DETAIL B9
AT ABOVE AND BELOW GROUND EXTERNAL WALL
13mm Plaster finish.
RIW Flexiseal to manufacturers guidance (yellow dashed line) with 25mm x Weep hole.
25mm fillet of RIW Cementfill HB to internal corner of cavity.
50mm Portland stone paviours.
65mm concrete screed to Structural Engineers specification. 50mm Kingspan Styrozone N300R insulation.
British Gypsum Casoline MF suspended ceiling system. RIW Sheetseal 9000 DPC.
Geotextile layer.
RIW Cavity Drain membrane sealed at top to underside of slab using RIW RIW Structureseal.
35 Avenue Road
London
NW8
Basement Details 01
A
EQR_DTL01
External
DETAIL B6
AT ABOVE AND BELOW GROUND EXTERNAL WALL IN
SERVICE STAIR AREA
13mm Plaster finish.
Geotextile layer.
Plasterboard and skim finish.
RIW Structureseal.
RIW Cavity Drain membrane sealed at top level with the underside of the
concrete slab using RIW Sealing Rope to manufacturers guidance.
DETAIL B4
13mm Plaster finish. EXTERNAL WALL DETAIL AT LIGHTWELL
100mm Blockwork to Structural Engineers specification. 13mm Plaster finish.
25mm Kingspan TF70 insulation. 100mm Blockwork to Structural Engineers specification.
RIW Cavity drain membrane. 25mm Kingspan TF70 insulation.
FOR
Concrete structure to Structural Engineers specification. RIW Cavity Drain system 5mm. CONSTRUCTION
Concrete piling and temporary retaining structure to Structural Engineers 215mm Blockwork to Structural Engineers specification.
specification. BB PARTNERSHIP LTD
C H A R T E R E D A R C H I T E C T S
RIW Toughseal to manufacturers guidance (orange dashed line) to over lap
past drained cavity by minimum 500mm, aggregate to be applied to surface in
all areas which are to have render applied.
Sri Lankan High Commission
Concrete wall to Structural Engineers specification.
A
EQR_DTL02
EXTERNAL BASEMENT WALL & FLOOR JUNCTION AT 215mm Blockwork to Structural Engineers specification. RIW Sheetseal 9000 DPC.
RIW Flexiseal.
75mm Kingspan Kooltherm K8 insulation and 25mm air gap.
RIW Structureseal to exterior of concrete retaining structure continuing around Geotextile layer.
lightwell area and minimum 500mm past basement cavity wall (run behind 100mm Blockwork to Structural Engineers specification. RIW Structureseal.
drained cavity mambrane) and minimum 1000mm under concrete floor slab.
RIW Sheetseal 226 sealed to RIW Tooughseal and RIW Cavity Drain
Render finish, 20mm - reinforced as necessary. membrane.
RIW Toughseal with surface aggregate to manufacturers guidance (orange 25mm Kingspan TF70 insulation.
dashed line) aggregate to be applied to surface areas which are to take a
rendered finish. RIW Cavity Drain system 20mm, studs filled with non-compressable material.
Concrete upstand.
FOR
Stone paving tbc. CONSTRUCTION
Solobloc Twin Leaf manhole cover on cement mortar bed to Structural
Engineers specification. BB PARTNERSHIP LTD
C H A R T E R E D A R C H I T E C T S
35 Avenue Road
London
NW8
Basement Details 03
A B
EQR_DTL03
Lift pit and interior of lift shaft to have applied RIW Cementseal to manufacturers RIW Cavity Drain system 5mm sealed to RIW Cavity Drain 5mm using RIW
guidance (blue dash-dot-dash line) with 25mm x 25mm fillet of RIW Cementfill HB 'Wall/Floor Junction'.
to horizontal and vertical internal corners, Cementseal should continue to 500mm
above main basement slab level (level with the RIW Toughseal noted below) LIFT SHAFT RIW Sheetseal 9000 DPC sealed to RIW Cavity Drain membrane using
RIW Double Sided Tape 150mm.
2No. coats of RIW Toughseal (Orange Line) 150mm horizontal and 500mm
vertical application. RIW Grade 1 aggregate must be applied to the top 400mm of 1No. course of Foamglas Perinsul insulating loadbearing blockwork.
the vertical application while the second coat is still wet.
Weep holes, frequency to RIW guidance.
RIW Sheetseal 226 (pink dotted line).
Floor finish - 25mm zone.
90mm concrete screed to Structural Engineers specification.
65mm concrete screed to Structural Engineers specification.
25mm Kingspan TF70 insulation.
25mm Kingspan TF70 insulation.
RIW Cavity Drain system 20mm, studs filled with non-compressable material.
RIW Cavity Drain system 20mm, studs filled with non-compressable material
Concrete slab to Structural Engineers specification primed with RIW Cementseal and sealed to RIW Cavity Drain 5mm at wall using RIW 'Wall/Floor Junction'.
Primer.
Concrete slab to Structural Engineers specification primed with RIW
Cementseal Primer.
13mm Plaster finish. RIW Cementseal to manufacturers guidance (blue dash-dot-dash line).
Concrete structure to Structural Engineers specification. RIW Cavity Drain system 20mm.
RIW Cementseal to manufacturers guidance (blue dash-dot-dash line) with 25mm x RIW Sheetseal 9000 DPC.
25mm fillet of RIW Cementfill HB to horizontal and vertical internal corners. RIW Sheetseal 226.
RIW Flexiseal.
DETAIL B8
RIW Structureseal.
A B C
EQR_DTL04
DETAIL R1
Hanson 129-250 square beaded rebated chimney pot
450mm high in slate bodymix (colour).
Liquid Plastics 'Carrier Membrane' bonded with Fully reinforced Liquid Plastics Decothane Liquid Plastics 'Carrier Membrane' bonded with
'Decostik'. Waterproofing System dressed on to prepared and 'Decostik'.
primed stanchions/penetrations in strict accordance with
75mm 'Decotherm' insulation from Liquid Plastics. Liquid Plastics Project Specification 75mm 'Decotherm' insulation from Liquid Plastics.
Acoustic louvres - see EEC standard drawing 'Typical
Louvre Roof Perimeter Support' Liquid Plastics Vapour Control Layer. 75mm 'Decotherm' insulation from Liquid Plastics. Liquid Plastics Vapour Control Layer.
Insulated cavity closer. Liquid Plastics Vapour Control Layer. Insulated cavity closer.
Decotrim Type C (100mm) angle piece from Liquid Concrete deck to Structural Engineers specification Decotrim Type C (100mm) angle piece from Liquid
Plastics, waterproofing system terminated in the integral prepared in strict accordance with Liquid Plastics Plastics, waterproofing system terminated in the integral
protected upstand. protected upstand.
140mm Blockwork to Structural Engineers spec. 100mm Blockwork to Structural Engineers spec. 100mm Blockwork to Structural Engineers spec.
Void. Concrete deck to Structural Engineers specification Concrete deck to Structural Engineers specification
prepared in strict accordance with Liquid Plastics prepared in strict accordance with Liquid Plastics
100mm Blockwork to Structural Engineers spec. Project Specification. Project Specification.
20mm Painted render finish. 75mm Kingspan Kooltherm K8 insulation with 25mm air 75mm Kingspan Kooltherm K8 insulation with 25mm air
gap to outside face. gap to outside face.
Painted render band 75mm high projecting 35mm beyond
surrounding render coat. 215mm Blockwork to Structural Engineers spec. 215mm Blockwork to Structural Engineers spec.
20mm Painted render finish. Liquid Plastics roofing system from green roof area
dressed up wall and behind Decotrim metal angle piece.
Lift shaft.
Lift shaft.
DETAIL S1
Roofing system is Liquid Plastics 'Cold Fusion Delta 25' DETAIL R4
Concrete paving slabs or similar appropriately proportioned pre-cast concrete plinth Roofing system is Liquid Plastics 'Cold Fusion Delta 25'
used to evenly distribute loadings exerted by the item of plant supplied and positioned
as necessary for plant items. 2No. 'Decothane Root Resistant Detail Coats' applied to exposed upstands to overlap
horizontal by minimum 150mm.
Proprietary neoprene pad introduced to prevent abrasion of Decothane Waterproofing
System. Gravel ballast border.
215mm Blockwork to Structural Engineers spec. 50mm x 50mm treated timber sw fillet bonded with 'Decostik'.
75mm Kingspan Kooltherm K8 insulation with 25mm air gap to exterior face. Perforated Aluminium retaining angle.
100mm Blockwork to Structural Engineers spec. 'Decothane Root Resistant Inverted Top Coat'.
20mm Painted render finish. 'Decothane Base Coat' with embedded Reemat Premium GFM.
Render stop. Liquid Plastics 'Carrier Membrane' bonded with 'Decostik'.
'Decothane Waterproofing System dressed on to prepared and primed upstand Tapered 'Decotherm Insulation' from Liquid Plastics, for thicknesses and tapered
surface. layout see Liquid Plastics project drawing 18521-001.
50mm x 50mm treated timber SW fillet bonded with 'Decostik'. Liquid Plastics Vapour Control Layer.
'Decothane Top Coat'. Concrete deck to Structural Engineers specification prepared in strict accordance with
Liquid Plastics Project Specification.
'Decothane Base Coat'.
40mm thick pre grown Sedum Blanket.
Liquid Plastics 'Carrier Membrane' bonded with 'Decostik'.
Rooflight from www.Lonsdalemetal.co.uk Spangard range compliant with CDM
40mm thick Sedum Substrate.
Tapered 'Decotherm Insulation' from Liquid Plastics, for thicknesses and tapered non-fragility requirements, Class C resistant to person falling onto it.
layout see Liquid Plastics project drawing 18521-001. Liquid Plastics 'Filtration Layer'.
FOR
Minimum 50mm 75mm wide timber upstand to suit.
Liquid Plastics Vapour Control Layer. 38-40mm thick Biodrain water retention layer.
75mm Rockwool Cavity insulation.
Concrete deck to Structural Engineers specification prepared in strict accordance with
Minimum 150mm 18mm WBP Plywood.
Liquid Plastics Project Specification.
35 Avenue Road
London
NW8
Details 05
Superstructure
A
EQR_DTL05
40mm thick pre grown Sedum Blanket. Painted render band 75mm high projecting 35mm beyond
surrounding render coat.
40mm thick Sedum Substrate.
75mm Kingspan Kooltherm K8 and 25mm air gap.
Liquid Plastics 'Filtration Layer'.
Recon stonework detailing painted finish. 75mm Kingspan Kooltherm K8 and 25mm air gap.
38-40mm thick Biodrain water retention layer.
100mm Blockwork to Structural Engineers spec.
DETAIL G1
Front Doorset.
Drainage channel.
FOR
Floor finish.
65mm Screed.
CONSTRUCTION
DETAIL S3
Conservation Bax Sash window by Mumford & Wood.
Details 06
Superstructure
A
EQR_DTL06
DETAIL R6
Roofing system is Liquid Plastics 'Cold Fusion Delta 25'
Liquid Plastics type D Decotrim fixed to protect the corner bonded with Decostik.
2No. 'Decothane Root Resistant Detail Coats' applied to exposed upstands to overlap
horizontal by minimum 150mm.
Services void
DETAIL G3
Stone Balustrading
CONSTRUCTION
gap to outside face.
Details 07
Services void.
Superstructure
British Gypsum Casoline MF suspended ceiling system.
Steel support bracket for window surround to Structural Dec 2010 1:10@A1 Mike M
Engineers spec.
A
EQR_DTL07
Recon stone window surround.
100mm Blockwork to Structural Engineers spec. 30mm 'Decotherm Insulation' from Liquid Plastics.
Steelwork to Structural Engineers spec. 2No. 'Decothane Root Resistant Detail Coats' applied to exposed upstands to overlap
horizontal by minimum 150mm.
Steel support bracket for window surround to Structural
Engineers spec. Concrete slab to Structural Engineers spec. Gravel ballast border.
Concrete lintel to Structural Engineers spec. Services void. 50mm x 50mm treated timber sw fillet bonded with 'Decostik'.
Recon stone window surround painted finish. British Gypsum Casoline MF suspended ceiling system. Perforated Aluminium retaining angle.
15mm British Gypsum plasterboard and skim finish. 'Decothane Root Resistant Inverted Top Coat'.
Timber packing pieces to suit. 'Decothane Base Coat' with embedded Reemat Premium GFM.
12.5mm plasterboard and skim finish, 8mm skim to Liquid Plastics 'Carrier Membrane' bonded with 'Decostik'.
underside of window head.
Tapered 'Decotherm Insulation' from Liquid Plastics, for thicknesses and tapered
Mumford & Wood Conservation Box Sash with 85mm layout see Liquid Plastics project drawing 18521-001.
cill extension.
Liquid Plastics Vapour Control Layer.
Concrete deck to Structural Engineers specification prepared in strict accordance with 25mm Kingspan Kooltherm K8 insulation.
Liquid Plastics Project Specification.
Lead flashing code 5 dressed over Airtrak ventilator.
40mm thick pre grown Sedum Blanket.
Nicholson (tel 0845 0098 980) Airtrak AB abutment ventilator.
40mm thick Sedum Substrate.
DETAIL F5 Liquid Plastics 'Filtration Layer'. 18
Lead covered (code 5) wood core roll maximum spacing is
600mm.
150
Mumford & Wood Conservation Box Sash with 60mm 38-40mm thick Biodrain water retention layer.
minimum 225mm
Leadwork code 5 on separating membrane.
75
minimum 150mm
cill extension.
25 25
minimum 75mm
Insulated cavity closer.
25mm Kingspan TF70 insulation. 125mm Kingspan TP10 insulation between 200x50mm timber
joists to Structural Engineers spec.
Concrete structure to Structural Engineers spec.
50x50mm Timber battens at 450c/c.
Services void.
70mm Painted render band. British Gypsum 15mm plasterboard and skim finish.
Services void.
CONSTRUCTION
cill extension.
Planting.
35mm thick hardwood timber window cill.
Blockwork to Structural Engineers spec.
Timber packing piece to suit.
20mm Painted render finish.
13mm Plaster finish.
Concrete structure to Structural Engineers spec.
Concrete structure to Structural Engineers spec.
Earth.
Floor finish.
35 Avenue Road
20mm Painted render finish.
London
NW8
Details 08
Superstructure
DETAIL R8
Lead covered (code 5) wood core roll maximum spacing
is 600mm.
Leadwork code 5.
DETAIL R9
Mumford & Wood Conservation Box Sash with 85mm
cill extension.
Slate tiles. Treated timber firring battens 50mm at maximum and 25mm at
minimum.
175x50mm timber dormer framework to Structural
Engineers spec. Leadwork code 5 on separating membrane.
25x50mm Treated timber counter batten. 25x50mm Treated timber softwood batten.
SW Treated timber tilting fillet to suit. 125mm Kingspan TP10 insulation between 150x50mm timber
framework to Structural Engineers spec.
18mm WBP Plywood.
Two layers of 22mm WBP plywood trim.
SW Treated timber tilting fillet to suit.
Recon stone balustrading. 18mm WBP Plywood.
80mm + 70mm Kingspan Kooltherm K12 insulation with
25mm air gap to interior side. Tyvek roofing membrane.
Leadwork guttering using T-pren jointing system and
200x50mm timber mansard rafters to Structural laid to fall 75mm at maximum.
Leadwork code 5 on separating membrane.
Engineers spec.
Lead flashing code 5 on separating membrane.
100mm Kingspan Kooltherm K7 insulation between studwork.
Floor finish.
Cavity closer.
Vapour control layer.
65mm Screed.
Recon Stone detailing painted finish.
82.5mm Kingspan Kooltherm K18 insulation backed
25mm Kingspan TF70 insulation. plasterboard with plaster skim finish.
25mm Kingspan TR26 insulation.
Concrete structure to Structural Engineers spec.
50x50mm Treated SW timber fillet.
Services void.
100x50mm Timber studwork to Structural Engineers spec.
British Gypsum Casoline MF suspended ceiling system.
32.5mm Kingspan Kooltherm K18 insulation backed
FOR
75mm Kingspan Kooltherm K8 insulation and 25mm air plasterboard with plaster skim finish.
gap.
Details 09
Superstructure
Lift shaft.
A
EQR_DTL09
DETAIL F7
Roofing system is Liquid Plastics 'Cold Fusion Delta 25'
Roofing system is Liquid Plastics 'Cold Fusion Delta 25'
Recon Portland Stone coping 75mm at maximum and 50mm at
100mm Blockwork to Structural Engineers spec. Liquid Plastics 'Carrier Membrane' bonded with 'Decostik'. Liquid Plastics 'Carrier Membrane' bonded with 'Decostik'.
Steelwork to Structural Engineers spec. Tapered 'Decotherm Insulation' from Liquid Plastics, for thicknesses Tapered 'Decotherm Insulation' from Liquid Plastics, for thicknesses
Minimum 50mm and tapered layout see Liquid Plastics project drawing 18521-001. and tapered layout see Liquid Plastics project drawing 18521-001. Minimum 50mm
Floor finish.
Liquid Plastics Vapour Control Layer. Liquid Plastics Vapour Control Layer.
65mm Screed.
Minimum 150mm Concrete deck to Structural Engineers specification prepared in Concrete deck to Structural Engineers specification prepared in Minimum 150mm
25mm Kingspan TF70 insulation. strict accordance with Liquid Plastics Project Specification. strict accordance with Liquid Plastics Project Specification.
DETAIL G7
50mm Painted render finish over window surround.
Services void.
Steel support for recon stone window surround to Structural Engineers spec.
FOR
CONSTRUCTION
BB PARTNERSHIP LTD
C H A R T E R E D A R C H I T E C T S
35 Avenue Road
London
NW8
Details 10
Superstructure
A
EQR_DTL10
215mm Blockwork to Structural Engineers spec. Mumford & Wood 'Conservation Box Sash Window'.
75mm Kingspan Kooltherm K8 insulation and 25mm air 13mm plaster finish.
gap.
215mm Blockwork to Structural Engineers spec.
Insulated cavity closer.
Insulated cavity closer.
Timber window cill.
75mm Kingspan Kooltherm K8 insulation and 25mm air
Mumford & Wood 'Conservation Box Sash Window'. gap.
140mm Blockwork to Structural Engineers spec. Recon stone window surround painted finish.
DETAIL G9
13mm plaster finish.
DETAIL F8
215mm Blockwork to Structural Engineers spec.
Timber window cill.
Architrave (see finishes schedule). DETAIL G10 Mumford & Wood 'Conservation Box Sash Window'.
75mm Kingspan Kooltherm K8 insulation and 25mm air
gap. 13mm plaster finish. Architrave (see finishes schedule).
Insulated cavity closer. 215mm Blockwork to Structural Engineers spec. 13mm plaster finish.
Timber window cill. Architrave (see finishes schedule). 140mm Blockwork to Structural Engineers spec.
Mumford & Wood 'Conservation Box Sash Window'. 75mm Kingspan Kooltherm K8 insulation and 25mm air Insulated cavity closer.
gap.
75mm Kingspan Kooltherm K8 insulation and 25mm air
Insulated cavity closer. gap.
Front Doorset.
35 Avenue Road
London
NW8
Recon stone cill painted finish. Recon stone window surround painted finish.
100mm Blockwork to Structural Engineers spec.
100mm Blockwork to Structural Engineers spec. Recon stone cill painted finish.
A
EQR_DTL11
Drainage channel.
Floor finish.
65mm Screed.
Knauf Aquapanel external cement board lining system consisting of Exterior British Gypsum Casoline MF suspended ceiling system.
grade steel frame system, Aquapanel exterior cement board, Aquapanel
exterior joint filler, Aquapanel exterior primer, Aquapanel exterior reinforcing 15mm British Gypsum plasterboard and skim finish.
mesh, Aquapanel joint filler and skim coat - white.
215mm Blockwork to Structural Engineers specification.
100mm Blockwork to Structural Engineers specification.
Concrete lintels to Structural Engineers spec.
Timber packing piece to suit.
13mm Plaster finish.
Render finish, 20mm - reinforced as necessary.
75mm Kingspan Kooltherm K8 insulation and 25mm air gap.
RIW Toughseal with surface aggregate to manufacturers guidance (orange
dashed line) aggregate to be applied to surface areas which are to take a Mumford & Wood Conservation Box Sash with 60mm cill extension.
rendered finish.
RIW Toughseal with surface aggregate to manufacturers guidance (orange 25mm Kingspan TF70 insulation.
dashed line) aggregate to be applied to surface areas which are to take a
rendered finish. RIW Cavity Drain system 20mm, studs filled with non-compressable material.
Concrete upstand.
PUMP CHAMBER
TO STRUCTURAL
ENGINEERS
SPECIFICATION
FOR
CONSTRUCTION
BB PARTNERSHIP LTD
C H A R T E R E D A R C H I T E C T S
35 Avenue Road
London
NW8
Basement Details 12
A
EQR_DTL12
RIW Flexiseal.
Geotextile layer.
RIW Structureseal.
DETAIL B7
DAMP PROOFING AT LIFT PIT AND JUNCTION WITH
FLOOR DRAINED CAVITY
13mm Plaster finish.
Service lift shaft. 25mm Kingspan TF70 insulation. 100mm blockwork to Structural Engineers specification.
100mm Blockwork to Structural Engineers specification. RIW Cavity Drain system 20mm, studs filled with non-compressable material. 25mm Kingspan TF70 insulation.
25mm Kingspan TF70 insulation. Concrete slab to Structural Engineers specification primed with RIW Cementseal RIW Cavity Drain system 5mm (red line).
Primer.
RIW Cavity Drain system 5mm. RIW Sheetseal 9000 to manufacturers guidance sealed to RIW cementseal and
RIW Cavity Drain (purple dash-dot-dash line).
Concrete wall to Structural Engineers specification.
Preformed metal drainage channel with falls towards stair area.
Green shading shows extent of Aluminium drainage channel, which is to fall
from the centre of the run to either end, drainage channel to be sealed to 110mm Concrete upstand.
surrounding structure using RIW cavity drain sealant to manufacturers
guidance. RIW Cementseal to manufacturers guidance (blue dash-dot-dash line) with 25mm
x 25mm fillet of RIW Cementfill HB to horizontal and vertical internal corners.
FOR
CONSTRUCTION
BB PARTNERSHIP LTD
C H A R T E R E D A R C H I T E C T S
35 Avenue Road
London
NW8
Basement Details 13
EQR_DTL13