You are on page 1of 67

Material Waste and Cost Overrun 1

Running Head: MATERIAL WASTE AND COST OVERRUN

A Study of Material Waste and Cost Overrun

(Based on Evidence from Construction Project in United Arab Emirates)

[Name of the Writer]

[Name of the Institution]


Material Waste and Cost Overrun 2

DECLARATION

I declare that the literature and research included in this study is my own work. Some concepts

and theories have been adapted or taken from other researchers and authors that have been cited

properly. This study consist around 15000 words approximately.

Signed - …………………………………….

Date - ………………………………………
Material Waste and Cost Overrun 3

ACKNOWLEDGEMENT

My sincere thanks to everyone who helped me in many ways either it was verbal assistance or

material help, this contribution from all has enabled me to complete the study in the most

effective way.
Material Waste and Cost Overrun 4

ABSTRACT

In the construction field, materials wastage is a significant issue which needs to be addressed on

urgent basis. Wastage of materials creates a massive difference in increased project costs which

has affected several completed construction projects around the globe. This research aims to

study the link between the cost overrun and waste of materials to reduce run at the project’s

construction phase. The results obtained after the completion of the projects shows that all the

factors that causes waste of materials have a direct impact on the cost overrun of the construction

project.

The objective of the research is to signify the outcomes of an independently conducted research

on the subject of the waste materials’ impact on the cost overrun in the construction field.

Current projects of housing schemes were included in the project from UAE, amongst all a

sample of nine houses under construction in two projects was intentionally chosen. The source of

the data for this study came from the archival records (BOQ, drawings, and Project development

report) and field analysis on cost overrun and waste of material. The data that was collected for

the study was examined by utilizing the method of Pearson moment correlation.

The results of the research showed a statically noteworthy connection between waste of materials

and cost overrun. The results imply that the increase in the amount of material waste is directly

proportional to the cost overrun.

This study suggests that the managers and supervisors of the project and also the other managing

personnel of the project must reflect on the causes of the waste materials handling since it can

significantly minimize the factors effecting the cost overrun of the project.
Material Waste and Cost Overrun 5

TABLE OF CONTENT

Contents

Introduction ..................................................................................................................................... 8

Need for the Study..................................................................................................................... 10

Problem Statement .................................................................................................................... 10

The Pre-contract Stage of a Construction Project ................................................................. 11

The Post Contract Stage of a Construction Project ............................................................... 11

Purpose of the Study ................................................................................................................. 12

Research Hypothesis ................................................................................................................. 12

Aim of the Research .................................................................................................................. 12

Literature Review.......................................................................................................................... 13

Waste in Construction ............................................................................................................... 18

Definition of Waste ............................................................................................................... 18

Material Waste .......................................................................................................................... 19

Physical Construction Waste ..................................................................................................... 19

Amount of Waste Material in Construction .............................................................................. 20

Sources of Materials Waste ....................................................................................................... 21

Direct Waste .......................................................................................................................... 21

Indirect Waste ........................................................................................................................ 22

Causes of Material Waste .......................................................................................................... 24


Material Waste and Cost Overrun 6

Steel Reinforcement .............................................................................................................. 25

Concrete ................................................................................................................................. 25

Timber Formwork.................................................................................................................. 26

Block Work............................................................................................................................ 26

Cement Sand Mortar (Plastering) .......................................................................................... 27

Tile work................................................................................................................................ 27

Material Waste Control on Site ................................................................................................. 27

Waste Minimization in Construction ........................................................................................ 28

The 3 “Rs “ of Construction Waste Minimization .................................................................... 30

Source Reduction ................................................................................................................... 30

Benefit of the Construction Waste Minimization ..................................................................... 30

Relationship between Material Waste and Construction Cost Overrun .................................... 31

Construction Cost Overrun........................................................................................................ 32

Causes of Cost Overruns ........................................................................................................... 32

Construction-Material Waste and Cost Overrun ....................................................................... 34

Research Methodology ................................................................................................................. 35

The Qualitative Method ............................................................................................................ 36

Material Wastage Percentage during Construction Activities ............................................... 36

Percentage Contribution of Material Waste to Cost Overrun................................................ 42

Test of Hypotheses ................................................................................................................ 47


Material Waste and Cost Overrun 7

Factors That Contributes To Material Wastages on Construction Sites ................................ 48

Quantitative Method .................................................................................................................. 52

Data Collection Procedure ........................................................................................................ 53

Data Collection and Analysis .................................................................................................... 53

Outline of Methodology ............................................................................................................ 54

Field Investigation ..................................................................................................................... 54

Procedure for Data Gathering and Analysis .......................................................................... 55

Case Study ................................................................................................................................. 55

Statistical Data Analysis............................................................................................................ 57

Reinforcements.......................................................................................................................... 57

Ceramic Tile .............................................................................................................................. 58

Findings and Discussions .............................................................................................................. 58

Discussion of Factors Causing Waste of Material and Cost Overrun ....................................... 61

Category 1: Contractor's Site Management Related Factor (CSM) Contractor's Site .............. 61

Design and Documentation Related Factor (DDF) ............................................................... 65

Conclusion .................................................................................................................................... 66

References ..................................................................................................................................... 67
Material Waste and Cost Overrun 8

Material Waste and Cost Overrun

Introduction

The most vital and essential part in development of structures like roads and highways of

a country or a state is construction. Nonetheless, the building or construction material waste is

the most common problem which is faced by many countries. As compared to many other

manufacturing industries, the construction or building activities creates and produced the most

material waste. The wastage of materials in construction and building hustle causes to decrease

the productivity which affects the atmosphere badly and raises the price of the project and

schemes. It is hard and difficult to reuse and reutilize the constructing material waste. There is no

enough space for the removal of material waste as well. Mostly, the resources which are in

excess and get wasted are timber, mortar, bricks, steel, concrete, polyvinyl chloride pipes, paints,

glass etc... But the materials which get wasted in minimal quantity and disturb the effectiveness

of products are tiles, polyvinyl chloride pipes, paints and electrical fixtures. As these materials

are wasted in minimal quantity so they are not important in producing the waste material. These

materials can harm the environment and atmosphere as they are not decomposed substances

which can be easily dumped and disposed.

Building commercial enterprises sustenance towards public is equal as financial

development of any state through serving to keep up good and excellent living by offering the

structure like institutes, health care hospitals, roads and further elementary amenities. Therefore,

it’s significant that the building development or schemes should be accomplished in the arranged

or planned period, in accounted price and it should encounter the attributes. A huge proportion of

manufactured product’s price is shown by resources excess from the building industry which is

stated in so many researches. Hence, the deprived supervision of surplus and supplies compel to
Material Waste and Cost Overrun 9

raise the entire construction price. Apart from project revenue, waste excess is significant as well

but there are some problems rising because of the material waste which can harm the

atmosphere. There is no enough space for waste disposal in the state and it is very hard to

reutilize or reuse the waste material due to the increase in criminal activities.

The waste resources during the manufacturing process are a critical matter and it needs

concentration in the building enterprise. It harmfully affected the distribution of numerous

schemes and developments in the period of time and extra building resources are often purchased

because of the wastage of materials in the building processes. The amount of excess of resources

which is produced on many building and manufacturing sites surpasses the budget. (8 percent or

15 percent or whatsoever rely on the resources and roughly additional situations). Therefore,

maintain the wastage of resources when making the evaluation of the schemes or plan. It’s

difficult to comprehend the proportion of the extra price which is paid by the depletion of

resources to the building enterprise.

Waste contributed huge proportion of the entire project as it is stated by previous studies

from numerous states. For Example: Due to the added price of 15 percent to the construction

project, the price occupies the outcome of material wastages as it is stated in UAE study by

Skoyle in Tam et al (2007). Hong Kong Construction association and Hong Kong Poly technical

did a research in (1993) that the wastage of material increased the cost at 11 percent. There are

similar studies in Netherland which states that the sum of material wastages is among 20 percent

to 30 percent of project cost increase.

Therefore, any changes or enhancements in the construction supplies manages on the

location of construction throughout the building process which is able to raise the presentation of
Material Waste and Cost Overrun 10

the construction enterprise and it receives the cost profit and the construction material waste on

the location during the constructing procedure tends to increase the cost.

Need for the Study

All around the United Kingdom, pink chicken livers are in high demand in several

restaurants and pubs, and the fundamental reason for this trend is because the chicken liver is

served rare or pink (Paxton 2016). In a research conducted by the Manchester University, which

included more than 1000 participants, chefs, and the general public, were asked regarding their

choices, and whether they could spot carefully safe to eat meats. By sight, most of the

participants were not capable of identifying securely cooked pink chicken livers. Approximately

30% of the public categorized pink livers as safe to eat which in reality had forecasted rates of

survival of Campylobacter between 46% and 96%.

Problem Statement

The basic aim of this research was to investigate the impact of waste of materials

throughout the process of construction on construction fields and the cost overruns associated

with it. The other objective of this study was to examine the precise materials which are wasted

during the process of construction.

Following are the acts that could be included for the waste of materials at the pre & post

stage of the contact throughout the construction project.


Material Waste and Cost Overrun 11

The Pre-contract Stage of a Construction Project

There are several acts encompassed for the waste of materials at the pre-contract stage

from the beginning till the contract is awarded, for instance, budget proposal, feasibilities, BOQ,

initial and detailed design, and estimation. If these acts are not methodically controlled and

managed, it can result in waste of material and fitting cost overrun.

The Post Contract Stage of a Construction Project

The acts responsible for waste of material in the post contract stage in the construction

project involve the following things:

 Construction occurring on the site

 Management

 Scrutiny

 Authorization

 User occupation

 Finishing Point

 Client Hand over

 Correction of defects

 Contract completion

 Settlement of the final account

Though this research will only aims at issues related to construction and expect to signify

the real part of waste gathered from construction materials (throughout the process of

construction) to cost overrun in the construction project.


Material Waste and Cost Overrun 12

Purpose of the Study

As mentioned earlier, wastage of material during construction projects is a significant

issue which is needed to be addressed soon. Every stakeholder in construction field has

acknowledged this matter and they all have realized that it is having a major effect in the profit

of their project. However; not much has been done by the industry giants to find an answer to

this question. This was the reason to choose this topic for the research.

Research Hypothesis

The hypothesis presumed for this study is:

H1– There is a noteworthy connection between the cost overrun of a construction project and the

amount of waste generated from a variety of materials used in building throughout the

construction phases on sites.

Aim of the Research

Wastage of material is a significant issue in the industry of construction and how to

completely eliminate or reduce cost overruns from a construction project because of wastage of

material. This research looks to find the more building materials that are wasted during the entire

process of construction and the material waste percentage role of every recognized material to

cost overrun of the project.

Objectives

The basic objective was to investigate the exact contribution of material wasted during

construction to the construction project’s cost overrun. Other than the basic aim, there are going
Material Waste and Cost Overrun 13

to be several other small objectives linked with the major objective of the research. The sub

objectives include:

- Discover the additional wasteful building materials throughout the operation of the construction.

- The factors involved which affect directly to the material wastage during construction project?

- To identify why, where, and when those matters and factors happened during construction

project.

- To investigate the individuals responsible for these problems and factors

- To highlight how these issues can be resolved, waste of materials in construction project can be

minimized and how the cost overruns can be decreased.

Literature Review

The most important aspect for economic and social success of any state is construction

industry. Anyways, it is met with some serious problems of cost increase, waste of construction

and increase in time period. Wastage of material resources is a severe problem which needs to be

taken care of soon and it has somehow the power to deliver the projects.

Alternatively, cost overrun is usual issue in developing and developed states and

countries which tend to fail the projects to be accomplished in the given amount. Cost overrun is

a very common problem which is being observed in many countries of the world. The

arrangement in the construction industry is on how to decrease the cost overrun of the project

which is among the project holders, the workers for the past seventy years and build

conservational experts but there is no significant development or resolution in justifying the

harmful consequences; whereas on-site material wastage raises the final cost of the constructing

project. As the resources are wasted, it affects the cost of the project. Nonetheless, in order to

take care of waste, the contract which is made for the erection of building from materials is just
Material Waste and Cost Overrun 14

of 4 percent budget. Furthermore, in Hong Kong, the managers and owners of building projects

and schemes do not concentrate on the material which are produced on cost overruns on record

of 12 percent and it is stated in UAE that the material waste of development cost overruns on

record of extra 16 percent. There are so many studies about this matter but it still needs more

investigation that delivers the calculation of the connection amid the reasons of cost overrun in

construction industry and the wastage of material. Therefore, in this research it inspects the

connection among the cost overruns and reasons of wastage of materials and it is signifying the

conceivable conducts on how to lower or decrease the effects of material waste which happens in

construction projects stages.

It is stated inAmehOko John et al (2013) study about the relationship and link between

the most inefficient materials in construction and building process and they also detected the

aspects and factors that contributed the most wastage of material on sites and locations of

construction and building. Muhwezi (2012) calculated and studied about the classification of the

traits and characteristics of the building and construction waste on development and constructing

projects in Uganda and suggested the most possible ways on how to decrease their

manifestations. It is suggested that a construction waste management system is a necessity which

can deliver or provide the data or info about the waste quantities, to detect the parts or zones

which are little bit problematic in producing waste production and it should be capable of finding

the harms of these wastes.

Ali Asghar Najafpoor et al (2011) stated about the activities and the hustle about the

waste produced in the projects and developments, storage and transportation. During the

feedback from investigation, the most contributing aspect of waste production was obtained.
Material Waste and Cost Overrun 15

In 2008, Jiao-Yuan Wang ET a studied the construction on the sites and causes of

building waste info or data was found during the enquiry survey and the interviews were held in

Shenzhen. The suggestions were given for minimizing the waste and most important aims were

obtained for waste production.

In 2005, Elizara B M et al presented an innovative idea that supports project supervisors

at building locations to improvise completion of projects by means of construction waste

supervision preparation. These reasons are built on connection of construction waste

management which affected the aspects and factors in reducing waste. On construction projects,

the aspects and factors are based on interview and literature. Junli Yang et al (2005) researched

thoroughly about information analysis with the link to the production of waste and identification

methodologies of 3R principle (reduce, reuse, recycle) and management system.

In 2004, Bon-Gang Hwang et al studied the survey results based on different project

attributes, affect observation on advantages from construction waste management. A survey was

planned to give opinions about the selection of the schemes and project attributes and to increase

awareness about the benefits of construction waste management. In 2004, Andrew R F Dainty et

al searched about the productivity of procedures which was applied for minimalizing waste

production in a report in construction and building projects of UK. An extensive series of waste

plans was discovered in case studies which were reviewed through a feedback from survey from

waste minimalization experts. In addition, throughout the supply chain, useful procedures were

assigned to the encourage experts of waste minimalization.

In 2003, Carlos T. Formoso et al emphases on the outcome of two researches which were

held in Brazil that examined the presence of material waste on building and construction sites
Material Waste and Cost Overrun 16

and locations construction sites and cost price successful precautionary procedures were

recognized as well.

The fact that the construction industry generates a high level of waste from material

usage has been proven by previous studies. For example, one-quarter of the world’s timber is

consumed in the construction business while the construction industry consumes 3.1 billion tons

of raw resources yearly (UNEP, 2007; WGBC, 2010). Some of these resources will inevitably

end up as demolition and construction waste, thinking realistically. In the US, the landfills are

yearly filled with about135 million tons of demolition and construction, which combines up to

become 32 percent of the waste from the entire business (Mclaren, 2009).

By (Napier, 2012), there are several construction phases in which construction waste

occurs, ranging from finishing to founding works and almost all of them originate from masonry,

material handling, metals, aggregate, wooden materials, gravels, aggregate, electrical and

plumbing fittings, plastic, and concrete.

Research conducted in the US recently in (2015-2016) the following percentage wastage

of some building materials was identified from the processing of 20,000 tons of construction and

demolition waste. The following date was discovered; asphalt roofing 5 percent, dry wall 3

percent, gravels, ferrous and nonferrous metals 9 percent, dry wall 3 percent, wood 30 percent,

aggregate and fines 20 percent, paper 3 percent, disposal as refuse 5 percent and cardboard and

plastic 1 percent (Napier, 2012). Even though the research put forward the conclusion that the

main waste product in the US is wood, however wood shows a great possibility for reuse in other

industries such as manufacturing but also in the construction business.


Material Waste and Cost Overrun 17

To reduce the impact of construction resource waste on the environment the United

States Government has instigated the green rating conditions for all construction ventures’s to

further strengthen the eco-friendly performance (Amatruda, 2012).

Various scientists/scholars have struggled to examine the material waste on construction

sites in Brazil (Formoso et al. 2002; Junior, 2009; Saraiva et al. 2012). Although Brazil has not

yet set up the amount of demolition and construction waste that goes to landfills yearly, there are

statistics for the quantity of C&D waste from key sites in the nation (Angulo et al. 2009; Junior

et al. 2009).

74 percent of natural materials, 45 percent of the overall energy in use which combines

up to make 40 percent of the total waste which is generated by Brazil’s construction industry

(Saraiva et al. 2012). Brito Filho (in Junior et al. (2009) put forward a research which denoted

that the mean waste resource in the construction sites of Brazil is composed of; 32 percent mortar

and concrete, 30 percent ceramics, 32 percent soil and 6 percent others. Also, it was further

confirmed that almost all C&D waste in Brazil comes from masonry and concrete material

(Angulo et al. 2003; Angulo et al. 2009).

Ahmed, Andel's and Gihan (2010) study in Egypt was fixated on controlling and

minimizing the occurrence of resource waste through its origin. The authors found it essential to

build their research on an in-depth study that would cover the current situation, due to the

absence of an accurate database on the rates and causes of material waste in the Egyptian

Construction Industry. The research found that the chief waste percentage (14% in average) was

linked to timber outlines. Since it is sold at the end of the project to scrap dealers which in turn

use them for minor jobs its impact on the environment is less negative than that of other

materials. Cement and steel waste percentage appear to be in the boundaries of the mean
Material Waste and Cost Overrun 18

permissible percentage of 6 percent and 8 percent correspondingly. The high cost of the bill of

quantities which would have led to a higher effort from contractors to control their waste is a

major influence in this case.

Waste in Construction

Definition of Waste

Waste can be defined as the exceeding quantity in the usage of resources, labor, supplies

or equipment than that measured as a mandatory threshold in the erection of a structure. The

procedure of construction such as material supplies, planning, and design as well as the erection

stage may be all causes for the production of waste. The main causes of waste in construction

can be termed into:

- Planning

- Procedure

- Resource Supply

- Residual

- Design

- Procurement

- Operation

Nevertheless, product waste at the building phase of the project will only be taken into

consideration for this research.


Material Waste and Cost Overrun 19

Material Waste

Waste of material can be defined to contain the following things:

- Profuse resources produced throughout the construction phase

- Unwanted resources

- Excess materials ordered or spare to necessity

- Discharged and used resources.

Material waste can also be defined as the capacity break amongst the resources precisely

measured and appropriately used on site and delivery resource cost. Additionally, waste of

resources is defined as “any resource other than the earth’s resources, which requires being

moved to another place than that of within the project site or outside of the project site with the

objective of recycling, reusing, composting, land filling or incineration independent of the

planned explicit purpose of the venture because of non-use, resource damage, noncompliance or

excess with the requirement or a side-product of the building process” (Ekanayake and Ofori ,

2000). Despite of discrepancy in the project, possible resource waste is due to comparable

inadequacies in procedure, procurement, design, operation, resource handling, and residual on-

site waste such as packing or planning (Fomoso et al., 1993; Gavilan and Bernold, 1994).

Physical Construction Waste

The waste from renovation and construction hustle and activities like civil engineering

works and building works is called Physical construction waste. Though, it is mentioned as

inactive waste: the hard or rock-hard waste, including bricks, tiles, plastics, cane, glass, sand,

concrete wreckages, blocks, wood and papers and living matter. These waste matters cannot be

reuse and recycle because of its components and they can never be repaired. Non-Physical
Material Waste and Cost Overrun 20

Construction Waste lands are filled with the waste material as they are removed from the

construction sites and locations.

During the construction development, the non-physical waste and surplus usually arises.

However, for construction and building projects the waste material or non-physical waste

recounts the cost overruns and time increment. Correspondingly, according to researchers it is

stated that the wastage of material is caused by the time waiting and delaying in repairing. In

addition, the waste material is measured in wastefulness as in labor, materials, money and

equipment. However, the waste material in construction and building development and projects

does not only requires the amount of materials which are wasted on the construction location or

site but it also includes problems of material handling, catalogs and records, over production,

time and pointless activities of labors.

Amount of Waste Material in Construction

The configuration and proportion of resource waste were identified by research in

Malaysia which shows that: metal product 1 percent, wood 5 percent, soil 27 percent, concrete

65.5 percent, bricks, and blocks 1.16 percent and roofing materials aggregate to about 0.2

percent (Begun et al., 2006).

Rameezdeen and Kulathunga (2004) in Srilanka carried out a research that recognized the

chief resource wastes as the following, Cement 14 percent, Rubble 7 percent, Sand 25 percent,

Paint 5 percent, Ceramic tiles 10 percent, Cement Block 7 percent, Lime 20 percent, Steel 7

percent, Timber 10 percent, Bricks 14 percent, and asbestos sheets 3 percent.


Material Waste and Cost Overrun 21

Per Datta (2000), about 25–30 percent of resources are unexploited on project site in

Botswana, Zimbabwe, Tanzania, and Zambia. Fatta et al., (2003) also specified that in Greece,

50m3 waste is produced involving 1000m3 of building activity.

Sources of Materials Waste

Construction waste can also be the result of repairing, work, refurbishment and

construction. At the construction, planning and design phase; most of these inefficient tasks can

happen, without increasing the worth of the construction project.

Direct Waste

Direct waste cost is defined as the waste which can be stopped and which encompasses

the definite loss or replacement and exclusion of resources (Skyoles and Skyoles., 1987). Usually

direct waste cost does not tally in the cost of resources; instead, it tallies in the cost of disposing

and eliminating. Therefore, to gain a financial advantage for the project, direct waste needs to be

eliminated. At any phase of the construction procedure, direct waste can take place, after

combining the material to the building to before the unloading of resources to the site

(Kulatungaet al., 2006; Formoso et al., 2002).

CATEGORY REASON EXAMPLE

Delivery Wastage -Materials being transported to site Glassing, Bricks

-Placing and unloading in accumulation to

the preliminary storage


Material Waste and Cost Overrun 22

Conventional waste - Cutting material into different Tiles, Formwork

and Cutting uneconomical shapes and sizes.

Waste due to Repair Spoiled, discarded or disposed resources Roof tiles, Bricks

during repair

Waste on application Extra resources toughening on Mortar, Plaster, Paint

and residue Can/Container etc.

Other traders causing Subsidiary trades causing damage to Painted surface

waste materials.

Criminal – Waste Theft& vandalism. Cement bags, Tiles

Waste due to Lack of supervision / Wrong decision Excess material not

management issues being stored instead

thrown away

Waste due to incorrect Incorrect materials being selected Tile with interior quality

use rejected

Table .1.Direct waste categorize

Indirect Waste

Resources are not physically lost here. Instead, they are financially lost. An example of

this would be, the thickness of a concrete block according to the structural design being smaller

than the block itself (Kulatunga et al., 2006; Formoso et al., 2002). Waste caused by incorrect

distribution of resources, replacement of resources where resources are used in surplus amount
Material Waste and Cost Overrun 23

than those designated or not evidently identified in the agreement, from waste caused by

negligence, to mistakes, where resources are used in excess to the quantity needed by the

agreement due to the project contractor’s carelessness can be the chief cause of unintended waste

(Shen et al., 2002).

SOURCE CAUSE

Procedure Severe climate

,, Mistakes by operatives or tradesman

,,
Consequent damage and trade mistakes.

,,
Accident

,,
No awareness of essential amount due to flawed preparation

,, Materials being replaced due to damaged or incorrect materials

Unconsumed Conversion waste - cutting uneconomical shape

,,
Off cuts - Material cutting required length

,,
application process waste

,,
No idea about required quantity - Materials over mixing

Table 2- Causes of Construction Waste


Material Waste and Cost Overrun 24

Causes of Material Waste

Waste production on site may take place due to many aspects. There may be one or more

causes due to which waste may be produced. By Poon at al., (2001), a study in Hong Kong

which denoted the production of waste may have many influential aspects; they can comprise of

mechanical or human actions.

In the Turkish Construction industry, the material wastage is due to the reasons listed in

the following table:

SOURCE CAUSES OF MATERIAL WASTE FREQUENCY

Workers Mistake 33 percent

Procedure Imperfect planning of construction

62 percent

Materials damaged consequent of trade 05 percent

Unconsumed Conversion waste - Cutting uneconomical 21 percent

shape

Etc. Lack of waste management plan 11 percent

Lack of onsite material control 24 percent

Table 3 – Main source and cause of material waste

Following is the list of materials that are subjected to waste on the site of construction:
Material Waste and Cost Overrun 25

 Formwork

 Steel Reinforcement

 Concrete

 Tiles

 Cement

 Cement Sand mortar

 Blocks

Steel Reinforcement

In the building site, the weight and shape of the steel makes it difficult to handle and

control the use of steel reinforcement. Moreover, the steel is mainly damaged due to cutting

during rusting and storage.

According to researchers, there exist three major reasons for steel reinforcement waste:

- When bars are chopped, some short useless pieces are produced.

- There might be some bars that have extra large diameter resulting from trespassing and

fabrication.

- Waste generated due to non-optimized cutting bars resulting from poor structural design.

Concrete

There exist two kinds of mixed concrete namely concrete site mixed and concrete ready

mixed. In both superstructure and substructure buildings, concrete is considered as the most

effective material. The waste is mainly caused when the quantity of concrete orders is higher

than required. This is because, the contractor may not be aware of the exact quantity needed
Material Waste and Cost Overrun 26

resulting in excess concrete being ordered. Due to the wastage of concrete, projects are delayed

and inappropriate waste handling takes place. According to the survey of 22 sites of construction

conducted in Hong Kong, ready mixed concrete was used in 80 percent of the construction work.

It was revealed that on average, 2 to 4 percent of the material was wasted due to broken

formwork, excessive ordering of material and poor quality of concrete placement. According to

researchers, the exact quantity to be ordered may not be known to the contractor due to in

adequate planning. These results in excessive transport costs associated with over ordering.

Timber Formwork

In the generation of waste, timber used for formwork plays a major role. Timber is

considered as an effective construction material as it has several advantages. It carries high load

bearing capacity, is light weighted and is inexpensive as compared to other materials. Moreover,

Timber is considered a material of high wastage due to its low reusability and durability. Waste

is mainly caused due to the damage resulting from usage and cutting. After using it several

times, most of the timber transported to the site was disposed of as ate in the case of formwork.

Block Work

The most popular process for walling is Block work. Cutting usually results in block

waste during walling. The fragile nature of the materials along with unpacked supply may result

in increased wastage. Blocks that are left unused at the site may result in trash afterwards.
Material Waste and Cost Overrun 27

Cement Sand Mortar (Plastering)

Most of the time, cement sand mortar is left on the ground during the process of wall

construction, plastering etc. This left out cement sand mortar is not picked by worked after the

process resulting in residual. Cement mortar is mixed by workers in the morning before initiating

the process.

Tile work

Due to poor storage facilities and transportation, ceramic tiles get damaged. In order to

produce the desired architectural design, tiles should be molded and cut in to required size and

shape. When changes in design is required by the client, some of floor tiles may need to be

removed resulting in waste. When the tiles are ordered in excess quantity, this also results in

waste.

Material Waste Control on Site

Material control is a process that involves ensuring that the availability of materials in

terms of quantity and time is in accordance with the preset corporate objectives. The process also

includes activities such as requisitioning, fabrication of components, determination of material

requirement, record keeping, and procedure relating to status reporting.

The contractor takes on the responsibility of material control a soon as he starts working on the

site. Other than the general waste of materials on the site, lack of supervision results in increased

damage and more waste on the site.


Material Waste and Cost Overrun 28

The person handling the materials must take responsibility of material control process.

Most of the supervisors and foreman does not handle materials appropriately as they consider

themselves as supplier of materials they are responsible for.

Many foremen and supervisors see their main function as that of material supplier to the group

they are responsible for, hence, ignoring material handling. If the task of distributing supplies

and setting material requirements is assigned to the controller, the trade’s foremen will be able to

focus on their job properly. The handling and use of materials is solely the responsibility of site

management.

Waste Minimization in Construction

Considerable amounts of resources are being used at the building site. However, on close

examination of the lifecycle of materials on site, it can easily be revealed that large quantity of

waste is generated at the building site due to poor material control procedures.

There exists significant potential for reducing and even eradicating the waste generated at

the construction site. Knowledge about the causes of construction waste is required to formulate

effective waste management strategies.

The waste in construction industry is significantly being reduced due to behavioral

changes in most people. In construction industry, waste is inevitable. For this reason, there exist

less resources and support to reduce waste as it is considered a low project priority. The study

conducted by Lingered et al (2002) also emphasizes on the need of effective resources and

support to reduce construction site waste. The study recommends that in order to improve

attitude towards waste management, there should be clear communication of waste management

policies and availability of required resources.


Material Waste and Cost Overrun 29

MEASURE OF WASTE MINIMIZATION

- Ensuring that materials purchased contain an expiry date

- In order to avoid excessive ordering, coordination with the concerned individual

- Implementation of appropriate site management technique and strategy

- employee training

- Use of efficient equipment

- Purchasing adequate amounts

- Use of technology that generate minimal waste

- Storing the suite materials appropriately

- Ensuring that the materials are receive in right quantity and quality

- Careful use of equipment and tools at the site

- Taking specific measures to avoid ordering wrong materials

- Employing skilled workers

- Ensuring that right quantity of materials is batched

- Practicing effective construction management

- Inducing positive attitude in workers with respect to handling of materials

- Re utilizing waste materials in project

- Strict supervision

- Recycling waste materials on site.

Table .5 List of waste minimization measure


Material Waste and Cost Overrun 30

In Table 5, waste minization measures are listed as identified from the literature source:

Begum et al ., 2006 ; Shen et al., 2002 ; Shen and Tam, 2002 ; Poon et al., 2001 ; Ho, 2001 ;

Faniran and Caban. 1998; Peng and Scorpio.1997; Sherma, 1996)

The 3 “Rs “of Construction Waste Minimization

In minimization of construction waste, there exist three “Rs” namely recycling, reuse and

reduction. The prevention of waste generation at the first place is known as Source reduction or

waste reduction, Waste reduction is one of the vital principles of sustainable construction. If

minimal or no waste is generated during construction process, there would be less cost involved

and more natural resources would be conserved. Cost such as disposable cost, and material

handling cost is greatly reduced by designing with standard size of building materials.

Source Reduction

The process of waste eradication at the source is known as Source reduction. In the

construction waste management hierarchy, source reduction remains at the top level. This

process is highly effective as it has positive environmental impacts and gives direct results.

Benefit of the Construction Waste Minimization

A business can incur high cost due to management of construction waste. This is because,

waste management requires complex and expensive technologies and equipment’s to be used at

the construction site. A business can enjoy both environmental as well as financial benefits due

to waste minimization.
Material Waste and Cost Overrun 31

Financial benefits include:

- Low cost of transportation for waste materials

- Low disposable cost of waste materials

- Less quantity required to be purchased resulting in low overall cost

- Less waste is generated

- Pollution resulting from disposal is greatly reduced.

- Transportation waste to be disposed is reduced (Hence, less energy used, pollution from vehicle

emission etc.)

Relationship between Material Waste and Construction Cost Overrun

Construction waste is generally classified into two, namely: the physical waste and the

nonphysical waste (Nagapan et al., 2012). Physical construction waste is the waste from

construction, renovation activities, including civil and building construction, demolition

activities, and roadwork. It is, however, referred by some directly as solid waste: the inert waste

which comprises mainly sand, bricks, blocks, steel, concrete debris, tiles, bamboo, plastics, glass,

wood, paper, and other organic materials (Nagapan et al., 2012 and Ma, 2011). This type of

waste consists of a complete loss of materials, due to the fact that they are irreparably damaged

or simply lost. The wastage is usually removed from the site to landfills (Nagapan et al., 2012).

Conversely, the non-physical waste normally occurs during the construction process. By contrast

with material waste, non-physical waste relates to time and cost overruns for a construction

project (Nagapan et al., 2012). Similarly, Ma (2011) defines waste as not only associated with

wastage of materials, but also to other activities such as repair, waiting time, and delays. Besides

that, waste can be considered as any inefficiency that results in the use of equipment, materials,
Material Waste and Cost Overrun 32

labor, and money in the construction process. In other words, waste in construction is not only

focused on the quantity of materials on-site, but also overproduction, waiting time, material

handling, inventories, and unnecessary movement of workers (Nagapan et al., 2012).

Memon et al. (2014) added that non-physical waste includes undesired activities, which

can cause the physical waste, such as rework, unnecessary material movements, and so 126 forth.

Figure 1 shows the general classification of construction waste and further depicts that, since

construction waste entails both the physical and the non-physical waste, there is a relationship

between material waste originating from the physical waste and cost overrun from the non-

physical waste, since they originate frame the same waste family.

Construction Cost Overrun

Cost overruns are part of the non-physical waste that has plagued construction projects

for decades or even centuries (Edward, 2009). Cost overrun is also known as

"Cost increase" or "budget overrun"; and it involves unanticipated costs incurred in excess of the

budgeted amounts (Shanmugapriya and Subramanian, 2013). It has also been referred to as the

percentage of actual or final costs above the estimated or tender costs of the project (Ubani et al.,

2011; Jenpanistub, 2011).

Azhar et al. (2008) view cost overrun simply as an occurrence, where the final or actual

cost of a project surpasses the original or initial estimates. It is the actual or final costs, minus the

estimated cost, divided by the estimated/tender costs of a project expressed as a percentage.

Causes of Cost Overruns

Cost overruns in the construction industry have been attributed to a number of causes,

including technical errors in design or estimation, managerial incompetence, risks and


Material Waste and Cost Overrun 33

uncertainties, suspicions of foul play, deception and delusion, and even corruption (Ahiaga-

Dagbui and Smoth, 2014). The two main causes of cost overruns in a project, according to

Flyvbjerg, Holm and Buhl (2004) are: optimism bias and strategic misrepresentations.

Optimism bias summarizes the systematic tendency of decision-makers to be more

positive about the results of planned actions; whereas strategic misrepresentations have to do

with confusing or misleading actions used by planners in politics and economics, to ensure that

projects proceed. Furthermore, other surveys have identified the four major factors that cause

cost overruns for a project are: variations in design, insufficient project planning, inclement

weather conditions, and building materials' price fluctuation (Allahaim and Liu 2012).

In another study, the top five (5) important causes of cost overruns in large projects in Vietnam

were: poor site management and supervision, poor subcontractors and project management

assistants, owners' financial constraints, contractors' financial difficulties, and changes in design

(Le-Hoai ET el., 2008).

Al-Najjar (2008) investigated the causes of cost overruns in the Gaza strip, and found that

fluctuations in the prices of construction materials as a result of border closure, was the major

cause of cost overruns. Other factors were: delays in the delivery of materials and equipment to

site, and inflation of the prices of materials.

In another study, Subramani et el. (2014) surveyed the causes of cost overruns in India.

The results indicated that, slow decision-making at the planning stage of a project, poor project

schedules and management, increases in the prices of materials and machines, poor contract

management, poor design, delay in producing design, rework due to mistakes, land-acquisition

problems, poor estimation or estimation techniques, and the long-time taken between the design

and the time of bidding/tendering are the major causes of cost overruns.
Material Waste and Cost Overrun 34

Construction-Material Waste and Cost Overrun

Moreover, research evidence revealed that material waste accounts for additional

percentage of cost overrun in countries like the UK, Hong Kong, Netherlands, Nigeria and so

forth (Ameh and Itodo, 2013; Saidu and Shakantu, 2015; Saidu and Shakantu, 2016a; Saidu,

2016). For instance, Tam et al. (2007 in Ameh and Itodo, 2013) reported that, in the UK,

material waste accounts for an additional 15% of construction project cost overruns and for

approximately 11% of construction cost overruns in Hong Kong.

Similarly, a study conducted in the Netherlands revealed a cost overrun of between 20%

and 30% as a result of construction-material wastage (Bossink and Bounwers, 1996). However,

the methodologies adopted to achieve these contributions of material waste to cost overruns are

based on surveys and considered a subjective assessment. Nonetheless, these studies have failed

to objectively (quantitatively and empirically) address the contributions of material waste to

project cost overruns, because of wrong perceptions and this calls for actual data such as on-site

observation and records (Saidu and Shakantu, 2016b). It was on this basis that Saidu and

Shakantu (2016b) carried out an objective assessment of the contributions of material waste to

cost overruns in Abuja, Nigeria. The results revealed that material waste contributes an average

of 4.0% to project cost overruns for the entire projects.

Construction waste entails both the physical and the nonphysical waste; therefore, there is

a nexus between material waste originating from the physical waste and cost overrun from the

non-physical waste, since them both originate from the same waste family (Saidu and Shakantu,

2016a). This classification is shown in Figure 1


Material Waste and Cost Overrun 35

Research Methodology

A term used liberally for any investigation that is intended to uncover interesting or new

facts is known as research. The accuracy with which this task is carried out, as with all tasks will

be reflected in the distinction of the results. A fundamental review of the nature of research and

the methods which are used to undertake a variety of investigations relevant to a wide range of

subjects, such as the politics, healthcare and nursing studies, social science, natural sciences,

psychology, leisure studies and sport, social anthropology, hospitality, the environment,

business, education and the humanities will be presented by this book.

An element of research that students must carry out independently is now included in

almost every university course, in the form of dissertations, projects, thesis, and the more

advanced the topic and degree, the tougher and greater the research content. There is frequent

need to research in any workplace to improve or develop the service or business, while some

firms ultimately depend on researching for their very being.

A range of tools that are used for different types of inquiry are known as research

methods, just as for various practical jobs, various different tools are used, such as, a rake for

clearing leaves or a pick for breaking up the ground. However, in all cases, it is vital to

understand or to know the appropriate equipment for completing a particular job or task, and one

must also know how to use that tool most efficiently. Basic information will be provided by this

book about the equipment or tools used in research, indicating briefly how they are used by

giving practical examples and the situations in which they can be applied. Concluding on the

above description given on the types of research informs us that there are two basic approaches

to research, the qualitative approach, and the quantitative approach. The quantitative approach is

the method in which one must generate data in the quantitative method which can be subjected to
Material Waste and Cost Overrun 36

precise quantitative analysis rigidly and formally. Research which is concerned with opinions

and behavior and subjective assessment of attitudes is known as the Qualitative approach of

research. It is the ability of a researcher’s impressions and insights to research such scenarios.

Results are generated either in the form which is not subjected to precise quantitative analysis or

in the non-quantitative form in this approach of research. Commonly, projective techniques,

depth interviews and the techniques of focus group interviews are utilized.

There exist number of quantitative as well as qualitative research methods, ranging from

observation, questionnaires, interviews, experiments and case studies. The study in

considerations involves two research methods namely questionnaire or qualitative method and

quantitative method. For the purpose of collecting responses from the respondents, a

questionnaire is used to ask questions relating to the study. Questionnaires are not only

designed for statistical analysis, but also allow researchers collect adequate amount of data at

low cost. The target group can be sent the questionnaire through post and the respondents can

choose to answer the questions whenever they wish to. Cost can be further reduced through the

use of email for communicating with the respondents.

The Qualitative Method

Material Wastage Percentage during Construction Activities

Questionnaires were provided to project managers (05), construction managers (04), site

engineers (6nos), Chief quantity surveyors (02), resident engineers (6nos), civil foremen (10nos)

and (12nos) other individuals indulged in the process of construction. Based on their experience,

the participants were asked to rate the materials with respect to wastage during construction.
Material Waste and Cost Overrun 37

Rating had to be done on a 5-pointLikert scale ranged from 1-5. (1= extremely low and 5+

extremely high)

The responses of 43 participants to the questions asked regarding material waste are listed in the

following table- 6:

RESPONDENT CONCRETE TIMBE R /F CENE TILE BLOCK

R T WORK

F/WOR SAND

K PLAST

ER

Cons. Manager - 1 4 4 3 4 3 3

Cons. Manager - 2 4 4 3 3 3 3

Cons. Manager - 3 4 3 3 3 3 3

Con.Manager - 4 3 2 3 3 2 2

Proj. Manager - 1 3 2 3 3 3 2

Proj. Manager - 2 4 3 3 4 2 2

Proj. Manager - 3 4 3 3 3 3 2

Proj. Manager - 4 3 2 2 4 3 2

Proj. Manager - 5 4 2 3 4 3 2
Material Waste and Cost Overrun 38

Chief.Q . S - 1 3 2 3 3 2 2

Chief.Q . S - 2 4 3 3 3 3 2

Site Engi. - 1 4 3 2 4 3 3

Site Engi, - 2 4 4 1 4 3 2

Site Engi. - 3 4 2 2 2 1 3

Site Engi. - 4 3 3 2 3 2 3

Site Engi. - 5 2 2 1 2 1 3

Site Engi. - 6 2 2 2 3 2 3

Resi. Engi. - 1 4 3 1 3 2 3

Resi. Engi. - 2 4 2 2 4 1 3

Site QS – 1 4 3 2 3 2 3

Site QS – 2 4 3 2 4 1 3

Civil Forman - 1 3 2 1 3 1 2

Civil Forman - 2 2 2 2 4 1 3

Civil Forman - 3 3 3 2 4 2 3

Civil Forman - 4 2 2 3 3 1 2
Material Waste and Cost Overrun 39

Civil Forman - 5 2 3 2 4 1 2

Civil Forman - 6 3 2 3 3 2 3

Civil Forman - 7 4 2 3 3 3 2

Civil Forman - 8 4 3 2 3 3 2

Civil Forman - 9 3 3 1 4 2 3

Civil Forman - 10 4 2 1 3 1 2

Other – 1 3 2 1 3 1 2

Other – 2 4 3 1 3 3 2

Other – 3 4 2 1 4 3 2

Other – 4 2 3 2 3 3 2

Other – 5 2 3 2 3 2 2

Other – 6 4 3 2 3 3 2

Other - 7 4 2 1 3 3 3

Other – 8 2 2 1 3 3 2

Other – 9 3 2 1 3 3 2

Other – 10 3 2 1 4 3 2
Material Waste and Cost Overrun 40

Other – 11 4 3 2 4 3 2

Other – 12 3 4 3 4 3 3

Mean Value
3.32 2.57 1.57 3.73 1.78 3.16

Rank
2 3 6 1 5 4

Table.6 .Percentage and rank order of material waste on construction project

Table .7 is showing the mean response and their according rank (prepared using Table. 6.)

BUILDING NO OF MEAN RANK

MATERIAL RESPONDENTS
RESPONSE

Sand, mortar& cement 43 3.43 1

(Plastering)

Concrete 3.32 2
43

Timber form work 2.57 3


43

Block worm 3.16 4


43

Ceramic tile 1.78 5


43
Material Waste and Cost Overrun 41

Reinforcement 1.57 6
43

Table 7-Most frequently used building materials and its wastage rank

According to the results, cement-sand mortar is the most effective and commonly used

building material for plastering having a mean value of 3,53. Concrete followed Cement sand

mortar with a mean value of 3.12 and timber followed by mean value 2.56. Ceramic tile had the

mean value of 1.98 and there was reinforcement in the order with the man value of 1.77. The

result of previous studies is supported by the findings of this study that plastering through

mortar generate most of the waste at building site. According to previous studies, structural

elements lacking on modular coordination contributes to high wastage in mortar during the

process of plastering. Other reasons are the lack of supervision, careless workmanship and

unskilled workers. According to researchers, source of transportation and poor formwork may

contribute to the high wastage in concrete. It should also be noted that mix design may also lead

concrete wastage at the building site. Moreover, wastage may also result from hiring unskilled

workers, carless work and lack of supervision at the building site. Researchers also revealed

that waste and natural decay from cutting is responsible for high wastage in timber formwork.

In foundation work, up to 20% wastage can occur during the timber formwork process. The dull

and wet nature of most foundation work may contribute the high wastage during timber

formwork process. It should be noted that timber formwork is highly influenced by both wet and

dry weather. According to the study conducted in Egypt, steel reinforcement was found to have

low wastage percentage of about 5 % as compared to considerably high waste percentage of

cement mortar that was found to be 20%.


Material Waste and Cost Overrun 42

Percentage Contribution of Material Waste to Cost Overrun

The study aimed at estimating the parentage contribution of materials wasted at the

building site to project cost overrun. Based on their experience, the participants were asked to

estimate percentage of materials wasted to project cost overrun, the participants were required to

rate on Likert scale ranged from 0 to 5 (0 + less than 5% and 5= more than 25%). In percentage

interpolation, the mean average is used for each material used at the building site for

construction. The participants response to the questions asked is shown in the below table- 8.

The question was “what is the percentage contribution of materials waste to project cost

overrun.”

0 = Less than 5% 3 = 16 % - 20 %

1 = 6 % - 10 % 4 = 21 % - 25 %

2 = 11 % - 15 % 5 = More than 25 %

RESPONDENT CONCRE EMENT BLOCK TIMBER CERAMI RIENF

TE SAND WORK FOMWO C TILES ORCE

MORTA RK MENT

Construction 4 4 2 2 2 2

Manager - 1

Construction 4 4 2 2 3 2

Manager - 2

Construction 4 4 2 2 2 2
Material Waste and Cost Overrun 43

Manager - 3

Construction 4 4 2 2 3 2

Manager - 4

4 4 2 2 3 2

Project Manager -

Project Manager - 4 4 3 3 3 3

5 4 4 4 3 2

Project Manager -

4 4 2 2 2 2

Project Manager -

4 4 3 3 3 2

Project 5 Manager -

4 3 3 3 2 3

Chief QS - 1

4 4 2 2 3 3

Chief QS - 2

Site Engineer - 1 4 4 3 3 3 2

3 4 4 3 3 2
Material Waste and Cost Overrun 44

Site Engineer – 2

4 4 5 4 3 3

Site Engineer - 3

3 4 4 4 4 3

Site Engineer - 4

4 4 4 4 3 3

Site Engineer - 5

4 4 3 3 3 2

Site Engineer - 6

3 4 4 4 4 3

Resident Engineer

-1

4 4 3 3 3 2

Resident Engineer -

Site Quantity 4 4 4 4 3 3

Surveyor - 1

Site Quantity 4 4 3 3 3 3

Surveyor - 2

Site Forman - 1 4 4 3 3 3 2

Site Forman - 2 5 4 4 4 4 2

Site Forman - 3 4 4 3 3 3 3

Site Forman - 4 5 4 4 3 3 2
Material Waste and Cost Overrun 45

Site Forman - 5 4 4 3 3 3 2

Site Forman - 6 4 4 3 3 3 2

Site Forman - 7 4 4 2 2 2 3

Site Forman - 8 4 4 4 4 3 2

Site Forman - 9 4 4 3 3 3 3

Site Forman - 10 4 4 3 4 4 3

Other - 1 5 4 3 3 3 2

Other - 2 4 4 3 3 3 3

Other – 3 4 3 3 3 3 2

Other – 4 4 4 2 2 2 2

Other – 5 3 3 3 3 2 2

Other – 6 4 4 3 3 3 2

Other – 7 4 3 2 2 2 3

Other – 8 4 4 3 3 4 3

Other – 9 3 4 3 3 3 3

Other – 10 4 4 2 2 3 3

Other – 11 4 4 3 3 3 2

Other - 12 4 4 3 4 4 3

MEAN VALUE 3.91 2.91 2.37 2.34 2.28 1.86


Material Waste and Cost Overrun 46

Contribution % 16 % - 20 11 % -15 11 % -15 11 % - 15 11 % - 6 % - 10

for cost overrun % % % % 15 % %

RANK 1 2 3 4 5 6

Table. 8. Percentages and rank order of cost overrun due to material waste

The table. 8 results reveal the percentage as well as the mean contribution of materials for

building to project cost overrun. According to the recent study conducted in Nigeria, cost

overrun is highly influenced by generation of waste on the building site. Moreover, table 8 also

reveals that amongst the most commonly used construction materials, the materials with highest

percentage contribution to cost overrun is concrete with mean average of 3.91 followed by

cement sand mortar (2.91), block work with mean average of 2.37, timber form worker (2.34)

and lastly ceramic tile with mean average of 2.34.Furthermore, it was revealed that for cost

overrun, 16% to 20% is the percentage contribution of concrete wastage. For ceramic tiles,

timber and block work, the percentage contribution remains 11 % - 15 % respectively. Around 5

to 10 % is the Reinforcement contribution percentage which is lower than that of others. It is

evident from previous research that plastering generates highest amount of waste at the

construction site. Despite generating the highest amount of waste at the construction site, cement

sand plaster still does not account to the highest contribution percentage to cost overrun. The

only material that is considered to having the highest percentage contribution to cost overrun is

Concrete. This is because; around 10m3 of cement and plaster can be produced within the cost

producing 1 m3 of concrete. This could be so since the cost of producing 1 m3 of concrete could
Material Waste and Cost Overrun 47

produce 10 m3 of cement sand plaster. This is quite clear and evident from previous studies that

wastage increases the cost of the project significantly.

With exception to Concrete, most of the materials have the percentage contribution of 15

to 20% and some have less than 15%. This indicates clearly that wastage results in increased

costs. Waste from materials cannot always be avoided. Waste is generated throughout the

process of building and construction at the building site regardless of the duration and size of the

project.

Test of Hypotheses

Parsons Correlation is used to test hypotheses for collected data as shown below:

Descriptive Statistics

Mean Std.Deviation N

VAR00001 3.2417 .75045 6

VAR00002 18.8333 4.91596 6

Table .9 Parson Correlations– (Relationship between the level of material wastage and cost

overrun)

The results as revealed by table 9 shows p-value to be 0.001 whereas the rho value is

indicated at 0.973. The critical p value of 0.01 is greater than this p value indicated by the table.

Hence, the hypothesis is approved. This p value is less than the critical p value 0.01. Therefore

the hypothesis is accepted. It implied that the higher the level of material wastage the higher the

project cost overrun. In order to cover the cost of waste that has also reduced the profit of the
Material Waste and Cost Overrun 48

contactor, materials equal in amount to the materials wasted should be purchased. According to

this study in consideration, timber formwork, concrete, ceramic tiles and cement sand plaster are

regarded as materials with highest level of waste generation. These materials are also considered

to increase the cost overrun significantly.

Factors That Contributes To Material Wastages on Construction Sites

The aim of the study was to identify factors contributing wastage of materials in

construction industry. The table below reveals the actors contributing most to the wastage of

materials at the site of construction. For the collection of data, a questionnaire was formulated

and used as a major tool. Sixteen factors contributing most to the wastage of materials had to be

rated by participants on the scale of 1-5( 1- extremely low, 5- extremely high).Random sampling

strategy was used to provide the questionnaire to project managers, construction managers, site

engineers, chief estimators, civil foremen, resident engineers, and other relevant individuals

involved in the construction process.

RESPONDENT CONCRE SAND BLOCK TIMBER CERAMI RIENF

TE MORTA WORK FOMWO C TILES ORCE

R RK MENT

CEMEN

Construction
5 3 3 3 3 3
Manager - 1
Material Waste and Cost Overrun 49

Construction
5 3 3 3 2 3
Manager - 2

Construction
5 3 3 3 3 3
Manager - 3

Construction
5 3 3 3 2 3
Manager - 4

5 3 3 3 2 3
Project Manager -

Project Manager -
5 3 2 2 2 2
2

4 3 3 3 2 3
Project Manager -

5 3 3 3 3 3
Project Manager -

5 3 4 4 2 3
Project Manager -

5 4 4 4 3 2
Chief QS - 1
Material Waste and Cost Overrun 50

5 3 3 3 2 2
Chief QS - 2

Site Engineer - 1 5 3 2 4 2 3

4 3 5 4 2 3
Site Engineer - 2

3 3 4 3 2 2
Site Engineer - 3

4 3 5 3 3 2
Site Engineer - 4

3 3 5 3 4 2
Site Engineer - 5

3 3 4 4 4 3
Site Engineer - 6

4 3 3 3 3 3
Resident Engineer

-1

3 3 4 4 4 3
Resident Engineer -

Site Quantity
3 3 3 3 4 2
Surveyor – 1

Site Quantity 3 3 4 4 4 2
Material Waste and Cost Overrun 51

Surveyor – 2

Site Forman - 1 3 3 4 4 4 3

Site Forman - 2 4 3 3 3 3 3

Site Forman - 3 5 3 4 4 4 2

Site Forman - 4 4 3 3 4 4 3

Site Forman - 5 5 3 4 3 4 3

Site Forman - 6 5 3 4 4 4 3

Site Forman - 7 5 3 3 3 3 2

Site Forman - 8 5 3 3 3 2 3

Site Forman - 9 5 3 2 2 2 2

Site Forman - 10 5 3 4 3 3 2

Other – 1 4 3 3 4 4 3

Other – 2 5 3 2 4 4 2

Other – 3 5 4 2 4 4 3

Other – 4 5 3 3 3 3 3

Other – 5 4 4 2 4 3 3

Other – 6 3 3 2 3 2 3

Other – 7 3 4 3 3 3 2

Other – 8 3 3 2 2 3 2

Other – 9 4 3 2 2 4 2

Other – 10 3 3 3 3 2 2

Other – 11 3 3 2 2 4 3

Other – 12 3 3 2 3 3 2
Material Waste and Cost Overrun 52

MEAN VALUE 4.92 3.12 2.57 2.54 2.39 2.06

Contribution % 15% - 19 10% - 16 10 % -16 10 % - 16 10% - 5%-9

for cost overrun % % % % 16 % %

RANK 1 2 3 4 5 6

Table 10– Factor that Contribute to material wastage on construction site

According to researchers, waste can be controlled most effectively if it is not generated at the

first place.

Quantitative Method

The data was collected in the form of on-site material waste volume and calculated figure

of project cost over runs. To undertake this study, two housing scheme projects were selected.

These were large projects that tend to generate more material waste as compared to smaller

projects. The cost overrun also remains high due to increased material waste in larger projects.

Moreover, large projects can provide more accurate and reliable information as compared to

smaller projects.
Material Waste and Cost Overrun 53

Data Collection Procedure

For this research, two methods of collection were used namely primary data and

secondary data collection method. The data was mainly collected through primary data

collection method that involved field investigation and reviewing project documents (project

progress report, drawings, specifications, bills of quantities etc.) Secondary data was collected

through books, articles, newspapers, internet sources and journals.

Data Collection and Analysis

From the priced bill of quantities, the material volume (concrete, block work, plaster,

reinforcement, tile, and formwork) was determined. The value of materials was then checked

against structural and architectural drawings and check with the architectural and structural

drawings. Unit rate in BOQ was then used to calculate the estimated cost of these materials.

Through field investigation and site records, data revealing the actual quantities of these

materials was obtained. Finally, BOQ unit rate was used to calculate the actual cost of these

materials.

Below is the calculation of estimated cost (EC) and actual cost (AC) to find cost overrun

percentage:

(AC – EC) X 100 = COST OVERRUN PRECENTAGE

EC
Material Waste and Cost Overrun 54

Outline of Methodology

START

IDENTIFY THE AIM IDENTFY THE OBJECTS

ORGANIZING RESEARCH SCHEAM

COLLECT ENOUGH DATA COLLECT ADDITIONAL DATA


USING DATA COLLECTION USING DATA COLLECTION
TYPE 1 TYPE 2

ANALYZE THE DATA


IN PROPER WAY

PREPARE THE FINAL


CONCLUTION WITH
THE ANSWERABLE
Figure – 1
SOLUTION

Field Investigation

For the study, 5 houses were chosen from Dubai Hill residency project whereas 4 houses

were chosen from Reem development housing project based in Dubai UAE. From the time of

construction, three houses from Dubai hill residency were carefully observed. Moreover, two of

the houses were almost constructed when observation was initiated. Observation from the

beginning was ensured in the case of all four houses in Reem development housing project. In

order to collect the information regarding wastage of materials, A survey was carried out that
Material Waste and Cost Overrun 55

lasted from September 2016 to January 2017.Interviews were conducted with several site

workers, contractors and officers to get information regarding project materials. The details

about project materials are summarized as following:

Procedure for Data Gathering and Analysis

The study aims to estimate the actual amount of wastage from materials being generated

at the housing schemes and the effect of the wastage on the cost overrun percentage. The

estimated amount of wastage will then be compared with the wastage allowed at the site. In order

to achieve this objective, the approach that would be undertaken would be deductive. The

approach would be adopted to test the hypothesis that the use of theoretical material+ allowance

of wastage in (BOQ) is less than the actual use of materials at the site.

HI: Actual material usage > Theoretical material usage +Wastage allowance (BOQ)

Case Study

The variance between definite and hypothetical figures of building resources used

throughout designated houses finalized recently will be the measurements used. Houses will be

providing the data, and the following parameters will be considered.


Material Waste and Cost Overrun 56

 Material usage will be affected by the financial worth and size of the homes. As the

houses get bigger and their financial worth increases, more resources will be needed and

used and then there will be a higher chance of material wastage.

 To guarantee that the statistics are gathered precisely the homes will be chosen using a

range of different site engineers and quantity surveyors. Different construction activities

will be carried out in different ways by each site engineer who will result in varied usage

of resources. Similarly, the agreed final accounts will be providing the final data, as the

quantity surveyors missing some works carried out on site is an imminent possibility.

Theoretical quantities not being included and only actual material is being used on site

will be the result.

To ensure data collected is accurately and fairly the data from construction houses will be

selected within the above parameters, this will permit precise decisions. A variety of houses (9

houses) will be designated for the definite measurements to be obtained, the department

undertakes the varied type of maintenance schemes, and it will be ensured the data represents

that. Plastering work, reinforcement work, form work, block work, tile, and concrete will all be

measured. The quantity of materials wastage occurring on site will be discovered by this, and

this material wastage quantity will easily be compared to theoretical quantities through this

procedure. The difference between theoretical material quantities against definite on-site material

quantities will be used to find the quantity of expenditure happening. This percentage of cost

overrun on site will be found using the quantity of expenditure taking place. Store report, daily

progress report and measured in-site will be used to acquire the actual material quantities. Plants

and materials used to undertake construction work for the particular day, Details for labors are all
Material Waste and Cost Overrun 57

included in these daily progress report. Shop drawings and bill of quantities will be used to

establish the theoretical quantities used.

Statistical Data Analysis

The materials used to measure differences in actual waste from the theoretical were found

from site investigation and experience, they are as follows: formwork (square meters),

reinforcement work (tons), tile (Nos), concrete (cubic meters) and block work (Nos). Theoretical

materials quantities will be compared against actual on-site material quantities using the result to

determine the number of wastages taking place. Theoretical and actual materials quantities used

on all of the homes for each type of resource will be shown using graphs. All the homes and

assessment of the theoretical and actual resource quantities, ratio of related and wastage cost

overruns will all be shown through detailed charts.

Reinforcements

Common resource used in constructions is steel reinforcement bars. The use of steel

support bars in building sites is tremendously hard to control since it is bulky to hold because of

its shape and weight (Formoso et al., 2002). Damage during storage and rusting, cutting is the

main causes of the wastage of steel (Shen et al., 2002).

The three chief aspects that pointed out steel reinforcement wastage were given by Formoso et

al. (2002). They

 Some bars have unreasonably large width due to manufacturing issues or trespassing

 Short, ineffective pieces that are produced when bars are cut
Material Waste and Cost Overrun 58

 Mechanical design that is poor compared to standardization and detailing, causing waste

due to the non-optimized cutting of bars.

Ceramic Tile

A fragile material ordered excessively due to waste and tolerance anticipation, and a

similar bunch of manufacturing to evade mismatching with other input is known as a tile. Poor

storage and transportation are the two chief reasons for the wastage of tiles. Some odd shapes in

architectural design are required therefore to prevent the wastage of tiles; they are cut to balance

and the right shape. Sometime consultant or client’s change the design of some floor tiles or wall

tiles to replace other tiles. Those tiles are then removed and cannot be reused due to their hard

cement backing, and the probability of all of them being wasted is high.

Due to the above reason, much permission are to be taken from the consultant, main

contractor, client, etc., before tiling commences such as finish level, size of tile, texture, quality,

surface, the design of the tile, orientation, the color of the tiles, direction, slop, etc. Then the

amount of tile wastage is easier to diminish. Proper storage of tiles without moving too many

locations is to be provided by the site facilities.

Findings and Discussions

The table below is representing the reasons of cost price increase which are linked to the

reasons of wastage of materials in current development or project.


Material Waste and Cost Overrun 59

S.N CAUSES OF COST OVERRUN COST MATERIAL

OVERRUN WASTE

1 Contractor made meager developments. √ √

2 Less interaction among partners. √ √

3 Lacking of tools. √ √

4 Enhance the opportunity of labor. √ √

5 Poor administration and site management. √ √

6 In expert worker. √ √

7 Detailed material detection. √ √

8 Advertisement state. √ X

9 Increase in material amounts. √ X

10 Rise in pays. √ X

11 Supplementary labor. √ X

12 Lack of resources. √ √

13 Impractical time period. √ √

14 Postponement in obtaining materials. √ √

15 Lack of site labors. √ √

16 Problems of work safety. √ √

17 Making changes in works to make it up-to-date. √ √

18 No usage of technology and contemporary √ √

equipment.
Material Waste and Cost Overrun 60

19 Equipment accessibility / Breakdown. √ √

20 Amount of works happening at same time period. √ √

21 No expert labors. √ √

22 Faults throughout building process. √ √

23 Postponement in making resolutions and √ √

assessments.

Table .23. Reasons for wastage of material which are found in reasons of cost increase in current

project.

The constructing materials only start about fifty percent of building project cost price

which is based on mutual agreement. Usually, the wastage of constructing materials throughout

the construction process causes to increase the cost of project. This signifies that if there is any

development made in amounts of wastage of constructing material on building locations or sites,

it is possible to improve the construction commercial enterprise’s presentation with the

advantage of cost saving.

The minimization of wastage must be coordinated into the construction development and

it should be planned at an early phase. As a part of their scope, the assortment of contractors has

to ponder upon their plan of diminishing or decreasing the amount of wastage. It is important to

give some teachings about the reduction of waste to the staff which are present on the sites to

decrease the production of wastage of materials. Furthermore, collecting information of waste

production, identifying the main zones of waste production, studying the reasons for the

production of waste, producing resolutions for lessening of waste and giving response to the

outcome of production to the labors who work on significant areas, this is all proposed by the

waste control system.


Material Waste and Cost Overrun 61

However, the price of the resources alone constitutes to around 55 percent of the

venture’s cost. A common belief is that venture cost overrun contributes to construction resource

wastage throughout the building phase of the process. The construction industry’s performance

can be enhanced with cost saving benefit by improvement in building material wastage level on

construction sites.

Development of the building procedure should commence at a tender stage, and wastage

minimization should be integrated acutely into the strategy. The wastage lessening strategy

should be considered for the selection of subcontractors and should be a part of their scope. To

reduce production of material wastage and generate a better working technique, a waste

reduction drill will be given to the on-site staff. Waste regulatory systems shall be a part of the

site development function, which classifies the major areas of waste generation, analysis the

causes for the waste generation, collects waste generation data, gives feedback to the

executives/managers and the working staff who work in those key areas and produce solutions

for mitigating waste.

Discussion of Factors Causing Waste of Material and Cost Overrun

The aspects or reasons that produced the cost overruns and time period of construction

are categorized and classified into 7 groups shown below. The classifications were modified

from Rahman et al., (2013).

Category 1: Contractor's Site Management Related Factor (CSM) Contractor's Site

The problems or harmful factors which are caused by the servicers or contractors relates

or involves Management Related Factor. It involves meager supervision and site management,

delay in schedule or planning, useless subcontractors, lacking of planning and scheduling, lack of
Material Waste and Cost Overrun 62

skills and practice, cost approximations and wrong timing, blunders and faults during building

and construction, and lacking of management and supervising and checking. Generally, the

reasons in this group happen on building or construction stage which is under the charge

contractor as it is shown and examined below:

 Poor Site Management or Supervision: The faults of contractors in controlling,

monitoring and supervising have an effect on the cost price and time period in

construction and building projects are represented by the Poor Site supervision and

management. It happens due to the absence of qualified and skilled building and

construction supervisors and lack of information about site or location management. This

causes harmful effects on the developing effort or work that directs to upgrade the work,

alteration of project extent, bad quality, and normal modification of orders by contractors.

Therefore, the effect from this aspect will affect the cost of project and time overruns. In

2008, it was maintained by Le-Hoai et al., who discovered that the poor site supervision

and management were the main difficulties and problems in Vietnam building projects.

Moreover, in 2007, Sambasivan& Soon discovered that these aspects and reasons were

the most important sources of construction interruptions and postponements in Malaysia.

Whereas, in 2010 Ali & Kamaruzzaman stated that this reason was one of the reasons

that caused the increase in cost of construction or building projects of Klang Valley.

 Incompetent Subcontractors: Reason of unskilled subcontractor is associated to the lack

of skills and experience or ability of subcontractor in managing the productions which

heads toward the risk of postponements.

 Schedule Delay: The accomplishment of projects is guaranteed if one of the main factors

which is to finish the project within the time limit. But the delay in schedule is quite
Material Waste and Cost Overrun 63

normal in building projects which causes cost and time overruns in project. These

problems occur due to variations in the accessibility of constructing and building

materials, usually extended delaying times and insecurities about distributions of the

materials, lack of resources to obtain materials, and lack of transportation.

 Inadequate Planning and Scheduling: In the initial stages of construction, scheduling and

planning should be done accordingly as it includes so many works from planning phase

till the project completion. It will initiate the delay at several stages if the planning is not

done properly and accordingly. Generally, it is linked to not holding the accurate

materials, the correct info, well training or coaching, the correct equipment and the true

individuals, altogether at the right time at correct place. Owing to this factor, it raises the

time of the projects, increases the cost and the profits of projects are relatively low. In

2009, Abdullah et al. researched that the project management consultant (PMC) showed

that the lacking of scheduling and planning via the contractors was the most important

reason of postponement. However, it was revealed that the contractors were held

responsible for not managing the tasks on the considered and planned schedule.

 Lacking in Experience: Consultants & clients usually incriminate the influence of

deficiency of contractor experience on-site as one of the chief influences of postponement

in building ventures. Contractors hold the consultants responsible for the discrepancies in

the early stage of construction due to the lack of design experience. Odeh&Battaineh

(2002) also highlighted the fact that the inability of contractors to plan describes the lack

of experience. A project can suffer from many negative impacts when the contractors are

incapable of planning and managing their projects smoothly, for example, unable to
Material Waste and Cost Overrun 64

finish the venture in the planned time. When the contractors employ young personnel and

inexperienced management to get high profit for their projects then the chances of facing

these problems arise.

 Regrettably, the project cannot be handled by them because of the deficiency of

knowledge or experience related to the work. This factor can cause delay or waste of

material indirectly and can also have a negative impact on the cost of the venture. It can

be detected that for cost overrun problem in the context of economic organization where

most contractors did not have the ability to distribute the costs due to lack of experience,

and this caused the projects to be planned poorly.

 Inaccurate time and cost estimates: Many parties usually set up the cost & project time

estimations, but since the contractors are the main party in producing the estimation they

are the ones who take all the blame. This, however, occurs because of the designs, which

are either prepared by the consultants or owners, that does not consist of enough

information of the project and are not clear or precise. Therefore, the responsibility of this

problem is shared equally by all parties. The main factors that contribute to cost overrun

of a project are inaccurate cost and time estimates, so it is vital that this problem is

avoided for the project to be successful.

 Mistakes during construction: Communications, labor, and equipment are all chief

aspects of mistakes made during the construction phase of a project. When the labors are

careless in their works and do not follow the proper procedures, they can cause mistakes

to happen which can then result in accidents to happen. Although, lack of maintenance is

the main cause of mistakes made by equipment which then leads to inefficiency of that

equipment. Also, lack of communication or miscommunication between parties can also


Material Waste and Cost Overrun 65

force blunders to take place during the operational phase of the project. Hence, to avoid

these mistakes during construction a person must be well informed & educated on

professional management. Nevertheless, if these discrepancies happen, it will indirectly

increase the cost and time of projects and can also lead to complete reworks.

 Inadequate monitoring and control: Apolot, Alinaitwe, &Tindiwensi (2011) presented a

study whose results denoted the fact that poor control and monitoring is ranked as the

third main influence in contributing to cost overruns. Additionally, schedule creep and

poor workmanship will be caused by this factor.

Design and Documentation Related Factor (DDF)

Problems or adverse factors attributable to designers/consultants are known as Design

and Documentation Related Factors. Mistakes and errors in design, approval of drawings, poor

design and delays in design, delay preparation, frequent design changes and incomplete design at

the time of tender are chief influences which are the responsibility of consultants. These aspects

occur during design and construction phase are related to the design of the project as debated

below:

 Frequent design changes: The most important factor that inhibits the ability to control

time and cost of projects is considered as frequent design. Consequently, the cost, as well

as the time of the project, will be impacted negatively. Environmental information and

inadequate site are the main causes of this discrepancy. Per Alwi& Hampson’s (2003)

study, owners demand to meet their preferences & requirements are the main cause of

design change. Therefore, the volume and type of materials, the cost estimation for the

project and even the personnel will be affected by design change. Additionally, it can also

lead to the extension of project time as it can cause rework completed tasks.
Material Waste and Cost Overrun 66

Conclusion

In this study, the aspects that paid or contributed to resources and materials which were in

minimal quantity were recognized. Furthermore, it is necessary to focus on materials that are

wasted in minimum quantity, the improvement in decreased amount of waste production benefits

in cultivating the productivity of the project and changes the construction commercial enterprises

presentation with the advantages of saving cost. Moreover, it is necessary to concentrate on

waste management plan. In material wastages, variations in conditions also play an important

part. The site manager must concentrate minimizing the material management plan. This

improves the waste supervision strategies as well as reduces the wastage of material, productivity

and diminishes the cost overruns.

Global problems which affect the success of many construction projects are defined as

cost overruns and material waste. They are induced by numerous reasons at various phases of

projects. Identification of these causes at different stages and the application of applicable

regulatory ventures to diminish their incidence is a pace in the direction of lessening the damage

of the outcomes. However, little attention is given to the effects of waste generated on cost

overrun by most managers of construction projects. Examining the relationship between the

influences of cost overruns and those of material waste with an opinion signifying the probable

and economical methods of diminishing their effects at the post-contract and the pre-contract

phase of a venture was the main objective of this research. An average of 86.83 percent

relationship between the causes of cost overruns and those of material waste at the post-contract

and pre-contract phases of a venture was also revealed by this study. The research also finds that

100 percent of the reasons of cost overruns were found to be among the reasons for material
Material Waste and Cost Overrun 67

waste at the post-contract and the pre-contract phases of a venture, while 81.35 percent and 96.87

percent of the reasons of material waste cause cost overruns at the post-contract and at the pre-

contract phases correspondingly. The macroeconomic and micro economic factors are also

reasons but are not related to this topic hence they have no importance. To accomplish effective

construction resource waste management for any construction venture, it is found that resource

waste must be regulated at the origin and all the causes must be dealt with at all the various

phases of a venture.

It can be concluded that operative managing of resource waste would decode into a

decrease in the threshold of cost overrun by 87.85 percent based on these findings. The study

recommends that to potentially minimize the cause of cost overrun for a project dealing and

resolution of all material-waste causes should be encouraged.

References

You might also like