Professional Documents
Culture Documents
Matthew Cocklin
April 2013
182
www.scl.org.uk
INTERNATIONAL APPROACHES
TO THE LEGAL ANALYSIS OF
CONCURRENT DELAY: IS THERE
A SOLUTION FOR ENGLISH LAW?
Matthew Cocklin
Introduction
Concurrent delay is one of the most complex and controversial aspects of
construction dispute resolution.1 It is a ‘strategically important’ defence2 and
its practical application and evaluation challenge most legal systems.
Unsurprisingly, it has been described as a ‘minefield’ in England;3 compared
to untangling a ‘knot’ in the United States (USA);4 and expressed as
‘unscrambling the egg’ in Canada.5 Common to all jurisdictions is that delay
analysis takes a quantum leap when interrupted by concurrency.6
The English courts have grappled with the doctrine but failed to offer
authoritative guidance.7 A Scottish recognition of apportionment8 created a
‘flurry of excitement’.9 However, that contribution has now been dismissed in
English law.10 Therefore, the questions must be asked:
1
(a) Can the English courts learn from the courts of other
jurisdictions?11
(b) Is there an international solution or alternative approach to
concurrent delay that can be injected into English law?
This author submits that the answer to both questions is ‘yes’ and will
establish this by comparing the benchmark position in English law to the legal
systems of Scotland, the USA, Canada, Hong Kong and Australia.12
11 This question may be reversed to ask: what do parties to construction contracts and their
professional advisors need to know when working internationally in other jurisdictions?
This question and its answer may act as an aid to the increasing number of English
contracting organisations, engineering consultancies, claims consultancies, law firms and
barristers’ chambers establishing business operations in regions where English law does
not apply.
12 This paper concentrates on the principle of time including the employer’s right to
liquidated damages. It does not consider the other aspect of concurrent delay to which
different rules apply: that is, the recoverable losses of the contractor also known as ‘loss
and expense’. However, the paper will unavoidably cross this boundary in jurisdictions
where time and money are intrinsically linked (for example, the USA and Canada).
13 A detailed consideration of such approaches remains outside the scope of this paper. For
further information see Stephen Furst QC and The Hon Sir Vivian Ramsey (editors),
Keating on Construction Contracts (9th edition, Sweet & Maxwell, 2012) paras 9-062 to
9-066.
14 Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70 Con
LR 32 (TCC).
15 Keating, note 13, para 9-067.
16 Motherwell Bridge Construction Ltd v Micafil Vakuumtechnik 81 Con LR 44 (TCC);
Royal Brompton Hospital NHS Trust v Hammond (No 7) [2001] EWCA Civ 206, (2001)
76 Con LR 148; Steria Ltd v Sigma Wireless Communications Ltd [2008] BLR 79, 118
Con LR 177 (TCC); Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848
(Comm), [2011] BLR 384, 136 Con LR 190; and Walter Lilly: note 10.
17 Walter Lilly: note 10.
18 This argument is a typical concurrent delay defence. See Kutil and Ness: note 6. ‘The
owner’s first line of [defence] is simply that the contractor failed to demonstrate that the
owner was the cause of the delay. Second, the owner can argue that its delay was not on
the critical path and did not cause the overall project delay. Third, the owner can argue
that the contractor failed to mitigate the effect of the owner-caused delay. Fourth, the
2
jurisdiction under the EOT provision19 to take account of the facts and matters
cited by Malmaison Hotel to establish that the causes of delay were the fault of
Henry Boot.
The court decided that the arbitrator did have jurisdiction. Mr Justice Dyson
(as he then was) held that the architect, when determining the delaying effect
of a relevant event under clause 25, is not precluded from considering the
effect of contractor culpable events, notwithstanding the existence of an
‘admitted delay’ on the part of the employer:
‘In my view, the respondent is entitled to advance these other matters by
way of defence to the EOT/I claim. It is entitled to say (a) the alleged
relevant event was not likely to or did not cause delay eg because the
items of work affected were not on the critical path, and (b) the true
cause of the admitted delay in respect of which the claim for an
extension of time is advanced was something else. The positive case in
(b) supports and fortifies the denial in (a). The respondent could limit its
defence to the claim by relying on (a), but in my view there is nothing in
clause 25 which obliges it to do so.’20 [emphasis added]
The English courts, however, have side-stepped the full effect of this judgment
in favour of a restrictive interpretation. This is premised on an ‘agreement’21
between the parties to the case:
‘… it is agreed that if there are two concurrent causes of delay, one of
which is a relevant event, and the other is not, then the contractor is
entitled to an extension of time for the period of delay caused by the
relevant event notwithstanding the concurrent effect of the other
event.’22
This agreement, however, was one between the parties and not part of the
judgment of Mr Justice Dyson. Nonetheless, it is widely represented as a
general principle of English law on concurrent delay, known as the
‘Malmaison approach’. It is deemed to support the proposition that the
architect, when determining the delaying effect of a relevant event under
clause 25, is not permitted to consider the effects of other events.23
owner can show that the contractor was responsible for a concurrent delay that negated
the compensability of the owner’s delay. Fifth, the owner can argue that the contractor
failed to provide sufficient evidence for the trier of fact to segregate the owner’s delay
from the contractor’s delay.’
19 Standard Form of Building Contract, 1980 edition, Private with Quantities, as amended,
Joint Contracts Tribunal, Clause 25.
20 Malmaison, note 14, para [15].
21 Also referred to as ‘common ground’.
22 Malmaison, note 14, para [13].
23 ‘Other events’, in this context, means ‘contractor culpable events’.
3
‘Where Contractor Delay to Completion occurs or has effect
concurrently with Employer Delay to Completion, the Contractor’s
concurrent delay should not reduce any EOT due.’24
The question must, therefore, be asked: why have the English courts favoured
this restrictive interpretation, contrary to the full judgment of Mr Justice
Dyson?28 The editors of Keating offer the rationale that, if the parties have
agreed a series of relevant events in their contract entitling a contractor to an
EOT, then they must have contemplated the possibility of more than one
effective cause of delay.29
This reason was approved in both Steria and (more recently) in Walter Lilly:
‘There is nothing in the wording of clause 25 which expressly suggests
that there is any sort of proviso to the effect that an extension should be
reduced if the causation criterion is established.’30
However, this author respectfully submits that such rationale does not justify
the resistance of Mr Justice Dyson’s full judgment. Silence within the
24 The Society of Construction Law Delay and Disruption Protocol (SCL, 2002), page 7:
www.eotprotocol.com. It should be noted that the Protocol is merely a statement of
principles and does not have legal effect unless incorporated into a contract. It is,
however, a respected document and may be persuasive in certain circumstances.
25 Steria v Sigma, note 16, para [131].
26 Walter Lilly, note 10, para [366].
27 Walter Lilly, note 10, para [370].
28 See the main text to notes 18-22 for the crux of the judgment, in particular, a quoted
extract.
29 Keating, note 13, para 8-025. The editors of Hudson apply a similar explanation: see
Nicholas Dennys, Mark Raeside and Robert Clay (general editors), Hudson’s Building
and Engineering Contracts (12th edition, Sweet & Maxwell, 2010),
para 6-060.
30 Walter Lilly, note 10, para [370].
4
contract cannot by itself preclude an architect from considering contractor
culpable delay. As Mr Justice Dyson acknowledged: ‘the respondent is
entitled to advance these other matters by way of defence’.31
31 Malmaison: main text to note 20. Indeed it would have been curious to reach any other
finding, since to do so would have made the concurrent delay defence redundant and
non-existent in the absence of an express contractual right.
32 See Hamish Lal, ‘Claims for Extensions of Time: A Turning Point?’ (2010) 21(10) Cons
Law 6; Brodie McAdam, ‘Apportionment and the Common Law: Has City Inn Got it
Wrong?’ (2009) 25 Const LJ 79, page 90; and Jeremy Winter, ‘How Should Delay be
Analysed – Dominant Cause and its Relevance to Concurrent Delay’, SCL Paper 153
(January 2009), page 20: www.scl.org.uk.
33 Walter Lilly, note 10, para [370].
34 The Protocol, note 24, para 1.4.12. The justification applies to Core Principle 9, set out in
the main text to this note.
35 Generally, a contractor who receives an EOT for concurrent delay will not receive loss
and expense for his difficulty in fulfilling the ‘but for’ test of causation. Hence the
position under English law is often described as ‘time but no money’.
36 De Beers UK Ltd v Atos Origin IT Services UK Ltd [2010] EWHC 3276 (TCC), [2011]
BLR 274, 134 Con LR 15, paras [177]-[178]. Mr Justice Edwards Stuart made indirect
reference to the Malmaison approach.
37 Adyard Abu Dhabi: note 16.
38 Trollope & Colls Ltd v North West Metropolitan Regional Hospital Board [1973]
1 WLR 601 (HL), [1973] 2 All ER 260, 9 BLR 60.
39 Adyard Abu Dhabi, note 16, para [282], citing Lord Denning in Trollope & Colls, note
38, [1973] 1 WLR 601, page 607.
40 This is because the contractor would have suffered delay in any event.
41 Jerram Falkus Construction Ltd v Fenice Investments Inc (No 4) [2011] EWHC 1935
(TCC), [2011] BLR 644, 138 Con LR 21, paras [49] and [52].
42 John Marrin, ‘Concurrent Delay Revisited, SCL Paper 179 (February 2013), page 7:
www.scl.org.uk.
5
general principle of English law. This has given rise to a debate: Malmaison v
the approach in Scots law (apportionment).
City Inn has received a frosty reception amongst supporters of the restrictive
interpretation of Malmaison. They present City Inn as:
(i) an alternative to Malmaison; and
(ii) a ‘rule’ for apportionment.
Herein lies the source of the Malmaison v apportionment debate. This author
submits that such perspectives may be unfounded and the debate may not need
to exist. City Inn does not have to be viewed as an alternative to Malmaison.
Neither should it be deemed as creating a rule for apportionment.
6
for quantifying matters that (according to Mr Justice Dyson) may be
considered when assessing an EOT.51
It is correct that the Outer House recognised the necessity for a preliminary
dominant cause test.53 However, the court did not hold that the delay ‘should
[otherwise] be apportioned’. This is patently clear from the judgment, in that
Lord Drummond Young used the words ‘may [apportion]’ not ‘should
[apportion].’54 When he departed from using ‘may’, he avoided creating a
‘rule’, stating that ‘apportionment will frequently be appropriate’.55 The
inference is that apportionment will not always be appropriate. Thus,
flexibility was paramount in Lord Drummond Young’s judgment, as was the
requirement to be ‘fair and reasonable’ in accordance with the express terms
of the contract.
51 This is apparent from the choice of words used for the grounds of appeal that City Inn
put before the Inner House on appeal. The main ground, for the purpose of this paper,
had nothing to do with the trigger for an EOT but concerned whether the Outer House
erred in law. See the judgment of the Inner House, note 8, para [16(3)]: ‘In the
approach taken…to assessing concurrent delaying events for the purposes of clause 25
of the contract, as regards (i) how a period of concurrent delay is to be defined, (ii) how
any period of concurrent delay is to be assessed and (iii) how to treat periods of
concurrent delay in the calculation of extensions of time.’ [emphasis added]
52 Keating, note 13, para 8-027.
53 This seems to be consistent with the position in English law.
54 See, for example, City Inn in the Outer House, note 8, paras [18] and [22], where the
word ‘may’ is used.
55 City Inn, note 8, para [157]. It should be noted that he said ‘frequently’ not ‘always’.
56 See [2010] BLR 473, page 476.
7
o English judges are highly experienced in apportionment under
contributory negligence legislation.
The editors of Keating argue that the court placed too great a weight on the
words ‘fair and reasonable’. This author agrees. Indeed, ‘fair and reasonable’
might justify other approaches aside from apportionment.57 However, with
respect, such criticism is inadequate by itself to deny the possibility of
apportionment.
City Inn has notably not been welcomed by the English courts. It is
respectfully submitted that the relevant decisions are dismissive without
explanation, lack persuasive reasoning and are predicated on an unexplained
affinity with the restrictive interpretation of Malmaison.58 This can be seen
from Adyard Abu Dhabi:
‘… the English law approach would be to recognise that the builder is
entitled to an extension of time, not an apportionment – see, for
example, Malmaison at para 13.’59
It follows that Malmaison and City Inn are viewed as rivals. This author
submits that so long as the English courts continue with their current
confirmation of the restrictive interpretation of Malmaison, so will
apportionment be rejected under English law. In fact, the judgments are not
necessarily rivals. If the courts were to apply the full judgment of
Malmaison,61 then the rivalry may subside, since apportionment might exist as
one method amongst others to assess the impact of a relevant event in the
context of contractor culpable delay.62 Such potential becomes apparent when
the approach of the US courts is considered.
57 For example, see the approach of the US courts to network or CPM schedules, discussed
below.
58 That is, aside from the high level judicial reasoning referenced in the main text to notes
30-36.
59 Adyard Abu Dhabi, note 16, para [288].
60 Walter Lilly, note 10, para [370].
61 See the summary in the main text to notes 14-22.
62 See note 57.
63 Stuart C Nash, ‘Delay and Disruption: Legal Considerations’, SCL Paper D14 (August
2002), page 1: www.scl.org.uk.
8
reason is that the US courts are more experienced than the English in the
complexities of concurrent delay.64 They offer three approaches:
(i) Time but no money;
(ii) Apportionment; or
(iii) Responsibility based on a network or critical path method
(CPM).65
The court refused the request to apportion, being unable to undertake the task
‘with any degree of certainty’ and bound by an existing ‘rule against
apportionment’.67
In Commerce International Co v US, the same court found that the US Army
had severely delayed Commerce International in the reconstruction of 500
tanks required for hostilities in Korea.69 However, Commerce International
ignored its own ‘concurrent and inseparable’ causes of delay. The court
rejected Commerce International’s case and held that ‘there can be no
recovery where the defendant’s delay is concurrent or intertwined with other
delays’. Thus, the rule against apportionment applied notwithstanding the
court’s inference as to the potential for recovery if the concurrency ‘knot’
could be untangled.
64 The earliest of the US cases on concurrent delay significantly pre-dates its English
equivalents and there is no shortage of reported authorities. US law on concurrent delay
has been evolving over the past 145 years since Stewart v Keteltas 36 NY 388 (1867).
65 Bramble and Callahan, note 2, §11.09, 11.110.
66 In Jefferson Hotel Co v Brumbaugh 168 F 867 (4th Cir 1909), three cases were cited as
authority for such a rule: Stewart v Keteltas; Heckmann v Pinkney 81 NY 211 (1880) and
Weeks v Little 89 NY 566 (1882).
67 Jefferson Hotel, note 66, page 874.
68 Greenfield Tap & Die Corp v US 68 Ct Cl 61, 1929 WL 2484 (Ct Cl), page 10.
69 Commerce International Co Inc v US 167 Ct Cl 529, 338 F 2d 81 (1964), pages 87
and 90.
9
Apportionment
The ‘time but no money’ rule has the hallmarks of the restrictive interpretation
of Malmaison coupled with the ‘but for’ test applicable in English law to loss
and expense. However, the influence of a ‘modern trend toward
apportionment … by segregation of delaying events wherever possible’
dictates that it applies less rigorously in the USA.70
In Calumet Construction v Metropolitan Sanitary District of Greater Chicago,
the Appellate Court of Illinois explained:
‘[The traditional rule against apportionment] … is now being abandoned
… in [favour] of the more modern rule of apportionment because of the
increasing popularity of liquidated damages clauses … due to the
increasing complexity of contractual relationships … and … due to the
fact that the older rule is too harsh in its application … This trend in
[favour] of apportionment is similar in nature to the trend in the courts to
apply a comparative negligence standard in tort cases.’71
The US courts will apportion the recovery of delay costs or damages when the
evidence permits the segregation of costs arising from the parties’ respective
causes. In Coath & Goss Inc v US, the US Court of Claims held:
‘Where both parties contribute to a delay neither can recover damage,
unless there is in the proof a clear apportionment of the delay and the
expense attributable to each party.’72
That approach was more recently approved in Essex Electro Engineers v US.74
Essex challenged a finding of ‘time but no money’ by the Armed Services
Board of Contract Appeals. The US Court of Appeals found that ‘the
sequential nature of Essex’s submissions and the government’s responses
[rendered] each party’s delays inherently apportionable’.75
70 Philip L Bruner and Patrick O’Connor, Bruner and O’Connor on Construction Law,
(Thomson Reuters Westlaw, 2012), §15:70.
71 Calumet Construction Corp v Metropolitan Sanitary District of Greater Chicago 178 Ill
App 3d 415 (1988), page 420.
72 Coath & Goss Inc v US 101 Ct Cl 702 (1944), pages 714-715.
73 Blinderman Construction Co Inc v US 695 F 2d 552 (1982) (US Ct of Appeals, Fed
Circuit).
74 Essex Electro Engineers Inc v US 224 F 3d 1283 (2000) (US Ct of Appeals, Fed Circuit).
75 Essex Electro Engineers, note 74, page 1292.
10
concerning the construction of a visitor centre and parking structure at the
Hoover Dam.76
Canadian approaches
Canada lacks literature on concurrent delay.81 This author considers this to be
the influence of US cases and texts which have removed the necessity for the
Canadian courts to reinvent the wheel. However, it also represents a simple
approach in Canada to apportionment.
Unlike the English and US systems, the Canadian courts do not recognise an
all or nothing default approach which is thought to lead to disproportionate
results.82 Furthermore, unlike the US courts, the Canadian system does not
place a high evidential burden on a claimant as a prerequisite to
apportionment. The courts simply roll up their sleeves and apportion the
11
liability of the parties.83 Apportionment is the standard reaction of the
courts.84
83 Grenier: note 5.
84 For cases where apportionment has been applied see RB Reynolds and SG Revay,
‘Concurrent Delay: A Modest Proposal’, (2007) 1 Journal of the Canadian College of
Construction Lawyers 199, pages 200-202. For example, Foundation Co of Canada Ltd
v United Grain Growers Ltd 1995 CanLII 3392 (SCBC).
85 Reynolds and Revay, note 84, page 205.
86 Wood v Grand Valley Railway (1915) 51 SCR 283, 21 DLR 614 (SCC).
87 Chaplin v Hicks [1911] 2 KB 786 (EWCA), page 792.
88 See the references in Reynolds and Revay, note 84, pages 206-207, to cases where the
court strived to ‘do the best it can’: Penvidic Contracting Co v International Nickel Co
[1976] 1 SCR 267, 53 DLR (3d) 748 (SCC) and Potter Station Power Co v Inco Ltd
(1998) 43 CLR (2d) 53 (Ont Gen Div), additional reasons at 1998 Carswell Ont 4986.
89 Reynolds and Revay, note 84, page 207.
90 It may reduce litigation costs (and indeed the need for litigation) in that the parties may
‘roll up their own sleeves’ and undertake the same ‘broad brush’ exercise that the courts
would otherwise undertake.
91 There are ten provinces in Canada and three territories. All, with the exception of
Quebec, operate a common law legal system. The provinces comprise Ontario, Quebec,
Nova Scotia, New Brunswick, Manitoba, British Columbia, Prince Edward Island,
Saskatchewan, Alberta and Newfoundland & Labrador. The territories comprise
Northwest Territories, Yukon and Nunavut.
12
recognised in all provinces. However, the courts of British Columbia and
Nova Scotia have extended its application to contract claims.92
Similar provisions exist in English law under the Law Reform (Contributory
Negligence) Act 1945.95 However, the Act has been doubted as a defence to a
claim for damages based purely in contract.96 Therefore, such an approach
would be of no effect in English law.
Notwithstanding this, the Outer House decision in City Inn has been positively
received by the Court of First Instance. Deputy Judge Simon Westbrook SC,
in W Hing Construction Co Ltd v Boost Investments Ltd, approved the
conclusions drawn by Lord Drummond Young including his recognition of
apportionment.99 This may be indicative of a movement in Hong Kong in
favour of apportionment.
Australian approaches
Australian law is deemed ‘less than clear’,100 with ‘… no clear judicial
guidance on principles that govern the correct approach’.101 Publishers of
Australian standard forms have attempted to rectify this by prescribing
13
procedures for the assessment of concurrent delays.102 However, this has not
entirely solved the problem. Firstly, not all forms of contract in Australia
adopt a prescriptive approach. Secondly, the standard forms are not as clear as
they could be. Consequently, the assessment and resolution of concurrent
delay may be taken out of the hands of the parties and placed into the hands of
judges and arbitrators.
102 Tobin, note 100, page 146. This approach highlights the importance of the construction
contract as the proper arena for the parties to control their commercial destiny. This is a
unique approach because, as the editors of Hudson, note 29, para 6-059 identify, the
complications of interacting delays are so diverse that many draftsmen prefer to leave
these problems unaddressed for tribunals to apply ‘ordinary causation principles’. It
follows, as noted by the editors of Keating, note 13, para 9-058, that any architect or
project manager making an assessment under the contract then lacks guidance in ‘how to
act and what conclusions to draw’.
103 Australian Standards, General Conditions of Contract. This example is referred to by
Tobin, note 100, page 142, and by Jim Doyle, ‘Concurrent Delays in Contracts’ (2007)
112 Australian Construction Law Newsletter 22.
104 JCT 80: note 19.
105 Doyle: note 103.
106 Tobin, note 100, page 146. As observed by Bidgood et al, note 4, the problem with a
failure to define concurrent delay is that ‘concurrency’ has various connotations. This
was recognised by Lord Osborne in City Inn, note 8, in that ‘concurrent delay’ means
different things to different people. He said at para [79] that it is ‘important in the
interests of clarity, to try to disentangle this confusion’. Unfortunately, however, the
global construction industry lacks a standard definition. The nearest to a standard
definition is that used in the Protocol, note 24. John Marrin, ‘Concurrent Delay’ (2002)
18(6) Cons Law 436, has described concurrent delay as ‘a period of project overrun
which is caused by two or more effective causes of delay which are of approximately
equal potency’. This has been adopted by the editors of Keating, note 13, para 8-025. It
has also been approved in Adyard Abu Dhabi, note 16, para [277], as a ‘useful working
definition’. Two types of concurrency are thought to exist: (a) simultaneous or
concurrent causes with concurrent effects (referred to in the Protocol, note 24, page 53 as
‘true concurrency’); and (b) sequential causes with concurrent effects. For other useful
commentaries and discussion on the definition of concurrency see: Bidgood et al, note 4;
Keith Pickavance, Delay and Disruption in Construction Contracts (4th edition, Sweet &
Maxwell, 2010); David W James., Concurrency and Apportioning Liability and
Damages in Public Contract Adjudications, 20 Public Contract Law Journal, page 490.
14
drawbacks. A dispute under clause 35.5 of this AS form may still require
resort to the courts. This would take the parties back to square one and the
vagaries of judicial reasoning which the clause was designed to avoid.
15
In the event that the parties fail to address concurrent delay under the contract,
then the position under Australian law would reflect the approach of English
law by reverting to the common law. However, Jim Doyle suggests that
English cases, whilst not binding, may be persuasive, given that the common
law position in Australia lacks adequate legal authority.116 He observes that in
Thiess Watkins White Construction v Commonwealth the New South Wales
Supreme Court took a similar approach to Malmaison.117
Conclusions
This paper posed two questions. The first was: can the courts in England learn
from the courts of other jurisdictions? The answer is ‘yes’.118 The second
was: is there an international solution or alternative approach to concurrent
delay that can be injected into English law? The answer is ‘yes’:
‘apportionment’. Every jurisdiction considered in this paper presents
apportionment as a balanced outcome and modern solution to the concurrency
dilemma. That is an approach which the editors of the Building Law Reports
once described as ‘an intellectually respectable one’ which ‘merits respect and
detailed consideration’.119
The author contends that the rejection of apportionment by the English courts
is premised on an incomplete application of the Malmaison judgment.
According to this author’s interpretation of the full judgment, the decision-
maker under a contract may take full account of contractor culpable events
when assessing an entitlement to an EOT.120 This means that the contractor is
not automatically entitled to full EOT for the period of critical delay caused by
a relevant event. Rather, the contractor must discharge the burden of proof.121
116 Doyle, note 103, page 23. Support for this can be found in a list of concurrency and non-
critical delay cases prepared by Robert Fenwick Elliott on behalf of SCL Australia. See
Society of Construction Law Australia, ‘Aide Mémoire of Some Key Cases:
Concurrency and Non Critical Delay’, (27th June 2011): www.scl.org.au. Only two out
of 15 cases are Australian (Kane Constructions Pty Ltd v Sopov [2005] VSC 237 (VSC)
and March v Stramare Pty Ltd [1991] HCA 12, [1991] 171 CLR 506, (1991) 9 BCL
215); and neither directly addresses the subject of concurrent delay.
117 Thiess Watkins White Construction Ltd v Commonwealth, unreported, Giles J (NSWSC,
23 April 1992), cited in Doyle, note 103, pages 23-24.
118 This author suggests that construction dispute resolution practitioners ought to look
beyond their own backyard. The reason is that construction dispute resolution is
becoming increasingly international. For example, the parties to a major international
project may select a dispute adjudication board or arbitral tribunal with members sourced
from all corners of the globe, each with differing approaches and influences based on
personal experience of approaches adopted in their home jurisdictions.
119 See note 8, City Inn Ltd v Shepherd Construction Ltd, [2008] BLR 269, page 271.
120 That is, of course, subject to any prohibitions in the contract conditions.
121 This must follow the occurrence of a ‘triggering event’ to an EOT under the contract.
122 Under JCT 80, note 19, he must act in a ‘fair and reasonable’ manner; other contracts
may impose other standards of fairness.
16
an approach to concurrent delay under English law. Notwithstanding this, the
preference under English law is to provide the contractor with a full EOT.
Indeed, the dismissal of apportionment by Mr Justice Akenhead J in Walter
Lilly123 is reminiscent of the early US cases, which applied the so-called ‘harsh
rule against apportionment’ notwithstanding persuasive arguments to the
contrary.
For this reason, the English courts would doubtless find a review into the
approaches of other jurisdictions to be a pointless exercise. This is because
the international arena will only offer the same solution as Scotland:
apportionment. However, this author would suggest that the potential exists
for an operational review: that is to say, an investigation into the practical
application of apportionment to cases of concurrent delay within a common
law legal system.
It is submitted that the USA would be the most appropriate arena for that
investigation. Firstly, English law shares the default position applied by the
US courts: ‘time but no money’. Secondly, the USA has proved an ability to
embrace apportionment as an alternative to ‘time but no money’ thereby
demonstrating that the so-called rival approaches (‘time but no money’ and
apportionment) can co-exist.124 Thirdly, there are no adequate alternatives.
The Australian courts have seemingly followed the lead of the English courts.
The Scottish approach has been rejected by the English courts but approved in
Hong Kong. In Canada, contributory negligence legislation has justified
apportionment in certain provinces but this author doubts similar potential
under English law.125 The principle that the court must ‘do the best it can’
must also be doubted.126 Also, the Canadian approach may unhelpfully
promote rough justice.127
The US courts have also shown that difficulties with apportionment may be
overcome in that they only allow apportionment where there is, in the proof, a
clear apportionment of the delay and the expense attributable to each party.
The claimant must be able to segregate its own liability events from those of
the delaying party. With this preliminary hurdle in place, the only argument
against apportionment could be the risk of offending the prevention principle.
This has been expressed by English commentators, Mr Justice Akenhead in
17
Walter Lilly and more forcefully expressed as a concern in Australia.128
However, the English courts have also indicated that concerns with the
prevention principle, in the context of concurrent delay, may be overcome.129
Until that day, this author recommends that the parties to construction
contracts help themselves. The appellate decision of the Inner House in City
Inn will remain for some time.131 Thus, an extreme measure may be for
English parties, who wish to apportion, to subject their contracts to Scots law.
However, the better approach, in this author’s submission, is a more thorough
use of the contract. The parties must, until this matter finally comes before the
higher courts, take the concurrency debate into their own hands and apply the
lessons of the Australian approach by using their contracts to effectively
address the dilemma in whatever way that they wish to deal with it on their
construction projects.
The views expressed by the author in this paper are his alone, and do not necessarily
represent the views of the Society of Construction Law or the editors. Neither the
author, the Society, nor the editors can accept any liability in respect of any use to
which this paper or any information or views expressed in it may be put, whether
arising through negligence or otherwise.
128 De Beers: note 36. See Tobin, note 100, page 156. See also Andrew Stephenson,
‘Concurrency, Causation, Commonsense and Compensation (Part 1)’ [2010] ICLR 166,
pages 194-195.
129 See notes 37-42 and linked main text and note 114.
130 City Inn had a fundamental psychological impact resulting in what Mr Justice Akenhead
in Walter Lilly, note 10, para [366], described as: ‘two schools of thought … which
currently might be described as the English and the Scottish schools’.
131 This means that parties under Scots law will reap the benefits of apportionment.
18
‘The object of the Society
is to promote the study and understanding of
construction law amongst all those involved
in the construction industry’
MEMBERSHIP/ADMINISTRATION ENQUIRIES
Jill Ward
The Cottage, Bullfurlong Lane
Burbage, Leics LE10 2HQ
tel: 07730 474074
e-mail: admin@scl.org.uk
website: www.scl.org.uk
19