OBRA: "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE SANEAMIENTO BASICO DE LABORPAMPA,

ITIJECANAN Y HUAMANVILCA, DISTRITO DE PARIAHUANCA, PROVINCIA DE CARHUAZ - ANCASH".

CURVA DE AVANCE DE OBRA "S" PROGRAMADO - EJECUTADO - NOVIEMBRE DE 2018

100.000% 100.000%

% DE AVANCE
94.995%
90.000%

80.000%
78.209%

70.000%
65.694%

60.000%

50.000% 49.879%

40.000%
37.096%
32.938%
30.000%

20.000%

10.000% 10.306%
5.862%

0.000% 0.000%
24-Aug-18 AGOSTO 2,018 SETIEMBRE 2,018 OCTUBRE 2,018 NOVIEMBRE 2,018 DICIEMBRE 2,018
TIEMPO (Meses) LEYENDA Programado Ejecutado

### AGOSTO 2,018 SETIEMBRE 2,018 OCTUBRE 2,018 NOVIEMBRE 2,018 DICIEMBRE 2,018

COSTO DIRECTO PROGRAMADO (CON I.G.V.) ### 29,540.02 136,453.14 85,379.82 142,771.35 109,819.04

COSTO DIRECTO PROGR. ACUMULADO (CON I.G.V.) 29,540.02 165,993.16 251,372.99 394,144.34 503,963.38

PORCENTAJE AVAN. PROGR. (CON I.G.V.) ### 5.86% 27.08% 16.94% 28.33% 21.79%

PORCENTAJE AVAN. ACUM. PROGR.(CON IGV) ### 5.86% 32.94% 49.88% 78.21% 100.00%

COSTO DIRECTO EJECUTADO (CON IGV) ### 51,938.81 135,012.27 144,123.86 147,664.84

COSTO DIRECTO EJECUTADO ACUMULADO (CON IGV) 51,938.81 186,951.08 331,074.94 478,739.78

PORCENTAJE AVANCE EJECUTADO (CON IGV) ### 10.31% 26.79% 28.60% 29.30%

PORCENTAJE AVANCE ACUM. EJECUTADO (CON IGV) ### 10.31% 37.10% 65.69% 94.99%

CONDICION EN EL MES (ADELANTADO +) (RETRAZADO -) 4.44% -0.29% 11.66% 0.97%


CONDICION EN EL MES ACUMULADO 4.44% 4.16% 15.82% 16.79%