You are on page 1of 24

CHAPTER - 1

ORGANISATION PROFILE

Neyveli, Home of the Neyveli Lignite Corporation, is today India’s energy


–bridge to the 21-century. Neyveli is a town located about 55 km east of
Cuddalore in the South Arcot district of Tamil Nadu. Pt.Nehru launched a
mining operations with his golden touch in May 1957. During the
construction of irrigation wells occurrence of lignite deposits at shallow
depths was noticed in Neyveli area. When systematic geological
investigations were taken up in the area, occurrence of lignite over an area of
260 sq.km. With reserves of 2100 million tones discovered. NLC has
achieved the objectives it has set for itself. Fulfilling its corporate mission to
be the leader in the industry. Neyveli Lignite Corporation is certified ISO
9001:2000 for “Quality Management”, ISO 14001:2004 for
“Environment Management”, OHSAS 18001 for “Safety Management”.

Neyveli Lignite Corporation Limited (NLC) is a government-owned


lignite mining company in India and is in service of the nation for the last 4
decades. One of the public sector undertakings, the company is wholly
owned by the Union Government (49 percent) and administered through the
Ministry of Coal. Computing of two open cast mines, two pit head Thermal
Power Stations, with an installed capacity of 2490 MW of electricity per
year. Of this, the origin state of Tamil Nadu consumes 1167 MW, with the
neighboring states (Kerala Karnataka, and Andra Pradesh) consuming most
of the rest. NLC’s growth is sustained and its contribution to India’s social
and economic development is significant. Neyveli Lignite Corporation
Limited’s net current assets stand at Rs 3744.81 crore as on FY 2006-2007.
1
1.1 MINES - I

Demarcated over an area of 16.90 Sq.km. with a reserve of about 287


million tones. Mine-I is situated on the Northern part of the field adjacent to
the Neyveli Township. The lignite seam was first exposed in August 1961
and regular lignite mining was commenced in May 1962. The mine has a
production capacity of 10.5 million tones of lignite per annum and feeds
lignite to the 600 MW capacities of first Thermal Power Station and 420MW
Thermal Power Station-I Expansion.

1.2 MINES – IA

Mine –IA is adjacent to the existing Mine-I block on the eastern side. The
project was commissioned in 2001. The total reserve in Mine-IA is 120
million tonnes in an area of 11.6 sq.km. The annual capacity of this mine is
3 million tonnes and lignite was first exposed in March 2003. This mine
feeds lignite to M/S ST-CMS, an independent Power project 250 MW and
NLC’s Thermal Power Station.

2
1.3 THERMAL POWER STATION - I

An opitome of India-Soviet collaboration, Neyveli-Thermal Power Station-I


(TPS-I) was commissioned with one unit of 50 MW each and three units of
100 MW each.

The unique features of this power station.

 First lignite-fired Thermal Power Station in South East Asia


 First pit head Thermal Power station in India

 First largest Thermal Power station in South India

Continuously achieving over 70% plant load factor, from 1982-83 to


1991-92 against the national average of around 50% and has
continuously bagged the meritorious productivity award instituted by
the Department of Power, Government of India.

The power generated from The Thermal Power Station is fed to the grid of
Tamilnadu Electricity Board, the sole beneficiary.

1.4 THERMAL POWER STATION-I EXPANSION

This Power Station consists of two units of 210 MW each. The first unit of
this Power Station was synchronized on 21.10.2002 and the second unit on
22.07.2003. The power generated from this Power Station is shared by
Tamilnadu, Kerela, Karnataka and Pondichery.

3
Some of the special features of this power station are:

 Fully Automated Plant controlled by Distributed Digital


Control Monitoring and Information System(DDCMIS),
 Environment-friendly equipment and Dry Ash collection
system,

 Online Sulphur dioxide (SO2) Monitoring,

 Oxides Nitrogen (NOx) Analyzers.

1.5 MINES - II

Mine – II is located 5 Kms South of Mine-I spread over an area of 26


sq.kms. with 390 million tonnes reserve. The lignite steam was first exposed
in September 1984 and regular lignite mining commenced in March 1985.
The maximum overburden is 103m, and the lignite thickness varies from 8 to
22 m. Initially, the mine was started with a production capacity of 4.7
million tonnes and in February '83 the capacity was enhanced to 10.5
million tonnes per annum. The lignite production in this mine meets the
fuel requirement of Thermal Power Station-II.

4
1.6 THERMAL POWER STATION-II

The Second Thermal Power Station consists of 7 numbers of 210 MW Units


and hence having an installed capacity of 1470 MW. Units 1, 2&3 were
constructed in the First Stage followed by the Second Stage Units 4, 5, 6 & 7.
Lignite for the station is supplied from Mine-II having an annual capacity of
10.5 Million Tonnes. Unit 1 was commissioned in March 1986 and
commissioning of the 7th unit was carried out in June 1993. Year after year
production records are broken by Thermal Power Station –II. The southern
states of TamilNadu, Kerala, Karnataka and AndraPradesh and the Union
Territory of Puducherry are the beneficiaries of the power produced in the
power station.

The First Stage units are fully of foreign origin. Boilers are of M/s EVT
Germany design and manufactured, supplied and erected by M/S Traselectro
of Hungary. Turbines are of M/S Westing house U.S.A design and
manufactured, supplied and erected by the erstwhile M/S Franco Tosi of Italy
(now merged with M/S Ansaldo of Italy). Generator is of Ercole Marelli, Italy’s
supply. Stage-II units are fully of M/S BHEL’s supply even though the Boilers
are of M/S EVT Germany’s design, Turbines are of M/S KWU Germany’s (a
Siemens subsidiary) design and Generator is of Russian design. 9014.04
Million units of Electricity can be generated per annum from this power station
at 70% annual plant load factor; but the actual production figures in recent years
are much higher.

5
1.6.1 SWITCH YARD – TS II

The switchyard is to transmit power generated by 7 Nos. of 210 MW units


(3Units in stage 1 and 4 units in stage 2). The transmission voltage is 230 kV
and 400kV. Thermal Power Station II switchyard is one of the biggest switch
yard in the Southern Grid. 230kV system is connected to TNEB grid and
Puducherry Electricity system. 400kV system is connected to Southern
Electricity grid through Power Grid Corporation Limited lines. The total share
of power from central generating stations such NLC, Ramagundam, MAPS,
Kaiga, Taltcher etc is fed to Puducherry Electricity System through the 2 Nos.
of 230kV feeders from the Thermal Power station –II 230kV yard. The 230kV
and 400kV system in switchyard are interconnected through 400kV/230kV
interconnecting auto transformers.

The bus arrangements in switchyard are 2 Main bus and 1 transfer bus system.
There are 3 system buses in 230kV and 400kV yard namely First Bus, Second
Bus and Transfer Bus. Each bay is meant for each equipment to connect with
any one bus. The bay consists of first Bus isolator (89A), Second bus isolator
(89B), Line isolator (89C), Transfer Bus Isolator (89 D, Breaker, current
Transformer, Capacitance Voltage Transformer, Lightening arresters, Breaker
earth bus side (89E1), Breaker earth line side (89 E2), Line earth (89E3) etc.
Each bay has respective control panel and relay panel in control room. Wave
Traps are provided in transmission lines except mining feeders for PLCC
purpose.

6
Isolator is an off load device. It can be operated only without load since it is not
having arc quenching medium. Isolator is used to select any one of the bus
system to the element and also for perfect isolation of breaker.

Breaker is an on load device. It can be operated either with load or without load.
Through the breaker only the element is charged or isolated. The breaker is an
fast acting device During fault the protection relays senses the fault and trips the
breaker. The faulty equipment is isolated from the system by tripping of
respective breaker.

230KV SYSTEM OPERATION

There are 22 bays in 230kV switchyard as follows

 3 Nos. of Generator bays for stage 1 units.


 2Nos. of Station Transformers bays for Station Transformer (ST1 and

ST2) of capacity 50MVA each. The station Transformers are feeding

supply to Stage1 Station Auxiliaries.


 2Nos. of Station Transformers bays for Station Transformer (ST3 and

ST4) of capacity 30 MVA each. The station Transformers are feeding

supply to Stage2 Station Auxiliaries.


 2 Nos. of Mining feeders bays ( Mining Feeder 1 and Mining Feeder

2) to feed supply to Mines 1 and Mines 1A


 2Nos. of Mining feeders bays ( Mining Feeder 3 and Mining Feeder

4) to feed supply to Mines 2

 2 Nos. of Tie line (Tie Line 1 and Tie Line 2 ) feeder bays are inter
7
linking Thermal Power station 1 and Thermal Power Station 2

 STCMS-1&STCMS-2 bays are to inter linking the STCMS Thermal

Station
 Kadalangudy bay is to connect the TNEB sub station at

Kadalangudy
 Puducherry feeder bay is to connect Villianur sub station in

Puducherry.
 Bhahoor feeder bay is to connect Bhahoor sub station in Puducherry.
 Inter connecting Transformer 1 and Interconnecting Transformer 2

bays are to inter connect 400kV system through 2 Number of Auto

Transformers of each of capacity 250 MVA


 One number of Bus coupler bay is to connect the 2 Main buses

namely Bus 1 and Bus 2


 One number of Bus Transfer bay with Transfer Bus is to divert load of

any one bay main breaker to Bus Transfer breaker without supply

interruption and with all protection.

400kV SYSTEM

There are 13 bays in 400kV switchyard as follows

8
 4 Nos. of Generator bays for stage 2 units.

 5 Nos of Transmission line bays namely (Chennai, Salem-1, Salem-2,

Trichy- 1and TS-1 Expansion to TSII

 2 Nos of inter connecting Transformers of capacity 250 MVA


 1 No Bus coupler bay
 1 No of Bus Transfer Bay.

1.7 THERMAL POWER STATION-II EXPANSION


Government of India sanctioned the installation of 2 units of 250 MW each as
an expansion of Second Thermal Power Station on 18th October 2004 at a cost
of Rs. 2030.78 crore. The time schedule for commissioning of Unit – I is 53
months and for Unit – II is 57 months from the date of sanction of GOI.
Revised cost estimate of the project was approved by GOI for Rs. 2453.57
Crores during July 2008. During the year 2008-09, lifting of boiler drum for
unit – 2 was completed in May 2008. Erection of Chimney and Cooling tower –
1 have been completed. Erection works are in progress in respect of Boiler,
Turbine condenser and other packages. The first unit is expected to be
commissioned in May 2010 and second unit in November 2010.

1.8 FUTURE PLANS


NLC is poised for a rapid growth in the mining and power generation capacity
and is expanding its activities not only at Neyveli but also in other parts of the
country. NLC is also venturing in New projects with fuels other than Lignite.

9
The following projects are proposed to be taken up by NLC during the 11th
/12th Plan period :
 Bithnok Lignite Mine-cum-Power Project ( 2.1 MTPA Lignite Mine
with linked 250 MW Power Plant)
 Hadla Lignite Mine-cum-Power Project (Barsingsar Extension) ( 2.5
MTPA Lignite Mine with linked 250 MW Power Plant)
 Jayamkondam Lignite Mine cum Power Project ( 13.5 MTPA Lignite
Mine with linked 1600 MW Power Plant)
 Valia Lignite Mine cum Power Project at Gujarat ( 8 MTPA Lignite
Mine with linked 1000 MW Power Plant)
 A 15 MTPA Coal Mine under Joint Venture with MCL and a 2000
MW Power Plant in Ib valley in Orissa.
 NLC’s New Thermal Power Project at Neyveli ( 2 X 500MW ) in lieu
of TPS-I.
 Mine – III linked with TPS – III ( 8 MTPA Lignite Mine and 1000
MW Power Plant) at Neyveli.
 Coal based power project at Madhya Pradesh (1000 MW Power Plant)
 Coal based power project at Jharkand (1000 MW Power Plant)
 Coal based power project at Uttar Pradesh (2000 MW Power Plant)

Fund requirement of the above projects will be met from internal accruals and
borrowings. Upon successful completion of the above projects, NLC’s mining
capacity will be increased to 79.70 MTPA, ( both Lignite and Coal ) and power
generation capacity will be raised to 14740 MW.

CHAPTER 2
CONTROL AND INTERLOCKS
2.1 ISOLATORS AND INTERLOCKS

10
2.1 i INTRODUCTION

The Isolators are OFF LOAD electrical device in the 230 KV and 400 KV
Switchyard. There are 3 different types of isolators available in the switchyard. All
the isolators both bus and line in 230Kv side are of Double break center operated.
All the bus isolators in 400Kv side are of Pantograph type. The line isolators in
400Kv side are of center break type. All the isolators are motor operated. All the
power contactors, switches, fuses, limit switches, aux. contacts, motor with gear
assembly etc. are housed in the Motor Operated Mechanism (MOM) box.

2.1 ii ISOLATOR CONTROL

The motor operated isolators can be operated remotely from control room or from
the local MOM box electrically by selecting the local / remote accordingly only
when certain interlocks (conditions) are satisfied.. Normally this switch is set for
remote operation only. In case of failure of remote operation or for test purposes
local operation is done. A fly back control switch is provided in the control panel
for operating the isolators. The green lamp in the control panel will glow indicating
that the isolator is open. A red lamp would indicate the closed condition of the
isolator.

2.1 iii MANUAL OPERATION

In addition to electrical operation, manual operation with an operating handle is


also possible. When all the interlock conditions are satisfied if the push button
MPB in the MOM box is pressed the main solenoid coil MSC is energised. The
plunger shaft of the solenoid coil normally rests in the groove of the castle key
interlock shaft (KIMC). On energisation of the solenoid coil the plunger shaft is
lifted up, thus releasing the castle key. The castle key can now be turned in the
anticlockwise direction to release the mechanical interlock latch, which would be

11
normally act as stopper for the insertion of manual operation handle.

The manual operation handle can now be inserted through the opening provided
for and turned, to close or open the isolator. After the manual operation is carried
out the castle key is to be put back in position and turned in the clockwise direction
restoring the condition needed for remote/local operation by electrically.

2.1 iv ISOLATOR INTERLOCKS

The interlocks are implemented for safe guarding the equipments and for personal
safety. The isolator can be closed / opened electrically, only when certain interlocks
(conditions) are satisfied.

For 230Kv bus isolator 89A i.e. I bus isolator can be opened eclectically
from remote if the following conditions are satisfied.

a. KIMC (Key interlock main coil) key i.e. isolator manual operation

key shall be in the front panel of the MOM box and turned 'ON'.

b. Over load relay shall be in reset condition.

c. II bus isolator (89B) is open.

d. Breaker (52) is open

e. Local / remote switch is in remote position

f. Transfer bus isolator ( 89D) is open

The I bus isolator (89A) can be closed electrically from remote if the following
conditions are satisfied along with the above mentioned conditions (a to f). (If the
element is being taken in to service from shutdown).

g. Earth switch (E1) is open


12
h. CVT-A isolator in closed in condition i.e. 230Kv I bus shall be in

charged condition.

If the element is already in service on transfer bus then 89A can be opened if
transfer bus isolator (89D) is in closed condition, bus transfer isolator (89TrA) in
closed condition along with the above mentioned conditions ‘a to e’. If the element
is already in service on transfer bus then 89A can be closed if transfer bus isolator
(89D) is in closed condition, bus transfer isolator(89TrA) in closed condition and
the above mentioned conditions ‘a to e’ and “g&h’.

2.1 v ISOLATOR OPERATION:

For both the opening and closing operations 3phase AC and 220V DC switches
shall be in ON condition along with fuses. Fuse rating for 220V DC is 2A and for 3
phase AC is 4A. As soon as closing command is given from remote, Bus Bar
Protection CT switching relay 89AX (In CTMK) will pickup and extend DC
supply to the closing contact in MOM box.

The open indication of 89A will vanish immediately as soon as command is given
provided all the above interlocks are satisfied. Close indication is in series with
89A aux. Contact (NO) and 89AX(NO). When aux. contacts have changed while
closing, 89AY relay will pick up (In relay panel).

The open indication will come when the aux. Contacts are changed and 89AX is
reset. The open indication is in series with aux. contact (NC) and 89AX (NC).
When aux. contacts have changed while opening, 89AY relay will reset. This 89AY
relay is used for isolator contact multiplication purpose. A typical control circuit
for a 1st bus isolator is shown in fig 1.1.1

13
89A ISOLATOR CONTROL CIRCUIT
+ve -ve
220V DC SUPPLY
J 23

K529 89BY K567 52 K569 89D


FS 28
J 5A J5 J 7 FS KIMC OLR 89D 89TRA

4A K23
2A
89BY K537 89BCX K549

K49 89AX
K551 O NC 89A
LR K51
RC

K55 PBO C.C LSO


K53 K59 K547
OC

OC LSC
K31 CC K33 OC K43 K47
K45
CC
89E1 K571 89CVTA K531 K63
89AX-
MSC
K35
PBC O NC
CC
K539 K541 89AX
L R

K547

FS J FS29
J6
8
2A 4A

89A 89AX RED


L251

L253

89A 89AX GREEN


89A K573 89AY
CC
89A K575
RC

Fig 1.1.1 FIRST BUS ISOLATOR CONTROL CIRCUIT DIAGRRAM

14
2.2 BREAKER CONTROL CIRCUIT
There are two types of breakers available in the 230/400 Kv yard; one is gang
operated and another is individual pole operated. In the gang operated type all the
three poles are controlled by a single operating mechanism. In the individual pole
type, each pole will have its own operating mechanism. At switchyard three
different types of operating mechanisms are available. One is Spring Charging
mechanism, another is Hydraulic mechanism (oil) and the third one is Pneumatic
(air) mechanism.

Each breaker irrespective of the type will have one number Closing coil (CC) and
two numbers of Tripping coils(TC1 & TC2). Since opening of the breaker in case
of a fault in the system is more important as a redundancy two nos. of Trip coils
are provided. Each TC will be monitored for its healthiness by Trip coil
supervision relays (95,195). When the breaker is in open condition two relays will
monitor the TC healthiness via breaker NC aux. Contact. When in service one
relay will monitor the TC healthiness via breaker NO aux. Contact. When there is
any problem in the TC then its circuit supervision relay will sense and give alarm.
These trip coil supervision relays contacts are used in the closing circuit interlock
of the breaker. If any TC is unhealthy then the breaker will not close.

Breaker can be closed from the remote when the following interlocks are satisfied.

1. Both the earth switches E1&E2 are kept opened.

2. All the trip relays 86, including the Bus Bar protection relay 96 are in reset

condition.

3. Trip coil supervision relays are reset.

4. Local- remote switch in remote condition.


15
5. All the synchronizing conditions are satisfied.

6. Spring charged or sufficient oil or air pressure availability shall be ok depending


on the type of breaker.

2.2 i LOCAL BREAKER BACKUP PROTECTION

If any protection relay senses the fault and initiates a tripping via trip relay contacts
then the breaker TC1 & TC2 will pickup and breaker will open. If the breaker fails
to open even after receiving tripping signal then the fault will not get cleared and
lead to unwanted damages to other related equipments. To avoid such things one
backup protection for the breaker is available which is called Local Breaker
Backup protection (LBB) .

When the element is in service all the three phases current will be passing thro’ the
LBB relay. As soon as the trip relay picks up one of its contact will extend DC
supply to the trip coils. Simultaneously one more contact of the trip relay will
extend the DC supply to the LBB relay. As soon as DC supply is extended to the
LBB relay, the LBB relay will pickup and initiates a timer 2/50Z, which starts
counting 200ms. The TC1&TC2 will pickup as soon as DC supply was extended to
them and breaker will open. When the breaker opens the current thro’ the LBB
relay will become zero and the timer 2/50Z resets. But if the breaker did not open
then the current in that pole will be flowing thro’ LBB relay and after 200ms time
was lapsed the timer 2/50Z will pickup and initiates a contact in the Bus Bar
Protection DC circuit which in turn trips all the elements connected that bus where
the faulty breaker was connected. When all the elements connected to the bus
including the Bus coupler opens then the corresponding bus will become dead the
fault will be cleared. Maintenance personnel can access the breaker, which was not
opened and can start working.

16
2.3 FEEDERS DISTANCE PROTECTION

Basically these relays operate on the principle of Impedance (ratio V/I)


measurement. Any conductor used in the transmission line will have its own
characteristic impedance the value of which will be given by the manufacturer of
the conductor. When ever a fault occurs in the line the impedance will reduce
depending upon the fault current. A relay, which measures this impedance
continuously, will operate and trip the feeder to clear the fault. Theoretically the
V/I ratio measured will be constant for any particular fault position and will only
vary if the position of the fault with respect to the relay point varies. Thus nearer
the fault to the relay lower would be the ratio V/I and conversely the farther the
fault from the relay higher would be the ratio V/I. Hence this impedance relays are
also called as Distance protection relays.

2.4 BUS BAR PROTECTION (BBP)

2.4 i INTRODUCTION
BBP is provided for bus faults like flashover at the isolators, at the circuit breaker
bushings, CT and PT faults. A large proportion of bus bar faults results from
human error rather than a switchgear components failure. It also covers the failure
of insulators of isolators and breakers during operation and mal-operation of earth
switches.

2.4 ii BBP SYSTEM


The BBP relays should be sensitive so that the bus faults are sensed and cleared
instantaneously to ensure grid stability. In BBP scheme there are three zones viz.
zone-A, zone-B, zone-C covering first bus, second bus and Tr. bus. The BBP
scheme is based on differential protection principle, which compares the
magnitude and phase of the circulating currents in the respective zones of
protection.
17
The BBP circuit is the combination of CTs and relays which are used to detect
faults occurring within the bus bar zones and which initiates tripping of all those
circuit breakers connected in that zone so that the concerned bus will become dead
to isolate this faults.

2.4 iii BBP CT CIRCUIT


When BBP operates in any one of the busses, all elements connected to the faulty
bus including bus coupler trip. If the Transfer bus breaker is in service, it also gets
tripped. BBP will be always selective irrespective of the configuration. Each zone
has got three BBP Differential relays namely 87A, 87B, 87C. All the BBP CTs of
that zone are connected differentially with these relays. Two secondary cores
namely Core4 and Core 5 of the Switchyard CTs (1600A/1A in 230Kv side and
2000A/1A in 400kv side) of each element are used for the BBP. Core-4 is for Main
zone and Core 5 is for Check Zone.

Whenever an element is connected to the 1st bus or 2nd bus or Transfer bus
accordingly CT switching relays 89Ax or 89BX or 89Dx housed in the CT
Marshalling Kiosk of the respective bay in outdoor yard will pickup. CT secondary
of the BBP core 4 will be connected to the Main Zone differential relay circuits
Zone A, Zone B or Zone C through the 89Ax or 89BX or 89DX relay contacts.
BBP Core 5 will be directly connected to the Check Zone Differential relay
circuits. This check zone is to ensure that the fault has really occurred in the bus.

For bus coupler Breaker tripping, the BBP core of the B/C CT on the 1 st bus side
of the breaker will be connected to Zone-B and the BBP core of the B/C CT on the
2nd bus side of the breaker will be connected to Zone-A. For the transfer bus main
zone core is connected to zone-A or zone-B through 89TRAx or 89TRBx and core
2 is connected to zone-C.

18
2.4 iv OPERATION OF BBP
During normal operation secondary current will circulate in the zone and there will
not be any differential current passing thro' differential relay 87. In case of fault
the differential current flow thro' the respective relays which will initiate in case of
open circuit of any one of the CTs or when the unbalance current increases due to
the saturation of the any of the CTs differential current will flow thro' differential
relays which will initiate unnecessary tripping. To avoid mal operation like this
BBP supervisory relays 95A,B,C and CH are provided. These relays are connected
parallel to the differential relay 87. For low differential current flow thro' 87 & 95,
95 relay picks up earlier than 87 relays which will short the differential relay 87
after a time delay. An annunciation “Bus Bar Protection Zone A/ B /C Faulty “ will
come. Immediately the concerned element has to be checked and problem shall be
corrected otherwise till 95 relay is in picked up condition Busbar Protection of that
zone will be out of service. But when actual fault comes the diff.current flow will
be high and 87 picks up faster than 95. The diff. Relay 87 picks up instantaneously
before 95 relay shorts this relay. The connections of the BBP circuits are shown in
the fig.2.4.1 to 2.4.3.

2.4 v BBP ACTUATION SCHEME


Each element has got a BBP relay (96) which will trip the particular element. In
case when the BBP operates 96 relay of all the elements connected to the particular
bus have to energise including B/C. For each zone BBP cut out switch is provided
in the control panel. In case BBP operates in any one of the buses, differential
relays 87CH along with 87A or 87B or 87 C will energise 96 relay of allthe
elements connected to that bus including B/C.

19
In case LBB operates for anyone of the elements 2/50z and 50z will initiate BBP.
87 CH check zone differential relay which get energized from separate CT core to
ensure that really a fault has occurred and BBP should not act for false pick up of
the main zone 87A, 87B, 87C differential relays. If the 87C Check Zone relay is
not available then for any false pick up of the Zone A,B,C differential relays
87A,87B or 87C the BBP will act.

20
TYPICAL TYPICAL
UNIT BUS I FEEDER BUS I

BUS II BUS II
TRANSFER BUS TRANSFER BUS

89A 89B 89A 89B


89D
89D

52 52

TTB2 TTB2
89C

TTB1
TTB1
89AX 89AX

ZONE 1 BUS B
WIRES
C

89BX 89BX

A
ZONE 2 BUS
WIRES B

89DX 89DX
A

ZONE 3 BUS B
WIRES
C

B
CHECK ZONE
BUS WIRES C

Fig : 2.4.1 BBP ZONE 1,2,3 & CHECK ZONE CT CONNECTION DIAGRAM

21
A B11 A B15 A B21
ZONE I

Z O N E II
B B31 B41

W IR E S
B B35 ZONE III B
WIRES
C B51 C B55 WIRES C B61
N B81 N B81 N B81
95CAX 95CBX 95CCX

SD1 SD2 SD3 SD4 SD6 SD7 SD8 SD9


SD5

10-70V 10-70V 10-70V

9
9 9
5 5
5
25-325V C C
25-325V C 25-325V
87 87 87 B 87 87 87 C
87 87 87 A
AC BA BB BC CA CB CC
AA AB

IN OUT IN OUT
IN OUT

A
B
Check Zone wires C
N B81
95CX

SD7 SD8 SD9

10-70V

9
5
25-325V C
87B
87A
CH
87C H
CH CH

IN OUT

Fig 2.4.2 BBP DIFFERENTIAL RELAYS


22
23
80T

- Ve
P11

P13
P15
TRANSFER BUS
COUPLER

CC

CC
CC

96

96
96
2/50Z
96
ABC
50Z 2/50Z

89TRBX 96 96 96
AB AB AB
89TRAX 96
C
89DX TYPICAL ICT.
50Z 2/50ZX

89BX 96 96 96

89AX 96
C
89DX
TYPICAL G.T
50Z 2/50ZX

89BX 96 96 96

89AX
97
C
89DX
96
X
I II B/T 50Z
TYPICAL
89BX FEEDER
96 96 96
+ve

89AX

96 96 96
B B B
C C C
2/50Z

B B B

50Z
2/50Z

96 96 96
B B B P2
C C C
A A A
OUT

P15

P13

P11
Zone C
IN

87CC
OUT

87CB
P9

Zone B

87CA
IN
OUT

CHECK

87BC
P7
P3
IN

OUT

87BB
Zone C

87BA
IN
P1

87AC
P5

87CHC
P3

87CHB 87AB

87CHA 87AA

Fig 2.4.3 BBP DC CIRCUIT

24

You might also like