MASONRY WORKS
1. CHB LAYING (productivity per day)
4" CHB 7 sq. m 1 Mason + 1 Labor
5"CHB 8-7.5 sq. m 1 Mason + 1 Labor
6"CHB 7 sq. m 1 Mason + 1 Labor
CARPENTRY WORKS/FORMWORKS
(productivity per day)
COLUMN 2 column 2 Carpenter + 1 Labor ***plus CONCRETE POURING
BEAM 12 m 1 Carpenter + 1 Labor
SLAB 3 span 2 Carpenter
STEELWORKS
(productivity per day)
RING FABRICATION 200-250 pcs 1 Steelman
INSTALLATION 2000-2500 Kgs 2 steelman + Labor
TILEWORKS
1. FLOORING (productivity per day)
60X60 10-12 sq. m 1 Tile Setler + Labor
40x40 10 sq. m 1 Tile Setler + Labor
30x30 6-8 sq. m 1 Tile Setler + Labor
CARPENTRY WORKS/FORMWORKS
(productivity per day)
COLUMN 2 column 2 Carpenter + 1 Labor ***plus CONCRETE POURING
BEAM 12 m 1 Carpenter + 1 Labor
SLAB 3 span 2 Carpenter
STEELWORKS
(productivity per day)
RING FABRICATION 200-250 pcs 1 Steelman
INSTALLATION 2000-2500 Kgs 2 steelman + Labor
SLAB REINFORCEMENT 33 sq. m 1 Steelman + 3 labor
TILEWORKS
1. FLOORING (productivity per day)
60X60 10-12 sq. m 1 Tile Setler + Labor
40x40 10 sq. m 1 Tile Setler + Labor
30x30 6-8 sq. m 1 Tile Setler + Labor