Subject : Site Progress

Date : 30/11/2018

Original Construction Period Original Approved Contractor's Contractor'sA


Item Site Staff Scheduled ctual Progress
Appointment Progress (%) (%)

1 December 2017 - January 2018 0.00 0.55


2 January 2018 - February 2018 2.71 1.00
3 February 2018 - March 2018 4.12 4.05
4 March 2018 - April 2018 5.35 5.60
5 April 2018 - May 2018 6.75 8.57
6 May 2018 - June 2018 11.03 15.40
7 June 2018 - July 2018 12.35 16.11
8 July 2018 - August 2018 13.67 17.88
9 August 2018 - September 2018 15.00 20.49
10 September 2018 - October 2018 17.32 24.00
11 October 2018 - November 2018 21.66 28.44
12 November 2018 - December 2018 23.74 -
13 December 2018 - January 2019 26.05 -
14 January 2019 - February 2019 29.71 -
15 February 2019 - March 2019 34.31 -
16 March 2019 - April 2019 37.42 -
17 April 2019 - May 2019 42.50 -
18 May 2019 - June 2019 48.22 -
19 June 2019 - July 2019 54.74 -
20 July 2019 - August 2019 60.24 -
21 August 2019 - September 2019 66.11 -
22 September 2019 - October 2019 74.91 -
23 October 2019 - November 2019 81.44 -
24 November 2019 - December 2019 87.20 -
25 December 2019 - January 2020 90.46 -
26 January 2020 - February 2020 95.16 -
27 February 2020 - March 2020 99.58 -
28 March 2020 - April 2020 99.82 -
29 April 2020 - May 2020 100.00 -
30 May 2020 - June 2020 100.00 -