Green Line LRT Stage 1 Inflight Work Summary
Enabling Works
Project Title Description Status Construction Progress
Highfield Landfill Removal of waste from landfill Ongoing, construction to be 95% complete
Remediation location complete Q4 2018. Minor
clean-up planned for 2019
(including landscaping).
Highfield Blvd Removal of waste from under Ongoing, construction to be Waste Removal 100%
Waste Removal Highfield Blvd (adjacent to complete Q4 2018. complete. Overall project
landfill) 85% complete
CN Reconfiguration Relocation of CN tracks and Construction start Q4 2018. 5% complete
at Highfield utilities Completion planned for Q4
2019. CN are causing delays
Inglewood/Ramsay Relocation of numerous utilities Construction start Q2 2019. 5% complete (material
Utility Relocations Completion planned for Q4 has been ordered).
at Jefferies Park 2019.
Bonnybrook WWTP Relocation of numerous utilities Ongoing, construction to be 60% complete.
Relocation of complete Q2 2019
Utilities
42 Avenue SE Water main upgrade to facilitate Complete 100% complete.
Waterline other water main shut-downs
required for Green Line
Utilities Hydrovac program in Centre City Ongoing, investigation 75% complete.
Investigation to identify utility conflicts complete Q4 2018
Pop Davies Area Regrading of Millican Rd for Park A review of the project -
and Ride facility. Construction recommended that the best
of parking lot at South to value for enabling Green
replace parking along Ogden Rd Line was to complete the
engineering to address
design and stakeholder
issues but that construction
value was best obtained by
planning construction in the
main GL contract.
Douglas Glen Construction of a new transit Construction complete 100% complete
Transit only road to facilitate station
Improvements construction during main
contract without transit
disruption
78th Ave SE Tunnel Construction of CP underpass Construction start Q1 2019 -
and Road Works and associated road
infrastructure to enable closure
of 69 Ave SE
Shepard Sludge Removal of conflicts from GL Construction complete 100% complete
Line Relocation alignment