You are on page 1of 23

T3 Top‐Up course ELS part I of II 2011/4/29

Objectives of ELS System


• Provide structural support with adequate margin of factor of safety to facilitate the 
HKIE Geotechnical Division &
excavation under lateral earth pressures & possible surcharges
Department of Civil Engineering, The University of Hong Kong
• Without impair the integrity of the surrounding roads & properties
Top‐up course for TCP T3 on GIFW and Building Works with significant geotechnical content

Excavation and Lateral Support
Excavation and Lateral Support
Part I

Ir. James Sze

Associate Director
Ove Arup & Partners HK Ltd
Nicholl Highway before collapse After collapse on 20 Apr 2004

1 2

Content
Part I
• Common retaining walls for excavation works
• Common lateral support systems
• Basement construction sequence
• Design and submission procedures
• Geotechnical design & considerations Common Retaining Walls for 
• Structural designs
g
• Points to note in ELS Design Excavation Works
Part II
• Site supervision requirement
• Technical supervision & reminders
• Instrumentation and monitoring
• Pumping test issues and a lesson learnt
• Case histories to illustrate key issues during site supervision – Police HQ III, 
TSTE Extension over CHT, TKR development, HKPolyU School of Hotel & 
Tourist Management
3 4

Commonly Embedded Wall Types in Hong Kong Temporary Channel Planking


Steel – usually temporary • Aligned channel 
sections
• Channel planking
• Suitable of shallow 
• Sheet pile wall excavation above  Adjacent building
• Pipe pile wall groundwater table, eg. 
• Soldier pile wall pile cap construction
• Usually “pushed” or 
Cast in situ Reinforced Concrete may be permanent
Cast in‐situ Reinforced Concrete – may be permanent vibrated into ground
g
• Able to be extracted 
• Secant pile/contiguous bored pile (RCD) wall afterwards
• Diaphragm (slurry) wall

Other less common ones – not covered

• Soil‐cement mix wall
• Pre‐cast diaphragm wall

5 6

Ir. James Sze, Ove Arup & Partners HK Ltd. 1
T3 Top‐Up course ELS part I of II 2011/4/29

Temporary Sheet Pile Walls Temporary Sheet Pile Wall – Hammer

• In basement construction usually used for temporary support
• Coupled sheet pile sections are effective in terms of strength/mass ratio
• Vibrator and drop/hydraulic hammer are common installation method
• Noise and vibration controls could inhibit use of sheet piles in urban areas
• Jacking method is available but less common
• In weathered rocks and colluvium, hard corestones and boulders are the 
obstacles whereas in fill the problems are boulders old foundation and
obstacles, whereas in fill, the problems are boulders, old foundation and 
seawalls. Pre‐boring through obstructions may be required
• Seepage cut‐off performance generally satisfactory but provision of grout 
curtains beneath toe may be necessary in deep excavations
• Usually left‐in with top few metres trimmed upon completion of permanent 
structures
Typical Larrsen 6 to 15W, FSP I to VI

7 8

Temporary Sheet Piling – Vibrator / Giken Sheet Pile Wall Installation


(Silent) Piling

Method Application Limitation


• Readily available in HK  • Noise & vibration 
Vibratory/ Drop  • Efficient • Restricted working hour
Hammer  • Cheap • High head room required
• Cause ground settlement
• Quiet • Heavy counter weight is  
• Soft/weak ground only required
Jack‐In System • High head room
• Large working space

• Limited head room • Expensive
• Limited work space •Limited trained local 
Giken System • Soft/weak ground operators
• Tight alignment tolerance
E.g. East Rail Mody Road Subway, CLP Cable 
Tunnel TWS access shaft 

9 10

Pipe Pile Walls Pipe Pile Wall – ODEX with Air Flushing
• ODEX or similar construction technique has been used to overcome the 
problem of inadequate penetration when driving sheet piles through 
weathered rock with corestones and through old foundations.
• By carrying a circular hollow section with the drillbit, it forms pipe piles.

Expandable wings
Circular hollow 
section
Typical 219mm dia. – 610mm dia. CHS

11 12

Ir. James Sze, Ove Arup & Partners HK Ltd. 2
T3 Top‐Up course ELS part I of II 2011/4/29

Concentric Drilling & Close loop drilling Pipe Pile Wall Installation
• Concentric drilling ‐ less disturbance to surrounding ground due to better air‐
flow
• Close loop drilling – air only used for powering the hammering action. Low 
pressure water/bentonite used lifting debris

1: advance ODEX drill bit  2: terminate the drill bit at  6: completed pile


into ground with steel  design founding level
ODEX drill bit Concentric/ringbit drill bit CHS followed

13 14

Pipe Pile Wall Installation Soldier Pile Wall

• Soldier pile walls have two basic components : Soldier pile (vertical component) 
& Lagging (horizontal component)
• Soldier piles are either driven or placed in pre‐drilled holes, which are  
backfilled to the ground surface with lean concrete
• Excavate in lifts, weld on channel or steel plate lagging between the soldier 
piles
• Lagging serves as a secondary support to soil face and prevents progressive 
Mixing of cement grout
Mixing of cement grout
deterioration of soil arching between the piles
• Requires moderately dry ground conditions and soil with sufficient strength to 
maintain vertical face prior to support from horizontal lagging

Installation of pipe pile
Tremie grouting

15 16

Soldier Pile Wall Soldier Pile Wall Installation

1: ODEX drilling onto  2: extract ODEX bit & change  3: clean the hole & 


sound bedrock with  to down‐the‐hole hammer to  lower H‐pile section
temporary casing form rock socket

17 18

Ir. James Sze, Ove Arup & Partners HK Ltd. 3
T3 Top‐Up course ELS part I of II 2011/4/29

Soldier Pile Wall Installation Soldier Pile Wall Installation

Installation of H‐pile section
4: tremie grout to cut‐ 5: extract temporary casing,  6: completed pile
Mixing of cement grout
off level top up grout level

19 20

Soldier Pile Wall Installation Contiguous/Secant Bored Pile Wall


• Contiguous piles: bored or CFA piles built 
to be almost touching. Typically nominal 
50mm gap between adjacent piles
• Secant piles: interlocking concrete piles 
formed using bored  or CFA equipment. 
Spacing to suit verticality tolerances but 
typically 50mm to 100mm overlap 
between piles
• Hard‐soft wall: concrete ‘male’ piles 
H d ft ll t ‘ l ’ il
interlocking with low strength 
unreinforced female piles. Built using 
bored or CFA equipment. Spacing of male 
piles typically 1.2 to 1.3D
• It provides a near water‐proof wall for 
Tremie grouting Extraction of temporary casing both the temporary and permanent soil 
support.

Typical 0.8 – 3.0m
21 22

Contiguous/Secant Bored Pile Wall Contiguous/Secant Bored Pile Wall Installation

Secant pile wall 
Guide wall 

Cantilever contiguous 
bored pile wall 

23 24

Ir. James Sze, Ove Arup & Partners HK Ltd. 4
T3 Top‐Up course ELS part I of II 2011/4/29

Conventional Bored Pile Construction (1 of 2) Conventional Bored pile Construction (2 of 2)


Concrete 
water
delivery

1: Grabbing out soil with  2: RCD to excavate rock if  3: Install steel cage,  4: Concreting and tremie  5:  Removal of 


casing advanced necessary airlifting record temporary casing

25 26

Alternative Bored Pile Construction (1 of 2) Alternative Bored Pile Construction (2 of 2)

Recycling of 
bentonite

Soil Soil

Rock Rock

1: Guide casing & excavate in soil & rock 2: Cage installation 3: Tremie Concreting 4: Casing extraction

27 28

Diaphragm (Slurry) Wall Diaphragm Wall


• Continuous wall built in aligned discrete panels typically of 4m to 6m in length 
(on plan). Wall thickness 800mm to 1500mm
Panel 
• Diaphragm wall techniques was used extensively in the construction of  the  length
MTR underground stations and of deep basements for high‐rise buildings 
(temporary as well as permanent walls)
• Trench excavated under bentonite slurry support. Cable grabs still used but 
hydraulically operated trench cutter machines becoming more common
• Usually cast in‐situ. Pre‐cast panels can be used but limited to relatively 
Usually cast in situ Pre cast panels can be used but limited to relatively
shallow depth by lifting weight of individual units
• Bentonite slurry properties and net slurry pressure are key factors in 
maintaining stability of the trench so proper site quality control is vital 
• Guide wall to maintain slurry head, guide position & orientation, provide 
temporary support for cage installation

Typical 0.8m thk. – 1.5m thk.
29 30

Ir. James Sze, Ove Arup & Partners HK Ltd. 5
T3 Top‐Up course ELS part I of II 2011/4/29

Diaphragm Wall Construction (1 of 3) Diaphragm Wall Construction (2 of 3)

guidewall

grabbing

A trench 
cutter or 
hydrofraise

31 32

Diaphragm Wall Construction (3 of 3)

Common Lateral Support Systems

Cage installation Tremie concreting

33 34

Overview of Typical Lateral Support Systems Cantilever Wall

Bottom‐up construction
• Cantilever
• Braced (struts or alike)
• Tie‐back

Top‐down construction
p
• Permanent slab

35 36

Ir. James Sze, Ove Arup & Partners HK Ltd. 6
T3 Top‐Up course ELS part I of II 2011/4/29

Fully Braced Temporary Support Raking Struts

37 38

Tubular Propping No Strut – Special Case (Hoop Stress)


Ring beams for safety 
precaution

Strut action by 
internal hoop stress of 
the ring

Φ76m shaft formed by diaphragm wall cofferdam, 
excavation depth = 26m at ICC, Kowloon

39 40

Comparison of Different Strutting Systems Tied-back or Anchors


• Deadman anchor system
Types of Strutting Advantages Disadvantages
• Grouted anchor system
System
• Soil nails
Cantilever (no strut) Unobstructed clear Impedes construction
working space for
mucking out
Cross-lot strutting Suitable for narrower Impedes construction
excavations
Raking strutting Suitable for large Slow and radically
excavation in plan rather constraints programme
than in depth and access
Diagonal strutting Suitable for small and Structural elements can
preferably square be very large
excavation
Circular cofferdam Unobstructed clear Very tight control on
working space for positional and verticality
mucking out tolerances, required site
in particular shape

41 42

Ir. James Sze, Ove Arup & Partners HK Ltd. 7
T3 Top‐Up course ELS part I of II 2011/4/29

Deadman Tie-back/Anchor System Temporary Ground Anchor – less common in HK


Cable strands ‐ rely on high 
preload instead of stiffness

Rely on passive resistance in 
front of deadman

e.g. Festival Walk

43 44

Temporary Tie-back/Soil Nail Permanent Slabs – Top-down Construction


Completed G/F Slab

Completed B1 Slab

Excavation for B2

Diaphragm Wall

e.g. Tin Kwong Road development
45 46

Bottom-up Construction

Basement Construction Sequence

e.g. IFCII and many other building projects

47 48

Ir. James Sze, Ove Arup & Partners HK Ltd. 8
T3 Top‐Up course ELS part I of II 2011/4/29

Top-down Construction Basement Slab as Prop during Top-down

E.g. Chater House, Hongkong Station

49 50

Partial Top-down to Allow Tower Bottom-up

Tower 
portion to 
be in 
bottom‐up Design Aspects

Ring slabs as Lateral 
Support

E.g. Langham Place
51 52

Design Procedure
Is an embedded retaining wall  N Consider alternative construction 
methods e.g. open cut excavation, 
necessary? gravity retaining wall
Y

Design  Interactive Construction 


considerations considerations

• Establish geological model
Design and Submission Procedures • Determination
Determination & selection of 
& selection of
Select wall type and 
Select wall type and
construction sequence geotechnical and structural 
parameters and assumptions
• Selection of design codes
Analysis • Design calculation or computer 
modelling to derive loads on the ELS 
system
N
Filling objectives? • Mechanical stability check – overall 
sliding, overturning, toe kick
Y
• Hydraulic failure check
A • Movement prediction

53 54

Ir. James Sze, Ove Arup & Partners HK Ltd. 9
T3 Top‐Up course ELS part I of II 2011/4/29

Design Procedure (cont’)


A

Geotechnical and structural design of wall and 
associated works, eg. grouting

Structural design of shoring systems and other 
protection measures, eg. underpinning works

Prepare drawings and specification
BD Submission Issues
Approval & Consent Construction & approval in 
parallel if minor change

Site Construction
Modify design
Site supervision to validate the design assumptions, 
interpret actual ground response

Completion of works

55 56

Requirements for ELS Plan under Buildings ELS Plans Required for Approval
Ordinance
• Guidelines in APP‐57 (PNAP148)
• B(A)R8(1)(bc) • When excavation is deeper than 4.5m and greater than 5m in length
• Bulk excavation, even shallow, can be dangerous if not properly  • Liable to affect any road, building, structure, slope steeper than 30o or 
designed water main 75mm in diameter or greater
• ELS plans are required to be approved where excavations of 
substantial depth are to be carried out

57 58

ELS Work Submission shall include :- ELS Work Submissions

• existing conditions of site and surrounds;
• foundation details of adjoining structures; • RSE to prepare and sign plans, structural design and structural 
assessment report of effects of excavation and dewatering on 
• a schedule of geotechnical design parameters and  assumptions; adjoining structures, especially sensitive ones
• details and sequence of construction;
• assessment documents on topography, geology, groundwater,  • RGE to prepare and sign supporting documents to substantiate soil 
utilities, water mains, drains, etc; parameters and soil movements, such as geotechnical assessment 
• design calculations for lateral support systems; and reports
• assessment of effects on adjacent buildings and surrounds;
assessment of effects on adjacent buildings and surrounds;
• monitoring particulars for adjacent buildings, ground movements and 
water table;
• grouting and pumping test proposal, if necessary.

59 60

Ir. James Sze, Ove Arup & Partners HK Ltd. 10
T3 Top‐Up course ELS part I of II 2011/4/29

ELS Work Submissions Typical Statutory Procedure


To be submitted either Ground investigation

• in one submission; or
Submission of retaining wall design 
• in 2 stages (submission) (Stage 1 of ELS design)
• 1st stage ‐ pile wall system (e.g. sheet pile,  2 months
diaphragm wall, etc) with assumptions on  Consent for installation of vertical  Submission of structural design 
of shoring works (Stage 2 of ELS 
shoring system, such as capacity and stiffness wall and grouting (if any)
design)
1 month
• 2nd stage ‐ detailed arrangement & structural 
Install vertical elements, grouting  2 months
2 months
details of lateral support system
details of lateral support system works (if any), submit as‐built  Submission of permanent 
records, consent for pumping test basement structures or alike
1 month
Consent for shoring works  2 months
Carry out pumping test, submit  installation
report on success, consent for 
excavation Consent for construction of 
1 month
1 month permanent works
Carry out excavation and install  1 month
shoring
Construct Permanent Basement 
Reaching final formation level Structures or Alike

61 62

Design Considerations for ELS System

Primary factors
• Location of the site – urban area might have stringent requirement due to the 
consequence‐to‐life and consequence‐to‐economic. 
• Ground and groundwater conditions in and surrounding the site

Geotechnical Design & Considerations • Development history of the site – artificial obstructions, space to install 


temporary wall etc.
• Proximity & types of existing buildings, roads, tunnels and utilities in the 
vicinity – risk can be tolerated by these properties, eg. buildings rest on 
shallow foundation  high risk
• Movements associated with particular wall and shoring systems

63 64

Design Considerations for ELS system Geological Model

Secondary Factors
• Constructability  ‐ local resources, common sizes or construction technique Fill
column cofferdam
• Construction time and economic considerations – time vs cost usually does not 
Alluvium
co‐exist
• Short‐term vs long‐term retaining wall – if RC wall used do consider dual  Core Sand Fill CDG
functions, aware of water‐proofness requirement of basement or alike
• Flexibility of the system – bottom‐up give more buffer to finalisation of slab 
Alluvium
levels and column grids etc.
• Robustness – cantilever rigid wall vs flexible wall + strut ‐ Mat Foundation
16mP Weathered 
D
Fault Zone Dipping 
Rock
40‐500 

Bedrock

2‐D 3‐D plus geological interpretation

65 66

Ir. James Sze, Ove Arup & Partners HK Ltd. 11
T3 Top‐Up course ELS part I of II 2011/4/29

Selection of Design Line & Parameters Geotechnical Design Codes/Guides


'N' value (blows/300mm)

0 50 100 150 200 • GEOGUIDE 1 2nd Ed.


5

• GCO Publication No. 1/90
0
• Zoning for large site • CIRIA Report C580 (limit states design)
-5 • Usually adopt lower 
conservative line –
-10 lower quartile
Elevation (mPD))

-15

-20

-25

-30

-35

-40

67 68

Loads to be Resisted by ELS System Methods of Analysis


• Lateral soil pressure
• Hand calculations – e.g. charts in GCO Publication No. 1/90
• Groundwater pressure (usually major factor in Hong Kong) • Sub‐grade Reaction Method – e.g. Wallap, FREW
• Lateral forces due to adjacent structures or construction surcharge eg.  • Pseudo‐finite element method – e.g. FREW, Wallap
hoarding, truck load • 2‐D finite element/finite difference method – e.g. Plaxis, SAFE, FLAC
• Vertical forces, such as temporary traffic deck, permanent column loads • 3‐D finite element/finite difference method – e.g. 3‐D FLAC, DYNA 3D

69 70

BM, SF, Prop force by Limit Equilibrium Apparent Pressure Diagrams for Computing
• Factor of safety on Pp = 
Strut Loads in Multi-strutted Excavations
2.0 to determine toe‐in 
requirement

Peck (1969)

Navfac, DM7
71 72

Ir. James Sze, Ove Arup & Partners HK Ltd. 12
T3 Top‐Up course ELS part I of II 2011/4/29

Toe Stability Check Pseudo-FE Program – eg. FREW


Features of FREW
• Factor of safety on Pp = 2.0 to 
determine toe‐in requirement
• Flexible retaining wall analysis
• Staged analysis
• Ms = 0 for cantilever or single 
propped wall • Wall modelled as elastic beam elements
• Soil modelled as elasto ‐ plastic
• Soil each side uses full stiffness matrix
• Allowance for redistribution and arching
• Long term creep of the wall
• Built‐in partial factors
• Built‐in close form solutions for Ka & Kp

Figure 29, GCO 1/90 (NAVFAC, 1982b)

73 74

Example illustrating FREW staged Analysis Example illustrating FREW staged Analysis

15kPa 15kPa

75 76

Example illustrating FREW staged Analysis Example illustrating FREW staged Analysis

15kPa 15kPa

77 78

Ir. James Sze, Ove Arup & Partners HK Ltd. 13
T3 Top‐Up course ELS part I of II 2011/4/29

Example illustrating FREW staged Analysis FREW Output

15kPa 15

10

Allow creep
5

‐5

Water Pressure
Actual Pressures
Pressure Limits
‐10 ‐250 ‐125 0 125 250
Pressure [kPa]

STAGE 0 : Initial condition
79 80

FREW Output FREW Output


Displacement [mm] Displacement [mm]
‐25 ‐12.5 0 12.5 25 ‐25 ‐12.5 0 12.5 25
15 15

10 10 229.21 kN/m

5 5

0 0

‐5 ‐5
Water Pressure Water Pressure
Actual Pressures Actual Pressures
Pressure Limits Pressure Limits
Displacements Displacements
‐10 ‐250 ‐125 0 125 250 ‐10 ‐250 ‐125 0 125 250
Pressure [kPa] Pressure [kPa]

STAGE 1 : dig to 8.5 STAGE 2 : prop at 9, dewater & dig to +1.5
81 82

FREW Output FREW Output


Displacement [mm] Displacement [mm]
‐25 ‐12.5 0 12.5 25 ‐25 ‐12.5 0 12.5 25
15 15

94.21 kN/m 146.79 kN/m
10 10

5 5

27.60 kN/m 160.48 kN/m

0 0

‐5 ‐5
Water Pressure Water Pressure
Actual Pressures Actual Pressures
Pressure Limits Pressure Limits
Displacements Displacements
‐10 ‐250 ‐125 0 125 250 ‐10 ‐250 ‐125 0 125 250
Pressure [kPa] Pressure [kPa]

STAGE 3 : permanent slabs, remove temporary prop STAGE 4 : Relax wall & props
83 84

Ir. James Sze, Ove Arup & Partners HK Ltd. 14
T3 Top‐Up course ELS part I of II 2011/4/29

Max. BM & Deflection during Temporary


BM & Deflection in Long Term Stage
Stage
Bending [kNm/m] Bending [kNm/m]
‐1000 ‐500 0 500 1000 ‐1000 ‐500 0 500 1000
15 15

94.21 kN/m 146.79 kN/m
10 10

5 5

27.60 kN/m 160.48 kN/m

0 0

‐5 ‐5

Bending Bending
Displacements Displacements
‐10 ‐25 ‐12.5 0 12.5 25 ‐10 ‐25 ‐12.5 0 12.5 25
Displacement [mm] Displacement [mm]

STAGE 3  (permanent slabs, remove temporary prop) STAGE 4 (Allow wall & slabs relaxation)
85 86

FEM Analysis FEM Analysis

Ground movement and forces in wall

Able to analysis interaction of the 
ELS works with external elements, 
such as buildings on raft – usually 2‐
D

87 88

3-D FE Analysis – eg. Dyna 3-D Groundwater Control

An effective seepage cut‐off shall be provided such that 

• to avoid excessive groundwater drawdown outside the site which may affect 
the groundwater regime of the surroundings, e.g. KCRC Lok Ma Chau Spurline 
through wetland

• to prevent the adjacent structures from excessive settlement due to increase 
in effective stress or loss of fine materials, e.g. most excavation sites in urban 
area

Able to analysis 3‐D effect of and 
excavation and interaction with external 
elements, such as tunnel crossing which is 
not a 2‐D problem

89

Ir. James Sze, Ove Arup & Partners HK Ltd. 15
T3 Top‐Up course ELS part I of II 2011/4/29

FEM Seepage Analysis Hydraulic cut-off to Prevent Piping

91 92

Control of Groundwater at Passive Zone Ground Settlement Estimation - Empirical


Pump well to control pore water 
Fill pressure (piezometric head is more 
critical)
Alluvium

CDV

Rock

94

Ground Settlement Estimation –FEM Program Building/Ground Settlement Control

Rule of thumb
• Total settlement usually limited to 25mm for buildings or alike. Ground 
settlement  may be relaxed to 50mm in some cases
• Differential settlement usually limited 1:500

95 96

Ir. James Sze, Ove Arup & Partners HK Ltd. 16
T3 Top‐Up course ELS part I of II 2011/4/29

Relative Deflection Approach for Buildings Degree of Building Damage


Relationship of Damage Category to Deflection
• Boscardin & Cording (1989) Ratio and Horizontal Tensile Strain

0.4
• Burland et al (1997)
0.35

n Ratio,  / L (%)
0.3

0.25
L 0.2
3 reference points
3 reference points

Deflection
0.15

0.1
Differential settlement 
Usually no building  0.05

damage 0
0.00 0.05 0.10 0.15 0.20 0.25 0.30
Horizontal Ground Strain,  h (%)
Distortion
Category 0-1, Negligible - Very Slight
 Category 1-2, Very Slight - Slight
Relative deflection     Category 2-3, Slight - Moderate
 / L Category 3-4, Moderate - Severe
Predicted from ground movement assessment

97 98

Categories of Building Damage Case Histories


• Cheung Kong Centre – Court of Final Appeal
Building and Structure Damage Classification
(after Burland et al 1997 & Boscardin et al 1989) • 118 Gloucestor Road – Wanchai Police Station
Predicted Description of damage Approx. width Limiting
degree of of cracks tensile strain
damage (mm) (%) • MTRC and KCRC projects
Negligible Hairline cracks < 0.1 0 to 0.05
Very slight Fine cracks easily treated during normal redecoration. Perhaps 0.1 to 1 0.05 to 0.075
isolated slight fracture in building. Cracks in exterior brickwork visible
upon close inspection.
Slight Cracks easily filled. Redecoration probably required. Several slight 1 to 5 0.075 to 0.15
fractures inside building. Exterior cracks visible, some repointing may
be required for weather tightness. Doors and windows may stick
slightly.
Moderate Cracks may require cutting out and patching. Recurrent cracks can 5 to 15 or 0.15 to 0.3
be masked by suitable linings. Tuck-pointing and possibly several cracks
replacement of a small amount of exterior brickwork may be > 3mm
required. Doors and windows sticking. Utility services may be
interrupted. Weather tightness often impaired.
Severe Extensive repair involving removal and replacement of sections of 15 to 25 also > 0.3
walls, especially over floors and windows required. Windows and depends on
door frames distorted. Floor slopes noticeably. Walls lean or bulge number of
noticeably. Some loss of bearing in beams. Utility services disrupted. cracks
Very severe Major repair required involving partial or complete reconstruction. Usually > -
Beams lose bearing; walls lean badly and require shoring. Windows 25mm
broken by distortion. Danger of instability. depends on
number of
cracks

99 100

Structural Design Codes


• Structural Use of Concrete
• Structural Use of Steel

Structural Designs

101 102

Ir. James Sze, Ove Arup & Partners HK Ltd. 17
T3 Top‐Up course ELS part I of II 2011/4/29

Structural Design of Embedded Wall Structural Design of Shoring


Working load approach Working load approach
RC wall Steel wall Strut Waling Kingposts
Working envelope of BM, SF; vertical  Maximum working BM, SF, vertical  Working axial forces from  Working BM, SF, axial force if  Working vertical & 
load (if any) from analysis load (if any) from analysis analysis diagonal struts lateral forces
LF = 1.4 LF = 1.4 LF = 1.4
Load factor 1.4 Load factor 1.4
Ultimate axial force Ultimate BM, SF, axial force
Ultimate BM, SF, axial force Ultimate BM, SF, axial force Ultimate SF, axial force

SSelect member size with axial 
l t b i ith i l
stiffness comply with design  Select member size & steel grade
Select member section with bending  Select member section with bending  Check against ultimate 
stiffness comply with design  stiffness comply with design assumption,  assumption, steel grade capacity (buckling 
requirement, concrete grade steel grade strengths)
Check against ultimate  Check ultimate capacity with 
capacity with respect to  respect to appropriate codes 
appropriate codes (buckling  (combined stress usually govern) Check required toe 
Reinforcement design according to  Check against ultimate capacity against 
strengths) embedment
RC design code combined stress, buckling if applicable 
following steel code Design for welds, dowels, bolts

103 104

Associated Works - Temporary Decks Temporary Deck etc, Underpinning Works


Supporting 
beams

Temporary 
utility  Pipe pile wall
support

Underpinning work for a 
footbridge Underpinning work for 
a Champion Tree

Pre‐fabricated steel traffic deck
Stablisation of adjacent 
Temporary Deck for  structures
mucking out

105 106

Points to Note in ELS Designs Constructability

107 108

Ir. James Sze, Ove Arup & Partners HK Ltd. 18
T3 Top‐Up course ELS part I of II 2011/4/29

Buildable Design Over-excavation

• Easy and fast construction
• Less risks
• Safer working 
environment Large clear 
spanned struts
• Could be more cost 
effective

E.g. KCRC Tsuen Wan West Station

Unworkable sequence vs Opportunistic contractor 
109 110

Things to Watch out during Design Optimization of ELS Design at Kowloon Bay

vert. 2m c/c

Temporary deck
Fill

MD

Temporary deck ALL

CDG/MDG
Which system would be more constructable ?

Original Design Optimized
111 112

Minimising Workmanship Problem - Modular Modular Strutting System


Strutting System
• Modular system is constructed using site bolts without the need of 
extensive site welding. 
• Main struts comprise beam members laced with diagonal steel 
angles bolted to the top and bottom flanges. Members may be 
delivered to site either in pieces or completely bolted, to suit 
storage conditions.
• Hydraulic and screw jacks are supplied, as standard components. 
y j pp , p

113 114

Ir. James Sze, Ove Arup & Partners HK Ltd. 19
T3 Top‐Up course ELS part I of II 2011/4/29

Robustness & Reliability Uncertainties in Excavation Works


More robust !
• Variability in ground condition
Stability highly 
• Ground response
sensitive to over‐
excavation and  • Change in groundwater table
change in load
• Sequence of works – over‐excavation
• Workmanship – strut levels, welds etc
• Response of adjacent structures

Cantilever stiff wall vs Strutted flexible wall

115 116

Ways to Limit Wall Deflection Hence


Ground Movement
• Stiffer wall
• Stiffer shoring system
• Preloading of struts
• Improve soft soils within excavation (passive side)
Ways to Limit Ground Movement • Form circular cofferdam – very stiff
• Top
Top‐down
down instead bottom
instead bottom‐up
up sequence
sequence

117 118

1. Relative Stiffness of Retaining Systems 2. Stiffer Shoring System

• Steel – low grade with bigger cross‐sectional area
1
• Reinforced concrete – thicker section
• Shorter effective length by moving support closer to the wall
Sheet Pile Wall
• Truss system for large sites
Pipe Pile Wall

Bored Pile Wall

Diaphragm Wall
0
0 1 2 3 4 5 6 7
EI/m (x106 KNm 2)

  ( h4) / EI

119 120

Ir. James Sze, Ove Arup & Partners HK Ltd. 20
T3 Top‐Up course ELS part I of II 2011/4/29

3. Preloading of Struts Procedure of Preloading

• Apply a force at the strut against the wall prior to final connection
• Reduces the shear stress set up in the soil due to previous excavation 
activities
• Removes slack from the support system
• Use of preloads in the struts reduces movements, although there are 
diminishing returns at higher preloads
• However, very high preloads may, in fact, be counter
However very high preloads may in fact be counter‐productive
productive, since local 
since local
outward movements at support levels can damage adjacent utilities Apply force through 
jacking

Insert shim 
plates

Release and 
Remove the jack

121 122

4. Improve Weak Soils Prior to Excavation


• Smaller movement 
• less toe‐in
• less strut

Fill Fill

5. Adopting Circular Cofferdam
virtual span

Jet grouted 
virtual span of  raft prior to 
Soft soil wall due to  Soft soil excavation
little passive 
resistance

Stiff soil Stiff soil

123 124

+4.4mPD ‐2mPD

+5.6mPD ‐5mPD

76m

+5.6mPD
+4.4mPD ‐1mPD

125 Day 18 ‐ Ring Beam construction in progress 126 Day 51 ‐ Excavation reached ‐5.0mPD at deepest by earth‐ramp

Ir. James Sze, Ove Arup & Partners HK Ltd. 21
T3 Top‐Up course ELS part I of II 2011/4/29

‐3mPD

‐8mPD

‐17mPD

‐3mPD ‐9mPD

Day 68 ‐ Excavation reached ‐8.0mPD at deepest by mucking hoisting. First Ring Beam in progress
127 128 Day 111 ‐ 2nd Ring Beam completed. Excavation reached ‐17mPD at deepest

Lateral deflection of wall


wall deflection (mm)
0 10 20 30 40 50
0

5
Actual  10
Predicted Movement
measured
15

20
Raft cap 
25 location
depth (m)

‐21mPD 30
Excavation level
35

40

45

50

55

60

65

129 Day 159 ‐ 50% of subgrade blinded 130

Comparison of Bottom-up & Top-down Bottom-up vs Top-down - Movements


Option Advantages Disadvantages
Bottom-up •Allow maximum flexibility for the •Usually induce large movements
final basement layout & column •Conflict of shoring wall with permanent
positions slabs/walls may required special treatment
•Using involves flexible temporary •Generally large construction time for entire
wall which is fast to construct development
•Faster excavation for basement
alone, allow foundations to be
Typical 
constructed upon reaching
range in 
formation level. Top‐down
HK
•Unconfined, healthly working Bottom‐up
environment for workers
Top down •Better control on movements •Fix the column positions and load at early
•Allow simultaneous start of stage
superstructure and basement •Require extra deep foundations if mat
•Avoid conflict between temporary foundation is viable for the tower
shoring and permanent slabs •Extra cost for heavy weight stanchions
•Confined excavation implies longer period
for sub-structure construction especially in
hard materials

⇒ Rating will be project and site specific !
131 132

Ir. James Sze, Ove Arup & Partners HK Ltd. 22
T3 Top‐Up course ELS part I of II 2011/4/29

End of Part I

133

Ir. James Sze, Ove Arup & Partners HK Ltd. 23

You might also like