New Mexico Public Regulation Commission "ION COM
Santa Fe, NM $7501-2013,
Re: EI Paso Blectrie Company's NMPRC Rule 17.5.440 NMAC Notice of Filing
No. 70 Construction of the Talavera Distribution Substation and related
facilities.
Dear Ms. Sandeval:
Enclosed for filing please find an original and two copies of El Paso Electric Company's (*EPE’s")
Rule 440 Form 2, Notice of construction of a distribution substation and related facilities, EPE
submits the following information in support of Filing No, 70,
(CHARACTER OF UNDERTAKIN
‘The Talavera Distribution Substation project is located in Dofia Ana County east of the City of
Las Cruces in the Talavera area and east of EPE's existing 345KV and 115kV sransmission
corridor. It is located one mile south of Dripping Springs Road and west of Achenback Canyon
Road.
‘The project consists of EPE constructing the substation and 0.3 mile access road; creating al 1SkV
transmission in: in-and-out tap; upgrading 0.50 mile of an existing feeder; rebuilding 2.2 males
of an existing feeder to add a new feeder; and constructing two new feeders on a double cireuit
pole line, 2.8 miles in length. The substation facilities consist ofa six-position ring bus, two 50,
MVA-115 kV/24 kV distribution transformers (100 MV total), two sets of switchgear, and a 30,
MVAR capacitor bank,
BACKGROU
EPE’s Distribution Systems 2018-2027 Ten Year Expansion Plan identified the need for @ new
113KV/24KV substation to replace the smaller Talavera temporary substation which is currently in
use. The existing Amoyo and Salopek Substations that serve the area and associated 24KV feeders
are reaching their maximum capacity. A new substation is required to meet current electrical
demand, suppor: future growth and improve system reliability in the southeastern area of Dofia
‘Ana County and City of Las Craces. The new substation will back up these facilities and eliminatethe risk of overloading feeders and significantly reducing the risk of extended forced outages. The
roject is necessary to improve EPE’s ability to back-feed to the surrounding distribution system
in the event of an outage.
RENEFIT TO EPE'S CUSTOMERS, SYSTEM AND PURPOSE TO BE
ACCOMPLISHED:
‘The new permanent substation will offset large amounts of load from neighboring Salopek and
Arroyo feeders and will allow them to accommodate increasing loads inthe area, This will alow
EEPE to continue to reliably serve existing and future load requirements in Dofia Ana County and
the City of Las Cruces, New Mexico, The area near and around Centennial High School i in the
process of being developed creating an emerging load growth area,
MEANS BY WHICH PURPOSE IS TO BE REALIZED:
Approximately 0.10 mile of new transmission line will be constructed to connect the substation to
the existing Arroyo to Anthony 11SkV transmission line, forming the 115kV Arroyo to Talavera
and 115kV Talavera to Anthony transmission lines. Approximately 0.50 mile of an existing 24kV
tree phase single circuit distibution feeder will be rebuilt to replace the existing #2ACSR
conductor with 795AAC conductor with 336ACSR stati to inerease capacity. EPE will replace
the existing poles on that lin. The poles ofan existing 2.2 miles of 24KV feeder will be replaced
to allow the attachment of a new 24k - 795AAC feeder to increase capacity. ‘The conductor on
that existing feeder will remain the same, The 2.28 miles of now 24KV feeders will be constructed
a a three-phase double circuit line using a 795AAC conductor with 336ACSR static. The start
date is January 21, 2019,
RISK ASSOCIATED WITH NO ACTION:
‘The 24kV feeders and equipment at the Arroyo and Salopek Substations are reaching their
‘maximum capacity. The risk associated with no action, wll be inability, to serve new load growth
in these area and overloading ofthe existing distribution system, resulting in sustained outages for
majority of customers in these area and damage to electrical equipment.
ESTIMATED Costs:
‘The estimated cost of the projec is approximately $9,810,967.44,
CONCLUSION:
‘The project is required for EPE to continue reliability for existing and future customer load
requirements in the area and to improve EPE's contingency planning by providing back-feed to
the surrounding distribution system inthe event of an outage.Please date stamp and retum the two copies provided to EPE's messenger, Thank you for yout
aceite inthis matte.