You are on page 1of 11

IPA03-E-059

PROCEEDINGS, INDONESIAN PETROLEUM ASSOCIATION


Twenty-Ninth Annual Convention & Exhibition, October 2003

THE APPLICATIONS OF JET PUMPS AS A COST EFFECTIVE WAY TO ENHANCE


GAS PRODUCTION AND RECOVERY

M.M. Sarshar*
Najam A. Beg*
Ian Andrews**

ABSTRACT The pressure of this gas is often considerably below


that of the transportation lines or the inlet of the
The produced or processed gas is often at a lower compressors and, as a result, in many cases, it has
pressure than that demanded by the transportation or been flared as waste gas. The flaring of waste gas is
process system and costly compressors are generally becoming more and more unfavorable and
used to boost its pressure. In some applications the unacceptable because of environmental issues.
field layout and operation conditions also cause
restrictions in production from the producing wells. A cost effective solution to some of these problems is
The use of jet pumps is a cost effective way to boost the use of jet pumps which are in most cases of much
the pressure of low pressure (LP) gas or increase lower cost than the alternative boosting systems. This
production from LP wells at a fraction of the cost of paper describes the principle of their operation and
compressors. Jet pumps can also help to debottleneck refers to some of the recent field examples
the existing compressors. worldwide. The economic benefits of the jet pump are
also highlighted for these field examples.
This paper describes the principle of their operation,
factors affecting their performance and the common JET PUMP TECHNOLOGY
range of applications of the system in the oil and gas
industry. Some recent field examples are given, Jet pumps, or sometimes known as “eductors” or
together with comments on the economic aspects of “ejectors”, are simple passive devices which use
their use. Recent field applications have proven that energy from an existing high pressure (HP) fluid to
the payback period for the capital is achieved in a few boost the pressure of the low pressure (LP) fluids.
days to a few weeks, depending on the field
conditions. The general configuration of the jet pump is shown in
Figure 1. High pressure (HP) fluid passes through a
INTRODUCTION nozzle where the velocity of the flow is increased
substantially. As the flow passes through the nozzle,
Transportation, utilization and export of the produced part of the potential energy (pressure) is converted to
gas often bring about both technical and economical kinetic energy (velocity). This energy conversion
challenges for the operators when the pressure of the results in the generation of a low pressure zone in
gas is low. front of the nozzle. It is at this point where the low
pressure fluid is introduced. The high momentum and
The pressure of the produced gas is often boosted energy of the (HP) motive flow carries the LP flow
using costly compressors in order to meet the required through a mixing tube where transfer of momentum
delivery pressures. In addition, there is often gas from and energy takes place. The mixture then passes
the later stages of the process system in the fields through a diffuser where the velocity is gradually
with a very low pressure. reduced and further pressure recovery takes place.
The pressure of the mixture at the outlet of the jet
pump is at an intermediate level between the HP and
* CALTEC Limited, UK
** BP, UK LP pressures.
The jet pump therefore offers two main benefits; gas is required in comparison with the flow rate of the
LP gas.
a) It enables the low pressure fluids to be exposed
only to the low pressure zone in front of the
nozzle and not to the back pressure imposed by RANGE OF APPLICATIONS
the high pressure fluids or the downstream
process or transportation system. The application of jet pumps in gas production varies
and the following are the most common examples;
(b) The jet pump boosts the pressure of the LP fluids
to that of the inlet of the pipeline system, the • Boost production of low pressure gas wells
manifold or process facilities. (Figure 3)
• Well kick-off
The fluids may be gas, liquid or a mixture of the two. • Removing produced liquid accumulated in gas
In this paper the gas application is mainly considered wells
with a brief reference to jet pump applications in • De-bottlenecking existing compressors (Figure 4)
multiphase oil production. • Boosting the pressure of LP processed gas to an
intermediate pressure (Figure 5)
Jet pumps are not new and date back to 1852, • Boosting the pressure of very low pressure (LLP)
invented by James Thomson in England. In the past gas to prevent flaring. (Figure 6)
fifteen years, further research and development work
• Ideal for pressure boosting in remote or
has led to an improved design and efficiency and a
hazardous environment.
better understanding of their operation and use in the
oil and gas industry and promises to offer cost saving In these cases the source of the (HP) motive pressure
and simple solutions to some of the said boosting could be from one of the following;
problems.
• HP well(s)
PERFORMANCE IN GAS PRODUCTION
• Lift gas
APPLICATIONS :
• HP gas from the outlet of a compressor
The performance of the jet pumps handling gas is • Gas from HP separators
dictated mainly by the following factors; • HP gas from any other sources such as (HP)
pipelines etc.
P HP / PLP or HP/LP Pressure Ratio • HP liquid, which has specific limited applications
FLP / FHP or LP/HP Flow Ratio
Pd / P LP or discharge/LP Pressure Ratio The higher the pressure of the motive gas, the more
beneficial would the jet pump be in generating the
The performance may be presented by the required level of boost for the LP pressure, using a
dimensionless pressure ratio of Pd/P LP , which is the minimum amount of HP gas. A further benefit of
ratio of the discharge (Pd) to LP pressure (P LP ). using HP gas from sources such as lift gas, or the
Figure 2 shows a typical range of performance curves outlet of a compressor is that this pressure, apart from
for jet Pumps. The performance is also affected to a being relatively very high, remains unchanged, while
lesser extent by other factors such as the operating if HP Wells were used their pressure would
temperature and gas properties. It is worth noting that eventually decline with time.
in order to achieve a discharge to LP Pressure ratio of
greater than 2, relatively high HP/LP pressure and In most cases, the boost in production of the aging
lower LP/HP flow ratios are required, as shown in wells has been achieved using HP motive gas from
Figure 2. In some applications where the required high pressure wells (Ref 2), or from the existing
discharge to LP Pressure ratio is above 2, more than compressors as in the case of the described INDE
one jet pump may be used in series to achieve the field.
desired target. Figure 2 also shows that for high
HP/LP pressure ratios a better level of boost is Figure 5 shows how by lowering the operating
achieved for the LP flow and a smaller amount of HP pressure of the separator the back pressure on
producing wells can be reduced, thus increasing oil agreement quota. A cost effective solution with a
production. short period for the delivery of the system was highly
desired. The review of options such as upgrading the
Well kick -off can in some cases be achieved by using existing compressor and further drilling and workover
the jet pump at surface. By lowering the flowing of some wells showed to be very costly, with long
wellhead pressure of the well below the normal duration to implement.
operating pressure of the production line or the
manifold pressure, the well may in this case flow at a An assessment of using jet pumps proved to be very
rate sufficient to offload the liquids that have been attractive both from the economic point of view and
accumulated in the well bore during its normal for the delivery period. The motive gas was provided
operation or shutdown. The success of this operation by high Pressure Rotliegend wells (160 MMscfd @
is, however, dependant on the flow rate and pressure 800 Psig) on one platform and the Zechestein wells
of the HP gas available and the conditions of the well. (71 MMscfd at 375 Psig) for the second 52/5A
Removal of the accumulated liquids in gas wells or platform. These jet pumps enabled the production
gas pipelines has been achieved successfully as from the two platforms to increase by 25 MMscfd and
experienced in fields operated by Agip and BP. 15 MMscfd, which amounted to an increase of 25%
and 41% respectively (see table 1). This solution was
Boosting the pressure of very low pressure gas (LLP) economically so attractive that a payback period of
which is often flared is a challenge as the level of four weeks was achieved.
boost required or the discharge to LP pressure ratio is
often well in excess of two. In some cases this ratio is The Monster Jet Pump! –Indefatigable (INDE)
in excess of five to six. Such a high level of boost is Field-UK
achievable but demands a high pressure gas with a
significant HP/LP pressure ratio and flow ratio as A further example is the use of the Jet pump on BP’s
shown in figure (2). In some applications more than INDE 23A platform in the Southern North Sea. The
one jet pump (two or possibly three) may be required, mature state of the INDE field meant that the
demanding a significant volume of HP gas (Figure 6). compressors were required to generate lower suction
Despite these challenges, using several jet pumps is pressures in order to maintain the desired production
often more economical than the alternative options rate.
such as the use of additional compressors or
upgrading the compressors. The use of jet pumps is The INDE platform, located in block 49/23A of the
therefore well worth considering in these cases, Southern North Sea, is the central compression
particularly in circumstances where flaring is not facility for the field and acts as the transport hub for
permitted. the area, providing 90,000 KW of gas compression
capacity, liquid handling and hydrate inhibition
While HP liquid (oil or water) can be used facilities. The platform receives gas from eleven
successfully as the motive flow to boost the pressure satellite platforms owned by four different Partners.
of LP gas, the jet pump requires a relatively high This field also receives production from two
volume of the liquid phase to achieve the desired neighboring platforms (Juliet and Kilo) operated by
boost and if high pressure gas is available, in most Shell U.K.
cases, it offers a better solution.
These fields vary from the very large and mature
INDE field which came online in 1972, to the
FIELD EXAMPLES relatively small North Davy field which came online
in November 2001.
Hewett field North Sea:
The vastly different stages of depletion of these fields
One of the earliest examples is the jet pump installed placed contradictory demands on the Compression
in 1987 – 1988 on Phillips petroleum’s, Hewett field System. The compressors are required to operate at a
in the Southern North Sea (Ref.1). In this case, suction pressure close to 95 psia in order to handle the
Phillips petroleum faced a potential shortfall in gas peak demand capacity of 460 MMscfd. This inlet
production from the Hewett field to meet their sales pressure for the compressors was, on the other hand,
too high for fields such as Shell 49/24 juliet and kilo The system has operated with no problems or
and thus restricted production from these fields. maintenance requirement since 2001 and, as claimed
by BP, the capital cost of the Project was recovered in
A detailed review of the options showed that using a less than ten days, assuming gas price at 12 pence a
jet pump was the most cost effective and fastest way therm.
of solving this problem. The alternative solution of
upgrading the compressors would have involved three The cost effective use of jet pumps to increase
to four times additional capital expenditure and a production, to prevent flaring and to debottleneck
much longer delivery period. Also one of the main compressors has been demonstrated convincingly by
restrictions for the platform was that the gas received operators including; Agip (ref 2), BP, Marathon,
from Shell platforms contained some liquid phase. If Arco, Britannia, Chevron and Shell (UK). These
a separate compressor were to be used, it would have examples have brought about the awareness and
needed to be a multiphase booster compressor as benefits of the system for future field applications.
there was no room to install an additional gas-liquid
separator on the Platform. Conventional multiphase / THE EFFECT OF LIQUID IN GAS PHASE
compressor pumps are, however, relatively low
volume systems and a single unit could not handle 68 Jet pumps handling gas may operate satisfactorily if a
to 70 MMscfd of low pressure gas. small amount of liquid (water or condensate) is
present in either the HP or LP flow. If, however the
The jet pump system was designed to provide amount of the liquid increases to more than 1% or 2%
flexibility and minimum use of HP gas as the by volume, its effect on the performance of the jet
production demand varied (Figure 7). The jet pump pump starts to become significant, as shown in Figure
with an overall length of over 7 meters and inlet and 8. It is worth noting that the jet pump can handle
outlet pipe diameters of 24” was named the monster satisfactorily transient conditions such as start-up
jet pump!, handling a total throughput of up to 140 when a large volume of liquid accumulated in the
MMscfd. A portion of high pressure gas at 1200 Psia well bore or the production line may be discharged.
from the outlet of the compressor was used as the
motive flow. This enabled a reduction in back In applications when the amount of the liquid phase
pressure on Shell’s platforms by 30 to 35 psi, which produced continuously is significant and above 1% or
led to an increase in production from the field by 20% 2% by volume, separation of the phases may become
to 25% . This pressure boosting, in turn, removed the necessary in order to maximize the performance and
requirement to operate the compressors at very low the efficiency of the jet pump. Compact separators are
suction pressures, thus creating a net 160 MMscfd available to achieve this in cases where sufficient
increase in net gas export capacity. space is not available on platforms to install bulky
separators and a simpler operation is desired (Ref. 4).
A control valve on the HP inlet of the jet pump
enabled the correct amount of HP gas to be used THE EFFECT OF PRODUCED SAND
when the LP flow rates varied or when the
compressor inlet pressure changed, as dictated by The industry is well aware of the destructive nature of
production demand. The operation of the control produced sand and the damage it causes to equipment
valve was simply linked to the required differential such as choke valves. Gas velocities are high through
pressure between the LP inlet line of the jet pump and the jet pump, particularly through the nozzle (HP
its outlet target delivery pressure needed by the flow) and the mixing tube (HP & LP mixture). To
compressor. This rather unconventional method of prevent excessive erosion, two solutions are offered
control for the jet pump was achieved as a result of and have been used successfully;
having a high HP/LP pressure ratio of eighteen to one
and prevented wastage of HP gas at low LP flow (a) Reinforce the surfaces subject to high velocities.
rates. The system also offered a further benefit of This is achieved by having a coating of hard
being able to handle multiphase flow (gas-condensate chrome or tungsten carbide or equivalent. In some
and water) without the need to separate the small cases the entire surface is protected by using a
amount of the liquid phase present in the gas and ceramic insert which provides the best resistance
accumulated in the pipelines from Shell platforms. because of its superior hardness.
(b) The jet pump is designed with interchangeable of energy. In the case of very low pressure gas which
sections. This enables easy change out of the has been normally flared, the jet pump provides
eroded parts at low cost whenever needed. further environmental benefits by preventing flaring
and meeting the regulatory requirements.
The wall thickness of parts experiencing high gas
velocities is significantly more than that needed based The capital spent for the system includes that of the
on the specified design pressure. There is therefore a jet pump and the additional associated pipework,
further adequate margin to provide added safety and valves, instruments and modifications to the existing
structural integrity even if the unit experiences pipeline system which may be required. The total
erosion. capital spent can be compared against the increase in
production and the revenue from the additional gas
NOISE produced.

The level of noise generated by jet pumps handling A simple way to assess the economic aspects is to
gas may exceed the general limit of 85 dBA specified work out the pay-back period achieved from the
by the industry. increased revenue to recover the capital spent.

The noise level is defined and measured at a distance


of one meter from the jet pump. The level of noise Recent field examples experienced by Agip,
generated depends on the pressure ratio and flow ratio Marathon, BP (UK), Britannia, Phillips petroleum,
of HP and LP gas. The generated noise travels along Shell and others has shown that the payback period
the LP and discharge lines. In order to suppress the has ranged from as short as ten days to a few weeks.
noise and to prevent its spread, silencers can be This has shown clearly the economic attractiveness of
installed at the LP inlet and the discharge point of the this concept.
jet pump. Silencers are in form of spool pieces which
can be supplied and installed as part of the system.
The short pay-back period also enables jet pumps to
OIL PRODUCTION APPLICATIONS be used economically and successfully even over a
short period of a few months in applications where
In oil Production applications, and in gas production the high pressure source diminishes rapidly or the LP
cases when the produced liquid phase is significant wells seize production. Jet pumps can therefore be
and is in excess of 1% or 2% by volume, separation used successfully even as a temporary solution to
of the gas and liquid phases is required for the HP increase production, to meet production quota or to
flow and in many cases, also for the LP flow. prevent flaring when other longer term costly
solutions with a long lead time, such as upgrading
In these applications, it is important that the HP flow compressors, are being considered. The jet pumps
through the nozzle of the jet pump is in single phase. have also been used successfully to debottleneck the
The combined system involving the separation of gas existing compressors at a fraction of the cost of
and liquid phases and using jet pumps is patented and upgrading the compressors.
is marketed under the name of the “Wellcom
System”. Details of this system, its Performance, the
range of applications and the features of a compact REFERENCES
separator (I-SEP) used in such cases are described in
references 3 and 4. Ashton, K., Green, A.J., and Read, A., 1993. Gas
Production Improvements using Ejectors. Society of
ECONOMIC BENEFITS – CONCLUDING Petroleum Engineers – SPE Paper 26684, Offshore
REMARKS Europe, Aberdeen.

The main benefits of the jet pumps in most Villa, M., DeGhetto, G., and Paone, F., 1997. Use of
applications are the increase in production and Ejectors for Boosting Low Pressure Oil and Gas
recovery from the field or preventing wastage or Wells. The Offshore Mediterranean Conference &
flaring of low pressure gas, using an available source Exhibition in Ravenna, Italy.
Sarshar, M.M., and BEG, Dr. N.A., 2000. The Sarshar, M.M., and BEG, Dr. N.A., 2001. The
applications and performance of jet pumps in oil and applications and performance of a novel compact
gas Production handling Multiphase flow, 2nd North separator, 2nd GCC-EU Advanced oil and Gas
American conference on Multiphase Technology, Technology Conference, Abu Dhabi , UAE , May 21-
Banff, Canada, June 21-23, 2000. 22, 2001.
TABLE 1

PERFORMANCE OF THE JET PUMPS OPERATING OFFSHORE ON THE HEWETT FIELD

EJECTOR 52/5A
MOTIVE GAS ROTTLEGENDES ZECHSTEIN
FLOWRATE - MMSCF/DAY 160 71
INLET PRESSURE - psi 800 375

SUCTION GAS LOWER BUNTER UPPER BUNTER


EJECTOR STATUS OFF OFF
FLOWRATE - MMSCF/DAY 100 36
PRESSURE- psi 265 170

EJECTOR STATUS ON ON
FLOWRATE - MMSCF/DAY 125 51
INLET PRESSURE - psi 235 140
TOTAL FLOW RATE - MMSCF/DAY 285 122
DISCHARGE PRESSURE - psi 295 180
RATE BENEFIT - MMSCF/DAY 25 15
Figure 1 - General configuration of a jet pump.

Figure 2 - Gas jet pumps performance curves for a range of pressure and flow ratios.
Figure 3 - Boosting production of LP gas wells.

Compressors

Boosted
Production To Export
Jet Pump

LP Gas From
Wells

Figure 4 - De-bottlenecking existing compressors.


High Pressure Jet Pump

Intermediate Pressure

LP Gas

Low Pressure
Wells

Separator

Oil To Process
or Pumping System

Figure 5 - Boosting pressure of separated gas.

Alternative

Gas To Gas-lift
Compressor Or Export
s

Intermediate
Pressure Gas Jet Pump 1

LLP Gas From


Process System
Intermediate
Pressure Gas

Jet Pump 2
Figure 6 - Pressure boosting of a very low pressure gas.
Davy Line

Export
Bessemer Line
Compressor
Jet Pump

DP
Low Pressure
Gas Wells
Shell
Juliet
Shell
Kilo
Subsea Line

Figure 7 - BP INDE platform jet pump for production and pressure boosting.

Figure 8 - Gas jet pump performance under liquid in the LP gas.

You might also like