Safe Work Method Statement (SWMS)

ORGANISATION DETAILS

Contractor:- SEPCO III Contact


Address:-

Project Manager or Supervisor:- MR.SU Contact 059-4279115


Number &
Email:-

Person completing the SWMS:- TAMOOR SARWAR Contact 059-6478152


Number &
Email:- Tamoor.sarwar.786@gmail.com
Position:- HSE SUPV (LEAD) Reviewed By: ROMCO HSE
(Technical / Senior
Person)

Date Prepared:- 6/August/2018 Review Date:- 7/August/2018

PROJECT DETAILS

What is the Scope of the work? INSULATION & CLADDING INSTALLATION.


FGD Unit 1 & 2#

Who else was consulted / involved in ROMCO HSE DEP.


preparing this SWMS? (Internal or SEPCOIII (HSE & SITE ENGINNER).
external Senior Person)

What high risk work activities are INSULATION INSTALLATION,CLADDING,STUD WELDING.


covered by this SWMS?

References: Legislation, Codes of


Practice, and SOPs.

Other equipment involved in the Grander ,welding machine, hand tools


scope of work:

RC/HSE/SP-008/FM-013 Rev.00 Rev. Date 28 Aug 2017 Page 1 of 9


Safe Work Method Statement (SWMS)

What high risk license classes will be Trained Employees, Competent Supervisors
required to do the work? e.g. 3rd
Party Certification, training
Entry Attendant
certificates etc.

RISK MANAGEMENT

Identify each Specify the hazards What are the risks Describe your control Who is responsible for
task in order you have identified to health and measures, list as many as implementing and monitoring
safety? possible controls?
Manpower Supervisor not Various personnel Obtain PTW. conduct SEPCOIII
Organization competent for injuries toolbox talks. Supervisor SUPV.
for Insulation insulation shall be competent and
Works Activities. experience in insulation &
Supervisor not PTW cladding installation works
trained nor familiar Performer shall be a PTW
with the insulation trained. Name is at the
hazards and its Contractor PTW qualified
control measures. list Personnel nominated
Workers nominated for the grouting team shall
are not physically be competent to their
fit. respective area of
assignment.

Use of Tools, Mechanical failure Burn, cut Equipment to be inspected SEPCOIII


equipment & Failure of Tools and by a Competent Person. SUPV.
Electric Shock
machinery Equipment, Valid Inspection Sticker to
electrical shock be displayed. Current color
code to be displayed.
All tools shall be checked
before the start of the job.
Damaged tools to be

RC/HSE/SP-008/FM-013 Rev.00 Rev. Date 28 Aug 2017 Page 2 of 9


Safe Work Method Statement (SWMS)

removed from site


immediately. No loose
clothing allowed in the
vicinity of the grinding
activities.
Jewellery not to be worn at
work.
Material Physical injury due Hand Injury Ensure all materials shall SEPCOIII
handling & to be stored, handled and SUPV.
muscle
storage mishandling of used in safe manner, by
Strain, sprain.
materials. type, provide sufficient
access/egress
Pinch Point Employee shall be trained
for using safe methods in
Run over or struck handling materials. Suitable
by hand gloves to be worn.
Competent Supervision.
Workforce training in the
selection& use of tools,
material & equipment.
Inspection of all equipment
prior to use. All personnel
to undergo TBT briefing,
and PTW (where required).
Manual handling training.
Keep all body parts out of
the line of fire. Barricading
& signage.

Scaffolding Poor handling of Hand injury All scaffolding material SEPCOIII


Activities scaffolding material should be hoisted by rope SUPV.
Back pain
and pulley / gin wheels.
Cuts Loose scaffolding clamps

RC/HSE/SP-008/FM-013 Rev.00 Rev. Date 28 Aug 2017 Page 3 of 9


Safe Work Method Statement (SWMS)

Poor ground shall be hoisted with the


compaction help of tool bags.
Area survey to be
conducted before
scaffolding erection.
Ground to be compacted
properly. Use proper base /
sole plate. Scaffolding shall
be inspected and green
tagged by ROMCO HSE.
Scaffolding will be
inspected again if it is
modified. Only experienced,
certified and competent
scaffolders and supervisors
to be employed. Area to be
barricaded, Necessary
signboard to be arranged
during the erection and
dismantling of scaffolding.
scaffolding platforms are
not to be modified by
unauthorized personnel.
Working at Fall from height, Head injury Provide appropriate & SEPCOIII
Height Falling objects, standard fall protection. SUPV.
Fall
Adverse weather Scaffold must be inspected
Condition. Fractures and green Tagged. Do not
work on ladders. Use
appropriate PPE, all
personnel involved in work
at height activities must
use full body harness with
double lanyards with shock
absorber. Only trained and

RC/HSE/SP-008/FM-013 Rev.00 Rev. Date 28 Aug 2017 Page 4 of 9


Safe Work Method Statement (SWMS)

experienced personnel are


assigned for job. All tools &
parts should be secured at
height. Do not climb
ladders when holding tools,
shift tools in appropriate
containers. Barricade the
area below to restrict the
access. Scaffolding should
be tight and secured. All
works at height to be
suspended at wind speed
above 65 km/hr.
Stud Welding & Fumes / Gases Fire Cut Hot work / Naked Flame SEPCOIII
Grinding & Explosion Use of precautions to be taken for SUPV.
Burn
abrasive all welding works. Provide
Wheel. fire blanket to stop
spreading sparks. Make
proper cable management.
Engage skilled person on
the job. Where possible
flammable materials should
keep out of any area where
hot work activity is going
on. Fire extinguisher must
be there.

Application of Inhalation of Difficulties in Insulation Material shall be SEPCOIII


Insulation airborne fibers or breathing supplied with specifications SUPV.
material dust particles and manufacturers
Burn on hands
recommendations to be
Uncovered Burn on neck strictly adhered. Suitable
insulation wool sneezing PPE’s should wear as per

RC/HSE/SP-008/FM-013 Rev.00 Rev. Date 28 Aug 2017 Page 5 of 9


Safe Work Method Statement (SWMS)

MSDS recommendation. All


involved workers must Use
N95 mask as well as
disposable coverall.
Remaining insulation
material must be wrapped
with polyethylene plastic
with properly sealed.
Physical barricading is
mandatory in the area.
Small bits and piece of the
insulation material left over
the job should be safely
stored in garbage bags.
Proper housekeeping to be
ensured time to time.
Dispose insulation material
properly as per procedure.
Working in Inhalation of Toxic respiratory Obtain required Permit to SEPCOIII
Confined space gases leading to distress work & Confined Space SUPV.
death, entry permits. Conduct Gas
respiratory
Oxygen enrichment test and allow the crew to
muscle
and deficiency, perform the task. Ensure all
dysfunction,
dehydration. CSE tasks are in place-hole
Confusion,
watch, entry log sheet &
Cough, Rapid
breathing. communication among the
Sweating, group and hole watch.
Inspect all equipment on a
daily basis. Provide
adequate warning signs
and caution boards,
Provide 110v illumination.
Emergency backup
illumination shall be

RC/HSE/SP-008/FM-013 Rev.00 Rev. Date 28 Aug 2017 Page 6 of 9


Safe Work Method Statement (SWMS)

installed. Full body harness


with life line for each
entrant. Means of
communication to be made
between workforce And
their supervisor While
working in the confined
space.
C.S.E permits conditions to
be followed strictly. Drink
plenty of water to avoid
dehydration.
Fabrication of Sharp edge Cuts Only experienced SEPCOIII
cladding personnel are allowed to SUPV.
Hand injuries
material Flying objects carry-out the job. Ensure
Struck in moving the excessive waste
parts material; cut pieces, small
metal sheet bits are cleared
from worksite regularly.
Carefully deal with sharp
cut sheets. Always use
hand gloves. Be careful
about pinch points. Use
face shield during
fabrication. Provide guard
for rotating parts to avoid
flying materials. Do not
modify the protection
guards.
Installation of Cuts due to sharp Always make sure proper SEPCOIII
Cladding Flying material edges of hand gloves were used SUPV.
Lifting/lowering cladding sheet, (bare hand work strictly
cladding material forbidden)
Head injuries

RC/HSE/SP-008/FM-013 Rev.00 Rev. Date 28 Aug 2017 Page 7 of 9


Safe Work Method Statement (SWMS)

Whilst lifting and lowering


the cladding material,
ensure suitable rope and
gin wheel used and ensure
the area underneath is
barricaded
Whilst making aluminized
steel metal jacketing
/fastening with SS strap
pinch points to be taken
care.

RC/HSE/SP-008/FM-013 Rev.00 Rev. Date 28 Aug 2017 Page 8 of 9


Safe Work Method Statement (SWMS)

This SWMS has been developed in consultation and has been read, understood, and signed by all workers undertaking the scope of works.

Name: Job Title / Designation Signature & Date:

Reviewed & Approved by NOMAC HSE: Revision Number:


(Name & Signature) Date:
(This section will be filled by ROMCO HSE)

RC/HSE/SP-008/FM-013 Rev.00 Rev. Date 28 Aug 2017 Page 9 of 9