Professional Documents
Culture Documents
g
PROCESS SPECIFICATION
P8A-AG3
GE Power & Water
Materials and Processes Engineering
Page 1 of 50
DOCUMENT REVISION STATUS: DETERMINED BY THE LAST ENTRY IN THE "REV" AND "DATE" COLUMN
P8A-AG3
g GE Power & Water _ Page 2 of 50
REV. U Materials and Processes Engineering
TABLE OF CONTENTS
Table of Contents
1. SCOPE ........................................................................................................................... 5
1.1 Statement of Applicability ........................................................................................ 5
1.2 Exclusions ............................................................................................................... 5
2. COMMUNICATION ......................................................................................................... 6
2.1 External Supplier..................................................................................................... 6
2.2 Internal Supplier. ..................................................................................................... 6
2.3 Requests for Deviations .......................................................................................... 6
3. APPLICABLE DOCUMENTS .......................................................................................... 6
3.1 Documents.............................................................................................................. 6
3.2 Hiearchy of Documents........................................................................................... 7
4. DEFINITIONS ................................................................................................................. 7
4.1 Personnel................................................................................................................ 7
4.2 Specification Deviation Documents ........................................................................ 8
4.3 Technical Terms ..................................................................................................... 8
4.4 Weld Symbols. ........................................................................................................ 8
4.5 Base Material Classification .................................................................................... 9
5. RESPONSIBILITIES ....................................................................................................... 9
5.1 Materials and Processes Engineering..................................................................... 9
5.2 Suppliers ................................................................................................................. 9
5.3 Sourcing Quality. .................................................................................................... 9
5.4 Plant Welding Engineer. ......................................................................................... 9
5.5 Audit of Supplier's Facilities and Practices ........................................................... 10
6. WELD CODES .............................................................................................................. 10
6.1 Assignment of Weld Codes ................................................................................... 10
TABLE 1 – Inspection Codes .................................................................................. 10
6.2 Weld Codes on Drawings ..................................................................................... 10
FIGURE 1 – Example of a Welding Symbol with Inspection Code D ................... 11
7. QUALIFICATION REQUIREMENTS............................................................................. 11
7.1 Approval................................................................................................................ 11
7.2 MPP and FPQ. ...................................................................................................... 11
7.3 Welding Procedure Qualification ........................................................................... 11
7.4 Welding Procedure Specifications ........................................................................ 12
7.5 Welder Performance Qualification ........................................................................ 12
P8A-AG3
g GE Power & Water _ Page 3 of 50
REV. U Materials and Processes Engineering
P8A-AG3
g GE Power & Water _ Page 4 of 50
REV. U Materials and Processes Engineering
P8A-AG3
g GE Power & Water _ Page 5 of 50
REV. U Materials and Processes Engineering
1. SCOPE
1.1.1 This specification states the welding and related process requirements for
fabrication of piping made to engineering drawings for Gas Turbine piping and
accessory systems piping. The specification is applicable to fabrications made
by GE, companies contracted to GE, and Suppliers to GE.
1.1.2 The requirements of this specification are in conformance with the fabrication
requirements for Normal Fluid Service or Category D Fluid Service piping of
ASME B31.3, Process Piping Code, except as stated in Section 1.2.
1.2 Exclusions
1.2.1 ASME B31.3 requirements for Severe Cyclic, Category M Toxic Fluid, and High
Pressure Piping Service are beyond the scope of this specification, and ASME
B31.3 requirements related to leak testing of completed piping systems are
modified per Paragraph 9.6.
1.2.3 This specification is not applicable to structural steel framing for pipe support
structures or pipe racks. Structural steel fabrication shall conform to AWS D1.1
Structural Welding Code.
1.2.4 Modification or repairs of existing piping systems shall comply with the intent of
this specification as applicable.
P8A-AG3
g GE Power & Water _ Page 6 of 50
REV. U Materials and Processes Engineering
2. COMMUNICATION
2.1 External Supplier (See Definition) - GE Power & Water Sourcing is the authorized
interface for all communication between GE and the External Supplier. All questions
or requests for additional information shall be submitted to GE Power & Water for
clarification. Conflicts between applicable Specifications or drawings shall be
submitted to GE Power & Water for resolution by Engineering.
2.3 Requests for Deviations - Requests for deviations to the requirements of this
specification shall be submitted as follows:
3. APPLICABLE DOCUMENTS
3.1 The following documents shall form an integral part of this specification to the extent
specified herein. Unless otherwise indicated, the latest issue shall apply.
P8A-AG3
g GE Power & Water _ Page 7 of 50
REV. U Materials and Processes Engineering
3.2 Hiearchy of Documents - In the event of a conflict between documents, the order of
precedence from highest
to lowest is:
Purchase Order
Part Drawing
Part Specification
Process Specification (casting, forging, welding, coating, etc.)
Material Specification
4. DEFINITIONS
4.1 Personnel
P8A-AG3
g GE Power & Water _ Page 8 of 50
REV. U Materials and Processes Engineering
4.3.6 T - thickness of the parent or base material, or the thinner member when parts
of unequal thickness are butt welded together
NOTE: Welding terminology is defined in AWS A3.0, Terms and Definitions, Welding
and Cutting.
4.4 Weld Symbols - Weld symbols are defined by the American Welding Society in AWS
A2.4.
P8A-AG3
g GE Power & Water _ Page 9 of 50
REV. U Materials and Processes Engineering
4.5 Base Material Classification - Base materials are classified by "P" numbers in
accordance with the ASME Boiler and Pressure Vessel Code Section IX or ASME
B31.3 or by GE Specification number for materials with no ASME-assigned "P"
number.
5. RESPONSIBILITIES
5.1 Materials and Processes Engineering - MPE shall maintain and update this
specification as needed.
5.2 Suppliers
5.2.1 Suppliers shall qualify all welders and welding procedures used. Approval of all
qualifications shall be in accordance with Section 7.
The buyer may request that all CoCs be maintained by the supplier in lieu of
submittals, and that CoCs must be available upon request or audit.
5.3 Sourcing Quality - Sourcing Quality shall ensure that all External Supplier welders
and welding procedures are properly qualified to this document before they begin
production work.
5.4 Plant Welding Engineer - GE Gas Turbines Plant Welding Engineer shall ensure that
welding procedures are qualified according to ASME Section IX and that all Internal
Supplier welders and welding procedures are qualified to the requirements of this
specification before they begin production work.
P8A-AG3
g GE Power & Water _ Page 10 of 50
REV. U Materials and Processes Engineering
5.5.1 The Purchaser reserves the right to periodically audit the Supplier's facilities
and practices. Such audits shall not relieve the Supplier from the responsibility
of producing the fabrications in a suitable condition.
5.5.2 The Purchaser reserves the right to perform additional checks, such as UT or
RT, in order to verify if the weld quality meets the requirements, even if there is
no such check required by the drawing/specification. The acceptance criteria
will be those of P8A-AG1 for the relevant inspection method used. If GE is
satisfied that the Purchaser’s inspection methods, techniques, and results are
valid and that the parts are truly defective, the Supplier shall repair or replace
such parts at the Supplier’s own expense.
6. WELD CODES
6.1.1 The weld code for Gas Turbine and Accessory systems piping is Code N
unless designated Code D in the engineering design specifications or within the
GE Piping Applied Practices specification 351A3700.
6.1.2 Code N exceeds ASME B31.3 inspection requirements for Normal Fluid
Service; Code D inspection requirements are the same as ASME B31.3
requirements for Category D fluid service.
6.2.1 The Weld Code shall be written as a general drawing note or shown in the tail
of the welding symbol.
6.2.1.1 If all or most welds on a particular drawing are of one Code, a general
note may be used. For example, “Unless otherwise specified, all welds are
Code D.”
P8A-AG3
g GE Power & Water _ Page 11 of 50
REV. U Materials and Processes Engineering
6.2.1.2 For individual weld joint asssigment, place the Code of the weld in the tail
of the weld symbol. Any Code specified in the tail of a weld symbol
supercedes general drawing notes
7. QUALIFICATION REQUIREMENTS
7.1 Approval
7.1.1 Welding is not released for production until the WPSs, PQRs, and welder
qualifications have been approved.
7.1.2 For fabrications made by suppliers outside the Gas Turbine Operation, WPSs,
PQRs, and WPQRs shall be submitted through Sourcing to the SQE and MPE
for approval.
7.1.3 For fabrications made inside GE Gas Turbines Manufacturing Plant Welding
Engineer shall be responsible for issuing welding special process and
manufacturing engineering instruction and qualification packages.
7.2 MPP and FPQ - An MPP and FPQ are required for each new supplier and a new
design unless otherwise authorized by GE. Detailed requirements for the MPP and
FPQ shall be presented according to the applicable part specific process
specifications or P28A-AL-0002.
7.3.2 PQRs developed by acquired companies may be used to qualify WPSs for the
new owners. The source of the PQRs shall be preserved.
7.3.3 All divisions of the General Electric Corporation have operational control of
Welding Procedure Qualifications produced within or acquired by any division
of the General Electric Coporation.
P8A-AG3
g GE Power & Water _ Page 12 of 50
REV. U Materials and Processes Engineering
7.4.1 Detailed WPSs shall be prepared for all welds. WPSs shall be qualified and
documented in accordance with ASME Section IX.
7.4.2 WPSs shall be qualified by a PQR in accordance with ASME Section IX.
7.5.1 Welders and welding operators shall be qualified in accordance with ASME
Section IX.
7.5.2 Suppliers shall assign an individual identification to each welder and welding
operator.
7.5.3 Suppliers shall maintain self-certified records showing the date and limits of
qualifications, and the identification designation assigned to each welder and
welding operator.
7.5.4 Internal Supplier (see Definitions) welders shall also meet the visual acuity
requirement of AWS D17.1 Paragraph 4.2.1.
7.5.5 All divisions of the General Electric Corporation have operational control of
Welder Performance Qualifications produced within or acquired by any division
of the General Electric Coporation.
8.1 Added Welds - If weld joints not shown on the drawing are required to fabricate a
piping assembly and the WPS or WPQ Essential Variables change, then they shall
be submitted and approved before the added welds are made.
8.2.1 Alignment tolerances for butt welded joints shall be the smaller of the values
stated in the welding procedure specification or the engineering drawing. If the
applicable drawing or welding procedure specification does not specify
alignment tolerances, the maximum offset in the weld joint inside diameter shall
be 0.062 inch for open root butt welds made without consumable inserts. See
Figure P10, P10A, or P10B.
P8A-AG3
g GE Power & Water _ Page 13 of 50
REV. U Materials and Processes Engineering
8.2.2 Joints exceeding tolerance limits shall have the pipe with the smaller inside
diameter trimmed so that the adjoining surfaces meet tolerance requirements.
This trimming shall not result in a pipe wall thickness less than the minimum
design thickness and the change in contour shall not exceed 30 degrees. (See
Figure P10A).
8.2.4 Branch connection welds shall meet the following alignment tolerance
requirements.
Branch connection welds which abut the outside surface of the run pipe
shall be contoured for groove welds which meet the requirements of
Figure P14.
The inside bore of the branch pipe shall not be offset from the penetration
hole through the run pipe more than the lesser of 1/8 inch or 1/2 the
nominal wall thickness of the branch.
Branch connections which are inserted through a run opening shall be
inserted at least as far as the inside surface of the run pipe at all points.
The weld joint root gap shall not exceed 0.09 inch.
8.3 Bare Wire Storage - Bare wire shall be clean when used. It shall be stored in a
manner which will keep it clean. Each spool of electrode used for automatic welding
shall be covered or removed from the wire feeder if it could become contaminated
from exposure to the atmosphere.
8.4 Clad or Lined Piping - Welding of clad or lined piping shall be done in accordance
with applicable provisions of the ASME B&PVC, Section VIII, Division 1, UCL-30
through UCL-52.
8.5.1 All flux covered electrodes shall be clean and dry before use.
8.5.2 Low hydrogen electrodes (EXX15, 16, 18, 28) and (EXXX15, 16, 18) shall be
kept in their sealed, undamaged shipping containers or stored in heated ovens
to ensure their low hydrogen characteristics are maintained. The oven
P8A-AG3
g GE Power & Water _ Page 14 of 50
REV. U Materials and Processes Engineering
temperature shall be held at 300°F ± 50°F. The oven shall be used only for
welding electrode storage and it will be kept in proper working order. Electrodes
of the EXXX15, 16, or 18 class shall be used within 1 hour after removal from
their sealed container or the oven. Electrodes of the EXX15, 16, 18, or 28 class
shall be used within 4 hours after removal from their sealed container or the
oven.
8.5.3 Stainless steel, nickel base, and cobalt base alloy electrodes shall be kept in
sealed containers or stored in heated ovens at 300°F ± 50°F. They shall be
used within 4 hours after removal from their container or the oven.
8.5.4 All other electrodes shall be stored in a clean dry area in a manner to maintain
their original condition and to minimize the possibility of mixing electrode types.
8.6.1 Austenitic filler metals deposited onto ferritic steels, and conversely, are
dissimilar metal welds (DMWs). One of the most common DMWs is with 309
filler metal welded onto ferritic steels. The 309 presents two issues when
welded onto ferritic steels: 1) carbon diffusion out of the ferritic steel into the
309, and 2) different coefficients of thermal expansion (CTEs).
8.6.2 At temperatures of about 750°F and up, the higher chromium content of the
309 causes carbon to diffuse from the ferritic steel into the 309, which creates a
narrow, low carbon zone (LCZ) in the ferritic steel along the weld fusion line.
The LCZ is lower strength than the ferritic steel and, depending on the service
environment, may be subject to either creep or corrosion fatigue failure
mechanisms.
P8A-AG3
g GE Power & Water _ Page 15 of 50
REV. U Materials and Processes Engineering
8.6.3 The 309 has a higher CTE than that of ferritic steels. Inco 82 is a high nickel
filler metal that has a CTE that is between that of austenitic and ferritic base
metals.
8.6.4 For DMWs at service temperatures below 750°F use Col BC in Table I.4 (Inco
82 or Inco 182). Col BC will mitigate the effects of differential CTEs. Whenever
PWHT is required, minimum time at PWHT temperature is recommended to
reduce the effects of carbon diffusion.
8.6.5 DMWs at higher temperatures require Col BT in Table I.4 (EPRI P87 filler
metal), in order to mitigate the effects of both carbon diffusion and differential
CTEs.
8.7 Electrical Characteristics and Meter Calibration - To ensure that welders, welding
operators and inspectors can determine the electrical characteristics of automatic
and semi-automatic welding operations, an ammeter and a voltage meter shall be
provided for determining the arc welding amperage and voltage output of the
welding equipment.
8.7.2 Instrument accuracy shall be plus or minus five percent of maximum meter
readings.
P8A-AG3
g GE Power & Water _ Page 16 of 50
REV. U Materials and Processes Engineering
8.7.3 The ammeter and voltage meter shall be calibrated at least annually.
Calibration shall be traceable to NIST standards or other suitable national
standards if outside the United States.
8.8 Flux Control - Flux shall be stored in its sealed shipping containers in such a manner
that the material is protected against exposure to moisture pick-up. This includes
both warehouse storage and transportation. If moisture pick-up is suspected, the flux
shall be discarded or dried in accordance with the manufacturer's recommended
practice before the material is put in service. The distribution of flux with pneumatic
equipment must be with a cleaned, dried and filtered air supply system. Flux that
was fused during welding shall not be recovered and re-used.
8.9.2 Open root welds shall employ a GTAW root pass with or without a consumable
insert, or a GMAW root pass without a consumable insert.
8.9.3 Backside inert gas shielding shall be employed for the root pass and not less
than the next two layers of all open root welds in stainless steel pipes, and as
required to provide acceptable root pass surface contours and freedom from
oxides in low alloy steels.
8.9.4 Where single-welded full penetration joints are used, particular care shall be
taken in aligning and separating the piping components to be joined so there
will be complete penetration and fusion at the bottom of the joint for its full
length.
8.9.5 Where double welded full penetration joints are used, the reverse side shall be
prepared by grinding or machining to sound metal, which shall be verified by
magnetic particle or liquid penetrant inspection, before weld metal is deposited
from the second side.
8.10.1 GMAW-S is a non-wave-form controlled, short arc mode of metal transfer that
is not allowed for piping welds.
P8A-AG3
g GE Power & Water _ Page 17 of 50
REV. U Materials and Processes Engineering
First piece qualification (FPQ) shall include cross sections to verify no lack
of fusion.
Semiautomatic GMAW-MS (hand held torch) shall be in the 1GR or 3GR
position.
Welder qualification shall be by bend testing.
Each pass made with GMAW-MS shall be visually inspected prior to
making additional passes. When the ID is accessible, the ID of the root
pass shall also be visually inspected.
8.11.1 The holding temperature and material thickness requirements for post weld
heat treatment shall be as follows, unless otherwise approved by MPE.
NOTE 1 - The P number refers to the grouping of materials by the ASME Boiler and Pressure Vessel
Code, Section IX.
NOTE 2 - Post weld heat treatment of P-1 materials is required when thickness exceeds 3/4 inch.
NOTE 3 - Post weld heat treatment of P-3 materials is required when the thickness exceeds 3/4 inch. Heat
treatment is required for all thicknesses of P3 materials whose specified minimum base metal
tensile strength exceeds 71,000 psi.
NOTE 4 - Post weld heat treatment of P-4 materials is required when thickness exceeds 1/2 inch, and for
all thicknesses when the specified minimum base metal tensile strength exceeds 71,000 psi.
NOTE 5 - Post weld heat treatment of P-5A materials is required when thickness exceeds 1/2 inch, and for
all thicknesses when either (1) the chromium content exceeds 3%, or (2) the carbon content
exceeds 0.15%.
NOTE 6 - Post weld heat treatment of P-6 materials shall be done at 1375°F, except A240 Gr. 429 and
A268 Gr. 429 which shall be heat treated at 1200°F.
NOTE 7 - When heat treatment of welds, other than longitudinal, is required for quenched and tempered
materials, the maximum heat treatment temperature shall be at least 50F below the tempering
temperature of the material. Longitudinal welds in materials with tensile properties enhanced by
a quench and temper heat treatment shall be re-heat treated in accordance with the applicable
material specification.
COPYRIGHT 1989-2014 GENERAL ELECTRIC COMPANY AND ITS AFFILIATES.
All rights reserved. The information contained herein is Proprietary Technical Information that belongs to General Electric Company, GE
Power & Water (USA), LLC and/or their affiliates, which has been provided solely for the express reason of restricted private use. All persons,
firms, or corporations who receive such information shall be deemed by the act of their receiving the same to have agreed to make no
duplication, or other disclosure, or use whatsoever for any, or all such information except as expressly authorized in writing by General Electric
Company, GE Power & Water (USA), LLC and/or its affiliates.
GE Proprietary Information - Class II (Internal) US EAR - NLR
DWG Number P8A-AG3 Rev U Released 10/27/2014 Page 18 of 50
P8A-AG3
g GE Power & Water _ Page 18 of 50
REV. U Materials and Processes Engineering
8.11.2 The following rules apply for determination of thickness in application of post
weld heat treatment. The thickness to be used shall be that of the thicker piping
component measured at the weld joint except as follows:
Fig. P12 = Tb + tc
Fig. P13 = Th + tc
(b) Slip-on and Socket Flange Fillet Welds - Heat Treat Thickness
Provisions - Heat treatment requirements that follow are applicable for
fillet welds at:
slip-on and socket welding flanges and piping connections NPS 2
and smaller,
seal welding of threaded joints in piping NPS 2 and smaller, and
attachment of external non-pressure parts such as lugs or other
pipe supporting elements in all pipe sizes.
Heat treatment is required when the thickness through the weld in any
plane is more than twice the minimum material thickness requiring heat
treatment (even though the thickness of the piping components at the joint
is less than that minimum thickness) except as follows:
(1) not required for P-No. 1 materials when weld throat thickness is 5/8
inch or less, regardless of base metal thickness;
(2) not required for P-No. 3, 4, or 5A materials when weld throat
thickness is 1/2 inch or less, regardless of base metal thickness,
provided that not less than the recommended preheat is applied, and
the specified minimum tensile strength of the base metal is less than
71,000 psi.
P8A-AG3
g GE Power & Water _ Page 19 of 50
REV. U Materials and Processes Engineering
8.12 Heat Treatment of Dissimilar Metal Joints - Heat treatment of assemblies having
welded joints between dissimilar ferritic metals, or between ferritic metals using
dissimilar ferritic filler metal, shall be at the higher of the temperature ranges for the
materials in the joint. However, cognizance must be taken of the lower critical
transformation temperatures of both materials so that heat treatment at a relatively
high temperature specified for one material does not exceed the lower critical
temperature of the other one. Welded joints including both ferritic and austenitic
piping components and filler metals or ferritic and iron, cobalt and nickel base super
alloys and filler metals shall be heat treated as required for the ferritic material or
materials unless otherwise specified in the engineering design.
8.13 Interpass Cleaning - All visible defects such as cracks, unfused areas, overlap, high
spots, poor bead contour, undercut, porosity or any other condition which might
detrimentally affect weld quality shall be corrected before the next weld bead is
deposited. The area shall be chipped out, ground or otherwise removed to sound
metal before re-welding. Slag and loose spatter shall be removed from each weld
bead and adjacent surfaces before a succeeding bead is deposited. Arc craters in
completed welds shall be filled to provide a uniform cross-section for the entire weld
length. Care shall be taken not to damage the remaining weld preparation or
adjacent base metal.
8.14 Peening - Peening shall not be performed without MPE approval, and when used
shall be included as a nonessential variable in the weld procedure. Cleaning of
welds with chipping hammers or needle descalers used to remove flux and slag is
not considered peening, as long as the weld metal is not deformed by such action on
the final weld cap pass.
8.15.1 Table 3 stipulates the minimum preheat requirements for welding Gas Turbine
piping. When conformance to other codes is required by the customer or local
prevailing regulations, the specific requirement shall be identified on the
drawing or in the ordering sheet and shall take precedence, but shall not be
less than that specified in Table 3.
8.15.2 There shall be no welding on any pipe whenever the pipe is not within the
specified minimum preheat temperature and the specified maximum interpass
temperature. When it is not feasible to uniformly preheat the part, local heating
may be performed in such a manner that the heated area completely surrounds
the welded area for a minimum of three inches.
P8A-AG3
g GE Power & Water _ Page 20 of 50
REV. U Materials and Processes Engineering
Note 1 - The P number refers to the grouping of materials by the ASME B&PVC Section IX.
For GE materials not listed in ASME Section IX, contact MPE for equivalent P numbers.
Note 2 - Precautions shall be taken to assure slow cooling of pipes if preheat is not maintained until the
start of post weld heat treatment. Cooling in still air is acceptable if ambient temperature is
above 50°F. If low ambient temperatures, drafts, or other conditions that could produce
detrimental effects exist, the welded regions shall be suitably insulated, or be held at 400°F to
700°F for at least 2 hours prior to cooling.
Note 3 - Preheat shall be maintained until the start of stress-relief treatment.
Note 4 - Materials with carbon contents greater than 0.15% or chromium greater than 3% shall be
maintained at preheat until the start of post weld heat treatment, or be held at 400°F to 700°F
for 2 hours minimum before cooling after completion or interruption of welding.
8.16 Pressure-Tight Welds - Pressure-tight welds shall be made with a minimum of two
layers wherever possible. Where it is impractical to use two layers, any interruptions
in the weld layer (starts or stops) should be carefully made to avoid leaks. In the
case of the shielded metal arc process, for instance, the weld shall be back stepped
in increments not exceeding the length of weld deposited with one electrode. The
end of each bead shall overlap the preceding bead by approximately 1/2 inch and
the crater shall be reduced to a minimum.
8.17 Repairs
8.17.1 Welds which do not meet the minimum specified acceptance standards shall
have the defects removed and be weld repaired if necessary.
8.17.2 Defects must be removed only to the extent that the weldment is acceptable
upon re-inspection by the same method that originally disclosed the defect prior
to weld repair.
P8A-AG3
g GE Power & Water _ Page 21 of 50
REV. U Materials and Processes Engineering
8.17.3 Weld repairs shall be made by a procedure qualified and approved for making
the original weld unless otherwise approved by MPE or the GE Plant Welding
Engineer.
8.17.4 The repaired areas shall be re-inspected by the same method or methods, and
shall be evaluated using the same acceptance standards that were originally
used and applied to inspection of the weld.
8.17.5 Weld repairs to base metal areas require approval via the SDR / QCR process.
8.18 Seal Welds - Seal welding shall be done by a qualified welder. Where seal welds are
employed, they shall cover all exposed threads.
8.19.2 All parts shall be free of foreign material such as dirt, oil, grease, etc. before
stress relief.
8.19.3 Each furnace charge shall have a minimum of 2 thermocouples placed in direct
contact with the metal so as to adequately monitor the temperature of the
anticipated hottest and coldest sections. Alternate method of furnace control
may be used if approved by MPE or the GTO Materials Engineer.
8.19.6 Parts shall be placed in the furnace at a temperature not exceeding 800°F, or
500°F more than the temperature of the weldment, whichever is less.
8.19.7 The temperature shall be raised and lowered uniformly at a rate not exceeding
the following:
P8A-AG3
g GE Power & Water _ Page 22 of 50
REV. U Materials and Processes Engineering
8.19.9 The weldment may be removed from the furnace when the temperature has
fallen below 600°F.
8.19.10 When an entire piping assembly cannot be fit into the furnace, it is permissible
to heat treat in more than one heat provided there is at least one foot overlap
between successive heats and the parts of the assembly outside of the furnace
are protected from harmful temperature gradients.
8.19.11 The required stress relief may be performed by local heating operations
provided the procedure is approved by MPE or the GTO Materials Engineer.
8.20 Tack Welds - Tack welds that are to remain in the weld shall be made only by
qualified welders in accordance with a qualified procedure. Tack welds at the root of
pipe joints shall be made with filler metal equivalent to that used in the root pass.
Cracked or defective tack welds shall be removed prior to final welding. Tack welds
shall be kept small or shall be tapered by chipping, grinding or burring to assure
complete fusion with the subsequent weld.
8.21 Weld Filler Metal - The weld filler metal shall be identified by column letter
designation per Appendix I or by GE or AWS specification. It can be specified in the
tail of the welding symbol or as a drawing note. If not designated on the drawing,
weld filler metal shall be per Appendix I, or as approved by MPE Fabrications.
8.22.1 Surfaces to be welded or thermally cut shall be cleaned of all foreign material
such as grease, oil, dirt, scale, slag and paint that would be detrimental to
either the weld or base material. The region cleaned shall include all of the joint
preparation surfaces and shall extend for a distance not less than 1 inch from
the edge of the joint preparation.
8.22.2 Care shall be taken when using chemical cleaning processes that the base
metal is not adversely affected by intergranular attack, alloy depletion, or
intergranular oxidation. Chemical cleaning techniques shall be referred to MPE
for evaluation.
P8A-AG3
g GE Power & Water _ Page 23 of 50
REV. U Materials and Processes Engineering
8.23.1 General - The weld joint design shall be per the figures in Appendix II of this
specification and the qualified and approved WPS. A welding procedure
specification shall be submitted to change joint designs.
8.23.2 Branch Connections - Piping unreinforced branch connections which abut the
outside of the run or are inserted in the opening in the run shall be attached by
fully penetrated groove welds. The welds shall be finished with cover fillet
welds having a throat dimension not less than the lesser of 0.7T (T is the
branch pipe wall thickness) or 1/4 inch. Basic joint details are shown in
Appendix II Figures P12 and P13.
The transverse reinforcing branch fillet shall fill and match with a smooth
transition to the fully penetrated weld matching the specific fitting.
8.23.3 Fabricated Laps - Joint designs for piping assembly fabricated laps shall be in
accordance with Appendix II Figures P15, P16, P17, P18, or P19.
8.23.4 Sleeve Joints - Welded sleeve joints are not permitted in pressure piping
applications. For other appilications, this joint type shall be approved by Design
Engineering and specifically detailed on the engineering drawings.
8.24.1 All surfaces to be welded shall be suitably prepared. Undercuts, gouges and
obstructions shall be blended free of re-entrant angles to be suitable for
magnetic particle or liquid penetrant inspection. Cracks and laminations shall
be removed, except laminations may be weld repaired per the requirements of
this specification after removal to a depth of 3/8 inch from the weld prep
surface.
8.24.2 When non-ferrous alloys are cut by thermal processes, the reaction layer shall
be removed by mechanical means to bright metal.
8.24.3 When ferrous alloys are cut by thermal processes, those materials which
require preheat for welding shall have the reaction layer removed by
mechanical means to bright metal.
P8A-AG3
g GE Power & Water _ Page 24 of 50
REV. U Materials and Processes Engineering
8.25.1 The welding positions shall be as defined in Section IX of the ASME B&PVC.
8.25.3 The progression of welding in the vertical position shall be upward unless the
base metal thickness is 1/8 inch or less.
8.26 Weld Weave Limitations - The weld weave limitations for SMAW shall not exceed
three (3) times the electrode core diameter for P-1, P-3, P-4, P-5A or P-5B materials,
except with the vertical up technique, the weave may be up to 6 times the core
diameter. The SMAW electrode weave limitations for all other materials shall not
exceed two (2) times the electrode diameter. For other welding processes, the
electrode weave shall not exceed 5/8 inch without prior evaluation by MPE, or by
Gas Turbine Quality Assurance, of workmanship samples suitably examined to
determine that weld quality standards can consistently be met.
8.27.1 Each welder and welding operator shall stamp the identification mark assigned
to him/her at three foot or smaller intervals within 1 inch of each weld she/he
deposits.
8.27.2 Stamped identification of thin wall (less than 1/8 inch) parts shall not be done
unless specifically requested on the drawing.
8.27.3 As an alternate to stamping, the Supplier may keep a record of the amount and
location of welds made by each welder and welding operator.
9.1 Required Inspections - Required inspections are per designated lot of material as
defined by GE Gas Turbines Manufacturing or by each Supplier, and approved by
Product Quality Engineering or by GE Sourcing Quality.
9.1.1 CODE N INSPECTION - Piping for Normal Fluid Service Conditions as defined
by 351A3700; i.e. service conditions not covered by ASME B31.3, Category D
Fluid Service, or Piping for Severe Cyclic Conditions, or Piping for Category M
Fluid Service, or High Pressure Piping; shall be examined and certified to the
extent specified as follows:
P8A-AG3
g GE Power & Water _ Page 25 of 50
REV. U Materials and Processes Engineering
9.1.1.2 All welds shall be visually examined. The GE Gas Turbine Manufacuring
organization shall use Characteristic Verification Program Operators to
verify visual examinations.
9.1.1.3 Longitudinal welds required to have an ASME B31.3 joint factor E of 0.90
shall be subjected to spot radiographic examination of at least 1 foot in
each 100 feet of weld for each welder or welding operator. Weld lengths
radiographed shall be identified by NDE stamp.
9.1.1.6 Not less than 5% of circumferential butt and miter groove welds shall be
examined fully by random radiography or random ultrasonic examination.
Welds to be examined shall be selected to ensure that the work of each
welder or welding operator doing the production welding is included. They
shall also be selected to maximize coverage of intersections with
longitudinal joints. At least 1 ½ inch of the intersecting longitudinal welds
shall be examined. Welds that have been ultrasonically examined or
radiographed shall be identified by NDE stamp.
P8A-AG3
g GE Power & Water _ Page 26 of 50
REV. U Materials and Processes Engineering
9.1.2 CODE D INSPECTION - All welds in piping for Category D Fluid Service as
designated in 351A3700 shall be 100% visually examined to satisfy that piping
components, materials, and workmanship conform to the requirements of
ASME B31.3, the engineering design, and the visual acceptance criteria for
Category D Fluid Service Welds in Table 5 herein. GE Gas Turbine
Manufacturing Organization shall use Characteristic Verification Program
Operators to verify visual examinations.
9.1.4 Welded Branch Connection - Examination and all required repairs to the
pressure containing weld of a welded branch connection shall be completed
before any reinforcing pad or saddle is added.
9.2.1 An examined item with one or more defects that exceed the acceptance criteria
shall be replaced or repaired in conformance with 8.17 and the new work shall
be re-examined by the same methods, to the same extent, and by the same
acceptance criteria as required for the original work.
(a) two additional items of the same kind welded by the same welder or
operator from the original designated lot shall be given the same type of
examination; and
COPYRIGHT 1989-2014 GENERAL ELECTRIC COMPANY AND ITS AFFILIATES.
All rights reserved. The information contained herein is Proprietary Technical Information that belongs to General Electric Company, GE
Power & Water (USA), LLC and/or their affiliates, which has been provided solely for the express reason of restricted private use. All persons,
firms, or corporations who receive such information shall be deemed by the act of their receiving the same to have agreed to make no
duplication, or other disclosure, or use whatsoever for any, or all such information except as expressly authorized in writing by General Electric
Company, GE Power & Water (USA), LLC and/or its affiliates.
GE Proprietary Information - Class II (Internal) US EAR - NLR
DWG Number P8A-AG3 Rev U Released 10/27/2014 Page 27 of 50
P8A-AG3
g GE Power & Water _ Page 27 of 50
REV. U Materials and Processes Engineering
(b) if the items examined are acceptable, the defective item shall be
repaired or replaced and re-examined in accordance with 9.2.1, and all
items represented by this additional examination shall be accepted; but
(c) if any of the items examined as required by (a) reveals a defect, two
further samples of the same kind shall be examined for each defective
item found by that sampling; and
(d) if all the items examined as required by (c) are acceptable, the defective
item(s) shall be repaired or replaced and re-examined as specified in
9.2.1, and all items represented by this additional examination shall be
accepted; but
(e) if any of the items examined as required by (c) reveals a defect, all items
represented by the progressive examination shall be either:
(1) Repaired or replaced and re-examined as required, or
(2) Fully examined and repaired or replaced as necessary, and re-
examined as necessary to meet the requirements of this
specification.
P8A-AG3
g GE Power & Water _ Page 28 of 50
REV. U Materials and Processes Engineering
9.3.4 Acceptance criteria are as stated for the applicable category of visual
examination herein and in the engineering drawing.
9.4.1 Inspectors shall have training and experience commensurate with the needs of
the specified inspections (SNT-TC-1A Recommended Practice for NDT
Personnel Qualification and Certification, may be used as a guide). As a
minimum, all inspection personnel, except visual, shall be Level 2. For visual
inspection of welds, AWS B1.11 may be used as a guide. The employer shall
certify and maintain records of the inspectors employed, showing dates and
results of personnel qualifications. These records shall be maintained by the
Supplier for 5 years after completion of fabrication.
P8A-AG3
g GE Power & Water _ Page 29 of 50
REV. U Materials and Processes Engineering
9.6.1 Welds shall be inspected using acceptance standards specified herein. These
standards meet or exceed those of ASMEB31.3 for Normal Fluid Service
Conditions and Category D Fluid Service piping.
P8A-AG3
g GE Power & Water _ Page 30 of 50
REV. U Materials and Processes Engineering
Indications are unacceptable if the amplitude exceeds the reference level established by the
basic calibration block for ultrasonic examination of welds as stipulated in ASME Boiler and
Pressure Vessel Code, Section V, Article 5, and the lengths exceed the following:
1/4 in. for T up to 3/4 in.
1/3T for T from 3/4 in. to 2-1/4 Where T is the thickness of the weld, or thinner member
in. when parts of unequal thickness are butt welded together.
3/4 in. for T over 2-1/4 in. where
Where indications are interpreted as cracks, lack of fusion, or lack of penetration, they are
unacceptable regardless of length.
9.7.1 Hardness tests shall be conducted on piping assemblies of P-Nos. 3, 4, 5A, 5B,
15E, and 6 materials, after heat treatment.
9.7.2 Hardness tests of production welds and of hot bent and hot formed piping are
intended to verify satisfactory heat treatment. The hardness limit applies to the
weld and to the heat affected zone (HAZ) tested as close as practicable to the
edge of the weld.
9.7.3 When dissimilar metals are joined by welding, the hardness limits specified for
the base and welding materials shall be met for each material.
P8A-AG3
g GE Power & Water _ Page 31 of 50
REV. U Materials and Processes Engineering
9.7.4 At least 10% of welds, hot bends, and hot formed components of those
materials in each furnace heat treated batch, and 100% of those locally heat
treated, shall be tested. The maximum hardness in the weld and heat affected
zone (tested as close as practicable to the edge of the weld) shall be as
specified herein. Brinell tests shall not be performed on pipes smaller than 2
inch O.D. or with wall thickness less than 0.2 inch.
9.8.1 The standard factory performance testing shall serve as the standard leak test
for all gas turbine piping systems on units and associated peripheral
skids/hardware except as follows.
9.8.2 Fuel gas and steam injection piping will be hydrostatically tested as individual
fabrications at a pressure at least 1.5 times the respective design pressure.
Refer to the job specific hydrostatic testing specification, typically MLI 0204 or
an equivalent specification.
9.8.3 Paras. 9.8.1 and 9.8.2 are noted exceptions to ASME B31.3 requirements.
Inclusion of the hydrostatic leak test requirement on GE Gas Turbine piping
and accessory systems piping is an optional feature when customer-specified.
Hydrostatic testing (or pneumatic) is a requirement for European PED
Compliance for Category I, II, and III piping. Refer to the specific GE drawings
or specifications for notes and other criteria for PED compliance.
9.8.4 GE shall advise the piping or equipment Supplier in writing when hydrostatic
tests or witnessing by the customer is required.
9.8.5 The ASME B31.3 Alternative Leak Test in accordance with paragraph 345.9
may be used where required subject to the conditions specified by the Code.
P8A-AG3
g GE Power & Water _ Page 32 of 50
REV. U Materials and Processes Engineering
9.8.6 Piping welds that are made as a result of cutting and fitting a previously welded
part requires a Leak test.
10. NOTES
None
/js 04-21-2014
COPYRIGHT 1989-2014 GENERAL ELECTRIC COMPANY AND ITS AFFILIATES.
All rights reserved. The information contained herein is Proprietary Technical Information that belongs to General Electric Company, GE
Power & Water (USA), LLC and/or their affiliates, which has been provided solely for the express reason of restricted private use. All persons,
firms, or corporations who receive such information shall be deemed by the act of their receiving the same to have agreed to make no
duplication, or other disclosure, or use whatsoever for any, or all such information except as expressly authorized in writing by General Electric
Company, GE Power & Water (USA), LLC and/or its affiliates.
GE Proprietary Information - Class II (Internal) US EAR - NLR
DWG Number P8A-AG3 Rev U Released 10/27/2014 Page 33 of 50
P8A-AG3
g GE Power & Water _ Page 33 of 50
REV. U Materials and Processes Engineering
I-1 Scope
To use the Filler Metal Selection Tables I.1-I.3, locate the row of the first base metal to
be joined and the column of the second base metal to be joined. The intersect of the
column and row gives the recommended Filler Metal Column to be used for that base
metal combination. If the box is on the top-right half of the table, switch the column and
row as only half of the table is filled in to prevent duplication. If no filler metal is listed for
a particular combination, contact MPE to determine correct filler metal.
Once a Filler Metal Column is determined from Tables I.1 through I.3, use Table I.4 to
determine the acceptable filler metals for that Column.
Unless the process is specified on the engineering drawing, Weld Filler Metals in the
same Column may be used interchangeably provided that (1) there is a qualified
procedure for that class of filler and process, (2) the electrode and process are suitable
for use in the intended welding position and within any limitations imposed on joint
accessibility by component configuration, and (3) consideration has been given to the
advisability of use of low carbon version of electrodes to avoid intergranular carbide
precipitation and reduced weld corrosion resistance, or to avoid lower weld creep and
rupture strength that may result from use of the low carbon versions. MPE shall be
consulted regarding the details of items (2) and (3).
P8A-AG3
g GE Power & Water _ Page 34 of 50
REV. U Materials and Processes Engineering
ASME
P1 P3 P3 P4 P5A P15E P11 P6 P7
No.
Low 1 Cr- ½ Mo
BASE METAL ½ 2¼ Cr- Grade 403, 405,
Carbon Corten and 1¼ Cr- ½ T-1
WELDED TO Mo 1Mo 91 410 409
Steel Mo
P8A-AG3
g GE Power & Water _ Page 35 of 50
REV. U Materials and Processes Engineering
ASME No. P8 P8 P8 P8 P8 P8
BASE METAL WELDED TO 304 304L 309, 309S, 310 316 316L 321, 347
P15E Grade 91 BT BT BT BT BT
P8 304 AE
P8 304L AE-L
P8 309, 309S, 310 AE AE-L AU/AF
P8 316 AH AH-L AH
P8 316L AH-L AH-L AH-L
P8 321, 347 AE-L AE-L BE
P43 Inconel 625 BI
- X40, X45, FSX-414 BH BH
P8A-AG3
g GE Power & Water _ Page 36 of 50
REV. U Materials and Processes Engineering
P8A-AG3
g GE Power & Water _ Page 37 of 50
REV. U Materials and Processes Engineering
P8A-AG3
g GE Power & Water _ Page 38 of 50
REV. U Materials and Processes Engineering
P8A-AG3
g GE Power & Water _ Page 39 of 50
REV. U Materials and Processes Engineering
P8A-AG3
g GE Power & Water _ Page 40 of 50
REV. U Materials and Processes Engineering
ASTM/ASME
Code NOTES GE Spec Industry Spec ASME F-No. UNS No. Trade Name
Classification
B21B44A2 A5.5 E9015/16-B3 4
B21B92A2 A5.5 E9018-B3 4
B21B156 A5.28 ER90S-B3 6
AL
None A5.23 F9PZ-EB3-B9 6
None A5.29 E91T5-B3 6
None A5.29 E9XT1-B3 6
B21B123A2 A5.1 E11018M 4
None A5.28 ER110S-1 6
AN
None A5.29 E110T5-K4 6
None A5.29 E111T1-K4 6
B21B26 AMS 5782, A5.4 E349-15/16 5 19-9 W Mo
AP
None AMS 5782, A5.9 ER349 6 19-9 W Mo
B50A485 AMS 5795BM Multimet N-155
AQ
None AMS 5794A Multimet N-155
AR obsolete
B21B35 A5.4 E410-15/16 4
AS 1, 2 B21B77 A5.9 ER410 6
None A5.22 E410TX-Y 6
A5.4 E410NiMo 4
AT 1, 2 A5.9 ER410NiMo 6
A5.22 E410NiMoTX-X 6
B21B33 A5.4 E309-15/16 5
AU 2, 3 B21B135 A5.9 ER309 6
None A5.22 E309TX-Y 6
B21B157 A5.4 E309L-15/16 5
AU-L 2, 3 None A5.9 ER309L 6
None A5.22 E309LTX-Y 6
P8A-AG3
g GE Power & Water _ Page 41 of 50
REV. U Materials and Processes Engineering
Code NOTES GE Spec Industry Spec ASTM/ASME Classification ASME F-No. UNS No. Trade Name
AY obsolete
AZ B21B111 AMS 5798 ERNiCrMo-2 43 N06002 Hastelloy X
B21B63B2 AMS 5797
BA
B21B70 AMS 5796 R30605 L-605, Haynes 25
B21B88 A5.11 ENiCrFe-3 43 W86182 Inco 182
BC
B21B110 A5.14 ERNiCr-3 43 N06082 Inco 82
None A5.11 ENiCu-7 42
BD
None A5.14 ERNiCu-7 42
B21B30 A5.4 E347-15/16 5
BE 2 B21B17 A5.9 ER347 6
None A5.22 E347TX-Y 6
BH B50A824 None Mar-M918
BI AMS 5837, A5.14 ERNiCrMo-3 43 N06625 Inconel 625
BJ same as BB
None A5.28 ER90S-B9 6
None A5.29 E100T1-B9M 6
BK 5 None A5.23 F9PX-EB9-B9 6
None A5.5 E9015-B9 4
None A5.5 E9016-B9 4
EPRI P87
BT 3, 6
AMS 5786/5787 ERNiMo-3/ENiMo-3 44 N10004 Hastelloy W
NOTE 1 Weldments between 410 and Cr-Mo steels should be limited to applications where the
operating temperature is below 950F (510 C).
NOTE 2 For FCAW electrodes, “X” may be 0 or 1, and “Y” may be 1 or 4 as appropriate for the
qualified welding procedure.
NOTE 3 See the section titled Dissimilar Metal Welds in this specification.
NOTE 4 Haynes 556 is prone to microfissuring. The filler metal listed in Col BI or Col BL are much
less prone to objectionable microfissuring.
NOTE 5 E9015-B9 is recommended over the E9016-B9 and E9018-B9, as it doesn't contain iron
powder and so eliminates one source of contaminates.
NOTE 6 EPRI P87 is available from Euroweld. EPRI P87 is preferable to Hastelloy W because
there is test data from EPRI for the P87 that is specific to dissimilar metal weld
applications. Hastelloy W chromium content is similar to EPRI P87, but it has not been
tested for viability as a dissimilar metal weld.
P8A-AG3
g GE Power & Water _ Page 42 of 50
REV. U Materials and Processes Engineering
II.1 If a preferred weld preparation does not suit the required application, the weld
preparation shall be described by the weld symbol.
II.2 Allowable tolerances on angles for weld preparation is + 2-1/2 unless otherwise
stated.
II.3 Fig. P8 is special socket weld for fuel nozzle application; use on piping components
is considerd a deviation from standard practice. Use of it requires the responsible
Design Engineering organization’s approval.
P8A-AG3
g GE Power & Water _ Page 43 of 50
REV. U Materials and Processes Engineering
P8A-AG3
g GE Power & Water _ Page 44 of 50
REV. U Materials and Processes Engineering
P8A-AG3
g GE Power & Water _ Page 45 of 50
REV. U Materials and Processes Engineering
P8A-AG3
g GE Power & Water _ Page 46 of 50
REV. U Materials and Processes Engineering
FIG. P14
P8A-AG3
g GE Power & Water _ Page 47 of 50
REV. U Materials and Processes Engineering
P8A-AG3
g GE Power & Water _ Page 48 of 50
REV. U Materials and Processes Engineering
Fig. P19
P8A-AG3
g GE Power & Water _ Page 49 of 50
REV. U Materials and Processes Engineering
1. Scope
Where Directive 97/23/EC is specifically noted in the purchase agreement or on the face
of design documentation, these additional requirements shall also be met.
2. Applicable Documents
Directive of European Parliament concerning pressure equipment.
Directive 97/23/EC of the European parliament and the Council of 29 May 1997 on the
approximation of the laws of the Member States concerning pressure equipment.
3. Qualification Requirements
3.1.1 Welding Procedure Specification (WPS) and the Procedure Qualification Report
(PQR) shall conform to the requirements of European Standard EN288.
3.1.2 For pressure equipment in categories II, III and IV, welding procedures must be
approved by a competent third party, i.e., notified body or a third-party
organization recognized by a EU Member State, at the manufacturer’s
discretion.
3.1.3 The third party must perform examinations and tests as set out in the
appropriate harmonized standards or equivalent examinations and tests or
must have them performed. This requires a certificate to be provided to indicate
that test coupons were welded in the presence of the third party. Testing is to
be done per EN 288 requirements. In addition, the third party must witness the
testing of the weld specimens. The latter may be waived if the specimens are
tested by a laboratory with ISO EN 17025 certification or equivalent (in the
USA, A2LA accreditation.)."
P8A-AG3
g GE Power & Water _ Page 50 of 50
REV. U Materials and Processes Engineering
3.2.2 For pressure equipment in categories II, III and IV, welding personnel must be
approved by a competent third party, i.e., notified body or a third-party
organization recognized by an EU Member State, at the manufacturer’s
discretion.
3.2.3 Welder approval tests must be carried out in the presence of the third party.
Specimen tests are to be done in accordance with the ASME B&PVC Section
IX and EN 287. In addition, the third party must witness the testing of the weld
specimens. The latter may be waived if the specimens are tested by a
laboratory with ISO EN 17025 certification or equivalent (in the USA, A2LA
accreditation.)."
3.2.4 Welders' Approval Certificates from the third party will be provided for all
welders approved for Pressure Equipment Directive Categories II, III and IV
applications.
4. Document Retention
Technical documentation (of which welding procedure and welder approval documents
are a part) shall be kept for a period of ten years following completion of fabrication.