Job shop
production
Product variety
Tc = To + Th + Tth -------------------1
where
Tc = cycle time, min/pc
To = processing time for the operation, min/pc
Th = handling time (e.g., loading and unloading
the production machine), min/pc and
Tth = tool handling time (e.g., time to change
tools), min/pc
4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 27
Tool handling time
• Time spent changing tools when worn out
• Time required for changing one tool to the
next.
• Tool indexing time for indexable inserts or for
tools on a turret lathe
• Tool positioning for next pass etc..
– These activities do not occur every cycle
– They must be spread over the number of parts
MTBF MTTR
Availability: A = -----------10
MTBF
MTBF MTTR
Availability: A =
MTBF
3) One million units of a certain product are to be manufactured annually on
dedicated production machines that run 24 hours per day. 5 days per week, 50
weeks per year, (a) If the cycle time of a machine to produce one part is 1.0
minute, how many of the dedicated machines will be required to keep up with
demand? Assume that availability, utilization, and worker efficiency = 100%, and
that no setup time will be lost, (b) Solve part (a) except that availability = 0.90.
Solution: Tc= 1 min
Tb = Tsu+QTc = 0+QTc
Tp= Tb/Q = Tc
Rp=60/Tp = 60 Parts/Hr
n= PC/SHRp
= 1000000/(50x5x24x60)
= 2.77 = 3 machines Hareesha N G, Dept of Aero Engg, DSCE, Blore
Manufacturing Lead Time
Manufacturing lead time (MLT) is the total time required
to process a given part or product through the plant,
including any lost time due to delays, time spent in
storage, reliability problems, and so on.
Production consists of a sequence of individual processing and
assembly operations. Between the operations are material
handling, storage, inspections, and other non productive activities.
MLTj = (T
i 1
suji Q jTcji Tnoji ) -----------11
where
MLTj = manufacturing lead time for part or product j (min).
Tsuji = setup time for operation i (min) for the product j,
Q j = quantity of part or product in the batch (pc),
Tcji = operation cycle time for operation i (min/pc),
Tnoji = nonoperation time associated with operation i (min), and
i indicates
4/3/2014 the operation sequence inof the
Hareesha N G, Dept processing;
Aero Engg, DSCE, Blore i = I, 2,... noj 47
To simplify and generalize the model,
let us assume that all setup times, operation cycle times, and non
operation times are equal for the noj machines.
Further, let us suppose that the batch quantities of all parts or
products processed through the plant are equal and that they are
all processed through the same number of machines, so that noj =
no , With these simplifications, Eq. becomes:
MLT = no (Tsu + QTc + Tno) -----------12
where
MLT = manufacturing lead time,
no = number of operations,
Tsu = setup time,
Q = batch quantity,
Tc = cycle time per part, and
Tno4/3/2014
= non-operation timeHareesha N G, Dept of Aero Engg, DSCE, Blore 48
• For a job shop in which the batch size is one (Q = 1), Eq.
(1.12) becomes
MLT=no(Tsu+TC+Tno)------------ (1.13)
Solution:
Given: The manufacturing lead time is computed from Fq
Q = 100 units noj
no = 5 MLT = (T
i 1
suji Q jTcji Tnoji )
Tsu = 3hr/operation
Tno = 12hr/machine
Solution:
a) MLT = no(Tr+MaxTo)
Given:
b) Rp3 = 60/Tp ; But Tp = Tc = To
c) Rp = 60/Tp; But Tp = Tc ; But Tc = Tr+Max To
4/3/2014 Hareesha N G, Dept of Aero Engg, DSCE, Blore 53
Work-In-Process
Work-in-process (WIP) is the quantity of parts or
products currently located in the factory that
either are being processed or are between
processing operations.
WIP is inventory that is in the state of being
transformed from raw material to finished
product.