Professional Documents
Culture Documents
SYSTEM
CONSTRUCTION,DESIGN,
COMMISSIONING,
OPERATION AND
MAINTENANCE
SinglePoint Mooring (SPM) system
is a kind of offshore platform for
the berthing of tankers to load /
unload materials.
Throughput requirement
Following requirements should be satisfied for
the selection of the location.
Suitable weather for Construction and Operation.
Requisite Draft for the large vessels berthing
Sea bed Profile to be smooth for offshore pipeline
laying.
Safe Channel for vessels.
Condition of seabed and its strata.
Distance of required draft from shore should be as
minimum as possible.
SPM location should be cleared from Navigational
channel.
Availability of suitable land at shore for tank farm.
Ship traffic
Fishing activities
Offshore installations
Existing pipelines and cables
Unstable seabed
Turbidity flowSeismic activity
Obstructions
Dumping areas for waste
Mining activities
Military exercise areas
Archaeological sites
Exposure to environment damage, flora & fauna
Pipeline dia shall be decided on the basis of
distance (from SPM to tank farm) and
throughput requirement.
SPM system to be designed based on
throughput requirement.
Availability of suitable weather for operation.
Components of offshore pipeline design
Throughput requirement
Distance from SPM to tank farm
Density of sea water
Sea bed condition
Type of fluid to be transported.
Expected Life of the system
Pipeline route
Operating Pressure
Pipeline dimensions depends on the
following:
Throughput requirement (MMTPA)
Corrosion allowance
Impact load on the pipeline
Load on pipeline while laying on sea bed.
Throughput requirement
SPM is designed to feed the refineries as per their
capacity of processing crude oil.
In case of PHCPL SPM system, it is designed to feed
Haldia and Barauni refinery and their combined
requirement is 11.0 MMTPA.
Considering 57% berth occupancy with 70% VLCC
and 30% other vessels the required diameter of
offshore pipeline comes to 48”.
CLASSIFICATION OF TANKERS
TYPE TONNAGE
Premium Range <16500
General Purpose 16500- 24999
Medium Range 25000-44999
Large Range (LR I) 45000-79999
Large Range (LR II) 80000-159999
Very Large Crude Carriers(VLCC) 160000-319999
Ultra Large Crude Carrier(ULCC) >320000
*MR, LR-I & LR-II (less capacity) range of crude tankers are berthing
at Haldia only in partially loaded condition.
In case of PHCPL The total length of the
offshore pipeline is approximately 19.75
kms and the pipeline will be subjected to
maximum pressure of 12 kg/sq.cm to push
the crude oil to Shore tanks.
To take care of this pressure the
requirement of nominal wall thickness is
less than 5.0 mm but the thickness of 48”
offshore pipeline has been taken 20.3 mm
to take care of all types of load during
laying of pipeline.
For the calculation of required thickness
during laying of offshore pipeline, DNV code
has recommended D/t ratio as 60.
1219/t = 60 (OD = 1219 mm)
t = 20.3 mm
Thickness of 20.3 mm takes care of corrosion
allowance as well as impact load. However, for the
external corrosion protection, sacrificial anodes are
provided.
Concrete weight coating to maintain negative
buoyancy.
◦ Following formula to be used for the calculation of the
concrete weight requirement.
For 48” dia bare steel pipe it comes to approx. 18000 kg. The weight of
12 meters bare pipe is approx. 8000 kg and total weight of pipe after
concrete coating comes to 26.0 T approx.
Installation of sacrificial anodes
For offshore terminals, Impressed current cathodic
protection system cannot be maintained.
Only sacrificial anode are used as cathodic
protection alternative.
Quantity of sacrificial anodes mainly depend on
total area to be protected, required life of the
system and for offshore pipeline or under water
structure it depends on the depth.
Topography of seabed requires detailed
investigation for the following point of view.
Obstruction in the form of rock outcrops, large
boulders, pock marks etc.
Potentially unstable slopes, sand waves, deep
valleys and erosion in the form of scour pattern.
Soil testing is required for the following:
Problems with respect to excavation and burial
operation.
Problems with respect to pipeline crossing
Settlement of pipeline
Possibility of mud slides
SPM SYSTEM
Design Factors
Selection and design of a specific configuration for an SPM application
is dependent upon a number of factors. Primary design factors include:
Size of the largest vessel to be accommodated, and range of vessel sizes.
Number of products to be handled, as well as types of fluids, maximum
flow rates and maximum operating pressure.
Water depth, and tidal range.
Maximum operating and maximum survival environmental conditions
(including waves, current and wind and their relative angles).
Characteristics of the seabed.
Design life of the system.
Additional factors peculiar to a specific site, such as earthquake
conditions, or ice etc.
Many other factors are also involved, to varying degrees, depending on
the specific system; a variety of environmental conditions influence the
design as well as factors related to the development, fabrication,
installation and operation of the SPM.
Types of Single Point Mooring Systems
◦ CALM (Catenary Anchor Leg Mooring)
It consists of a buoy anchored by 4 or more chains extending in
catenaries to anchor points on sea floor.
◦ SALM (Single Anchor Leg Mooring)
It consists of a buoy which is anchored to a base on sea floor
through a pre-tensioned single anchor leg consisting of a pipe
riser pivoted on universal joint and a short anchor chain with a
chain swivel.
◦ VALM (Vertical Anchor Leg Mooring)
It consists of a buoy with 3 or more vertical pre-tensioned
chains anchored on seabed.
◦ SPMT (Single Point Mooring Tower)
It consists of a rigid structure erected on seabed and extended
upto above water surface with a mounted turret on a swivel.
Platform
VALM
SALM Buoy Buoy
Swivel
Chain
Pre- Single
Chain Universal tension Point
Joint ed Mooring
Tower Riser
Swivel Chains
CALM Buoy.
Mooring hawser and Anchors chains.
Submarine and Floating Hose Systems.
Tanker Mooring Hawser Assembly.
Pipeline End Manifold (PLEM) and Valves.
THANK YOU FOR YOUR ATTENTION
24
© UNEP GERIAP