Professional Documents
Culture Documents
INTRODUCTION ......................................................................................................2
CHECKLIST #1 .........................................................................................................4
st
1 WORKING DAY ..................................................................................................5
SITE SELECTION AND PREPARATION 5
FOUNDATIONS FOR COMPOSTING CHAMBERS AND STEPS 6
nd
2 WORKING DAY .................................................................................................8
REMAINING ROWS OF BLOCKS 8
rd
3 WORKING DAY ..................................................................................................8
PLASTERING INNER CHAMBERS 8
SOAKAWAY 9
rd
4 WORKING DAY ..................................................................................................9
TOILET HOUSE SLAB (FLOOR) 9
th
5 WORKING DAY ................................................................................................ 11
ACCESS DOORS FOR THE COMPOSTING CHAMBERS 11
TOILET SEAT PEDESTAL (STOOL / CHUTE) 12
CHECKLIST #2 ....................................................................................................... 13
th
6 WORKING DAY ................................................................................................ 14
TOILET HOUSE (ROOM /OUTHOUSE / SUPERSTRUCTURE) 14
th
7 WORKING DAY ................................................................................................ 18
Construction and maintenance USE AND MAINTENANCE GUIDELINES .................................................................. 19
V.1
INTRODUCTION
2
BENEFITS OF COMPOSTING TOILETS
Waterless-double-chamber
composting toilets:
Protect water sources. Faecal
material does not leak or get
flushed into rivers, lakes, the ocean
or the water table.
Do not waste clean water on CONTEXT
every flush. These guidelines were created as part of the project “Improved Community
Sanitation, Hygiene and Residue Disposal in Santa Rosa and San Roman,
Save money on water and
Belize”. The project was funded by the German Cooperation through the
fertilizer bills. Embassy of Germany in Guatemala and co-funded and implemented by
Humana People to People Belize (HPPB). The project aimed to:
BEFORE YOU START Increase access to improved sanitation and adequate hygiene and
residue disposal practices by building 12 waterless-double-chamber
With this guideline, users will be able to build a 4’ by 8’ toilet house ( ’ = feet). composting toilets (2 at community centers and 10 at households).
To save money, the materials from the toilet house and toilet seats can Improve awareness and knowledge of adequate hygiene and residue
be changed to use available materials or less expensive ones. However, disposal practices at a national level by creating printed and digital
to prevent water contamination, pests and bad odours - it is crucial to material as well as community events.
follow all the steps and use cement and blocks to build the composting HPPB is a non-governmental organization registered and operating in Belize
chambers. since 2007. HPPB works with rural and hard-to-reach communities in Toledo
The construction materials can be bought in two separate purchases. The and Stann Creek districts. HPPB’s mission is to empower and mobilize
st
1 purchase (page 4) includes the composting chambers and toilet seats. The 2
nd individuals, families and communities to reduce poverty and vulnerability
purchase (page 13) includes the toilet house and steps. through local action and capacity building.
If the user is not familiar working with carpentry and/or masonry, it’s This publication was produced with the financial support of the German Cooperation.
recommended that expert advice is sought before starting each Its contents are the sole responsibility of Humana People to People Belize and do not
necessarily reflect the views of the German Cooperation.
construction phase.
If dimensions for the composting toilet are changed, material quantities HPPB encourages the use, reproduction and dissemination of this guideline. Contents
may be copied, downloaded and printed for private study, research, teaching purposes
will need to be modified respectively.
and for non-commercial purposes; provided that appropriate acknowledgement of
Go to www.humana-belize.org to get the latest version of the guidelines. HPPB as the source is given.
3
CHECKLIST #1
5
FOUNDATIONS FOR COMPOSTING CHAMBERS AND STEPS
Be sure to finish all the steps in the same working day:
3. Dig 12” stakes made out of bush stick (2” thick) so the frames do not bend when the
concrete mix is poured.
4. Bend the 3/8 construction steel into a 4’ by 8’ rectangle and place it inside of the
composting chamber’s frame.
Tie the loose end with a tying wire.
Put small stones underneath the steel to center it vertically on the middle of the
foundation making sure that it does not touch the ground in any place.
8. Scatter 2” rocks in the center of the frames to optimize concrete use. About 50 rocks for
the chamber’s frame and 20 for the steps’ frame.
6
CONCRETE POURING
1. Mix the concrete with 4 bags of cement and 28 five-gallon-buckets of sand and gravel.
(Add 7 five-gallon-buckets of sand and gravel to every cement bag).
2. Mortar the joints and around the soakaway pipes securing that all joints are
fully closed. Use a small board so the joints are straight and levelled.
3. Fill with concrete mix (cement with sand and gravel) the corner blocks (where
the rebar columns are placed).
The first row should always be complete with blocks (with no spaces in between) to
ensure that the composting chambers do not contaminate groundwater.
7
SLAB AND BLOCK CARE
1. When finished for the day, wet the concrete to prevent the concrete from drying too fast and cracking and remember to wash the concrete off
the tools before it dries!
2. The next day, sprinkle water in the cement early in the morning.
3. After 24 hours have passed, take out carefully both frames from the foundations and remove any remaining concrete with a brush or a
machete. All frame boards can be reused when making the slab and access doors.
On each row, remember to fill with concrete mix (cement with sand and gravel) the corner
blocks (where the construction steel is placed)
2. Place a support for the blocks on the 4th row on both access door openings.
The support can be two frames of 17” by 17” each or a block standing up with a board on the top.
3. Lay the 4rd and 5th rows of blocks and mortar all joints.
8
SOAKAWAY
1. Centred in the back of the composting chambers, dig a hole that is 2’ wide, 4’
long and 2’ deep. Dig 3” away from the foundation.
2. Place a 2” PVC elbow on each pipe.
3. Connect each elbow to a 2” PVC pipe that is 2” long.
4. Fill the soakaway with 4” coarse stones.
5. Cover the stones with a 2” layer of soil.
6. Plant grass on top of the soil. The grass will “drink”
the liquid that drips from the soakaway pipe.
4rd WORKING DAY
3. Fill the last row of blocks with 2” stones so the concrete mix used to make
the slab is not wasted by entering through the blocks.
4. Place the 4” by 8” hardboard panel centred on top of the composting
chambers.
SLAB FRAME
1. Make an 8’ by 4’ frame that is at least 6” high. The frames from the
composting chamber slab can be reused for this purpose.
9
2. Place the frame 3” bellow the block line.
With the level, make sure the frames are levelled.
Secure the frame with 3” concrete nails and bush stick stakes or lumber boards.
5. Tie each grid intersection with tying wire. Tighten each tie with pliers.
6. Center the grid vertically in the middle of the slab by placing rocks
below it. The grid should not touch the base of the slab at any place.
CONCRETE POURING
1. Mix the concrete with 2 bags of cement with 14 five-gallon-buckets of sand and
gravel.
2. Pour the concrete and trowel it smooth with a board trowel. Someone should hold
the PVC pipes while pouring the concrete.
3. To avoid getting the buckets stuck into the concrete mix, shake the them lose 10
minutes after the concrete mix is poured then shake them again once every hour; for
the next two hours.
Or put motor oil in the buckets so they do not get stuck.
Leave the PVC pipes as the slab dries.
10
SLAB CARE
1. When finished for the day, wet the concrete to prevent it from drying too fast and cracking.
2. The next day, early in the morning, sprinkle again with water to help the slab cure evenly without cracking.
3. 24 hours after finishing the slab, take out the frames and clean them.
4. 48 hours after finishing the slab, take out the hardboard, frame and bush sticks and clean the boards.
The hardboards will be reused to make the toilet seat pedestals and the boards, to make the house frame diagonal braces.
5. Before continuing any work, let the slab cure for three days and don’t put any weight on the slab during that time (this includes stepping on it).
2. Pour the cement mix. Mix 2 shovels of cement and 2 of fine sand for each door.
3. Cut two pieces of 3/8 construction steel 1’ long and bend them into handle shapes.
4. Place the handles on the ends of each door, not too close to the edges.
5. For the first 24 hours, let doors rest on the ground.
6. When 24 hours have passed:
11
TOILET SEAT PEDESTAL (STOOL / CHUTE)
To reduce costs:
Toilet pedestals and seats can be done out of timber. To reduce the necessity for cleaning, the inside hole of the pedestals should be at least 10”
wide so faecal matter does not adhere to the sides.
It is possible to have/make only one toilet seat that is placed above the active composting chamber while the inactive chamber is closed with a
wooden or concrete a lid. However, for practical reasons, it’s recommended that two toilet pedestals are made (with the outer and inside walls it
will be harder to move the toilet seat around).
1. Make the seat pedestal formwork by reusing the hardboard used on the slab support.
If it is not possible to reuse the board, use flat metal sheeting.
Cut the boards as high as a five-gallon-bucket and 5” longer than the circumference
of the bucket.
Turn the 2 five-gallon-buckets upside-down (its better if the buckets are old and black).
Wrap each board around a bucket, leaving 4” of space between the bucket and the board.
Tie each board with tying wire to keep them in place when pouring the concrete mix.
2. Mix the remaining cement bag with 7 five-gallon buckets of sand and gravel.
Leave a bit of cement out, to use when sticking the plastic toilet seat and lid to the pedestal.
3. Pour the concrete mix on each pedestal formwork making sure that the cement does not
go higher than the top of the bucket. The top of the bucket will be taken out when the seat
pedestal is dry.
12
CHECKLIST #2
13
6th WORKING DAY
STEPS
1. Make two upright supports with two 1x10x6 boards. Make a 45° angle on each side
and cut a corner so the supports rest on the step foundation.
2. Nail the upright supports to the cement blocks. Leave 6’ between the supports
and make sure they are centred in front of the composting chambers.
3. With 2x4 scrap wood, nail side supports next to the boards as
shown on the photo.
4. Leaving 1’ between the 1st step and the floor, nail one step
supports on each upright support.
5. Make the 1st step by placing a 1x10x6 board on top of the step
supports and nailing it to the supports. Repeat this step for the
remaining steps.
The hand rail will be assembled after the walls have been placed.
FRAMES
To reduce costs, house frames can be made out of bush stick (4” thick).
3. Drill holes on the boards so the construction steel bars from the corners
can pass through the boards.
4. Bend the construction steel bars over the boards so they grab the base
of the house and keep it from moving.
14
WALL SUPPORT
1. Nail 2x4x8 boards to the front wall base.
Nail the center and corner posts first.
To allow the 2’ wide doors to fit, make sure that the 2nd and 4th post are
rd
2’ away from the 3 /centre post.
2. Cut 2x4x8 boards to 3 pieces 7’ long and nail them to the back of the house. The back
wall is shorter than the front wall so the rain drains away from the door.
4. Nail the diagonal wood braces to each post. They keep the walls from collapsing in the wind.
5. Cut and nail wall supports with 2x4x8 board. The supports are 3.5’ away from the floor.
15
ROOF SUPPORT
1. Nail the 1x3x8 boards to the front and back wall posts.
st
(1 drawing).
DOOR FRAMES
ROOF
1. Place zinc sheets on top of the roof support making them overlap for 6 to 8 inches.
To reduce costs and/or use available
2. Nail the zinc roof with umbrella head nails making sure to nail at the high point of the
materials, the roof can be thatched or
ribbing (otherwise, water will come through the nail holes). Place nails on every other
use zincalume.
ribbing, the whole roof should use at least 40 nails.
16
WALLS AND DOORS
To reduce costs and/or use available materials, the walls and doors can be made out
of local hardwood, zinc, fabric and/or plastic rolls. However, it’s important that:
The toilet house is dry, strong, private and attractive.
The selected materials are rot resistant.
DOORS
1. Cut and nail 2x8 plysen board pieces on each door. Add a nail every 8”
along all the sides of the board.
2. Nail the door hinges on the doors and then nail the hinges to the house
frames.
WALLS
1. Connect a 2” PVC elbow followed by a 2’ pipe to the ventilation pipe.
2. Attach the plysen boards to the house frames by nailing every 8” along
the sides of each board. Place:
2 plysen boards horizontally on the back wall. The 2 board is 3’ high and leaves
nd
3. Cut and nail plysen board pieces so they cover the remaining openings on the front wall.
Place the boards vertically.
ACCESSORIES
Inside the toilet house place:
1. A barrel bolt inside each door so it can be locked from the inside to secure privacy
when using the toilet.
2. A toilet roll holder and a toilet roll package holder (a board from wood scraps).
17
On the doors place:
3. Door pulls.
4. A safety hasp so the doors can be locked from the outside with a padlock.
It is important to lock the inactive chamber to secure no one uses it.
You can also put electricity on the toilet rooms.
HANDRAIL
1. Cut a 2x2x10 board with a 45° cut 3’ long.
2. Place the 3’ rail support in front of the step foundation and burry it 6”.
Make sure that the 7’ hand rail will touch the toilet house wall when placed
on top of the hand rail.
3. Nail the 7’ rail to the rail support and to the toilet house wall.
4. Nail a support on the toilet house, underneath the rail.
7th WORKING DAY
1. WATERPROOF WALLS, DOORS AND STEPS: Paint the board and steps with enamel/oil
based paint to waterproof them. Do not thin/mix the paint with turpentine, gasoline nor other
materials. / Remember to wash the brushes with turpentine or gasoline before they dry!
2. LOCK THE INACTIVE COMPOSTING CHAMBER: With a padlock close the toilet room that
will remain empty until the 1st/ active chamber is full. Children and uninformed people may
be tempted to use the inactive latrine if it’s easy to access. You may also put a big stone over the
toilet seat to dissuade people from using it.
4. SEAL BOTH COMPOSTING CHAMBERS: Mix up a little bit of mortar and seal the gaps
around both doors, making sure that there are no holes where flies or other insects can
enter.
Congratulations! You have finished your waterless-double-chamber composting toilet! It is ready for use.
18
USE AND MAINTENANCE GUIDELINES
20
WHEN THE COMPOSTING CHAMBER IS FULL
Depending on how many people use the toilet, the composting chamber will take from 9 to
24 months to fill. When the active chamber is almost full (only 6” are left to fill):
21
ACTIVATE THE EMPTY TOILET ROOM
22
HAND WASHING TIPS
REFERENCES
24