PRODUCTIVITY RATE

MASONRY WORKS
1. CHB LAYING (productivity per day)
4" CHB 7 sq. m 1 Mason + 1 Labor
5"CHB 8-7.5 sq. m 1 Mason + 1 Labor
6"CHB 7 sq. m 1 Mason + 1 Labor

2. PLASTERING (productivity per day)


WALL 7.8 sq. m 1 Mason + 1 Labor
COLUMN 1 Column 1 Mason + 1 Labor
BEAM 3.5 L.M 1 Mason + 1 Labor

CARPENTRY WORKS/FORMWORKS
(productivity per day)
COLUMN 2 column 2 Carpenter + 1 Labor ***plus CONCRETE POURING
BEAM 12 m 1 Carpenter + 1 Labor
SLAB 3 span 2 Carpenter

STEELWORKS
(productivity per day)
RING FABRICATION 200-250 pcs 1 Steelman
INSTALLATION 2000-2500 Kgs 2 steelman + Labor

TILEWORKS
1. FLOORING (productivity per day)
60X60 10-12 sq. m 1 Tile Setler + Labor
40x40 10 sq. m 1 Tile Setler + Labor
30x30 6-8 sq. m 1 Tile Setler + Labor

2. WALL(CR) (productivity per day)


20x60 4-5 sq. m 1 Tile Setler + Labor

EXCAVATOR (productivity per day)


1.5 cu.m 2 Labor ***depends on soil structure

DOOR INSTALLATION (productivity per day)


3-4 sets 1 carpenter + Helper

DOOR JAMB INSTALLATION (productivity per day)


3-4 sets 1 carpenter + Helper

CEILING WORKS (productivity per day)


1. METAL FURRING + 40 sq. m 2 finishing carpenter
ACCESSORIES
2. UPVC Panel 30 sq. m 2 finishing carpenter
PRODUCTIVITY RATE
MASONRY WORKS
1. CHB LAYING (productivity per day)
4" CHB 7 sq. m or 85 pcs 1 Mason + 1 Labor

CONCRETE POURING (productivity per day)


1. ROOF BEAM 2.5 cu.m manpower: 5
PRODUCTIVITY RATE
MASONRY WORKS
1. CHB LAYING (productivity per day)
4" CHB 7 sq. m 1 Mason + 1 Labor
5"CHB 8-7.5 sq. m 1 Mason + 1 Labor
6"CHB 7 sq. m 1 Mason + 1 Labor

2. PLASTERING (productivity per day)


WALL 12.66 sq. m 1 Mason + 1 Labor
WALL 7.21 sq. m 1 Mason + 1 Labor ***tiktik + layout + wall edge
COLUMN 1 Column 1 Mason + 1 Labor
BEAM 3.5 L.M 1 Mason + 1 Labor

CARPENTRY WORKS/FORMWORKS
(productivity per day)
COLUMN 2 column 2 Carpenter + 1 Labor ***plus CONCRETE POURING
BEAM 12 m 1 Carpenter + 1 Labor
SLAB 3 span 2 Carpenter

STEELWORKS
(productivity per day)
RING FABRICATION 200-250 pcs 1 Steelman
INSTALLATION 2000-2500 Kgs 2 steelman + Labor
SLAB REINFORCEMENT 33 sq. m 1 Steelman + 3 labor

CONCRETE POURING (productivity per day)


1. ROOF BEAM 2.5 cu.m manpower: 5

TILEWORKS
1. FLOORING (productivity per day)
60X60 10-12 sq. m 1 Tile Setler + Labor
40x40 10 sq. m 1 Tile Setler + Labor
30x30 6-8 sq. m 1 Tile Setler + Labor

2. WALL(CR) (productivity per day)


20x60 4-5 sq. m 1 Tile Setler + Labor

EXCAVATOR (productivity per day)


1.5 cu.m 2 Labor ***depends on soil structure

DOOR INSTALLATION (productivity per day)


3-4 sets 1 carpenter + Helper

DOOR JAMB INSTALLATION (productivity per day)


3-4 sets 1 carpenter + Helper
CEILING WORKS
1. METAL FURRING + (productivity per day)
ACCESSORIES 40 sq. m 2 finishing carpenter
2. UPVC Panel 30 sq. m 2 finishing carpenter