You are on page 1of 3

2018 December 6 TT2018-1335

Attachment 2
Green Line LRT Stage 1 Inflight Work Summary

Enabling Works
Project Title Description Status Construction Progress
Highfield Landfill Removal of waste from landfill Ongoing, construction to be 95% complete
Remediation location complete Q4 2018. Minor
clean-up planned for 2019
(including landscaping).
Highfield Blvd Removal of waste from under Ongoing, construction to be Waste Removal 100%
Waste Removal Highfield Blvd (adjacent to complete Q4 2018. complete. Overall project
landfill) 85% complete
CN Reconfiguration Relocation of CN tracks and Construction start Q4 2018. 5% complete
at Highfield utilities Completion planned for Q4
2019. CN are causing delays
Inglewood/Ramsay Relocation of numerous utilities Construction start Q2 2019. 5% complete (material
Utility Relocations Completion planned for Q4 has been ordered).
at Jefferies Park 2019.
Bonnybrook WWTP Relocation of numerous utilities Ongoing, construction to be 60% complete.
Relocation of complete Q2 2019
Utilities
42 Avenue SE Water main upgrade to facilitate Complete 100% complete.
Waterline other water main shut-downs
required for Green Line
Utilities Hydrovac program in Centre City Ongoing, investigation 75% complete.
Investigation to identify utility conflicts complete Q4 2018
Pop Davies Area Regrading of Millican Rd for Park A review of the project -
and Ride facility. Construction recommended that the best
of parking lot at South to value for enabling Green
replace parking along Ogden Rd Line was to complete the
engineering to address
design and stakeholder
issues but that construction
value was best obtained by
planning construction in the
main GL contract.
Douglas Glen Construction of a new transit Construction complete 100% complete
Transit only road to facilitate station
Improvements construction during main
contract without transit
disruption
78th Ave SE Tunnel Construction of CP underpass Construction start Q1 2019 -
and Road Works and associated road
infrastructure to enable closure
of 69 Ave SE
Shepard Sludge Removal of conflicts from GL Construction complete 100% complete
Line Relocation alignment

TT2018- Attachment Page 1 of 3


ISC: Unrestricted
2018 December 6 TT2018-1335
Attachment 2
Green Line LRT Stage 1 Inflight Work Summary
Ogden Landfill Removal of waste from landfill Ongoing, construction to be 90% complete
location complete Q4 2018

Building Conflicts Acquisition and demolition of Ongoing 10 Demolished


properties 26 Scheduled for
demolition
Shallow Utilities Resolution of shallow utility Ongoing 30% complete
conflicts

Elbow to Shepard Resolution of deep utility Ongoing 48% complete


Deep Utilities conflicts
Conflicts
Resolution
Centre City Deep Resolution of deep utility Utility reocation design 90%
Utilities – 10 conflicts complete. Tender targeted
Avenue Portal Area for Q1 2019.
Centre City Shallow Resolution of shallow utility Atco gase reloction 5% complete
Utilities – 10 conflicts. complete. Enmax relocation
Avenue Portal Area scheduled to proceed in Q2
2019.
City Shaping
Milestones Community Support Initiative Project Input Community
Enhancement Projects
Q1 2018 - Data gathering placemaking - Provide input into the Area - Coordinate with
tool developed Redevelopment Plans/Area stakeholders from
- Baseline data gathered at Structure Plans Community Services to
Westbrook and Sunalta stations develop a toolkit
Q2 2018 Three (3) pilot placemaking City Shaping included in the City Shaping toolkit
events held at Westbrook and Green Line Technical Project developed.
Sunalta Stations Requirements document.
Q3 2018 - Feasibility Analysis for the
GL Railway Garden Initiative
- Pilot GBA+ tool as part of
the stations design

Transit Oriented Development (TOD)


Milestones Description Status Progress
Q1 2018 -Established population targets Ongoing Monitoring progress
within 400m and 1000m of GL through annual census
to base Key Performance data
Indicators for Provincial and
Federal Funding Partners

TT2018- Attachment Page 2 of 3


ISC: Unrestricted
2018 December 6 TT2018-1335
Attachment 2
Green Line LRT Stage 1 Inflight Work Summary
Q2 2018 -Drafted an Updated TOD Policy Ongoing -Second draft to be
Guidelines Document to replace circulated internally –
2005 version Ongoing Mid October
-Created a specific CPAG Team -Fully functioning team
for Stage 1 Applications along reviewing the
the Green Line Development Liaison
Application for Stage 1
Q3 2018 -Finished the development of Complete Implementing
Project Charter for TOD Strategy
– Approved by TOD Working
Group and Steering Committee

TT2018- Attachment Page 3 of 3


ISC: Unrestricted

You might also like