Quality Control
Quality
Part of quality management
Degree to which a set of focused on fulfilling quality
inherent characteristics requirements [prevention of
fulfills requirements production of defectives
economically]
Quality Assurance
Systematic & planned activities focused
on providing confidence that quality
requirements will be fulfilled.
Part of QMS.
7 IGC Pr C TEST ASTM A262 as per Clause 8.6.1 of P.O 2 SAMPLES / LOT P W
8 IGC Pr A/ E TEST ASTM A262 as per Clause 8.6.2 of P.O 2 SAMPLES / LOT P W
450
400
350
300
250
200
150
100
AFTER IMPLEMENTING
50
UNIVERSAL CODES & STANDRDS
0
1880 1890 1900 1910 1920 1930 1940 1950 1960 1970 1980 1990 2000
SPECIFICATION
(Purchaser/
Manufacturer)
PROCEDURE
(Manufacturer)
2/27/2015 MVK COSS 2015
ASME - Boiler and Pressure Vessel Code
Cons:
High degree of cleanliness ( low tolerance to contamination)
Poor corrosion resistance under Chloride environment
Higher coefficient of Thermal expansion
Lower Thermal Conductivity
Forgings
Fittings
•Diagonal Plate & Sheet size Over Under Over Under Over Under Max. Max.
Cut & dent marks 10X 7000 15.9 0 11.1 0 0.75 0.25 23 3.18
treatment 12 X 4000 19.1 6.35 15.9 6.35 1.4 0.25 7.9 3.18
Yellowish acid stain 12 X 5000 31.8 6.35 15.9 6.35 1.4 0.25 7.9 3.18
Handling scratches 14 X 3000 19.1 6.35 15.9 6.35 1.4 0.25 7.9 3.18
Seam lines 14 X 4000 19.1 6.35 15.9 6.35 1.4 0.25 7.9 3.18
Hard scales 32 X 3000 19.1 6.35 15.9 6.35 1.78 0.25 6.4 3.18
• Hardness test
Tubular Product:
• Flattening test
• Flaring test Hydrostatic test
• Supplementary tests:
1. Impact testing
2. Ultrasonic testing Type
Number &
3. IGC test Location of
a) Pr E test specimens
are very
b) Pr C test
important
4. Crevice corrosion test
5. Pitting Corrosion test
6. Stress corrosion cracking test
2/27/2015 MVK COSS 2015
Nature of testing specimens
t
Weld 900 to
D direction of
H
applied
force
600
Specimen
Two Types
Exogenous Indigenous
- Derived from external causes - Inherent in molten metal
treatment
- Slag, entrapped mould material
and refractory - Sulphides, Nitrides, Oxides
(Al2O3, SiO2)
- Macroscopic
- Microscopic
- Non-uniform distribution
- Uniformly distribution
• Type A: Sulphide
• Type B: Alumina
• Type C: Silicate
A262 50% H2SO4 + 2.5% One 120 hour Weight loss per Chromium
Practice B Fe2(SO4)3 Boiling period unit area depleted area
(Streicher)
A262 65% HNO3 boiling Five 48 hour Avg. wt. loss per Chromium
Practice C periods unit area. Fresh depleted area, σ
(Huey) soln. each phase &
period carbides
Step
Dual
2/27/2015
Ditch
MVK COSS 2015
Practice E
• 15 hrs in Cu + Copper sulfate + Sulfuric Low carbon
SS shall be
acid. tested in
• Bend test @ 1T, 1800 Sensitized
condition
• No cracks on tension side.
( 675oC @ 1
hr)
Practice C
• Applicable for nitric acid service
• 48 hrs in 65 wt % Boiling Nitric Acid / 5 periods
• Corrosion rate based on Weight loss ( mpy)
• Acceptance criteria is based on client specifications
• Cannot be taken as base line data for design purpose
• Sample wt shall not cross 100 g
• Analytical reagent grads acid shall be used.
2/27/2015 MVK COSS 2015
Welding of Austenitic Stainless Steel
Carbide (Sensitization)
Ferrite (Micro fissuring & Embrittlement during service)
Sigma Phase (Embrittlement)
Distortion
Residual Stress (Stress Corrosion Cracking)
• Processing Control
Low Cold Work (LTS, Residual Stress)
Welding parameters: Low heat input & interpass temp., Stringer bead
Heat treatment: Removal of oil, grease
No grinding of pipe internal surface after welding
• Environmental Control
O2, pH, Chloride thermal insulation
2/27/2015
Surface contamination (Fe, C, MVK COSS 2015
Halides)
PWHT of Stainless Steel
• A PQR is a record of the welding data used to weld a test coupon and also
contains the test results of the tested specimens.
• Essential Variables
A change in a variable affects mechanical properties of weldments and calls for
requalification
Ex : P Number , Change in T, F Number, PWHT etc.,
Flat 1G PA
Horizontal 2G PC
Vertical Upwards
Progressio 3G PF
n
Vertical
Downward
s 3G PG
Progressio
n
Overhead 4G PE
Pipe Fixed
Horizontal 5G PF
Pipe Fixed @ 45
degrees 6G HL045
Upwards
Pipe Fixed @ 45
degrees
Downward 6G JL045
s
Horizontal 2F PB
Horizontal
2FR PB
Rotated
Vertical
Upwards 3F PF
Progression
Vertical
Downwards 3F PG
Progression
Overhead 4F PD
Pipe Fixed
5F PF
Horizontal
Material of construction
- to
2/27/2015 measure Geometric
MVKCharacters
COSS 2015
Typical NDT Test Set-up
Eddy Magnetic
Currents Flux
Sound
X-Rays Waves
Test Block
Output
INDICATION
Relevant
Acoustic
Visual Radiography
Emission
Ultrasonic
Liquid Penetrant Leak Test
Testing
Magnetic
Particle
Eddy Current
2/27/2015 MVK COSS 2015
NDT Methods for different Products
Product Surface Volumetric
Plates - UT
Tubes - ECT / UT
• Surface lighting
• Angle of inspection
• Visual Acuity
All shells & dished ends formed from plates & all tube & pipe bending
Rate of heating shall not exceed 220oC per hour per inch thickness
Points to ponder :
Visual Examination
Check for the assessment of chloride content on SS surface after
surface treatment. (Turbidity test)
Test for acid in wash after surface treatment (Methyl Orange
Indicator test)
Test for Iron contamination (Copper Sulfate test)
Immersion bath:
- Water or compatible solution.
- Compatible with temp. of test.
Evaluation:
- No continuous Bubble formation.
- No pressure drop
- Repair for leaks & retest.
Location :
- Remote locations – Readily visible to operator.