 1
3.9 RODILLO NEUMATICO AUTOP. 81-100HP 5.5-20T 1
3.10 RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T 1
3.11 MEZCLADORA DE CONC.(TAMBOR) 11 P3,18 HP 1
3.12 VIBRADOR A GASOLINA Y 1 3/4", 4 HP 1
3.13 CORTADORA DE CONCRETO 13 HP 1
3.14 CAMION VOLQUETE 4x2, 210/280 HP, 8 M3 1
3.15 TEODOLITO Y MIRA 1
3.16 BARREDORA MECANICA 10-20HP
3.17 PAVIMENTADORA SOBRE ORUGAS 105HP 10-16'
3.18 CAMION IMPRIMADOR 6x2 178-210HP 2000 GLN
CRONOGRAMA DE ADQUISICION DE MATERIALES
MANO DE OBRA
30369.23
MATERIALES
2.3 CLAVOS CON CABEZA DE 2 1/2", 3", 4" kg 2.32 2.80 6.49
2.35 TAPA DE CONCRETO C/MARCO F°F PARA BUZON ø 0.60m und 5.00 300.00 1500.00
2.45 TAPON PVC SAL P/DESAGUE 08” und 4.42 36.76 162.54
29628.27
EQUIPOS
3.9 RODILLO NEUMATICO AUTOP. 81-100HP 5.5-20T h-m 1.21 127.67 154.29
3.10 RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T h-m 1.21 93.28 112.73
3.14 CAMION VOLQUETE 4x2, 210/280 HP, 8 M3 h-m 3.87 196.77 760.75
3.17 PAVIMENTADORA SOBRE ORUGAS 105HP 10-16' h-m 1.21 133.17 160.94
CRONOGRAMA DE ADQUISICION DE MATERIALES
3.18 CAMION IMPRIMADOR 6x2 178-210HP 2000 GLN h-m 0.25 122.29 30.16
6411.24