CONSTRUCTION SCHEDULE AND REQUIREMENTS FOR BORED PILING

WORKS OF PIER 1 TO 5 OF MAGSAYSAY VIADUCT PROJECT

MANPOWER REQUIREMENT:
1 – Project Engineer
1 – Service Engineer
1 – Boring Machine/crane operator
1- Bored piling foreman
1- Service crane operator
1- Backhoe operator
1- Bentonite plant operator
1- Pump operator
1- Varisco pump/desanding machine operator
2- Welders
1- Air compressor operator
4- Riggers
1- mechanic/serviceman
1- Dump truck driver
======
18 - Total

EQUIPMENT AND TOOLS REQUIREMENT:

1.0 Mechanical Drilling Machine (RM–21) or equivalent with 18-30 tons torque
capacity
2.0 Service Crane-crawler type, 45-60 tons capacity
3.0 Vibro Hammer, with Power Pack and Power Supply,
( Double Clamp )
4.0 Crawler Backhoe and Dumptruck for Dispossal of Excavated Materials
5.0 Bentonite Mixer
6.0 Bentonite Rotovator
7.0 Set of Bentonite Pipe/ supply hose – 100 meters L
8.0 Generator Set with Panel Board
9.0 Varisco Pump
10.0 Welding Machine
11.0 Desanding Machine with Desanding Pipe and other Accessories (return hose – 100
meters L)
12.0 Air Compressor 200 – 250 cfm and with 60 meter hose
13.0 Set of Tremie Pipe and Platform
14.0 Drilling Bucket
14.1 1000mm ø
14.2 1200mm ø
14.3 15000mm ø
15.0 Auger
16.0 Bento/mud Tester
17.0 Bentosand mud (available at Butuan Project)

SCHEDULE OF BARGE NENE AND MOBILIZATION FOR BOREDPILING WORKS

July 16, 2006 (sun) - Departure of Barge nene from PASAR to MAC builders, Albuera, Ormoc
( with 80ton crane, casagrande, other accessories)
July 17, 2006 (mon) – Loading of Aggregates for Butuan project

July 18, 2006 (tues) – Departure to Butuan Project

July 20, 2006 (thurs) – Arrival at Butuan Project, Unloading of equipment and matls for 2
days.

July 22,2006 (sat) – departure to Cebu to load T Beams and Tie Beams for PASAR Project

July 25, 2006 (tues) - Arrival of Barge Nene at PASAR Project.

CONSTRUCTION SCHEDULE (BOREDPILING WORKS PIER 1 TO PIER 5 )

July 24 to Aug 06, 2006


-Preparation and Set up of equipments and bentonite plant
-Construction of mud pool (tent or tarpauline method)
-Set up of Temporary Casing requirement and pipe linings to site
-MIXING OF BENTOSAND MUD FOR 2-3 DAYS
-Batching plant preparation (supply of Cement, Aggregates and
Sand)
-Preparation of flat form for drilling pad

NOTE: MOBILIZATION OF BENTONITE PLANT IS VERY URGENT


TO THE SCHEDULE OF BOREDPILING WORKS TO MEET THE NOVEMBER
09, 2006 COMPLETION DATE OF THE PROJECT.

Aug 07 to Sept 04, 2006


-START OF BOREDPILING WORKS (28 DAYS ONLY)
-30 SETS – 24Mtr to 34 Mtr DEPTH
- 1 set BP / day rate = 30 DAYS
- 5 EXTRA DAYS INCLUDED will be for the demolition of the
existing Approach of Magsaysay Bridge

Sept 05 to Nov 09,2006


-66 DAYS FOR THE REMAINING WORKS
-CONSTRUCTION OF PILECAP, COLUMN, COPING
BEAM AND ERECTION OF GIRDER, SLAB.

NOTE: Completion of Girder Fabrication for P1 to P5 sched on 1st week


August, 2006.