Professional Documents
Culture Documents
INTRODUCTION: Boiler Water Circulation Pump used in high capacity boiler (super critical or sub critical),
it assisted the circulation of water to overcome friction losses in pipe lines.
In this power plant unit is designed on the basis that the boiler can operate in the full load only by using two
of three pumps. In order of flexibly, three pumps can be operate at same time. If only one pump put into
service, boiler load must decrease to 60 % of MCR. If continuous operating load is 60 % MCR, it is allowed
one pump in service. During light up, it is suggested that at least two pumps should be in service.
RESPONSIBILITY: Unit Control Engineer, Field Engineer and Desk Engineer.
SAFETY PRECAUTIONS:
Ensure no permit to work is pending on this system.
Use proper PPE where necessary.
Ensure all Manual Call Points, Public Address System and Fire Alarms in working condition.
Ensure housekeeping and proper area lighting.
Ensure all electrical connections to be tight.
Proper tools to be used for field operation.
Leakages to be informed and barricading the same should be ensured.
Area should be clear of any material.
Ensure proper approach to instruments for maintenance.
Ensure all measuring instruments working properly.
OPERATING PROCEDURE –
RESPONSIBILITY
Sr. No. Description
UCE DE FE EE
PRE- START CHECKS:
1. All permits and cross permits have been returned. √ √ √
2. Area is clear of any other material. √
1|Page
NOTE
02 BCP are strictly prohibited to start at the same time
In case if BCP starts to fail in 5 sec, it should be stopped
immediately and start again after identifying the cause of failure
RESPONSIBILITY
Sr. No. Description
UCE DE FE EE
Cavity filling ,Flushing and Venting of BCP
1 Flush the heat barrier line and do the proper venting of the line. √
2 Flush the cavity filling line √
3 Cavity filling can be done from CEP OR BFP √
Drain valve of first strainer kept open to ensure purge cooler line √
4
and strainer get flushed
Than charge up to second strainer and open its drain and keep √
5
first strainer drain close
Flushed continued till water reaches following parameters:- √ √ √
PH › 6.5
6
Halogen (specially CI) ≤ 50 ppm
Solid content ≤ 5 PPM
2|Page
4|Page
Don’ts
Avoid operating BCP without getting required motor cavity cooling water parameters.
Avoid bypassing permissive/protection logics.
Permit unqualified personnel to operate the equipment.
REFERENCE DOCUMENTS:
Boiler Operation Manual
ABBREVIATIONS / NOTATIONS:-
o SOP: Standard Operating Procedure
o UCE: Unit Control Engineer
o DE: Desk Engineer
o FE: Field Engineer
o DCS: Distributed Control System
o EE: Electrical Shift Engineer
o MFT: Main Fuel Trip.
o RB : Run Back
5|Page