Professional Documents
Culture Documents
Front End Engineering Design (FEED) for Large Industrial Projects: FEED Maturity and
Its Impact on Project Cost and Schedule Performance
Abstract
Assessing the maturity of front end engineering design (FEED) for large industrial
projects is a critical task with significant influence on overall project success. The owner's
expectation is to be able to make informed decisions including cost and schedule predictions to
determine whether the project should proceed to the next phase, the level of contingency needed
for the project, and the predicted impact of FEED maturity on the success of follow-up phases.
The primary objective of this paper focuses on FEED maturity and its impact on project
performance in terms of cost change and schedule change. The authors collected data from 33
completed large industrial projects representing over $8.83 billion of total installed cost. A key
result is that projects with high FEED maturity outperformed projects with low maturity by 20
percent in terms of cost growth in relation to the approved budget at Phase Gate 3.
Keywords: Front end planning; Front end engineering design; Maturity; Industrial.
INTRODUCTION
Front end planning (FEP) is the process of developing sufficient strategic information
with which owners can address risk and decide to commit resources to maximize the chance for a
successful project (Gibson et al. 1993). Arguably, FEP is the single most important process in a
large industrial project’s lifecycle (CII 2006). While addressing FEP, past research efforts have
not specifically focused on assessing the maturity of the engineering design component of front
end engineering design (FEED) activities. Both the owner and the engineer have to be aligned as
the project design process moves forward (CII 2005). The owner's expectation is to be able to
make informed and reliable decisions including cost and schedule predictions. These decisions
also include the contingency level needed for the project and the predicted impact on the success
of subsequent phases which include detailed design and construction, project execution, and
start-up. Moreover, it is well documented that schedule compression during FEP may lead to
challenges with design maturity (CII 2006). Due to these identified needs, Construction Industry
Institute (CII) formed a research team to assess the maturity and accuracy of FEED to support
phase-gate approvals during FEP. This research effort documents a method to measure FEED
maturity and its impact on performance within the industrial project sector.
© ASCE
Construction Research Congress 2018 2
BACKG
GROUND & LITERAT
TURE REVIIEW
Definitioons
The
T definitions and matu urity elemen nts were refifined throughh research ffocus groupss that
included 24 industry experts and d research sccientists, as w
well as an inndustry survey. Based onn this
collectivee knowledgee the researcch team developed standdardized deffinitions of F FEED and FFEED
maturity as follows: FEED is defined
d as a componentt of the FE EP process pperformed dduring
detailed scope (Phase 3), consistting of the engineering
e ddocuments, outputs, andd deliverablees for
the chossen scope of work. Consequently
C y, FEED m maturity is defined ass the degreee of
completeeness of the deliverabless to serve ass the basis ffor detailed ddesign at the end of dettailed
scope (Ph hase Gate 3)). The sectio
ons below prresent the litterature regaarding FEP aand FEED w within
the conteext of engineeering design
n.
Front En nd Planning g
FEP has been n considered d by CII to be
b a best prractice for oover 15 yearrs (Collins 22015).
FEP beg gins after thee project cooncept is connsidered dessirable by thhe business leadership of an
organizattion, and co ontinues unttil the beginnning of deetailed desiggn of a projject (Gibsonn and
Dumont 1995). Gibsson et al. (19 994) outlinedd 14 specifi c activities aand productts of a good FEP.
Some off these activ vities are options analyssis, scope deefinition andd boundariees, life-cyclee cost
analysis, cost and schhedule estimmates. Moreo over, FEP haas many otheer associatedd terms, incluuding
pre-projeect planningg, front end d loading (F FEL), progr amming, annd schematiic design am mong
others. Figure 1 showws the typicaal steps invollved in the F
FEP process and are adappted from thhe CII
FEP Too olkit (CII 20014a). The key
k takeawaay point froom Figure 1 is that FEE ED activitiees are
usually completed
c beefore detailed
d design is initiated.
Figure 1: Front
F End Planning
P Prrocess (CII 2014a)
Front En nd Engineerring Design (FEED)
Several reseaarch efforts have
h been coonducted meentioning FE EED; howeveer, there has been
little worrk done to develop
d a staandard defin
nition of FEE ED and deffine its matuurity componnents.
Additionnally, FEED is rarely mentioned
m ass a stand-allone term, aand frequenttly linked to the
different processes associated
a with
w FEP. Merrow
M (20111) characteerized FEED D of the oill and
chemicall industries specifically y in the thirrd phase off FEP, whicch consists of business case
developm ment, scope developmeent, project definition aand planninng, and the work proccesses
needed to o prepare a project for execution.
e A report from
m CII (2013) referred too FEED as ““basic
design.” O’Connor et e al. (2013) defined FE EED as a phaase that invoolves the opptimization oof the
design basis for the concept, ex xecution plaan, and commpletion of any work nneeded to innitiate
detailed engineering g design. By y the end off this phasee, the projecct has receivved fundingg, the
project teeam has been n formed, a preliminary y constructionn plan has bbeen put intoo place, and long-
lead equiipment have been identiffied. Schasch hke (2014) ddefined FEEED as a conceptual studyy used
for the development
d t and analyssis of process engineeriing projects. Overall, thhe key takeeaway
point froom this review is that FEED has many diffe ferent definiitions depennding on whho is
evaluatinng the projeect and what FEP phase they are eevaluating. Thus, a staandardized F FEED
definitionn for large in
ndustrial pro
ojects is need
ded.
© ASCE
Construction Research Congress 2018 3
© ASCE
Construction Research Congress 2018 4
part of the scope of this research. They are shown in order to distinguish the maturity component
of FEED from the whole PDRI-Industrial.
I. BASIS OF DECISION
A. Manufacturing Objectives C. Basic Data Research Development
A.1 Reliability Philosophy C.1 Technology
A.2 Maintenance Philosophy C.2 Processes
A.3 Operating Philosophy D. Project Scope
B. Business Objectives D.1 Project Objectives Statement
B.1 Products D.2 Project Design Criteria
B.2 Market Strategy D.3 Site Characteristics Available vs. Required
B.3 Product Strategy D.4 Dismantling and Demolition Requirements
B.4 Affordability/Feasibility D.5 Lead/Discipline Scope of Work
B.5 Capacities D.6 Project Schedule
B.6 Future Expansion Considerations E. Value Engineering
B.7 Expected Project Life Cycle E.1 Process Simplification
B.8 Social Issues E.2 Design & Material Alternatives Considered/Rejected
E.3 Design for Constructability Analysis
II. BASIS OF DESIGN
F. Site Information H. Equipment Scope
F.1 Site Location H.1 Equipment Status
F.2 Survey and Soil Tests H.2 Equipment Location Drawings
F.3 Environmental Assessment H.3 Equipment Utility Requirements
F.4 Site Permits
F.5 Utility Sourced with Supply Conditions I. Civil, Structural, & Architectural
F.6 Fire Protection and Safety Considerations I.1 Civil / Structural Requirements
I.2 Architectural Requirements
G. Process/Material
G.1 Process Flow Diagrams J. Infrastructure
G.2 Heat & Material Balances J.1 Water Treatment Requirements
G.3 Piping & Instrumentation Diagrams J.2 Loading/Unloading/Storage Facility Requirements
G.4 Process Safety Management J.3 Transportation Requirements
G.5 Utility Flow Diagrams
G.6 Specifications K. Instrument & Electrical
G.7 Piping System Requirements K.1 Control Philosophy
G.8 Plot Plan K.2 Logic Diagrams
G.9 Mechanical Equipment List K.3 Electric Area Classification
G.10 Line List K.4 Substation Req’mts Power Sources Ident.
G.11 Tie-In List K.5 Electric Single-Line Diagram
G.12 Piping Specialty List K.6 Instrument & Electrical Specifications
G.13 Instrument Matrix
III. EXECUTION APPROACH
L. Procurement Strategy M. Deliverables
Identify Long Lead/Critical Equipment and
L.1 M.1 CADD/Model Requirements
Materials
L.2 Procurement Procedures and Plans M.2 Deliverables Defined
L.3 Procurement Responsibility Matrix M.3 Distribution Matrix
N. Project Controls P. Project Execution Plan
N.1 Project Control Requirements P.1 Owner Approval Requirements
N.2 Project Accounting Requirements P.2 Engineering/Construction Plan Approach
N.3 Risk Analysis P.3 Shut Down/Turn-Around Requirements
P.4 Pre-Commissioning Turnover Sequence Requirements
P.5 Startup Requirements
P.6 Training Requirements
© ASCE
Construction Research Congress 2018 5
Figure 3. Structure of
o FEED M
Maturity Elem
ments
The
T 46 elemeents in the maturity
m asseessment are arranged in a score sheeet format annd are
supported d by descripptions and chhecklists. Th
he selection oof the level of definitionn of each eleement
is compleeted by assessing each of o the elemen nts individuaally, leadingg to an overaall maturity iindex
that is then normalizeed from zero o to 100 poinnts. A basic tenet of fronnt end plannning is that nnot all
items to be assessed are equally critical to project
p succeess. Certain maturity eleements are hhigher
in the hieerarchical orrder than oth
hers with resspect to theirr relative im
mportance. T
The research team
decided to use elem ment weigh hts directly from the P PDRI-Industtrial since tthese have been
developeed scientificaally and vetteed over 20 years
y by induustry.
© ASCE
Construction Research Congress 2018 6
Statistical analysis allowed the authors to interpret the data, and provided a basis to quantify the
impact of FEED maturity on project performance.
Table 1: Descriptive Statistics (N=33)
© ASCE
Construction Research Congress 2018 7
CONCLUSIONS
This paper focuses on FEED maturity and its impact on large industrial project
performance in terms of cost change and schedule change. The paper presented the first industry
agreed upon FEED and maturity definitions to better align owner and contractor communication.
The FEED maturity and its impact on project performance was investigated. The key result
based on the statistical analysis is that projects with high FEED maturity outperformed projects
with low maturity by 20 percent in terms of cost growth in relation to the approved budget at
Phase Gate 3. Thus, FEED maturity plays an important role in the success of industrial projects,
and could potentially save the owner 20 percent of the project cost.
ACKNOWLEDGEMENTS
This study was funded by the Construction Industry Institute (CII). The authors would
like to thank the research team and the industry professionals who volunteered their time,
expertise, and project data, which were all vital for the successful completion of this study.
REFERENCES
Collins, W. A. (2015). Development of the project definition rating index (PDRI) for small
industrial projects. Ph.D. Dissertation. Arizona State University.
Construction Industry Institute (1994). Analysis of Pre-Project Planning Effort and Success
Variables for Capital Facility Projects. SD 105. Austin, TX.
Construction Industry Institute (2006). Front End Planning: Break the Rules, Pay the Price.
Research Summary 213-1. Austin, TX.
Construction Industry Institute (2014a). Front End Planning Toolkit 2014.1. Implementation
Resource 213-2. Austin, TX.
Construction Industry Institute (2014b). Project Definition Rating Index: Industrial Projects.
Implementation Resource 113-12. Austin, TX.
Gibson Jr. G. E., Kaczmarowski, J. H. and Lore Jr., H. E. (1993). “Modeling Pre-Project
Planning for the Construction of Capital Facilities.” Source Document 94 prepared for
Construction Industry Institute, University of Texas at Austin, Austin Texas.
Gibson, Jr, G. E. and Hamilton, M.R. (1994). “Analysis of Pre-Project Planning Effort and
Success Varibles For Capital Facility Projects”. Source Document 105 prepared for
Construction Industry Institute, University of Texas at Austin, Austin Texas.
Gibson, Jr, G. E. and Dumont, P. (1995). Project Definition Rating Index (PDRI) for Industrial
Projects. Research Report 113-11. Austin, TX: Construction Industry Institute.
© ASCE
Construction Research Congress 2018 8
Morrison, J. (2009). Statistics for Engineers: an Introduction. Chichester, John Wiley &
Sons.
Merrow, E. W. (2011). Industrial megaprojects: concepts, strategies, and practices for success.
John Wiley & Sons.
O’Connor, J. T., O’Brien, W. J., & Choi, J. O. (2013). Industrial modularization: How to
optimize; How to maximize. The University of Texas at Austin: Construction Industry
Institute, Austin, TX. Research Report RR283-11.
© ASCE