ONE PROCESS, THREE STEPS TO SUCCESS: THE MILLING

Milling / Running / Backfilling


• Stepped milling: Width and depth are executed according to
customer-specific requirements
STREET SECTION:
• Output: up to 3 m per minute
Street layout • High flexibility: tight radii possible
according to • Cleanliness: Refuse is vacuumed off immediately
requirements of
road sustainer
PATENTED METHOD FOR STEPPED MILLING:
• For secure placement of piping
1 • For protection against vertical pressure

TELECOM/
THE RUNNING …

3
PROVIDER SECTION … and backfilling of piping for fibre-optic cables:
• Multiple pipes in a single working step
• Running performance: up to 1 kilometre per hour
• Empty pipes are cushioned with granulate or sand and fixated

2
at the deepest point of the kerf
• Additional safety measures available upon request

1 THE BACKFILLING
• The kerf is backfilled with asphalt or two-component
encapsulant (motorcycle-proof) from step one of the cut
CONNECTION VERSIONS • Instantly fit for traffic between each step of construction
• The combination of the milled step and the backfilling material
protects the underlying piping-channel from vertical pressure
Fibre to the Curb

Connected via distribution box


3
Direct connection

Fibre to the Home