Professional Documents
Culture Documents
1. Priority rules provide guidelines for the sequence in which jobs should be worked.
The rules generally involve the assumption that job setup cost and time is independent of
processing times. In using this rules, job processing times and due dates are important
pieces
of information. Job times usually include setup and processing times. Due dates may be
the
The rules are especially applicable for process-focussed facilities such as clinics, print shop
and manufacturing job shops. Priority Rules try to minimise completion time, number of
jobs in the system, and job lateness, while maximising facility utilisation.
As Soon as Possible: The default rule for scheduling. This provides the general solution
As Late as Possible: All activities are scheduled as late as possible without delaying the
project. The usual purpose of this heuristic is to defer cash outflows as long as possible.
Shortest Task First: Tasks are ordered in terms of duration, with the shortest first. In
general, this rule will maximize the number of tasks that can be completed by a system
Minimum Slack First: This heuristic orders activities by the amount of slack, least slack
going first. (It is common, when using this rule, to break ties by using the shortest task-
first rule.)
The best priority rule overall is minimum slack first. It usually resulted in the minimum
amount of project schedule slippage, the best utilization of facilities, and the minimum total
Work-Experience Application: This reminds me of the time during my job at CTCI; our
project manager always asked us to do the minimum slack works first. The minimum slack
actions are an essential schedule for the whole project. Moreover, he usually asked out
accounts, and the financial department doesn't transfer money to our subcontractor so
quickly. At first, I didn't know why we should keep our money so long, but right now, I
➔ Heuristic approaches employ rules of thumb that have been found to work
◆ They are the only feasible methods of attacking the large, nonlinear,
optimal, they are usually quite good—certainly good enough for most
purposes.
➔ Optimization approaches seek the best solutions but are far more limited in their
heuristic approach to complete our projects. Due to our projects usually are non-linear,
complex and large, we couldn't use optimization approaches to seek the best solution. We
needed more flexible ways to meet the unpredictable works or requirement; heuristic