CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

PROYECTO: ¨RENOVACION DE SISTEMA DE RIEGO; EN LA BOCATOMA VINZOS, DISTRITO DE VIRU, PROVINC


DEPARTAMENTO LA LIBERTAD”

ITEM DESCRIPCION DE LA PARTIDA TOTAL MES 1 MES 2 MES 3

01 OBRAS
OBRASPROVISIONALES,
PROVISIONALESTRABAJOS PRELIMINARES, SEGURIDAD Y SALUD
01.01 14,063.27 8,063.27 2,000.00 2,000.00
01.02 TRABAJOS PRELIMINARES 102,779.43 82,223.54
01.03 SEGURIDAD EN OBRA 9,343.91 4,671.96 2,335.98
02 BOCATOMA
02.01 TRABAJOS PRELIMINARES 3,822.80 3,822.80
02.02 MOVIMIENTO DE TIERRAS 25,435.57 25,435.57
02.03 OBRAS DE CONCRETO 117,042.22 117,042.22
02.04 JUNTAS Y SELLOS 1,887.99 1,887.99
02.05 CARPINTERIA METALICA 49,296.69 49,296.69
03 BARRAJE FIJO
03.01 TRABAJOS PRELIMINARES 6,332.16 6,332.16
03.02 MOVIMIENTO DE TIERRAS 66,578.21 - 66,578.21
03.03 OBRAS DE CONCRETO 273,982.81 273,982.81
03.04 JUNTAS Y SELLOS 4,291.81 4,291.81
03.05 OTROS 2,002.91 2,002.91
04 MUROS DE CONTENCION
04.01 TRABAJOS PRELIMINARES 544.12 544.12
04.02 TRABAJOS PRELIMINARES 47,803.26 ###
04.03 OBRAS DE CONCRETO 182,816.35 ###
04.04 JUNTAS Y SELLOS 1,221.60 1,221.60
04.05 OTROS 673.63 673.63
DEFENSA RIBEREÑA
05 -
05.01 TRABAJOS PRELIMINARES 10,719.58 10,719.58
05.02 DIQUES DE ENCAUZAMIENTO
05.02.01 MOVIMIENTO DE TIERRAS 88,475.64 88,475.64
04.02.02 ENROCADO 327,559.23 114,645.73
06 CANAL DE CONCUCCION
06.01 TRABAJOS PRELIMINARES 314.83 -
06.02 MOVIMIENTO DE TIERRAS 27,685.29 -
06.03 OBRAS DE CONCRETO 68,305.30 -
06.04 JUNTAS Y SELLOS 4,588.27
07 OTROS 13,015.36 3,253.84 3,253.84 3,253.84
COSTO DIRECTO 1,450,582.24 295,697.88 244,644.96 568,286.51
GASTOS GENERALES (10%) 145,058.22 29,569.79 24,464.50 56,828.65
UTILIDAD (5%) 72,529.11 14,784.89 12,232.25 28,414.33
=========================== =========== ============
SUBTOTAL 1 1,668,169.58 340,052.56 281,341.70 653,529.48
IGV (18%) 300,270.52 61,209.46 50,641.51 117,635.31
========================== =========== ============
TOTAL PRESUPUESTO 1,968,440.09 401,262.02 331,983.21 771,164.79
TOTAL MENSUAL DE AVANCE 401,262.02 331,983.21 771,164.79
TOTAL ACUMULADO DE AVANCE 401,262.02 733,245.23 ###
PORCENTAJE MENSUAL DE AVANCE 20.38% 16.87% 39.18%
PORCENTAJE ACUMULADO DE AVANCE 20.38% 37.25% 76.43%
A VALORIZADO DE AVANCE DE OBRA
RIEGO; EN LA BOCATOMA VINZOS, DISTRITO DE VIRU, PROVINCIA VIRU,
DEPARTAMENTO LA LIBERTAD”

MES 4 TOTAL

2,000.00 14,063.27
20,555.89 102,779.43
2,335.98 9,343.91

3,822.80
25,435.57
117,042.22
1,887.99
49,296.69

6,332.16
66,578.21
273,982.81
4,291.81
2,002.91

544.12
47,803.26
182,816.35
1,221.60
673.63

10,719.58

88,475.64
212,913.50 327,559.23

314.83 314.83
27,685.29 27,685.29
68,305.30 68,305.30
4,588.27 4,588.27
3,253.84 13,015.36
341,952.89 ###
34,195.29 145,058.22
17,097.64 72,529.11
============= ============
393,245.83 ###
70,784.25 300,270.52
============= ============
464,030.08 ###
464,030.08
1,968,440.10
23.57%
100.00%
S10 Página

Presupuesto
Presupuesto 0402005

Subpresupuest 001
oCliente S10 S.A. Costo al 31/08/2017
Lugar LA LIBERTAD - TRUJILLO - VIRU

Item Descripción Und. Metrado Precio S/. Parcial S/.

01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD_x000D_ 169,554.27


01.01 OBRAS PROVISIONALES 13,684.79
01.01.01 CONSTRUCCIONES PROVISIONALES 11,684.79
01.01.01.01 OFICINA m2 30.00 54.12 1,623.60
01.01.01.02 ALMACEN m2 60.00 50.03 3,001.80
01.01.01.03 SS.HH. DE OBRA u 4.00 360.00 1,440.00
01.01.01.04 COMEDOR m2 70.00 54.12 3,788.40
01.01.01.05 CARTEL DE OBRA m2 11.52 158.94 1,830.99
01.01.02 INSTALACIONES PROVISIONALES_x000D_ 48,570.58
01.01.02.01 ENERGIA ELECTRICA PROVISIONAL 48,570.58
01.01.02.01.01 CONEXION E INSTALACION_x000D_ glb 1.00 1,000.00 1,000.00
01.01.02.01.02 CONSUMO Y MANTENIMIENTO glb 1.00 1,000.00 1,000.00
01.01.02.01.03 DESVIO DE RIO glb 1.00 46,570.58 46,570.58
01.02 TRABAJOS PRELIMINARES_x000D_ 121,104.85
01.02.01 MOVILIZACIÓN DE CAMPAMENTO, MAQUINARIA Y HERRAMIENTAS_x000D_ glb 1.00 102,451.18 102,451.18
01.02.02 LIMPIEZA Y ELIMINACION DE MALEZA Y ARBUSTOS DE FACIL EXTRACCION_x000D_ m2 3,500.00 0.41 1,435.00
01.02.03 TRAZO, NIVELACIÓN Y REPLANTEO EN PUENTE_x000D_ km 6.48 444.29 2,879.00
01.02.04 CONTROL TOPOGRAFICO EN PUENTE_x000D_ ha 32.29 444.09 14,339.67
01.03 SEGURIDAD EN OBRA 34,764.63
01.03.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y glb 1.00 4,349.60 4,349.60
01.03.02 SALUD EN ELDE
EQUIPOS TRABAJO
PROTECCION PERSONAL glb 1.00 19,794.63 19,794.63
01.03.03 EQUIPOS DE PROTECCION COLECTIVA glb 1.00 3,240.00 3,240.00
01.03.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 1,743.40 1,743.40
01.03.05 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 2,870.00 2,870.00
01.03.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD EN EL glb 1.00 2,767.00 2,767.00
02 TRABAJO
ESTRUCTURAS 4,408,981.61
02.01 FALSO PUENTE 563,687.36
02.01.01 FALSO PUENTE DE MADERA ROLLIZA_x000D_ p2 148,338.78 3.80 563,687.36
02.02 EXCAVACIONES 117,424.91
02.02.01 EXCAVACION PARA ESTRUCTURAS BAJO EL AGUA_x000D_ m3 33,454.39 3.51 117,424.91
02.03 RELLENO 156,311.35
02.03.01 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 25,489.93 4.58 116,743.88
02.03.02 ELIMINACION DE MATERIAL EXCEDENTE m3 9,557.36 4.14 39,567.47
02.04 CAPA FILTRANTE PARA ESTRUCTURAS 3,981.12
02.04.01 OVER SIDE (E= 0.50M)_x000D_ m3 124.80 31.90 3,981.12
02.05 OBRAS DE CONCRETO SIMPLE_x000D_ 212,514.88
02.05.01 CONCRETO SIMPLE F'C=145 kg/cm2_x000D_ m3 797.16 266.59 212,514.88
02.06 OBRAS DE CONCRETO ARMADO 3,005,189.16
02.06.01 ZAPATAS 951,995.10
02.06.01.01 CONCRETO PARA ZAPATAS f'c=280 kg/cm2 m3 1,044.14 406.35 424,286.29
02.06.01.02 ENCOFRADO DE ZAPATAS m2 1,215.14 37.79 45,920.14
02.06.01.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 127,457.32 3.78 481,788.67
02.06.02 ESTRIBOS 1,201,349.76
02.06.02.01 CONCRETO PARA ESTRIBOS f'c=280 kg/cm2 m3 1,129.97 406.35 459,163.31
02.06.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA PARA ESTRIBOS_x000D_ m2 1,575.18 37.79 59,526.05
02.06.02.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 180,597.99 3.78 682,660.40
02.06.03 VIGAS 625,725.48
02.06.03.01 CONCRETO PARA VIGAS f'c=280 kg/cm2 m3 287.28 404.82 116,296.69
02.06.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN VIGAS_x000D_ m2 1,335.33 52.85 70,572.19
02.06.03.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 116,099.63 3.78 438,856.60
02.06.04 LOSAS MACIZAS 226,118.82
02.06.04.01 CONCRETO PARA LOSAS MACIZAS f'c=280 kg/cm2 m3 230.00 404.82 93,108.60
02.06.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN LOSA MACIZA_x000D_ m2 600.00 52.85 31,710.00
02.06.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 26,799.00 3.78 101,300.22
02.07 VARIOS 349,872.83
02.07.01 BORDE CORTANTE DE CAISSONS L8"X8"X1/2_x000D_ m 153.00 163.19 24,968.07
02.07.02 APOYO DE NEOPRENO u 20.00 3,211.19 64,223.80
02.07.03 TUBO DE DRENAJE D=3"L=0.80m u 25.00 10.65 266.25
02.07.04 BARANDA METALICA m 200.00 163.61 32,722.00
02.07.05 RIEGO DE LIGA m2 610.00 4.86 2,964.60
02.07.06 CARPERA ASFALTICA EN FRIO 2" m2 610.00 45.34 27,657.40
02.07.07 PRUEBA DE CARGA glb 1.00 3,812.81 3,812.81
02.07.08 ENTIBADO DE PILARES_x000D_ m2 464.11 20.89 9,695.26
02.07.09 BOMBEO DE AGUA FREATICA_x000D_ h 8,640.00 17.32 149,644.80
02.07.10 CONSTRUCCION DE POZO PARA DRENAJE_x000D_ u 4.00 8,479.46 33,917.84
03 DEFENSA RIBEREÑA - ENROCADO_x000D_ 1,453,102.71
03.01 ENCAUZAMIENTO DE CURSOS DE AGUA R=1,000 m3/día m3 109,220.46 1.29 140,894.39
03.02 EXCAVACION PARA ESTRUCTURAS BAJO AGUA EN MATERIAL COMUN m3 42,219.69 3.51 148,191.11
03.03 EXCAVACION P/ ESTRUCTURAS EN MATERIAL COMUN EN SECO - ANCLAJES - MANUAL m3 143.93 30.51 4,391.30
03.04 RELLENO ESTRUCTURAS CON MATERIAL PROPIO m3 90,107.37 5.08 457,745.44
03.05 GEOTEXTIL 300 gr/m2 m2 20,137.93 8.80 177,213.78
03.06 ENROCADO DE PROTECCION m3 9,835.08 32.02 314,919.26
03.07 ELIMINACION DE MATERIAL EXCEDENTE m3 50,663.63 4.14 209,747.43
04 SEÑALIZACION 136,496.08
04.01 SEÑALES INFORMATIVAS m2 9.06 391.46 3,546.63
04.02 SEÑAL REGLAMENTARIA u 2.00 506.68 1,013.36
04.03 SEÑALES PREVENTIVAS u 1.00 506.68 506.68
04.04 ESTRUCTURA DE SOPORTE PARA SEÑAL INFORMATIVA u 4.00 230.00 920.00
04.05 GUARDAVIAS m 610.70 211.16 128,955.41
04.06 MARCAS EN EL PAVIMENTO m 100.00 15.54 1,554.00
05 ACCESOS AL PUENTE 223,993.30
05.01 MOVIMIENTO DE TIERRAS 223,993.30
05.01.01 RELLENO CON MATERIAL PROPIO _x000D_ m3 16,943.48 5.08 86,072.88
05.01.02 CONFORMACION Y COMPACTACION DE SUBRASANTE m2 2,280.46 1.69 3,853.98
05.01.03 BASE AFIRMADO E = 20cm. m2 2,190.44 7.00 15,333.08
05.01.04 ENROCADO DE PROTECCION m3 3,708.10 32.02 118,733.36
06 IMPACTO AMBIENTAL 15,374.38
06.01 PROGRAMA DE MEDIDAS PREVENTIVAS, CORRECTIVAS Y COMPENSATORIAS 13,086.38
06.01.01 TRATAMIENTO DE AGUAS RESIDUALES_x000D_ u 2.00 1,450.00 2,900.00
06.01.02 REFORESTACION DEL AREA DE CAMPAMENTOS Y PATIO DE MAQUINAS ha 0.08 3,123.85 249.91
06.01.03 DEPOSITO DE DESECHOS_x000D_ m3 6,022.10 1.65 9,936.47
06.02 PROGRAMA DE SEGUIMIENTO Y MONITOREO AMBIENTAL 1,200.00
06.02.01 MONITOREO DE AIRE, AGUA Y RUIDO u 1.00 1,200.00 1,200.00
06.03 PROGRAMA DE ABANDONO DE OBRA 1,088.00
06.03.01 LIMPIEZA Y RESTAURACION DE CAMPAMENTO_x000D_ m2 300.00 1.36 408.00
06.03.02 LIMPIEZA Y RESTAURACION DEL PATIO DE MAQUINAS m2 500.00 1.36 680.00
COSTO DIRECTO 6,454,072.93
GASTOS GENERALES 10% 645,407.29
UTILIDAD 5% 322,703.65
---------

SUBTOTAL 7,422,183.87
IMPUESTO (IGV) 18% 1,335,993.10
=========

TOTAL PRESUPUESTO 8,758,176.97

SON : OCHO MILLONES SETECIENTOS CINCUENTIOCHO MIL CIENTO SETENTISEIS Y 97/100 NUEVOS SOLES
1

31/08/2017

Parcial S/.

169,554.27
13,684.79
11,684.79
1,623.60
3,001.80
1,440.00
3,788.40
1,830.99
48,570.58
48,570.58
1,000.00
1,000.00
46,570.58
121,104.85
102,451.18
1,435.00
2,879.00
14,339.67
34,764.63
4,349.60
19,794.63
3,240.00
1,743.40
2,870.00
2,767.00
4,408,981.61
563,687.36
563,687.36
117,424.91
117,424.91
156,311.35
116,743.88
39,567.47
3,981.12
3,981.12
212,514.88
212,514.88
3,005,189.16
951,995.10
424,286.29
45,920.14
481,788.67
1,201,349.76
459,163.31
59,526.05
682,660.40
625,725.48
116,296.69
70,572.19
438,856.60
226,118.82
93,108.60
31,710.00
101,300.22
349,872.83
24,968.07
64,223.80
266.25
32,722.00
2,964.60
27,657.40
3,812.81
9,695.26
149,644.80
33,917.84
1,453,102.71
140,894.39
148,191.11
4,391.30
457,745.44
177,213.78
314,919.26
209,747.43
136,496.08
3,546.63
1,013.36
506.68
920.00
128,955.41
1,554.00
223,993.30
223,993.30
86,072.88
3,853.98
15,333.08
118,733.36
15,374.38
13,086.38
2,900.00
249.91
9,936.47
1,200.00
1,200.00
1,088.00
408.00
680.00
6,454,072.93
645,407.29
322,703.65
---------

7,422,183.87
1,335,993.10
=========

8,758,176.97