Professional Documents
Culture Documents
Printed initials in the approval boxes confirm that the document has been signed.
The originals are held within Document Management.
Procedure/Work Instruction/Job Note: ID-N-SB-LL0-PRO-ST-00-0001
Flange Management Proceure
ConocoPhillips Indonesia Page 2 of 32
Revision Sheet
ConocoPhillips Indonesia Inc. Ltd
Table of Contents
Table of Contents....................................................................................................................................... 3
1 Introduction............................................................................................................................ 4
1.1 Purpose................................................................................................................................... 4
1.2 Scope...................................................................................................................................... 4
1.3 References.............................................................................................................................. 4
2 Definition................................................................................................................................ 5
3 Flange Management Requirement and Procedure.............................................................5
3.1 Flange Joints Disturbance Procedure......................................................................................5
3.1.1 Reference Documentation....................................................................................................... 5
3.1.2 Breaking Flange Joints............................................................................................................ 5
3.1.3 Making Joints........................................................................................................................... 6
3.1.4 Tagging Procedure.................................................................................................................. 6
3.2 Flange General Requirements................................................................................................. 9
3.2.1 Bolting..................................................................................................................................... 9
3.2.2 Thread Lubricants and Preservatives......................................................................................9
3.2.3 Flange Faces......................................................................................................................... 10
3.2.4 Gaskets................................................................................................................................. 10
3.2.5 Insulation Gasket Sets and Specialty Gasket........................................................................10
3.3 Tightening.............................................................................................................................. 11
3.3.1 Tightening Methods............................................................................................................... 11
3.4 Hot Bolting and Preventative Bolting.....................................................................................13
3.4.1 Hot Bolting Requirement........................................................................................................ 13
3.4.2 Hot bolting procedure............................................................................................................ 14
3.4.3 Preventative Maintenance Bolting......................................................................................... 14
3.4.4 Preventative Maintenance Bolting Procedure........................................................................15
4 Flange System Records...................................................................................................... 15
5 Responsibilities...................................................................................................................... 15
Procedure/Work Instruction/Job Note: ID-N-SB-LL0-PRO-ST-00-0001
Flange Management Proceure
ConocoPhillips Indonesia Page 4 of 32
1 Introduction
Widely used in piping installation flange connection type that must be properly installed according to
existing standart. It is necessary to be a procedure that can be used as a reference for instating the flange
connection
1.1 Purpose
This document is intended as a guide on how to install flanged joints in service for plant and facilities. It
provides a framework to achieve this based on working with correctly designed joints.
This document also provides guideline when works disturb a flanged joint (repair/replacement) to ensure
integrity and quality requirements are met upon reinstatement.
In order to avoid failure it is very important that the relevant specifications for materials and components
are adhered to in full.
1.2 Scope
This guideline shall be applied within COPI facility when works disturb flange joints (interference from
original conditions) for the following type of asset:
all piping flange bolting
all flange bolting of connecting piping to flanged equipment (pressure vessel, heat exchanger,
valve, pipeline and tank)
1.3 References
1. API 570, Inspection, Repair, Alteration, and Rerating of In-service Piping Systems
2. API 510, Pressure Vessel Inspection Code: In-service Inspection, Rating, Repair and Alteration
3. API 574, Inspection Practices fro Piping System Components
4. API 572, Inspection of Pressure Vessels
5. ASME PCC-1 Guidelines for Pressure Boundary Bolted Flange Joint Assembly
6. COPI document ID-G-BU-00000-00000-01548 In-service Flange Integruty Guideline,
2 Definition
Hot Bolting – The sequential removal and replacement of individual fasteners on piping flanges with the
system still “live”. Existing fasteners are removed in a predetermined diametrically opposed sequence,
are examined for condition and then either cleaned, lubricated and re-fitted, or replaced by a correctly
specified fastener. Each refurbished or new fastener is then installed and tightened by controlled means
before the next fastener in the sequence is removed.
Preventative Bolting - The practice of checking for looseness and where necessary re-tightening
fasteners in flanged joints on a live (on-line) system. Tightening shall be done by controlled means even if
the bolt is equipped with a load-monitoring device (e.g. Rotabolt).
Tightening - The making tight of a flanged joint by torquing or tensioning the flange bolts.
Procedure/Work Instruction/Job Note: ID-N-SB-LL0-PRO-ST-00-0001
Flange Management Proceure
ConocoPhillips Indonesia Page 5 of 32
Torquing - The loading of flange bolts using manual or hydraulic torque equipment
2. Confirm that the line has been isolated, drained/vented or purged as appropriate before
attempting to break a joint. Ensure beyond all doubt that the line or piece of equipment being
worked upon has been correctly isolated and vented to atmospheric pressure and flushed and
purged if appropriate. the isolation requirement set out in ID-G-BU-00000-00000-00404 Lock Out
– Tag Out must be accomplished through an isolation certificate
3. Ensure that the correct tools for the job are available and are used. HSE document# ID-G-BU-
00000-00000-00391 – Hand Tools shall be complied.
5. When attempting to break a joint, avoid standing directly alongside or underneath the joint.
Always break the bolt that is furthest away from you first, preferably the bottom furthest bolt.
6. Continually check for leakage, seepage or signs of pressure in the line – a hissing sound, a smell
of gas, etc. Use a pair of wedges away from you to determine this.
7. If at any stage there is a sign of pressure in the line, stop work immediately. Re-tighten the joint to
contain the leak, if safe to do so, and then report the situation to the maintenance supervisor or
raise alarm. The line isolation will then have to be checked.
Procedure/Work Instruction/Job Note: ID-N-SB-LL0-PRO-ST-00-0001
Flange Management Proceure
ConocoPhillips Indonesia Page 6 of 32
8. Never remove nuts from studs until you have ascertained that the considered pipe/equipment is
depressurized and empty.
9. Before finally parting a joint, always assess the forces on the pipe. Will the joint spring apart? Is
one half of the joint unsupported? Temporary supports or restraints may be required.
1. Before starting, check that the permit to work/risk assessment is valid for the job in hand and that
the correct protective clothing/equipment is worn. Ensure that all safety precautions and work
permit instruction set out in ID-G-BU-00000-00000-00462 Permit to Work are in place and are
strictly adhered to.
2. Check if these are procedure in place for carrying out the intended work – and if so follow the
procedure. This includes using the Flange Disturbance Register and the use of flange
disturbance tags as detailed in section 3.1.4 below.
3. Determine the type, size and class of the flange to be bolted. Determine the referenced
document/specification as described in section 3.1.1 of the concerned joint. Check the material,
coating and size of the stud bolts. Check the type, pressure rating and size of the gasket. The
stud bolts and gasket specifications for the flanged joint must always match the descriptions in
the specification document (as mentioned in section 3.1.1).
4. Only use the correct materials for the job. Never use damaged materials and always uses a new
gasket when making up a joint. It is recommended that nuts/bolts are also renewed, however,
where this is not possible a visual inspection of these parts should be completed prior to
installation.
6. Ensure that the correct tools for the job are available and are used. HSE document# ID-G-BU-
00000-00000-00391 – Hand Tools shall be complied.
7. Ensure the joint faces are clean and properly aligned before inserting the gasket.
8. Visually check the flanges for equal gap. If a larger gap appears on one side of the flange, tighten
the bolt which corresponds with the larger gap first.
Each disturbed flange shall be ’tagged’ prior to assembly, only one flange tag per flange/joint will
be fitted. The tags are double-sided and comprise four distinct sections, the outer three sections
being perforated to allow tear off (all four sections of the tag are pre-printed with a unique
number). Tag should be made from water proof material e.g. plastic.
When Section 4 has been completed (on both sides), the tag indicates that the flange has been
assembled and tightened competently.
The tag should be fitted using a suitable tie and in a position adjacent to or on the joint.
Section 1 is removed and returned to the Maintenance Supervisor/Work leader to indicate that
flange has been disturbed. Person who disturbs the flange shall fill date and his/her name
complete with Permit work Number.
Section 4 of the tag will remain on the flange until such time that further maintenance is carried
out, only then will the existing tag be removed and replaced with a new tag. This shows visually
that both operations have been completed upon that flange.
PSSR shall be performed before joints back to online and operation should perform site
verification to check tagging system.
Procedure/Work Instruction/Job Note: ID-N-SB-LL0-PRO-ST-00-0001
Flange Management Proceure
ConocoPhillips Indonesia Page 8 of 32
Side A: This side of tag is completed by the Worker/Technician assembling the flange. The
worker/technician shall print his name and confirm the acceptable condition of the;
Side B: When the flange is ready for bolt tensioning/torquing, the Worker/Technician shall check
Side A of the tag to confirm the flange had been assembled correctly. The Worker/Technician can
then proceed to tighten the flange.
When bolt tightening is completed, the Worker/Technician shall print his name and confirm;
a) System Number
b) Line Number
c) The torque or tension applied. – Measured using hydraulic pressure gauges mounted on the
torque/tensioning machinery or set point on manual torque wrenches.
On completion of the above, Section 2 of the tag is removed and returned to the
Operation/Maintenance Supervisor/Work Leader who will retain it in the work pack for close out
audit.
A similar process is utilized after the flange has been leak tested (for information on leak testing
refers to Pressure and Leak Testing Guidelines.
The leak tests (service tests) are carried out with the pressure system in service, normally during
start-up. The test is normally carried out (but not necessarily always) at maximum normal
operating pressure using the process fluid as the test medium, supplemented by water or inert
gas from an external source if necessary.
When the flange has successfully passed a test, the Leak Test Technician shall confirm and write
on Side B Pressure and date of test then remove Section 2 of the tag and return it to the
Maintenance Supervisor/Work Leader who will insert the perforated ticket in the work pack for
close out audit.
On completion of testing the permit to work should be signed off as complete before handover
back to the operations department.
When all flanges have been tightened and tested the remaining portion of the tag should be kept
at disturbed flanges for at least 3 months after the start-up is complete. After that it is at the
discretion of the Facility Management as to how long the tags are kept.
To ensure consistent performance, it is essential that nuts and bolts are supplied with the precise
specification for tolerance and fit. Studs/Nuts shall be the correct material and size/length for the
application and free of corrosion, damage, dirt and grit.
Confirmation of the above is required to complete Section 4 of Side A of the flange tag.
Re-use of Bolts/Studs
Studs and or nuts can only be reused, subject to the following conditions:
There is no noticeable degradation.
Procedure/Work Instruction/Job Note: ID-N-SB-LL0-PRO-ST-00-0001
Flange Management Proceure
ConocoPhillips Indonesia Page 9 of 32
It is essential that when choosing fasteners for a flanged joint the grade of stud and nut used are
compatible and compliant with the piping specification. Matching stud and nut grades are given in
Table below:
2. The use of lubricants with a lower coefficient of friction can lead to excessive bolt stress being
applied and failure of flanges or bolts may result.
4. When bolt tensioning is complete, to prevent corrosion a liberal coating of lubricant should be
applied to the nuts up to the back of the flange, and to the stud ends protruding from the nuts.
Copperslip, Densotape or nut/thread protectors are considered to be suitable for this purpose.
5. The above information is required to complete Section 4 of Side B of the flange tag.
Note: this is particularly important where low alloy bolts are used on unpainted stainless steel
flanges. Marinel material bolting should not be lubricated.
Prior to assembly the flanges should be inspected to ensure the faces are in good condition
(particularly with respect to radial scoring), clean, parallel and axially aligned.
Pipe flange alignment tolerances shall comply with the relevant pipe fabrication/erection
specification.
Flange alignment is critical to the performance of the bolted joint. No excess pressure should be
exerted to align the bolt holes for the insertions of bolts without engineering approval. Excess
pressure used to assist with the insertion of bolts on flanges on rotating equipment could have
damaging effects on seals, shafts and bearings. For specific information on pipe alignment on
rotating equipment see API 686. General piping alignment specifications can be found in ASME-
PCC-1.
Every effort shall be made to align the joint. Applying large forces, through mechanical devices or
bolting, to align flange joint is bad practice and not permitted. Joints found in this condition should
be reported and seek consultation with COPI Asset Engineering prior to re-commissioning.
The above information is required to complete Section 4 of Side A of the flange tag.
3.2.4 Gaskets
A new gasket/RTJ/Seal Ring shall be used whenever joints are made or remade.
Gaskets shall be suitable for the operating conditions and remain flexible under a varying load
due to fluctuations in pressure and temperature. The type of gasket used shall comply with the
Pipe Specification. Where spiral wound gaskets are utilized, extra care shall be taken to protect
the face of the gasket.
When installing the gaskets, ensure the flange and gasket faces are clean and dry. Gaskets
should be of the correct type and correctly positioned. Note that it is not possible to mix and
match gaskets between proprietary clamped connectors (e.g. Graylok/Techloc & Galperti).
Where identified, it is imperative that insulation kits are fitted correctly. The purpose of the
insulation kit is to prevent undesired conductivity between dissimilar materials and corrosion
issues occurring. Insulation kits generally require a lesser bolt load to create an effective seal as
a result of the specially designed gasket, with spacers and washers playing an integral role. It is
essential that all components of the insulation kit are fitted to ensure the integrity of the joint and
that the manufacturer’s recommendations are followed when tightening the joint.
Note: A lower torque must be used for insulation kits to avoid cracking. If cracks or
damage occur whilst tightening the insulation kits must be replaced as they are no longer
usable.
3.3 Tightening
3.3.1 Tightening Methods
Flange bolts may be tightened by hand torque wrenches Conventional spanners/wrenches may
be used on Class 150 Non-Severe System piping systems only.
Flange bolts shall be tightened by torque wrenches on all hydrocarbon systems (all pressure
ratings), and utility systems rated at Class 300 and above.
Controlled torque wrenching shall be carried out using either manual or hydraulic torque
wrenches that are calibrated and “in certification”. The method chosen is dependent upon bolt
loading, access, clearance and tooling availability, which will be determined by the site personnel.
When the bolt loading requires a torque figure greater than 500 lbf.ft (678 Nm) to be applied, the
use of a hydraulic torque wrenches is recommended.
Note: if torque equipment cannot be applied due to access restrictions then the
Operation/Maintenance Supervisor/Lead shall be advised and a Risk Assessment
completed detailing the additional controls required to ensure joint integrity, this may
include using conventional spanners and joint make up verification by a second
Worker/Technician.
To achieve joint tightness it is important that the following procedure is adhered to:
(1) Check and ensure that the general requirements of Section 3.2 have been satisfied.
(2) To achieve uniform joint load/stress distribution the bolts shall be tightened in three stages,
representing 30%, 60% and 100% of the torque values stated in Appendices F. At each
stage of tightening, bolts shall be tightened in a controlled sequence as follows:
(3) Finally the bolts shall be chased round using the 100% torque value stated in Appendices F,
until uniform tightening has been achieved. Note: If tightening an RTJ, a second 100% chase
round shall be completed.
Where more stringent control of joint stresses is required, flange bolting should, whenever
practical, be tightened using hydraulic jack tensioning equipment. This technique is strongly
recommended for the following services and pressure ratings, (also see Appendices H)
(1) Bolt diameters of 2 inches and above in all services with pressure ratings up to and including
Class 900.
(2) Bolt diameters of 1½ inches and above in all services with pressure ratings Class 1500 and
above.
(3) Bolt diameters of 1 inch and above in critical applications. Critical applications are
considered to be joints exposed to cyclic stress i.e. frequent changes of pressure and/or
temperature.
The bolt tensioning operation must be carried out in accordance with the tension equipment
manufacturer’s specified procedure and the load loss factors should be recorded. Ideally
tensioning should be applied simultaneously to all studs in one operation. Where this is not
possible, tensioning should be applied in phases using differing pressures as per suppliers
guidelines.
Note: if tensioning equipment cannot be applied due to access restrictions then the
Operation/Maintenance Supervisor/Lead shall be advised and a Risk Assessment
completed detailing the additional controls required to ensure joint integrity, this may
include using conventional spanners and joint make up verification by a second
Worker/Technician.
Procedure/Work Instruction/Job Note: ID-N-SB-LL0-PRO-ST-00-0001
Flange Management Proceure
ConocoPhillips Indonesia Page 13 of 32
Holt bolting work should be approved by site manager and site specific procedure should be
developed.
Before any work commences ensure that hot bolting has been fully justified; that a risk
assessment has been performed and approved; that a permit to work states that hot bolting on
the joint is permitted; and that a contingency plan exists to isolate the joint in the event of a
problem during the hot bolting operation.
The hot bolting procedure given below shall be followed:
(1) Latest past history records of the joints in question shall be consulted to identify any
anomalies or previous problems with the joint.
(2) To anticipate any fastener or flange or gasket relaxation an attempt shall first be made to
evenly re-tension each fastener before attempting to loosen any single fastener. Both the
tightening and slackening activities shall be carried out by controlled means (if extra length
studs have been fitted, bolt tensioning is strongly recommended over torquing during hot
bolting as it maintains a more accurate gasket seating stress, and is less likely to result in an
overloaded bolt). Bolt tension and bolt torques shall be in accordance with Appendix F.
(3) The break out torque shall be recorded for every fastener. If the break out torque is
significantly less than the torque specified in Appendix F it may indicate a loose or
overstressed joint. In such cases the system shall be isolated, depressurized, purged and
Procedure/Work Instruction/Job Note: ID-N-SB-LL0-PRO-ST-00-0001
Flange Management Proceure
ConocoPhillips Indonesia Page 14 of 32
vented prior to any further fastener being removed. In this instance please notify the COP
onshore maintenance responsible engineer.
(4) Proceed to slacken the first fastener (on the side furthest away from personnel), monitoring
for leakage continuously. Under no circumstances shall two bolts be slackened
simultaneously. In the event of the gasket leaking the joint shall be immediately re-tightened.
(5) The removed stud and nut should be cleaned, examined for damage or strain, lubricated with
Copperslip only, reinstalled and re-tightened. If in doubt the stud and nut should be replaced.
(6) Only one fastener shall be removed and replaced at a time working in the diametrically
opposite sequence as shown in Table 1 of this procedure. Each fastener shall be replaced
immediately and shall be tightened to the torque or tension as specified in Appendix F.
(7) Continue with this procedure (6) until all the fasteners have been changed out.
(8) When all fasteners have been replaced their exposed nuts and threads shall be given a
liberal coating of grease in order to prevent corrosion.
(9) Any jacking bolts that have been removed to improve access should be greased and refitted.
The practice of checking for looseness and where necessary re-tightening fasteners in flanged
joints on a live (on-line) system is a potentially hazardous operation. It must not be undertaken on
a joint in a hydrocarbon, hazardous or toxic fluid system, unless all other options have been
considered and there remains an outstanding, and fully justified, operational reason to perform
preventative maintenance bolting in a safe manner. A risk assessment shall be carried out, and a
plan developed to achieve isolation of the joint in the event of a problem during the operation. The
joint must have a minimum of 8 bolts. This preventive works shall get approval from site
management representative.
(1) Bolt tightening shall be carefully performed by controlled means. Bolt tensioning shall be
used if possible (if extra length studs have been fitted), otherwise bolt torquing shall be used.
Controlled tightening shall be used even if the bolt is equipped with a load-monitoring device
(e.g. Rotabolt).
(2) Re-tensioning and re-torquing of the flange bolting shall be performed in accordance with
Appendix F, and bolt torquing shall be in the bolt sequence shown in Table 1 of this
procedure. It should be noted that although the thread lubricant may have dried out which will
increase friction losses, the bolt torque applied must not exceed the values stated in
Appendix F.
(3) Monitor the joint during the operation for leakage, and at the end of the work verifies that the
joint is totally leak-free.
Learning from incident is important. A gathering relevant data, which should be collected by everyone
involved in flanged joints and periodically reviewed to establish trends, performance and improvement.
This can be achieved if records and data are kept as part of a management control process.
It is recommended that as a minimum keeps records for all joints those on other services which have a
history of leakage, or potential to leak, and that this is kept with any relevant procedures for monitoring
specific joint. To minimize the possibility of the problem resurfacing, methods for countering the leak
should be included within the individual joint records.
Any changes from original specification should be maintained through MOC process.
5 Responsibilities
InspectorsAsset Integrity
IN-SERVICE ROUTINE INSPECTION Maintenance/Operation
Asset Integrity/Pipeline
Offshore Installation
Supervisor/Lead
Technician
RACI
Engineer
Manager
R Responsible
A Accountable
C Consult
I Inform
No Activity
FLANGE MANAGEMENT
InspectorsAsset Integrity
Specialist Flange Vendor
Asset Integrity/Pipeline
Offshore Installation
Superintendent
Field Manager
Maintenance
Engineer
RACI
R Responsible
A Accountable
C Consult
I Inform
No Activity
Operation Supervisor/Lead
InspectorsAsset Integrity
Specialist Flange Vendor
Asset Integrity/Pipeline
Offshore Installation
REQUIREMENT & PROCEDURE
Worker / Technician
Superintendent
Field Manager
Maintenance
Engineer
RACI
R Responsible
A Accountable
C Consult
I Inform
6 Torque/Tension to correct Value R R C C A I I I
APPENDIX A
L:\2.0 Project\16
Material & Corrosion\160079.01 COPI A&OI SIP 2010\11.0 ENGINEERING\SIP\SIP #3\WOR
Procedure/Work Instruction/Job Note ID-G-BU-00000-00000-01548 Rev. 2
In- Service Flange Integrity Guideline
ConocoPhillips Indonesia Page 18 of 32
APPENDIX-B
L:\2.0 Project\16
Material & Corrosion\160079.01 COPI A&OI SIP 2010\11.0 ENGINEERING\SIP\SIP #3\Flang
Procedure/Work Instruction/Job Note ID-G-BU-00000-00000-01548 Rev. 2
In- Service Flange Integrity Guideline
ConocoPhillips Indonesia Page 19 of 32
APPENDIX-C
L:\2.0 Project\16
Material & Corrosion\160079.01 COPI A&OI SIP 2010\11.0 ENGINEERING\SIP\SIP #3\CONT
Procedure/Work Instruction/Job Note: ID-G-BU-00000-00000-01548 Rev. 2
In- Service Flange Integrity Guideline
ConocoPhillips Indonesia Page 20 of 32
APPENDIX-D
LUBRICANT
Procedure/Work Instruction/Job Note: ID-G-BU-00000-00000-01548 Rev. 2
In- Service Flange Integrity Guideline
ConocoPhillips Indonesia Page 21 of 32
APPENDIX-E
APPENDIX-F
The following table covers the Torquing / Tensioning Details for the following Bolting Materials:
Carbon Steel, Duplex Stainless Steel, Super Austenitic Stainless Steel, B7 & Equivalent (Bolt Stress is
approx 310 Mpa (45000 psi)) using a Coefficient of Friction (COF) 0.10
B8M Class 2 (Bolt Stress is approximately 65% of yield load) using a Coefficient of Friction (COF) 0.10
APPENDIX-G
FLANGE
Flange surface scarred Installation error in the Renew sealing surface
tools used to insert or remove
the gasket
Damaged flange was not
inspected during make up
Flanged bowed Over torque Revise assembly
Flange pressure rating is procedure
too low for service conditions
Flange material is not
adequate for service conditions
Flange rotation Over torque Revise assembly
Flange pressure rating is procedure
too low for service condition New Flange
GASKET
Gasket crush all around Over torque Install a proper new
Gasket is too soft: low gasket
modulus of elasticity
Gasket is too thick
Gasket crush on one end Excessive pipe moments Additional passes
only Pipe misalignment In tightened correctly
Incorrect bolt up refer to Asset Integrity
procedure Engineer
Gasket crush on outer edge Flange rotation Crush control
Over torque Stretch control
Gasket is too hard: high Low stress gasket
modulus of elasticity
Flange pressure rating is
too low
Gasket cut Installation error in the Provide gasket
tools used to insert the gasket; handling instruction and
mishandling the gasket during fixtures
installation
Damaged gasket was not
inspected at installation
Gasket disintegration Incorrect gasket Material Change gasket
Contamination of the material
flange and/or gasket
Gasket blowout Flange surface is too Machine
smooth
Incorrect gasket material
Gasket is too thick
Gasket extrusion Gasket is too soft; low Stretch control
modulus of elasticity Gasket control
Incorrect gasket material
Over torque
Procedure/Work Instruction/Job Note: ID-G-BU-00000-00000-01548 Rev. 2
In-Service Flange Integrity Guideline
ConocoPhillips Indonesia Page 32 of 32
More detail about trouble shooting of flanged joint could be found in Appendix P of ASME PCC-1 (2010).
A series of diagnostic tables is provided with each dedicated to a specific type of leak event includes:
Leak during Hydro Test (LHT)
Leak during heat-up or initial operation (LIO)
Leak corresponding to thermal or pressure upset (LCU)
Leak after several months operation (LTO)
Leak during shutdown (LDS)