MANPOWER REQUIREMENT:
1 – Project Engineer
1 – Service Engineer
1 – Boring Machine/crane operator
1- Bored piling foreman
1- Service crane operator
1- Backhoe operator
1- Bentonite plant operator
1- Pump operator
1- Varisco pump/desanding machine operator
2- Welders
1- Air compressor operator
4- Riggers
1- mechanic/serviceman
1- Dump truck driver
======
18 - Total
1.0 Mechanical Drilling Machine (RM–21) or equivalent with 18-30 tons torque
capacity
2.0 Service Crane-crawler type, 45-60 tons capacity
3.0 Vibro Hammer, with Power Pack and Power Supply,
( Double Clamp )
4.0 Crawler Backhoe and Dumptruck for Dispossal of Excavated Materials
5.0 Bentonite Mixer
6.0 Bentonite Rotovator
7.0 Set of Bentonite Pipe/ supply hose – 100 meters L
8.0 Generator Set with Panel Board
9.0 Varisco Pump
10.0 Welding Machine
11.0 Desanding Machine with Desanding Pipe and other Accessories (return hose – 100
meters L)
12.0 Air Compressor 200 – 250 cfm and with 60 meter hose
13.0 Set of Tremie Pipe and Platform
14.0 Drilling Bucket
14.1 1000mm ø
14.2 1200mm ø
14.3 15000mm ø
15.0 Auger
16.0 Bento/mud Tester
17.0 Bentosand mud (available at Butuan Project)
July 16, 2006 (sun) - Departure of Barge nene from PASAR to MAC builders, Albuera, Ormoc
( with 80ton crane, casagrande, other accessories)
July 17, 2006 (mon) – Loading of Aggregates for Butuan project
July 20, 2006 (thurs) – Arrival at Butuan Project, Unloading of equipment and matls for 2
days.
July 22,2006 (sat) – departure to Cebu to load T Beams and Tie Beams for PASAR Project