BUILDING MANAGEMENT GRAHA IRAMA 2018

NO DATE PHOTO JOB DESCRIPTION REMARK

1 4/6/18 AHU routine maintenance, Done


PM Ground Floor tower A&B.

2 4/6/18 Installing Smoke detector in Done


Transformer Low-Zone Room
(B.2) by engineering team.
M&E audit finding by JLL.

3 5/6/28 Installing grounding system on Done


diesel pump fuel tank for safety
reason.

Base on M&E audit finding by JLL

4 5/6/18 Pump Panel routine


PM maintenance in Basement 3 by
engineering team.

5. 5/6/18 AHU routine maintenance,


PM Mezzanine Floor tower A&B.

WEEKLY REPORT PERIODE : 04/06/2018 – 10/06/2018


BUILDING MANAGEMENT GRAHA IRAMA 2018

6. 6/6/18 Checking and cleaning of Done


strainer PDAM by PT. Palyja.

7. 6/6/18 Gate valve did not close Done


completely in pump room. Gate
valve repair by engineering
team. Now the condition is well-
maintained.

8. 6/6/18 AHU routine maintenance, 2nd Done


PM Floor tower A&B.

9. 7/6/18 Contactor and thermal overload Done


relay replacement by
engineering team. New unit
brand : Fuji

10 7/6/18 AHU routine maintenance, 2rd Done


PM Floor tower A&B.

WEEKLY REPORT PERIODE : 04/06/2018 – 10/06/2018


BUILDING MANAGEMENT GRAHA IRAMA 2018

11 7/6/18 Repairing AC in Indosat control Done


room in Basement 3 by Indosat
vendor. There is trouble on AC
Indosat Control Room so it
should be repair recently.

12 8/6/18 Routine Generator Test Running, Done


PM including synchronization test
for Genset/Generator 1,2&3

13 10/6/18 Leveling marking for elevator In


wire rope by OTIS team. progress

M&E audit finding by JLL