Professional Documents
Culture Documents
• List of identified and assessed risks, screened to ensure that only genuine risks remain, assessed for
probability and impacts, and categorised by source of risk and area affected. Where time for
response planning is limited, it will be helpful to prioritise the list of risks, so that available time can be
spent on the most significant risks first.
• List of potential responses (if previously identified during the risk identification stage), to be
reviewed and confirmed.
• Agreed risk threshold for the project, to define the “acceptable” level of risk as a target for risk
responses to meet.
If any of these prerequisites are missing, the effectiveness of response development is likely to be
compromised.
What Approach Will You Use?
➢ "How much time should be spent?
➢ Should this be done first with the other stakeholders and then with the risk team, as
was done in the Identify Risk! Process?
➢ There are an infinite number of options, but thinking about a particular project's
needs, the resources available, and the priority of the project to the company will
help you make the proper decisions.
Criteria for Effective Responses
Appropriate
– the correct level of response must be determined, based on the “size” of the risk.
Affordable
– the cost-effectiveness of responses must be determined.
Actionable
– an action window should be determined, defining the time within which responses need to be completed.
Achievable
– there is no point in describing responses which are not realistically achievable or feasible
Assessed
– all proposed responses must work!
Agreed
– the consensus and commitment of stakeholders should be obtained before agreeing responses.
Which risk response technique is being used in these situations? Match each technique to its
scenario.
➢ If the weather’s good, then there’s a chance you could see a meteor shower. If
the team gets a photo that wins the meteor photo contest, you can get extra
funding. You have your team stay up all night with their telescopes and cameras
ready.
➢ You hear that it’s going to rain for the first three days of your trip, so you bring
waterproof tents and indoor projects for the team to work on in the meantime
➢ You read that there’s a major bear problem in the spring on the cliff where you
are planning to work. You change your project start date to happen in the fall.
Mitigate , Avoid , Transfer , Share , Exploit , Enhance , Accept
➢ On your way up the cliff, you meet another team that is looking to survey the area.
You offer to do half of the surveying work while they do the other half and then
trade your findings with one another
➢ There’s always the chance that someone could make a mistake and fall off the
cliff. No matter how much you plan for the unexpected, sometimes mistakes
happen
➢ About 10 years ago a really rare bird, the black-throated blue warbler, was seen
on this cliff. If you could get a picture of it, it would be worth a lot of money. So,
you bring special seeds that you have read are really attractive to this bird, and
you set up lookout points around the cliff with cameras ready to get the shot
Response planning can even find more risks
Secondary risks
Secondary risks are risks that come from a response you have to another risk.
For Example: If you dig a trench to stop landslides from taking out your camp, it’s always
possible for someone to fall into the trench and get hurt.
The project team should determine whether the risk position after implementation of a
response is better or worse than it was beforehand.
For example, suppose that Response R is proposed in order to address a primary risk
(Risk A), with the result that the original Risk A is reduced to Risk a. However if Response
R introduces a new Secondary Risk S, the project team needs to test whether a+S<A.
Residual Risks
Residual risks are those that remain after your risk responses have been implemented.
For example: Even though you reinforce your tent stakes and get weatherproof gear,
there’s still a chance that winds could destroy your camp if they are strong enough
NOTE:
Suppose that your project is to design a new piece of equipment that will be used to test water
temperature and current flow in the ocean. The project requirements call for the equipment to be
tested prior to its delivery.
Sharks live in this part of the ocean and could attack the testers while they are testing the newly
designed equipment, which could cause injury to the testers, resulting in project delay and
increased costs.
How could we avoid this threat?
Eliminating the threat could involve removing the activity, resource, or other negative risk-
generating cause. Can you think of a way to eliminate the threat of a shark attack? One solution
would be to kill all the sharks. Or we could take a humane and environmentally friendly
approach. How about getting approval to change requirements by deleting the testing activity
from the project.
To accept this risk (as for many risks) is simply to say, "If it happens, it happens." This may be
chosen when there are no possible contingencies for a risk, the other options create too many
new risks (secondary risks), or the options are too costly or time consuming.
Suppose that your project is to design a new piece of equipment that will be used to test
water temperature and current flow in the ocean. The project requirements call for the
equipment to be tested prior to its delivery.
Sharks live in this part of the ocean and could attack the testers while they are testing the
newly designed equipment, which could cause injury to the testers, resulting in project delay
and increased costs.
Because there are so many sharks in the ocean and this equipment will need to be installed
and maintained by people when it is in the ocean, we could design it to also test for sharks in
the vicinity of the equipment and thus make the equipment more valuable to those who
purchase it.
How could we exploit this opportunity?
• Since we are designing the equipment from scratch, we could design the equipment to also test for
tsunamis and thus have a greater market for the equipment
• Research how far away from the equipment the sharks need to be to be detected.
• Determine what the equipment will do when a shark is detected.
• Ask the customer about other ways the equipment could be more valuable to them.
• Allocate ownership of the opportunity to a third party that is best able to achieve the opportunity.
• Outsource the design of the shark detecting feature to a more experienced company familiar with
and experienced working with sharks.
• If people want to buy the equipment, we might add the shark-testing capability later.
• If we add the capability and the customer finds it more valuable, then they'll find it more valuable
Contingency Planning !!!!
Planned action to be taken if threat or opportunity occurs.
You should be aware of two common obstacles as you begin your contingency planning process:
People are often poorly motivated to develop a strong ‘Plan B’, because they have so much of an
emotional investment in the ‘Plan A’ that they want to deliver. Stress that Plan B needs to be
properly thought-through.
There’s often a low probability of a crisis occurring, so people often don’t see contingency
planning as an urgent activity. Unfortunately, this can mean that it gets stuck at the bottom of their
To Do Lists as a task that never gets done.
Here are some key steps in the contingency plan maintenance process:
Risk management involves creating plans in case the contingency plans fail. These are called fall
back plans,
Document Risk Responses in the Risk Register
By the time the Plan Risk Responses process begins, the risk register includes the following information:
• Description of risks
• The activities they relate to
• Potential risk owners, risk responses, and triggers
• The final probability and impact rating of each risk
• The risk's ranking among the remaining risks on the project
The Plan Risk Responses process uses that information collected throughout the project and adds the
following information to the risk register:
Check with management and the other project stakeholders to make sure the risk response
plans are viable and to make another go/no-go decision on the project cancelling a
project makes sense if the risk is too high or the cost too great. The concept of cancelling a
project based on its level of risk has not yet filtered into common project management
practice.