Professional Documents
Culture Documents
IS228500-EP-RP-002
21 September 2018
Environmental Risk Assessment
© Copyright 2017 Jacobs Australia Pty Limited. The concepts and information contained in this document are the property of Jacobs. Use or
copying of this document in whole or in part without the written permission of Jacobs constitutes an infringement of copyright.
Limitation: This document has been prepared on behalf of, and for the exclusive use of Jacobs’ client, and is subject to, and issued in accordance with, the
provisions of the contract between Jacobs and the client. Jacobs accepts no liability or responsibility whatsoever for, or in respect of, any use of, or reliance
upon, this document by any third party.
Jacobs Authorisation
IS228500-EP-RP-002 i
Environmental Risk Assessment
Contents
1. Introduction ....................................................................................................................................... 1
1.1 Project Overview ................................................................................................................................ 1
1.2 Purpose of this Report ........................................................................................................................ 1
2. Context .............................................................................................................................................. 2
2.1 Project Description ............................................................................................................................. 2
2.2 Regional Setting ................................................................................................................................. 2
2.3 Environmental Setting......................................................................................................................... 0
2.4 Scope of Works .................................................................................................................................. 3
2.5 Construction Methodology .................................................................................................................. 4
2.5.1 Berth 2 Infrastructure .......................................................................................................................... 4
2.5.2 Jetty Head ........................................................................................................................................... 4
2.5.3 Fenders .............................................................................................................................................. 5
3. Risk Assessment Framework ......................................................................................................... 6
3.1 Risk Criteria ........................................................................................................................................ 6
3.2 Risk Assessment Scope ..................................................................................................................... 7
4. Environmental Risk Assessment.................................................................................................... 8
IS228500-EP-RP-002 ii
Environmental Risk Assessment
1. Introduction
1.1 Project Overview
The Port of Hasting Development Authority (PoHDA) is proposing to undertake upgrade works to the Crib Point
Jetty located within Western Port and on the adjacent land owned by PoHDA on Victoria’s Mornington
Peninsula (Figure 2.1). The jetty is controlled and managed by PoHDA.
PoHDA has engaged Jacobs Group (Australia) Pty Ltd (Jacobs) to undertake an environmental risk
assessment of the Jetty Upgrade to understand environmental risks and protection measures required for
input to an Environmental Management Plan. This Environmental Risk Assessment has been updated
following the receipt of the below approvals in readiness for the commencement of works associated with the
project.
PoHDA have engaged an Owner’s Engineer team to design and manage PoHDA’s berth upgrade works
(Owners Team). The Owners team will utilise a number of third-party providers as required to carry out the
works.
A risk assessment approach has been used to identify and communicate the potential environmental risks and
impacts associated with the Jetty Upgrade. The outcome of the risk assessment is to reduce the risks to the
environment through the deployment of management and mitigation measures to be implemented in the
construction of the Jetty Upgrade.
This report details the risk assessment methodology and outcomes of the environmental risk assessment,
including proposed management and mitigation measures to reduce environmental risk of the Jetty Upgrade to
acceptable levels.
IS228500-EP-RP-002 1
Environmental Risk Assessment
2. Context
This section describes the context for the environmental risk assessment undertaken to inform the proposed
Jetty Upgrade. The context is the setting within which the project is being developed and the risks have been
evaluated. To determine the relevant context for the risk assessment an overview of the key design and
construction assumptions is provided.
PoHDA is proposing to undertake upgrade works to the Crib Point Jetty located within Western Port and on
the adjacent land managed by PoHDA on Victoria’s Mornington Peninsula. The jetty is controlled and
managed by PoHDA and accordingly, the works to the jetty will be managed by PoHDA and undertaken
under the Coastal Management Act approval dates.
The works associated with the Jetty Upgrade project (the subject of this EMP) will consist of:
Strengthening / modifications to the existing berthing and mooring dolphins
Strengthening / modifications to the existing pipe neck structure
Strengthening / modifications to the existing pier head
Installation of four mooring dolphins
Installation of two berthing dolphins
Construction of new service platform
Possible replacement of an existing berthing dolphin
New dolphin access catwalks
New Navigational Aid / Security Pile markers.
Geotechnical investigations including borehole samples and any other required investigation works.
The Project design is subject to change whilst detailed design is being undertaken.
The Crib Point Jetty is located in Western Port, 65km south-east of Melbourne (Victoria) on the Mornington
Peninsula (Figure 2-1). The jetty is situated on the Western Port coastline within the Shire of Mornington
Peninsula. PoHDA, as Port Operator, is responsible for managing the operations of the Crib Point Jetty,
including maintaining the associated port infrastructure. The jetty itself and the adjoining landside site is located
within the Port Zone. The Project Site and an extensive area to the north, west and south is within the Bushfire
Management Overlay in the Mornington Peninsula Planning Scheme. The Project Site and surrounding area,
including key features is provided in Figure 2-1 and Figure 2-2.
The Crib Point Jetty is located within Western Port bay, a large tidal bay opening into the Bass Strait which
incorporates around 260 kilometres of coastline. The bay features two large islands; French Island,
predominantly agricultural, and Phillip Island, known for its tourism industry. Hastings and Crib Point are key
urban centres on the coastline of Western Port bay and for more than 50 years have hosted a number of
industrial sites, including petroleum refining and storage as well as gas and steel processing facilities.
Hastings also features the main boat landing point in the bay. A submarine, HMAS Otama, is moored near
Crib Point and further south is HMAS Cerberus, a naval base.
Western Port bay is also used for recreational activities such as fishing and boating. It has been listed as an
international Ramsar site since 1982 with international significance for migratory birds1. The high environmental,
social and economic worth of Western Port bay is recognised further through the declaration of Western Port
bay as an UNESCO Biosphere reserve and the presence of several Marine National Parks within the Ramsar
site (Churchill Island, French Island and Yaringa).
There are a small number of community facilities and services, and places of special interest near the jetty.
IS228500-EP-RP-002 2
Environmental Risk Assessment
They include parks and reserves, which provide recreational opportunities for local communities and visitors
and contribute to environmental and amenity values. Woolleys Beach Reserve 2 is located immediately south of
the jetty and extending to Stony Point (Figure 2.2). It features dense bushland supporting a variety of
indigenous flora and fauna, BBQ, picnic facilities, and a boardwalk.
1
http://www.environment.gov.au/cgi-bin/wetlands/ramsardetails.pl?refcode=19.
2
http://cribpointstonypointforeshore.com.au/foreshore-reserve
IS228500-EP-RP-002 3
Environmental Risk Assessment
Figure 2:0: Western Port Ramsar Site (Western Port Ramsar Site Strategic Management Plan, Department of Sustainability and
Environment, East Melbourne, Victoria, Department of Sustainability and Environment, 2003
IS228500-EP-RP-002 4
Environmental Risk Assessment
IS228500-EP-RP-002 1
Environmental Risk Assessment
Adjacent
Land site
IS228500-EP-RP-002 2
Environmental Risk Assessment
Figure 2.3 : Jetty Upgrade Works (works are located within the ‘new lease boundary’)
IS228500-EP-RP-002 3
Environmental Risk Assessment – Crib Point Jetty
Upgrade
Figure 2.4 : View of Crib Point Jetty from the west Figure 2.5 : View of Crib Point jetty from the south-east and
land where the shore flange will be located.
The jetty largely falls within the defined boundary of the Western Port Ramsar Wetland site, which is
designated as a wetland of international significance as shown in Figure 2.0. The Ramsar site covers 59,950
hectares of Western Port including Crib Point. Western Port is one of eleven Ramsar sites in Victoria and is the
third most important area for wading birds in Victoria. All Ramsar sites are Matters of National Environmental
Significance under the Commonwealth Environment Protection and Biodiversity Conservation Act 1999 (EPBC
Act).
Western Port is an unusually diverse but compact marine environment. It comprises vast intertidal mudflats with
saltmarsh, seagrass and mangrove habitats as well as steep subtidal sloping banks with seagrass and deep
channels that connect the north of the bay with the oceanic waters of Bass Strait in the south.
The ecosystem components associated with the habitats are closely connected by their relatively close spatial
proximity and the strong tidal currents that transport water back and forth through the channels and over and off
the intertidal flats.
These characteristics contribute to the listing of a large part of Western Port as a Ramsar wetland of
international significance and the allocation of distinct areas as National Parks. Many of the animal and plant
species are not specifically protected or listed for conservation value, but the combination mangroves and
seagrasses, saltmarsh, fish, birds, crustaceans, worms and other strange invertebrates all form the Western
Port marine ecosystem that is highly valued by the public.
Marine Ecology
A marine ecosystem review has been undertaken by CEE3 and the findings are relevant within the context of
the Jetty Upgrade. The review covers relevant Commonwealth and Victorian legislation for marine protected
areas, protected marine species (flora and fauna, excluding birds and
3 CEE (2017), AGL Gas Import Jetty Project, Marine Ecosystem Regulatory Review. AGL Energy Limited. Working Draft A, 7 November 2017
IS228500-EP-RP-002 0
Environmental Risk Assessment – Crib Point Jetty
Upgrade
terrestrial fauna) and listed processes that may be relevant to the project. Various marine species, habitats and
ecological communities are protected by the EPBC Act and the Victorian Flora and Fauna Guarantee Act 1988
(FFG Act). In some cases, species or places are listed on both the EPBC and FFG Acts.
Through an assessment of marine EPBC Act matters of national environmental significance and FFG Act listed
species, it was identified that 33 threatened marine species (excluding birds) and one marine community that
the Acts list may occur in Western Port.
The review found that many of the marine species in the State and Commonwealth Acts were relatively widely
distributed, that Western Port represented a small component of their range and that Western Port was not
recognised as a significant aggregation, breeding or feeding location or migratory path for most EPBC identified
species and many FFG listed species (excluding water birds).
Of the 33 threatened marine species identified as potentially occurring in Western Port, the EPBC listed species
include four endangered species and four vulnerable species:
Endangered marine species: Blue Whales, Southern Right Whales, Leatherback Turtles and Loggerhead
Turtles. Assessment against the EPBC Act Policy Statement 1.1 - Significant Impact Guidelines,
determined that the Project is not expected to impact on these endangered species as there are no
apparent direct or indirect pathways that are likely to affect population size; area of occupancy; population
continuity; critical habitat, breeding cycle; or species recovery.
Vulnerable marine species: Humpback Whales; Great White Shark, Australian Grayling and Green
Turtle. Further assessment of these species is currently in process and the findings will allow assessment
against the EPBC Act Policy Statement 1.1 - Significant Impact Guidelines.
The marine habitat near the mooring and berthing dolphins comprises mixed soft sediments that are likely to
range from fine sand and silt to medium mobile sands. Water depth is greater than 12 m, which is greater than
the maximum depth range of 7 m depth for seagrasses in Western Port. Other than at the footprint of the
piles/dolphins, the works do not involve removal of habitat within the Western Port Ramsar boundary.
In relation to a proposal by Victorian Regional Channels Authority (VRCA) to flatten the area of seabed in the
vicinity of Berth 2 of Crib Point Jetty, CEE was engaged by VRCA to investigate the presence of threatened
ghost shrimps in this vicinity1. The investigation was designed by experienced marine biologists from CEE in
consultation with Dr J Watson (Marine Science and Ecology) and Dr G Poore from the Museums of Victoria.
The surveying was conducted on 13 July 2018. No threatened species of ghost shrimp were found during the
survey.
Aboriginal heritage
The Port Land adjacent to the jetty has previously been subject to a detailed inspection, including survey and
auger testing4 . This inspection determined that the “area has undergone significant ground disturbance as
defined by the Aboriginal Heritage Regulations 2007”. It was also reported that no surface evidence of
1 CEE (2018) Threatened ghost shrimp survey Berth 2 Crib Point Jetty Risk from bed levelling of isolated high points. Report to VRCA, August 2018.
IS228500-EP-RP-002 1
Environmental Risk Assessment – Crib Point Jetty
Upgrade
Aboriginal cultural remains was observed, and therefore it is unlikely that Aboriginal cultural material exists on
the site as surface indicators were not present.
4
Jones, Z. (2015). Allotment 2040, The Esplanade, Crib Point: Cultural Heritage Assessment and Implications for Development. Fitzroy, Port of
Hastings Development Authority.
IS228500-EP-RP-002 2
Environmental Risk Assessment – Crib Point Jetty
Upgrade
A due diligence assessment by Jacobs5 reported that there are no recorded Aboriginal Places located within
Port Land. This follows a search of the Victorian Aboriginal Heritage Register, which included a radial search of
3km. With this area a single Aboriginal Place is located approximately 650 m north west of the jetty (Jacks
Beach; VAHR 7921-0369), which includes shell midden and surface scatter components.
Historical heritage
A recent study by Jacobs6 , determined there to be one historical heritage place located in the vicinity of the jetty,
which is listed on the Victorian Heritage Register (VHR), the Mornington Peninsula Planning Scheme Heritage
Overlay (HO), and the Register of the National Estate (RNE): Former BP Refinery Administration Building (VHR
H1016/HO240/RNE 103692). There are three historical heritage sites within proximity to (within 1 km of) the
jetty, which comprise one item listed on the HO – Woolley’s Cool Room (HO322); one on the Victorian Heritage
Inventory (VHI) – William (Bill) Woolley’s Homestead (H7921-0112); and one on the National Trust (NT) register
– HMAS Otama (B6683). There are no places within or in proximity to the jetty on the Commonwealth Heritage
List (CHL), the National Heritage List (NHL), or the World Heritage List (WHL).
The Former BP Refinery Administration Building is located on the Esplanade, to the west of the Port Land and
approximately 400 metres from the head of the Crib Point Jetty. No Jetty Upgrade works including laydown
areas are proposed within the site of or within at least 100 metres of this building.
Western Port is an unusually diverse but compact marine environment. It comprises vast intertidal mudflats with
saltmarsh, seagrass and mangrove habitats as well as steep subtidal sloping banks with seagrass and deep
channels that connect the north of the bay with the oceanic waters of Bass Strait in the south.
A flora and fauna assessment including field survey of the Port Land (adjacent to the jetty), was conducted by
PKA in 20157. The study reported that “the vegetation and habitat quality of the study area is relatively low as a
consequence of prior site management. It is dominated by a range of native and exotic vegetation established
as part of site rehabilitation and natural regeneration. In its current state the biodiversity values of the site do not
make a significant contribution to the sustainable conservation of biodiversity in the vicinity.”
A desktop terrestrial flora and fauna assessment by Jacobs8 determined the study area appears to support areas
of native vegetation (approximately 2 ha of Heathy Dry Woodland and scattered native trees) and an area
cleared of native vegetation (approximately 1 ha).
The assessment also included review of threatened fauna within and in proximity to the study area. A search of
the Victorian Biodiversity Atlas and the EPBC protected matters was conducted to determine which species
have recorded observations within the search area (site plus 5 km buffer). Due to the diversity of habitat types
and the presence of a Ramsar-listed wetland within the 5 km search area, there are a large number of records
returned by the EPBC and VBA database search tools. These records were individually assessed to determine
the likelihood of the species being present on the works site, and/or being affected by the site works. The
Jacobs assessment concluded that the project is not expected to impact on migratory birds due to the lack of
suitable habitat within the study area. Further, the Southern Brown Bandicoot (Isoodon obesulus obesulus) has
suitable habitat present within and around the study area, however, a previous targeted survey9 (PKA, 2016)
failed to reveal the species at the time of survey within suitable habitat at the site.
5
Jacobs (2017), AGL Gas Import Jetty Project, Aboriginal Heritage Due Diligence Assessment. Report for AGL Energy Limited. Draft, 7 December
2017.
6
Jacobs (2017), AGL Gas Import Jetty Project, Historic Heritage Assessment. Report for AGL Energy Limited. Draft, 7 December 2017
7
PKA, 2015, Ecological (Flora & Fauna) Assessment Crib Point Jetty, Port of Hastings. Report for Port of Hastings. 23 December 2015.
8 Jacobs (2017), AGL Gas Import Jetty Project, Desktop Flora and Fauna Assessment. Report for AGL Energy Limited. Draft, 23 November 2017.
9
PKA, (2016) Southern Brown Bandicoot (Isoodon obesulus obesulus) survey at Crib Point Jetty, Port of Hastings. Report for Port of Hastings.
IS228500-EP-RP-002 3
Environmental Risk Assessment – Crib Point Jetty
Upgrade
Contaminated Land
Previous investigations of the Port Land adjacent to the jetty10 11 have identified contamination of soil, sediment
and groundwater beneath the Project Site. This is predominantly related to metals, with some hydrocarbons and
perfluoralkyl substances (in the presence of perfluoroctanesulfonic acid) identified in isolated areas. Fill soil is
present across the site up to depths of approximately 1 metre, with soil contamination predominantly identified
within this unit. Groundwater is present at depths around 6.8 to 7.5 metres and is unlikely to be encountered as
part of the proposed Project.
10
Jacobs, 2017, Baseline Environmental Contamination Investigation, Factual Report, prepared for Port of Hastings Development Authority, 1 June
2017
11
PPK, 1998. Statements of Environmental Audit, Port of Hastings Sites (No. 78J155A-pr29999d M7314). PPK Environment & Infrastructure Pty Ltd,
South Melbourne.
IS228500-EP-RP-002 4
Environmental Risk Assessment – Crib Point Jetty
Upgrade
The following construction activities are outlined as per the information provided as part of the project’s
preliminary design. These activities are subject to change upon completion of detailed design.
Berth 2 Infrastructure
One of the main existing infrastructure elements which limits the capability of Berth 2 is the Pier Head
itself. It is heavily dilapidated and requires a great amount of remediation works; likely total
replacement of Pier Head 2. All other concrete elements will undergo in-situ concrete repair
remediation, as outlined below:
Installation of a supporting manifold:
- To allow the installation of the new loading arms, a new manifold will be installed around the
middle of the pier head.
Replacement of old quick release hooks:
- Quick-release hooks will be installed at various locations to replace the existing
decommissioned units.
Installation of berthing and mooring dolphins:
- 4 x mooring dolphins and 2x berthing dolphins and a possible replacement of an existing
berthing dolphin will be made from either pre-fabricated structural steel or reinforced
concrete components and installed atop tubular steel piles which would be driven into the
seabed. Engagement depth and pile sizes are yet to be determined. Each dolphin will be
contained with hand railing, rope railing, lighting, power supply, access ladder and life
jackets. If constructed from reinforced concrete, additional concrete may be placed using
concrete pump and trucks, while structural steel components would be grouted to the piles.
- Each dolphin will require foundations to be piled into the seabed. The preferred method of
piling is driven steel piles, whereby each tubular steel pile is driven in to the ground using a
drop hammer. The piles will be handled, pitched and secured on to the seabed by a crane/rig
mounted either on a jack-up barge or floating barge restrained by mooring lines. Initially the
piles will be vibrated until refusal or until the pile reaches a certain depth above the final
embedment depth. The piling will then be completed by driving the piles with a drop hammer.
- Geotechnical conditions may require further action for installing the piles. This may require
the piling contractor to drill, chisel or bore into the seabed to achieve the required
embedment. It is also possible that if adequate embedment cannot be achieved, then some
of the piles may need to be anchored to the bedrock. Following the completion of the piling
works and trimming of piles to their approximate level, a temporary works platform will be
installed by clamping it to the piles. The platform will allow workers to install bracing to the
pile group to then allow the precast berthing and mooring dolphin units to be installed.
Jetty Head
Complete Replacement with Steel Deck with pre-cast concrete panels on top of deck
The first stage for complete jetty head replacement will be to remove the existing jetty head. The
contracting company will need to install a capture device underneath the jetty head to ensure
appropriate management of falling material.
The process for removing the existing jetty head would be to divide the jetty head into sections. Each
reinforced concrete section would be cut away from the remaining structure, one section at a time,
including 1-2m off the top of the foundation piles that lie within a section. A mechanical cut would be
suitable for separation of the foundation pile and the reinforced concrete sections. When completely
separated, each section will be lifted and removed by a crane mounted barge. The foundation piles
would next be prepared for installation of the deck structure.
The new steel deck can be prefabricated in smaller sections, brought to site via dumb barge, lifted by
IS228500-EP-RP-002 5
Environmental Risk Assessment – Crib Point Jetty
Upgrade
crane mounted barge one at a time onto the existing and new foundation piles and welded together on
site. If feasible, the entire steel deck can be prefabricated in one section offsite and lifted into place in
a single lift.
Fenders
New fenders for the berthing dolphins will be prefabricated off site and brought by dumb barge to site.
These will then be installed via crane mounted barge to the face of the berthing dolphins once fully
constructed. Any fixings required to be cast into the berthing dolphin to allow the fenders to be
mounted will be installed during the pre-casting works offsite.
IS228500-EP-RP-002 6
Environmental Risk Assessment – Crib Point Jetty
Upgrade
The likelihood and consequence criteria and risk assessment matrix are defined in the following section.
To assess the level of likelihood, qualitative measures were defined as shown in Table 3.1.
Rare The event is very unlikely to occur but may occur in exceptional circumstances.
Unlikely The event may occur under unusual circumstances but is not expected.
Possible The event might occur at some time under normal circumstances.
To assess consequence, the qualitative descriptions were separated into biophysical / environmental
consequences and socio-economic consequences, as shown in Table 3.2.
Negligible No detectable change in a local environmental setting. No detectable impact on economic, cultural,
recreational, aesthetic or social values.
Minor Short term, reversible changes, within natural Short term, localised impact on economic, cultural,
variability range, in a local environmental setting. recreational, aesthetic or social values.
Moderate Long term but limited changes to local environmental Significant and/or long term change in quality of
setting that are able to be managed. economic, cultural, recreational, aesthetic or social
values in local setting. Limited impacts at regional
level.
Major Long term, significant changes resulting in risks to Significant, long term change in quality of economic,
human health and/or the environment beyond the local cultural, recreational, aesthetic or social values at
environmental setting. Eventual recovery of ecological local, regional and State levels. Limited impacts at
systems possible but not necessarily to the same pre- national level.
incident conditions.
Severe Irreversible, significant changes resulting in Significant, permanent impact on regional economy
widespread risks to human health and/or the and/or irreversible changes to cultural, recreational,
environment at a regional scale or broader. Loss of aesthetic or social values at regional, State and
biodiversity on a regional scale. Loss of ecological national levels.
functioning with little prospect of recovery to pre-
incident conditions.
IS228500-EP-RP-002 7
Environmental Risk Assessment – Crib Point Jetty
Upgrade
The degree of risk was established by considering the components of likelihood and consequence in the matrix
shown in Table 3.3.
Consequence Rating
Development of management and mitigation measures has focussed on risks categorised as medium or higher.
For very low and low risks, no management measures have been proposed and the residual risk is therefore the
same as the initial risk.
The scope of the risk assessment includes the construction phase of the project, but excludes the operation of
ships utilising the jetty. The Project Site is shown in Figure 2.2. This excludes the proposed mooring of the
FSRU and operation of the cargo ships.
IS228500-EP-RP-002 8
Environmental Risk Assessment – Crib Point Jetty
Upgrade
A draft environmental risk assessment and accompanying report was disseminated prior to the workshop. The
workshop provided a forum to relay the project description and context, confirm risk assessment methodology
and discuss each risk and reach consensus on risk ratings, mitigation measures and residual risks.
IS228500-EP-RP-002 9
Environmental Risk Assessment
Consequence
Consequence
Management / mitigation
Risk rating
Risk rating
Likelihood
Likelihood
Aspect Identified risk Impacts
measures
Negligible
Negligible
Possible
Possible
presence of any additional
Low
Low
vessels/barges; new jetty
infrastructure and runoff from
the landside area.
2. Coastal management Local and regional coastal Stability issues on the coast.
Negligible
Negligible
Possible
Possible
hydrodynamics effects of Increase in sediment transport.
Low
Low
additional jetty infrastructure.
3. Flora and fauna values Construction of offshore Adverse impact to seabed Work methods developed to
components (piles, biota. Temporary loss of minimise potential impacts.
foundations) results in marine habitat. Minimise construction
Negligible
Negligible
Very Low
Very Low
Unlikely
Unlikely
disturbance to seabed biota impacts through appropriate
within the construction management plan and
footprint. optimising seabed footprint.
Avoiding any unnecessary
disturbance of seabed.
4. Flora and fauna values Localised, temporary Adverse impact to marine Work methods developed to
increases in turbidity from jetty species, including cetaceans minimise potential impacts.
works (pile driving). (dolphins and whales) and Minimise construction
Unlikely
Unlikely
Minor
Minor
seabed biota. Temporary loss impacts through appropriate
Low
Low
of marine habitat. management plan and
optimising seabed footprint.
Avoiding any unnecessary
disturbance of seabed.
IS228500-EP-RP-002 9
Environmental Risk Assessment
Risk
Initial rating Residual rating
No.
Consequence
Consequence
Management / mitigation
Risk rating
Risk rating
Likelihood
Likelihood
Aspect Identified risk Impacts
measures
5. Flora and fauna values Underwater noise from pile Adverse impact to marine Work methods developed to
driving and other construction species, including cetaceans minimise potential impacts.
Medium
Unlikely
equipment used. (dolphins and whales) and Minimise construction
Likely
Minor
Minor
Low
seabed biota. impacts through appropriate
management plan.
Appropriate noise
monitoring.
6. Flora and fauna values Airborne noise from Adverse impact to migratory Work methods developed to
generators, pile drivers and birds in the local area. minimise potential impacts.
other construction equipment Minimise construction
Possible
Possible
Minor
Minor
used. impacts through appropriate
Low
Low
management plan.
Appropriate noise
monitoring. Use appropriate
construction methodology.
7. Flora and fauna values Introduction of marine pests / Modification to natural marine Normal controls on visiting
introduced species to the local ecosystem composition. vessels in accordance with
environment via vessels used the following:
for the construction activities. Port Phillip certification
requirements, and
“Australian Ballast Water
Moderate
Possible
Medium
Unlikely
Management
Minor
Low
Requirements”, Department
of Agriculture and
Water Resources
(Commonwealth).
IS228500-EP-RP-002 10
Environmental Risk Assessment
Risk
Initial rating Residual rating
No.
Consequence
Consequence
Management / mitigation
Risk rating
Risk rating
Likelihood
Likelihood
Aspect Identified risk Impacts
measures
8. Flora and fauna values Construction activities cause Adverse impact to flora and Work methods developed to
Unlikely
Unlikely
Minor
Minor
adverse effect to the native fauna values and habitat. minimise potential impacts
Low
Low
vegetation within the landside to native vegetation.
area.
9. Water quality, Flora and fauna Accidental spills and Adverse impact to water Management procedures
Moderate
Possible
Medium
Unlikely
discharges of concrete slurry, quality. Adverse impact on (including containment of
Minor
Low
paint or other liquids during water quality and marine biota. concrete slurry), spill
construction. Loss of marine habitat. response procedures.
Reputational damage. Containment facilities.
10 Water quality, Flora and fauna Accidental oil/fuel spills from Adverse impact to water Management procedures,
Possible
Possible
generators and cranes over quality. Adverse impact on spill response procedures.
Minor
Minor
Low
Low
the water, maintenance and water quality and marine biota. Containment facilities.
chemical stores. Loss of marine habitat.
Reputational damage.
11 Water quality, Flora and fauna Hydro-demolition works have Adverse impact to water Work methods developed to
the potential to cause water quality. Adverse impact on minimise potential impacts.
Possible
Possible
quality effects (turbidity, etc.). water quality and marine biota. Including use of containment
Minor
Minor
Low
Low
Loss of marine habitat. measures and capture
device underneath the jetty
and monitoring as per Work
Method Statement.
12 Aboriginal heritage values Offshore works have the Impact to Aboriginal heritage.
Moderate
Moderate
potential to disturb unrecorded Reputational damage.
Rare
Rare
Low
Low
submerged sites.
IS228500-EP-RP-002 11
Environmental Risk Assessment
Risk
Initial rating Residual rating
No.
Consequence
Consequence
Management / mitigation
Risk rating
Risk rating
Likelihood
Likelihood
Aspect Identified risk Impacts
measures
13 Aboriginal heritage values Any disturbance of the soil Impact to Aboriginal heritage.
within the landside area has Reputational damage.
the potential to disturb
unrecorded Aboriginal
sites/artefacts. (Disturbance of
Moderate
Moderate
the soil is unlikely given that
Rare
Rare
Low
Low
the proposed use of the
landside area is only for
temporary construction
laydown and staff amenities.
No excavations would be
anticipated. Site has also
been previously disturbed.)
14 Soil contamination Excavation of the soil within Exposure to contaminated soils
the landside area has the (metals, with some
potential to disturb hydrocarbons and perfluoralkyl
contaminated soil. substances). Potential human
(Disturbance of the soil is health effects.
Very Low
Very Low
unlikely given that the
Minor
Minor
Rare
Rare
proposed use of the landside
area is only for temporary
construction laydown and staff
amenities. No excavations
would be anticipated.
Disturbance of contaminated
material is not expected).
15 Historical heritage values Earthworks, pile driving (etc.) Impact to historical heritage -
Very Low
Very Low
associated with the Jetty BP Refinery Administration
Minor
Minor
Rare
Rare
Upgrade have the potential to Building. Reputational damage.
disturb potential post-
European sites.
IS228500-EP-RP-002 12
Environmental Risk Assessment
Risk
Initial rating Residual rating
No.
Consequence
Consequence
Management / mitigation
Risk rating
Risk rating
Likelihood
Likelihood
Aspect Identified risk Impacts
measures
16 Public amenity Construction works (dust, Local community impacted. Minimise construction
noise, spills, construction Reputational damage. impacts through appropriate
Medium
Unlikely
vehicle traffic) may impact management plan. Follow
Likely
Minor
Minor
Low
local amenity. EPA Publication 1254:
Noise Control Guidelines.
Work according to specified
construction working hours.
17 Public safety Recreational craft risk or Accident with recreational Normal security controls not
any commercial craft risk craft/commercial craft near permitting recreational
Medium
Medium
jetty upgrade operations, vessels within 100m of the
Rare
Severe
Severe
potential human jetty will remain and VRCA
Rare
injury/death and impacts to harbor control measures.
environment from spill.
18 Solid waste management Impact to the marine Adverse impact to water Work methods developed to
environment if solid wastes fall quality. Loss of marine habitat. minimise potential impacts.
Possible
Possible
into the water through Including use of containment
Minor
Minor
Low
Low
demolition works and other measures and capture
remediation activities. device underneath the jetty
and monitoring as per Work
Method Statement.
19 United fuel pipeline operation Accidental impact (e.g. Potential human health Strict controls working in
collision, impact from impacts. Adverse impact to vicinity of fuel pipeline, in
Medium
Medium
Unlikely
Unlikely
vibration, other) to the existing water quality and marine flora accordance with necessary
Major
Major
United fuel pipeline (will and fauna. Loss of marine approvals and work method
remain operational throughout habitat. Impacts to United statement.
construction). operations. Reputational
damage.
20 Bushfire Construction activities cause Adverse impacts to natural Bushfire management plan.
Medium
Medium
Major
Major
increased risk of bushfire. environment, homes and Rare
Rare
Bushfire Management Overlay human health as a result of
applies to jetty area. bushfire.
21 Flora and fauna values, Water Construction activities cause Potential impact to values of Combination of mitigation
Negligible
Very Low
Unlikely
Unlikely
quality adverse effect on Western Western Port Ramsar Wetland. measures will address any
Minor
Low
IS228500-EP-RP-002 13