RENCANA ANGGARAN BIAYA

BANTUAN PENGEMBANGAN SARANA PRASARAN EKOWISATA


EMBUNG SIBLIGO UNTUK KONSERVASI ALAM

1 Rencana Pelaksanaan : 1 Januari s/d 31 Desember 2019


2 Sumber Anggaran : Bantuan LHK Prov. Jateng 2018
Melalui Balai Pengelolaan Hutan Wilayah III

Rincian Pendanaan
HARGA SAT JUMLAH
NO URAIAN VOL/SAT
( Rp ) ( Rp )
1 2 3 4 5
Pembangunan Sarana Prasarana Desa
I Wisata 100,000,000
Sumber Anggaran dari Bant. LHK Prov. 100,000,000
Jateng 2018
Betonisasi jalan menuju ke Obyek Curug
A Semirang 65,000,000
1 Belanja Barang dan Jasa
Belanja modal
Tenaga 15,476,000
- Tukang 26 OH 88,000 2,288,000
- Tenaga 156 OH 73,000 11,388,000
- Mandor 18 OH 100,000 1,800,000
Material 49,524,000
Semen 308 m 47,500 14,630,000
Pasir 28 m3 380,000 10,640,000
Benang 3 glg 2,500 7,500
Ember 11 bh 12,000 132,000
Batu blondos 8 m3 165,000 1,320,000
Batu pecah 1/2 31 m3 350,000 10,850,000
Besi beton 799 kg 10,000 7,990,000
Kawat beton/ bendrat 11 kg 16,500 181,500
Minyak bekisting 4 ltr 10,000 40,000
Paku 8 kg 16,000 128,000
Papan 1 m3 3,605,000 3,605,000
2 Sumber Anggaran Swadaya, Pertisipasi
dan
Gotong Royong Masyarakat
Belanja Barang dan Jasa
- Tenaga kerja bakti
Belanja Modal

B Pembangunan Gapura Wisata Curug


Semirang 14,000,000
1 Belanja Barang dan Jasa
Belanja modal
Tenaga 4,332,000
- Tukang 26 OH 88,000 2,288,000
- Tenaga 28 OH 73,000 2,044,000
Material 9,668,000
- Semen 10 zak 47,500 475,000
- Batu bata 300 bj 800 240,000
- Batu kali 3 m3 165,000 495,000
- Pasir 6 m3 380,000 2,280,000
- Pipa besi 1,5" 5 btg 275,000 1,375,000
- Pipa besi 2" 5 btg 320,000 1,600,000
- cat tembok 1 kg 30,000 30,000
- cat besi 4 kg 60,000 240,000
- Tiner 2 ltr 21,000 42,000
- Huruf ( tulisan ) 59 bh 49,000 2,891,000
C Pembangunan Gazebo 3 unit 21,000,000
Belanja Barang dan Jasa
Belanja modal 21,000,000
Tenaga 4,830,000
- Tukang 30 OH 88,000 2,640,000
- Tenaga 30 OH 73,000 2,190,000
Material 16,170,000
- Kayu balok 27 btg 310,000 8,370,000
- Papan kalimantan 30 lmb 145,000 4,350,000
- Usuk kalimantan 30 btg 70,000 2,100,000
- Paku 9 kg 16,000 144,000
- mur Baut 17 3 bh 2,500 7,500
- Semen 3 zak 47,500 142,500
- Pasir 1.5 m 380,000 570,000
- Plastik uv 18 m 27,000 486,000
JUMLAH (Rp.) 100,000,000

Mengetahui : Ketua Kelompok Tani …………………


Kepala Desa Lerep

……………………………. …………………….