CONSTRUCTION METHODOLOGY
The contractor will be responsible for the setting up of their facilities, equipments and
the disposition of various facilities at the end of the project construction. The contractor shall
bring in all the required equipment to the site.
The contractor will furnish, deliver, place and complete any and all necessary materials,
labor, equipment, supplies, utilities, transportation, supervision and other facilities in connection
with the project and to perform all operation necessary to complete and ready for use on the
work involved.
Samples of materials are to be tested for the corresponding materials and quality control
test prior to the usage of it.
Construction work starts with removal of existing pavement, existing sidewalk and curb
and gutter followed by the excavation of the propose RC Pipe Culvert drainage.
The next to be constructed will be the upgrading of roadway which includes subgrade
preparation, laying of aggregate base course and must be properly compacted which will be
monitored thoroughly by this office prior to concrete pouring. Restoration of sidewalk and curb
and gutter and construction of driveway is also included in the proposed project.
As soon as all phases of work have been done in accordance with the approved plans
and specifications, a joint final survey is to be conducted prior to the issuance of final
acceptance.