Professional Documents
Culture Documents
Project Management,
Stock Control &
Investment Appraisal
Business Decision Making
Rashida Yvonne Campbell
Page 1
Contents
ASSIGNMENT TASK 3
ANSWER Q1 5
STRATEGIC INFORMATION 6
TACTICAL INFORMATION 8
OPERATIONAL INFORMATION 10
ANSWER Q2 14
ANSWER Q 6 15
ANSWER Q8 16
ANSWER Q 9 17
ANSWER Q 10 18
Assignment Task
6. Placing an order for an item of stock costs $340. The stock costs
$60 a unit, annual storage costs are 10% of purchase price. Annual
demand is 900,000 units. What is the economic order quantity?
The company requires a return of 10% per annum. Use the Net
Present Value (NPV) method to assess whether the project is viable.
MIDDLE MANAGERS
LINE MANAGERS
information is provided to the
management at higher levels
Strategic
Infor-
mation Top
Senior
Managers
LINE MANAGERS
Payroll details
Delivery Schedules
STRATEGIC
INFORMATION
Top Senior
Managers
TACTICAL INFORMATION
Professional Middle-
Managers
Answer Q 6
Placing an order for an item of stock costs $340. The stock costs $60 a
unit, annual storage costs are 10% of purchase price. Annual demand is
900,000 units. What is the economic order quantity? The Economic Order
Quantity ‘EOQ’ is the order for an item of stock which will minimise costs.
The formula is:
EOQ = √2CoD
Ch
D= Demand
Co= Costs
Ch= holding cost
Q= re-order quantity
Therefore:
Co= $340
D= 900,000
Ch= $60 x 10% = $6
900,000 = 89.91 (90) orders placed each year, so the stock cycle
10,010
A D
E
B C
8b) Critical Path is A,D,E. The critical path is identified by which events
take the longest time, the critical activities are those activities which must
be started on time otherwise the total project will be increased.
Answer Q 9
A company is wondering whether to spend $36,000 on an item of equipment, in
order to obtain cash profits as follows:
Year $
A 12,000
B 16,000
C 10,000
D 2,000
The company requires a return of 10% per annum. Use the Net Present Value
(NPV) method to assess whether the project is viable.
The Net Present Value is negative; therefore the following conclusions can
be made:
1. It is cheaper to invest elsewhere at 10% than to invest in the
project.
2. The project would earn a return of less than 10%. Since 10% of
$36,000 is $3,600.
3. The project is not viable since the PV of the costs is greater than the
PV of the benefits.
Answer Q 10
The Net Present Value of an investment at 25% is $90,000 and at 30% are
$20,000. The internal rate of return of this investment (to the nearest whole
number) is:
A: 17%
B: 20%
C: 22%
a = one interest rate at 25%
b = other interest rate at 30%
A= NPV at rate a = $90,000
B= NPV at rate b = $20,000
None of the above IRR for this investment rates are correct. The project is
NOT viable.