Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
Replace Power Supply to Abu Ali Plants 303 34.63% 30/Apr/14 25/Feb/17 30/Apr/14 A 21/Mar/17
A1000 Contract Signed by Contractor - Start of Work 0 100% 30/Apr/14 30/Apr/14 30/Apr/14 A 30/Apr/14 A 30/Apr/14 A
A1010 Preparation & Holding Kick of Meeting 0 100% 01/May/14 04/May/14 01/May/14 A 05/May/14 A 05/May/14 A
A1030 Complete Design Office Contract 0 100% 06/May/14 28/May/14 06/May/14 A 29/May/14 A 29/May/14 A
Milestone Events 287 0% 10/Jun/14 25/Feb/17 10/Jun/14 A 21/Mar/17
Design & Procurement 0 0% 10/Jun/14 25/Apr/16 10/Jun/14 A 07/Apr/16
MS1000 Complete Design Office Mobilization 0 100% 10/Jun/14 10/Jun/14 A Complete Design Office Mobilization
MS1030 Issued of 50% Design Package 0 100% 27/Aug/14 27/Aug/14 A Issued of 50% Design Package
MS1010 Issue Work Detailed Schedule 0 100% 13/Dec/14 13/Dec/14 A Issue Work Detailed Schedule
MS1040 Complete 50% Design Review Meeting 0 100% 15/Dec/14 15/Dec/14 A Complete 50% Design Review Meeting
MS1060 ISSUE 90% DESIGN PACKAGE 0 100% 11/Jan/15 11/Jan/15 A ISSUE 90% DESIGN PACKAGE
MS1050 Issue Early IFC for Temporary Camp Facility 0 100% 29/Jan/15 30/Jan/15 A Issue Early IFC for Temporary Camp Facility
MS1070 Complete 90% Design Review Meeting 0 100% 15/Jun/15 15/Jun/15 A Complete 90% Design Review Meeting
MS1020 Award all Equipment & Bulk Materials Purchase Orders 0 100% 27/Jun/15 27/Jun/15 A Award all Equipment & Bulk Materials Purchase Orders
MS1080 Issue all IFC Drawings & Documents 0 0% 25/Apr/16 07/Apr/16 Issue all IFC Drawings & Documents
Construction 208 0% 16/Feb/16 25/Feb/17 07/Jan/16 A 21/Mar/17
MS1090 Site Mobilization Complete, including all Temporary 0 100% 16/Feb/16 07/Jan/16 A Site Mobilization Complete, including all Temp
MS1100 Partial MCC, 230kV GIS Substation Building S/S#4 0 0% 11/Aug/16 05/Sep/16 Partial MCC, 230kV GIS
MS1120 Provide Project Record Books and other Required Documents per SAEP-122 0 0% 14/Aug/16 19/Sep/16 Provide Project Record
MS1110 Partial MCC, 13.8kV Substation Building S/S#5 0 0% 17/Aug/16 22/Sep/16 Partial MCC, 13.8kV Su
MS1130 Final Testing & Mechanical Completion 0 0% 07/Feb/17 04/Mar/17 Final Test
MS1140 Contractor Demobilization 0 0% 25/Feb/17 21/Mar/17 Contrac
Contract Interface Milestones
Mile ( Tentative, Non-contractual ) 96 0% 05/May/16 09/Aug/16 30/May/16 03/Sep/16
Milestones by TITC ( LSTKII ) 96 0% 05/May/16 09/Aug/16 30/May/16 03/Sep/16
MS1102 Assigned Area of Cables Crossing for Wasit HV Cable Lines & FO Cables Clear & Accessi 0 0% 05/May/16 30/May/16 Assigned Area of Cables Crossin
MS1104 S/S #4 - 230KV Building - Cable Vault Floor Painted, Finished & Accessible 0 0% 05/May/16 30/May/16 S/S #4 - 230KV Building - Cable V
MS1106 S/S #4 - Communication Room Ready for Installation 0 0% 05/May/16 30/May/16 S/S #4 - Communication Room R
MS1103 GIS Cable Head Ready & Accessible to Start HV Cables Termination 0 0% 26/May/16 19/Jun/16 GIS Cable Head Ready & Acce
MS1108 S/S #4 - Cable Trays Installation Completed @ Communication Room 0 0% 29/May/16 22/Jun/16 S/S #4 - Cable Trays Installatio
MS1112 S/S #4 - Cable Tray Rout to LP Panels Completed 0 0% 02/Jun/16 27/Jun/16 S/S #4 - Cable Tray Rout to LP
MS1114 S/S #4 - LP Panels Installed & Accessible @ Protection Room 0 0% 22/Jun/16 23/Jul/16 S/S #4 - LP Panels Installed
MS1116 Wasit Lines Relays Final Setting Submittal & Approved 0 0% 31/Jul/16 24/Aug/16 Wasit Lines Relays Final
MS1118 Loading Lines Final Relay Settings @ S/S # 4 0 0% 09/Aug/16 03/Sep/16 Loading Lines Final Rela
MS1122 TITC Ready for End to End Testing @ S/S #4 0 0% 09/Aug/16 03/Sep/16 TITC Ready for End to E
Milestones by Others 24 0% 18/Jul/16 09/Aug/16 11/Aug/16 03/Sep/16
MS1124 Wasit HV Cable Lines Termination to GIS Completed @ S/S #4 & Giving Access Back to TIT 0 0% 18/Jul/16 11/Aug/16 Wasit HV Cable Lines Term
MS1126 Actual Measured & Approved Line Parameters 0 0% 18/Jul/16 11/Aug/16 Actual Measured & Approv
MS1134 FOC Wasit to S/S #4 Terminated & Tested both Sides 0 0% 18/Jul/16 11/Aug/16 FOC Wasit to S/S #4 Term
MS1128 Loading Lines Final Relay Settings @ Wasit 0 0% 09/Aug/16 03/Sep/16 Loading Lines Final Rela
MS1132 LSTK-I Ready for End to End Testing @ Wasit 0 0% 09/Aug/16 03/Sep/16 LSTK-I Ready for End to
Engineering 16 99.9% 31/May/14 25/Apr/16 31/May/14 A 07/Apr/16
Procurement 94 85.7% 16/Jul/14 28/May/16 16/Jul/14 A 16/Jun/16
Mobilization of TITC & Preconstruction
P Activities 0 100% 30/Oct/14 07/Jan/16 30/Oct/14 A 07/Jan/16 A
Construction / Installation
Installatio 364 30.46% 12/Mar/15 07/Feb/17 12/Mar/15 A 04/Mar/17
230KV Substation #4-Abu
#4-A Ali Plant 175 31.97% 12/Mar/15 10/Aug/16 12/Mar/15 A 05/Sep/16
SS #4 Civil Construction
Construc (Sub-contracted) 78 74.57% 12/Mar/15 08/May/16 12/Mar/15 A 01/Jun/16
SS #4 Cast-In-Situ RC
R Works 47 99.29% 12/Mar/15 09/Apr/16 12/Mar/15 A 03/May/16
SS #4 Foundation & Cable Vault 0 100% 12/Mar/15 15/Dec/15 12/Mar/15 A 15/Dec/15 A
CON1192 Excavation 0 100% 12/Mar/15 14/Apr/15 12/Mar/15 A 15/Apr/15 A 12/Mar/15 A 15/Apr/15 A
CON1194 Work Cavity Dewatering ( If Required ) 0 100% 12/Mar/15 14/Apr/15 12/Mar/15 A 15/Apr/15 A 12/Mar/15 A 15/Apr/15 A

Page 1 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON1196 Cavity Side Courtains & supports ( If Required ) 0 100% 12/Mar/15 14/Apr/15 12/Mar/15 A 15/Apr/15 A 12/Mar/15 A 15/Apr/15 A
CON1198 Backfilling , Compaction and Leveling 0 100% 07/Apr/15 20/Apr/15 07/Apr/15 A 21/Apr/15 A 07/Apr/15 A 21/Apr/15 A
CON1220 Lean Concrete 0 100% 23/Apr/15 23/Apr/15 23/Apr/15 A 23/Apr/15 A 23/Apr/15 A 23/Apr/15 A
CON62920 Foundation Formwork 0 100% 29/Apr/15 19/May/15 29/Apr/15 A 20/May/15 A 29/Apr/15 A 20/May/15 A
CON62910 REBARS of Building Foundation 0 100% 30/Apr/15 19/May/15 30/Apr/15 A 20/May/15 A 30/Apr/15 A 20/May/15 A
CON62970 REBARS of Cable Vault Columns Neck & Columns & Grade Beams up to elev. +3.6 0 100% 14/May/15 09/Aug/15 14/May/15 A 10/Aug/15 A 14/May/15 A 10/Aug/15 A
CON62930 Check Before Casting 0 100% 30/May/15 30/May/15 29/May/15 A 30/May/15 A 29/May/15 A 30/May/15 A
CON62940 Casting of Foundation 0 100% 30/May/15 30/May/15 29/May/15 A 30/May/15 A 29/May/15 A 30/May/15 A
CON62950 Curing of Building Foundation 0 100% 30/May/15 02/Jun/15 30/May/15 A 02/Jun/15 A 30/May/15 A 02/Jun/15 A
CON62960 Building Foundation Removal of Formwork 0 100% 04/Jun/15 07/Jun/15 04/Jun/15 A 07/Jun/15 A 04/Jun/15 A 07/Jun/15 A
CON62980 Cable Vault Columns Neck & Columns & Grade Beams Formwork up to elev. +3.6 0 100% 07/Jun/15 09/Aug/15 07/Jun/15 A 10/Aug/15 A 07/Jun/15 A 10/Aug/15 A
CON62990 Check Before Casting 0 100% 05/Jul/15 09/Aug/15 05/Jul/15 A 10/Aug/15 A 05/Jul/15 A 10/Aug/15 A
CON63000 Casting of Cable Vault Columns Neck & Columns & Grade Beams 0 100% 05/Jul/15 09/Aug/15 05/Jul/15 A 10/Aug/15 A 05/Jul/15 A 10/Aug/15 A
CON63010 Curing of Columns Neck & Columns & Grade Beams 0 100% 05/Jul/15 12/Aug/15 05/Jul/15 A 13/Aug/15 A 05/Jul/15 A 13/Aug/15 A
CON63020 Removal of Formwork of Columns Neck & Columns & Grade Beams up to elev. +3.6 0 100% 08/Jul/15 13/Aug/15 08/Jul/15 A 14/Aug/15 A 08/Jul/15 A 14/Aug/15 A
CON63030 Scaffolding of GIS Floor Slab & Beams 0 100% 11/Aug/15 22/Sep/15 11/Aug/15 A 27/Sep/15 A 11/Aug/15 A 27/Sep/15 A
CON63040 GIS Floor Slab & Beams Formwork 0 100% 27/Aug/15 29/Sep/15 27/Aug/15 A 30/Sep/15 A 27/Aug/15 A 30/Sep/15 A
CON63090 REBARS of GIS Floor Slab & Beams 0 100% 27/Aug/15 29/Sep/15 27/Aug/15 A 30/Sep/15 A 27/Aug/15 A 30/Sep/15 A
CON63050 Check Before Casting GIS Floor Slab & Beams 0 100% 01/Oct/15 01/Oct/15 01/Oct/15 A 01/Oct/15 A 01/Oct/15 A 01/Oct/15 A
CON63060 Casting of GIS Floor Slab & Beams 0 100% 03/Oct/15 03/Oct/15 02/Oct/15 A 03/Oct/15 A 02/Oct/15 A 03/Oct/15 A
CON63070 Curing of GIS Floor Slab & Beams 0 100% 03/Oct/15 07/Oct/15 02/Oct/15 A 07/Oct/15 A 02/Oct/15 A 07/Oct/15 A
CON63080 Removal of Scaffolding & Form Work 0 100% 12/Oct/15 25/Nov/15 12/Oct/15 A 26/Nov/15 A 12/Oct/15 A 26/Nov/15 A
CON1223 Water Proofing Works Backfilling & Compacting 0 100% 26/Nov/15 15/Dec/15 26/Nov/15 A 15/Dec/15 A 26/Nov/15 A 15/Dec/15 A
SS #4 Building Roo
Rooms 47 97.72% 20/Apr/15 09/Apr/16 20/Apr/15 A 03/May/16
CON1319 Battery & Communication Rooms Lean Concrete 0 100% 20/Apr/15 22/Apr/15 20/Apr/15 A 23/Apr/15 A 20/Apr/15 A 23/Apr/15 A
CON1334 Mechanical Room Lean Concrete 0 100% 20/Apr/15 22/Apr/15 20/Apr/15 A 23/Apr/15 A 20/Apr/15 A 23/Apr/15 A
CON1322 Grade Beam of Battery & Communication Rooms RCC 0 100% 04/Jun/15 05/Jul/15 04/Jun/15 A 05/Jul/15 A 04/Jun/15 A 05/Jul/15 A
CON1337 Grade Beam of Mechanical Room Rcc 0 100% 06/Jun/15 05/Jul/15 06/Jun/15 A 05/Jul/15 A 06/Jun/15 A 05/Jul/15 A
CON63130 Rooms Columns REBARS & Form Work 0 100% 09/Jul/15 28/Jul/15 09/Jul/15 A 28/Jul/15 A 09/Jul/15 A 28/Jul/15 A
CON63180 Rooms Columns Casting & Curing & Removal of Formwork (1st Level) 0 100% 29/Jul/15 29/Jul/15 29/Jul/15 A 30/Jul/15 A 29/Jul/15 A 30/Jul/15 A
CON63140 Scaffolding, Formwork & REBARS of Protection & Equipment Rooms Floor Slab 0 100% 11/Aug/15 29/Sep/15 11/Aug/15 A 29/Sep/15 A 11/Aug/15 A 29/Sep/15 A
CON63150 Casting & Curing of Protection & Equipment Rooms Floor Slab (2nd Level) 0 100% 03/Oct/15 03/Oct/15 02/Oct/15 A 03/Oct/15 A 02/Oct/15 A 03/Oct/15 A
CON1250 GIS Room Columns & Tie Beam Scaff. REBARS up to elev. +8.085 & +8.25 0 100% 04/Oct/15 07/Nov/15 04/Oct/15 A 07/Nov/15 A 04/Oct/15 A 07/Nov/15 A
CON63100 GIS Room Columns & Tie Beam Formwork & Casting up to elev. +8.085 & +8.25 (2nd Stage 0 100% 05/Oct/15 07/Nov/15 05/Oct/15 A 07/Nov/15 A 05/Oct/15 A 07/Nov/15 A
CON63160 Removal of Formwork & Scaffolding Protection & Equipment Rooms Floor Slab 0 100% 12/Oct/15 05/Nov/15 12/Oct/15 A 06/Nov/15 A 12/Oct/15 A 06/Nov/15 A
CON1327 GIS Room Scaff.&RCC of Columns & Beam (Grid D-D) up to elev. +9.750 0 100% 07/Nov/15 14/Nov/15 06/Nov/15 A 14/Nov/15 A 06/Nov/15 A 14/Nov/15 A
CON1329 GIS Room Scaff.&RCC of Columns & Beam up to elev. +14.975 (3rd Stage) 0 100% 17/Nov/15 21/Dec/15 17/Nov/15 A 22/Dec/15 A 17/Nov/15 A 22/Dec/15 A
CON57460 Platform Foundations RCC & Curing 21 80% 02/Dec/15 09/Apr/16 02/Dec/15 A 03/May/16 02/Dec/15 A 03/May/16
CON1260 Backfilling & Compaction Works Around Foundations & Slabs on Grade 11 99% 16/Dec/15 14/Feb/16 16/Dec/15 A 30/Mar/16 16/Dec/15 A 30/Mar/16
CON63110 GIS Room Scaff.&RCC of Roof Beam Final Stage 0 100% 23/Dec/15 25/Jan/16 23/Dec/15 A 26/Jan/16 A 23/Dec/15 A 26/Jan/16 A
CON63120 GIS Room Curing & Formwork Removal of Columns & Beams ( Ready for Pre-cast ) 0 100% 06/Jan/16 31/Jan/16 06/Jan/16 A 01/Feb/16 A 06/Jan/16 A 01/Feb/16 A
Pre-Cast Columns, Beams,
B Panels, TT Slabs & Parapets Erection 47 33.94% 15/Aug/15 09/Apr/16 15/Aug/15 A 03/May/16
CON1302 Interhnal Walls Erection 0 100% 15/Aug/15 24/Aug/15 15/Aug/15 A 24/Aug/15 A 15/Aug/15 A 24/Aug/15 A
CON73485 Remaining of Interhnal Walls Erection 2 92% 21/Feb/16 29/Feb/16 21/Feb/16 A 04/Apr/16 21/Feb/16 A 04/Apr/16
CON1343 Mech. Room Walls Panels Erection 5 92% 29/Feb/16 02/Mar/16 28/Feb/16 A 24/Mar/16 28/Feb/16 A 24/Mar/16
CON1328 Comm. & Battery Room Walls Panels Erection 2 80% 16/Mar/16 19/Mar/16 02/Mar/16 A 05/Apr/16 02/Mar/16 A 05/Apr/16
CON1352 Protection & Equip. Room & Communication Roof T Slabs Erection & Alignement 7 80% 26/Mar/16 28/Mar/16 07/Mar/16 A 10/Apr/16 07/Mar/16 A 10/Apr/16
CON1290 Cable Vault & GIS Room Pre-Cast Panels Erection (Lower Clad) & Alignement 15 30% 29/Feb/16 19/Mar/16 12/Mar/16 A 03/Apr/16 12/Mar/16 A 03/Apr/16
CON1349 Protection & Equip. Room Walls Panels Erection 7 92% 19/Mar/16 21/Mar/16 12/Mar/16 A 27/Mar/16 12/Mar/16 A 27/Mar/16
CON1300 GIS Room Pre-Cast Concrete Double T Slab 10 0% 19/Mar/16 28/Mar/16 03/Apr/16 12/Apr/16 03/Apr/16 12/Apr/16

Page 2 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON73480 Cable Vault & GIS Room Pre-Cast Panels Erection (Upper Clad) & Alignement 23 0% 19/Mar/16 09/Apr/16 12/Apr/16 03/May/16 12/Apr/16 03/May/16
Finishing - Completion
Completi of Works 68 11.93% 24/Dec/15 08/May/16 24/Dec/15 A 01/Jun/16
CON1330 Sealant, Putty & Painting & Finishing Works @ Cable Vault 15 72% 24/Dec/15 28/Mar/16 24/Dec/15 A 12/Apr/16 24/Dec/15 A 12/Apr/16
CON1340 Sealant & Putty Application of Internal Walls Above elev+3.6m 14 10% 20/Jan/16 23/Apr/16 20/Jan/16 A 17/May/16 20/Jan/16 A 17/May/16
CON63170 Grating Foundation and Grating Installation 15 40% 30/Jan/16 14/Apr/16 30/Jan/16 A 09/May/16 30/Jan/16 A 09/May/16
CON1318 Steel Stairs Erection ( GIS Room Side ) 21 0% 28/Mar/16 17/Apr/16 13/Apr/16 03/May/16 13/Apr/16 03/May/16
CON1303 Scuppers & Drain Pipes Erection 5 0% 04/Apr/16 09/Apr/16 28/Apr/16 03/May/16 28/Apr/16 03/May/16
CON1350 Supply & Installation of Doors & Hardwares 10 0% 09/Apr/16 18/Apr/16 03/May/16 12/May/16 03/May/16 12/May/16
CON1310 Roof Water Proofing Works 14 0% 09/Apr/16 21/Apr/16 03/May/16 16/May/16 03/May/16 16/May/16
CON1320 Steel Stairs Erection ( Relay Room Side ) 15 0% 17/Apr/16 01/May/16 03/May/16 17/May/16 03/May/16 17/May/16
CON1323 Roof Access Ladders Erection. 10 0% 17/Apr/16 26/Apr/16 03/May/16 12/May/16 03/May/16 12/May/16
CON1360 Painting Works @ Building above elev +3.6m 10 0% 19/Apr/16 28/Apr/16 14/May/16 23/May/16 14/May/16 23/May/16
CON1370 Floor Finishing Works, Self Level & Epoxy Coating (Ready for Installation) 15 0% 23/Apr/16 05/May/16 16/May/16 30/May/16 16/May/16 30/May/16
CON1315 Flood Test 2 0% 23/Apr/16 24/Apr/16 16/May/16 18/May/16 16/May/16 18/May/16
CON1316 Thermal Insulation 15 0% 24/Apr/16 08/May/16 18/May/16 01/Jun/16 18/May/16 01/Jun/16
CON1380 External Finishing Works (Touch up) 5 0% 28/Apr/16 03/May/16 23/May/16 28/May/16 23/May/16 28/May/16
SS #4 Electrical Installation
Insta 107 0% 14/Apr/16 30/Jul/16 09/May/16 23/Aug/16
SS #4 230KV GIS R
Room - Installation of 230kV GIS 107 0% 14/Apr/16 30/Jul/16 09/May/16 23/Aug/16
230KV GIS Mechanical
Mechan Installation 85 0% 07/May/16 30/Jul/16 30/May/16 23/Aug/16
CON1382 Mobilization of GIS Supervisor ( Vendor ) 0 0% 07/May/16 30/May/16 Mobilization of GIS Supervisor ( V
CON1384 Floor Check 3 0% 07/May/16 09/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON1386 Opening Box & Arrangement of Material & Equipment 3 0% 07/May/16 09/May/16 30/May/16 02/Jun/16 30/May/16 02/Jun/16
CON1388 Transfer of CBs to GIS Room 3 0% 09/May/16 11/May/16 01/Jun/16 05/Jun/16 01/Jun/16 05/Jun/16
CON1389 Transfer of VTs & CTs & Check before Installation 6 0% 09/May/16 14/May/16 01/Jun/16 07/Jun/16 01/Jun/16 07/Jun/16
CON1390 Positioning & Alignment & Installation of CBs 5 0% 09/May/16 14/May/16 01/Jun/16 06/Jun/16 01/Jun/16 06/Jun/16
CON1394 Disconnect Switches Installation 5 0% 14/May/16 18/May/16 06/Jun/16 11/Jun/16 06/Jun/16 11/Jun/16
CON1392 CTs Installation 5 0% 14/May/16 18/May/16 07/Jun/16 12/Jun/16 07/Jun/16 12/Jun/16
CON1395 Disconnect Switched Mechanisms Installation & Adjusting 5 0% 16/May/16 21/May/16 09/Jun/16 14/Jun/16 09/Jun/16 14/Jun/16
CON1398 Installation of BB-1 Compartments 5 0% 18/May/16 23/May/16 11/Jun/16 15/Jun/16 11/Jun/16 15/Jun/16
CON1400 Installation of BB-2 Compartments 5 0% 18/May/16 23/May/16 11/Jun/16 15/Jun/16 11/Jun/16 15/Jun/16
CON1408 On Equipment Cable Tray Installation 7 0% 18/May/16 24/May/16 11/Jun/16 18/Jun/16 11/Jun/16 18/Jun/16
CON1401 Cable Head Installation 4 0% 23/May/16 26/May/16 15/Jun/16 19/Jun/16 15/Jun/16 19/Jun/16
CON1410 Guages & Pressure Switches Installation 2 0% 23/May/16 24/May/16 15/Jun/16 18/Jun/16 15/Jun/16 18/Jun/16
CON1411 Hydraulic Control Units Check & Oil Filling if Required 2 0% 24/May/16 26/May/16 18/Jun/16 19/Jun/16 18/Jun/16 19/Jun/16
CON1403 Bay VT Supports & VTs Installation 6 0% 26/May/16 01/Jun/16 19/Jun/16 25/Jun/16 19/Jun/16 25/Jun/16
CON1422 Vacuming & SF6 Filling ( CBs & CTs) 20 0% 26/May/16 14/Jun/16 19/Jun/16 13/Jul/16 19/Jun/16 13/Jul/16
CON1402 Readiness for Wasit Lines HV Cables Terminations Start (By Others) 0 0% 26/May/16 19/Jun/16 Readiness for Wasit Lines HV
CON1412 Readiness to Start GIS Mechanical Pre-commisioning 0 0% 26/May/16 19/Jun/16 Readiness to Start GIS Mechan
CON1407 Platform / Catwalk Installation 7 0% 01/Jun/16 07/Jun/16 25/Jun/16 02/Jul/16 25/Jun/16 02/Jul/16
CON1404 BB VT Supports & VTs Installation 4 0% 01/Jun/16 05/Jun/16 25/Jun/16 28/Jun/16 25/Jun/16 28/Jun/16
CON1405 Contact Resistance Check (Internal) & Repair if Required 2 0% 05/Jun/16 06/Jun/16 28/Jun/16 30/Jun/16 28/Jun/16 30/Jun/16
CON1406 Bolt Tightening Check 3 0% 05/Jun/16 07/Jun/16 28/Jun/16 02/Jul/16 28/Jun/16 02/Jul/16
CON1423 Vacuming & SF6 Filling ( Isolators & Earthing Switches) 6 0% 14/Jun/16 20/Jun/16 13/Jul/16 19/Jul/16 13/Jul/16 19/Jul/16
CON1432 Vacuming & SF6 Filling ( BB-1) 6 0% 20/Jun/16 25/Jun/16 19/Jul/16 25/Jul/16 19/Jul/16 25/Jul/16
CON1442 Vacuming & SF6 Filling ( BB-2) 6 0% 25/Jun/16 30/Jun/16 25/Jul/16 31/Jul/16 25/Jul/16 31/Jul/16
CON1462 Vacuming & SF6 Filling ( VTs) 6 0% 30/Jun/16 12/Jul/16 31/Jul/16 06/Aug/16 31/Jul/16 06/Aug/16
CON1702 Readiness for GAS Checks & HV Test 0 0% 12/Jul/16 06/Aug/16 Readiness for GAS Checks
CON68990 SA Installation & Gasing 3 0% 27/Jul/16 30/Jul/16 20/Aug/16 23/Aug/16 20/Aug/16 23/Aug/16
230KV GIS Electrical
Electric Installation 63 0% 14/Apr/16 13/Jun/16 09/May/16 12/Jul/16
CON1472 Local Control Cubicles Installation 5 0% 09/May/16 14/May/16 02/Jun/16 07/Jun/16 02/Jun/16 07/Jun/16
CON1662 LCC Control Cables Looping & Termination 15 0% 14/May/16 28/May/16 07/Jun/16 21/Jun/16 07/Jun/16 21/Jun/16

Page 3 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON1672 CT Looping 10 0% 18/May/16 28/May/16 12/Jun/16 21/Jun/16 12/Jun/16 21/Jun/16
CON1681 Readiness to Start GIS Electrical Pre-commisioning 0 0% 28/May/16 21/Jun/16 Readiness to Start GIS Electric
CON1682 VT Looping 10 0% 01/Jun/16 11/Jun/16 25/Jun/16 10/Jul/16 25/Jun/16 10/Jul/16
Outgoing Bays 63 0% 14/Apr/16 13/Jun/16 09/May/16 12/Jul/16
CON1502 Control Cables Pulling From Bay-1 (706) to LCC 4 0% 14/Apr/16 18/Apr/16 09/May/16 12/May/16 09/May/16 12/May/16
CON1512 Control Cables Pulling From Bay-2 (707) to LCC 4 0% 18/Apr/16 21/Apr/16 12/May/16 16/May/16 12/May/16 16/May/16
CON1505 Control Cables Termination Bay-1 (706)( LCC Side) 12 0% 12/May/16 23/May/16 05/Jun/16 16/Jun/16 05/Jun/16 16/Jun/16
CON1517 Control Cables Termination Bay-2 (707)( LCC Side) 12 0% 12/May/16 23/May/16 05/Jun/16 16/Jun/16 05/Jun/16 16/Jun/16
CON1522 Control Cables Pulling From Bay-3 (708) to LCC 4 0% 25/May/16 29/May/16 18/Jun/16 22/Jun/16 18/Jun/16 22/Jun/16
CON1532 Control Cables Pulling From Bay-4 (709) to LCC 4 0% 29/May/16 01/Jun/16 22/Jun/16 26/Jun/16 22/Jun/16 26/Jun/16
CON1525 Control Cables Termination Bay-3 (708)( LCC Side) 12 0% 29/May/16 08/Jun/16 22/Jun/16 09/Jul/16 22/Jun/16 09/Jul/16
CON1507 Control Cables Termination Bay-1 (706)(GIS Side) 12 0% 01/Jun/16 12/Jun/16 25/Jun/16 12/Jul/16 25/Jun/16 12/Jul/16
CON1519 Control Cables Termination Bay-2 (707)(GIS Side) 12 0% 01/Jun/16 12/Jun/16 25/Jun/16 12/Jul/16 25/Jun/16 12/Jul/16
CON1527 Control Cables Termination Bay-3 (708)(GIS Side) 12 0% 01/Jun/16 12/Jun/16 25/Jun/16 12/Jul/16 25/Jun/16 12/Jul/16
CON1602 Control Cables Termination Bay-4 (709)( LCC Side) 12 0% 01/Jun/16 13/Jun/16 26/Jun/16 12/Jul/16 26/Jun/16 12/Jul/16
CON1612 Control Cables Termination Bay-4 (709)(GIS Side) 12 0% 01/Jun/16 13/Jun/16 26/Jun/16 12/Jul/16 26/Jun/16 12/Jul/16
Bus Sections & Bus
Bu Coupller 44 0% 02/May/16 12/Jun/16 25/May/16 12/Jul/16
CON1504 Control Cables Pulling From Bus Section (703) to LCC 5 0% 02/May/16 05/May/16 25/May/16 30/May/16 25/May/16 30/May/16
CON1537 Control Cables Pulling From Bus Coupler (705) to LCC 5 0% 07/May/16 10/May/16 30/May/16 04/Jun/16 30/May/16 04/Jun/16
CON1691 Control Cables Pulling From Bus Section (704) to LCC 5 0% 11/May/16 15/May/16 04/Jun/16 08/Jun/16 04/Jun/16 08/Jun/16
CON1506 Control Cables Termination Bus Section(703) ( LCC Side) 12 0% 12/May/16 23/May/16 05/Jun/16 16/Jun/16 05/Jun/16 16/Jun/16
CON1642 Control Cables Termination Bus Coupler (705)( LCC Side) 12 0% 12/May/16 23/May/16 05/Jun/16 16/Jun/16 05/Jun/16 16/Jun/16
CON1692 Control Cables Termination Bus Section(704) ( LCC Side) 12 0% 16/May/16 26/May/16 08/Jun/16 20/Jun/16 08/Jun/16 20/Jun/16
CON1508 Control Cables Termination Bus Section (703)(GIS Side) 12 0% 01/Jun/16 12/Jun/16 25/Jun/16 12/Jul/16 25/Jun/16 12/Jul/16
CON1652 Control Cables Termination Bus Coupler (705)(GIS Side) 12 0% 01/Jun/16 12/Jun/16 25/Jun/16 12/Jul/16 25/Jun/16 12/Jul/16
CON1722 Control Cables Termination Bus Sections (704)(GIS Side) 12 0% 01/Jun/16 12/Jun/16 25/Jun/16 12/Jul/16 25/Jun/16 12/Jul/16
Incommer Bays 47 0% 23/Apr/16 05/Jun/16 16/May/16 29/Jun/16
CON1524 Control Cables Pulling from Incommer (701) to LCC 10 0% 23/Apr/16 01/May/16 16/May/16 25/May/16 16/May/16 25/May/16
CON1577 Control Cables Termination Incommer (701) (GIS Side) 12 0% 02/May/16 12/May/16 25/May/16 06/Jun/16 25/May/16 06/Jun/16
CON1575 Control Cables Termination Incommer(701) (LCC Side) 12 0% 12/May/16 23/May/16 05/Jun/16 16/Jun/16 05/Jun/16 16/Jun/16
CON1731 Control Cables Pulling from Incommer (702) to LCC 10 0% 16/May/16 24/May/16 08/Jun/16 18/Jun/16 08/Jun/16 18/Jun/16
CON1732 Control Cables Termination Incommer (702)(LCC Side) 12 0% 25/May/16 05/Jun/16 18/Jun/16 29/Jun/16 18/Jun/16 29/Jun/16
CON1742 Control Cables Termination Incommer (702)(GIS Side) 12 0% 25/May/16 05/Jun/16 18/Jun/16 29/Jun/16 18/Jun/16 29/Jun/16
SS #4 Protection Sys
System Room- Installation of Protection Systems 83 0% 14/Apr/16 02/Jul/16 09/May/16 01/Aug/16
Panels Installation 6 0% 07/May/16 11/May/16 30/May/16 05/Jun/16
CON2040 Bay-3 (708) TRAFO Set-I Panel Installation 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON2050 Bay-3 (708) TRAFO+BF Set-II Panel Installation 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON2020 Bay-4 (709) TRAFO Set-I Panel Installation 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON2030 Bay-4 (709) TRAFO+BF Set-II Panel Installation 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON2070 Incommer (702) LP+BF Set-II Panel Installation 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON2060 Incommer (702) LP Set-I Panel Installation 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON2100 BB-1B Protection Panel Installation 2 0% 08/May/16 10/May/16 01/Jun/16 02/Jun/16 01/Jun/16 02/Jun/16
CON2140 Bus Section(703) BF Panel Installation 2 0% 08/May/16 10/May/16 01/Jun/16 02/Jun/16 01/Jun/16 02/Jun/16
CON2120 Bus Coupler (705) BF Panel Installation 2 0% 08/May/16 10/May/16 01/Jun/16 02/Jun/16 01/Jun/16 02/Jun/16
CON2130 Bus Section (704) BF Panel Installation 2 0% 08/May/16 10/May/16 01/Jun/16 02/Jun/16 01/Jun/16 02/Jun/16
CON2080 BB-1A Protection Panel Installation 2 0% 08/May/16 10/May/16 01/Jun/16 02/Jun/16 01/Jun/16 02/Jun/16
CON2090 BB-2A Protection Panel Installation 2 0% 08/May/16 10/May/16 01/Jun/16 02/Jun/16 01/Jun/16 02/Jun/16
CON2110 BB-2B Protection Panel Installation 2 0% 08/May/16 10/May/16 01/Jun/16 02/Jun/16 01/Jun/16 02/Jun/16
CON2190 Bay-1 (706) TRAFO Set-I Panel Installation 2 0% 10/May/16 11/May/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
CON2170 Bay-2 (707) TRAFO Set-I Panel Installation 2 0% 10/May/16 11/May/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
CON3000 Bay-1 (706) TRAFO+BF Set-II Panel Installation 2 0% 10/May/16 11/May/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16

Page 4 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON2180 Bay-2 (707) TRAFO+BF Set-II Panel Installation 2 0% 10/May/16 11/May/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
CON2160 Incommer (701) LP+BF Set-II Panel Installation 2 0% 10/May/16 11/May/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
CON2150 Incommer (701) LP Set-I Panel Installation 2 0% 10/May/16 11/May/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
Control & Instrumentation
Instrumen Cable Pulling 57 0% 14/Apr/16 07/Jun/16 09/May/16 01/Jul/16
CON2330 Cable Pulling from Incommer (701) LCC to LP Set-I Panel 3 0% 14/Apr/16 17/Apr/16 09/May/16 11/May/16 09/May/16 11/May/16
CON2340 Cable Pulling from Incommer (701) LCC to LP+BF Set-II Panel 3 0% 18/Apr/16 20/Apr/16 11/May/16 15/May/16 11/May/16 15/May/16
CON2350 Cable Pulling from Bay-2 (707) LCC to TRAFO Set-I Panel 3 0% 20/Apr/16 23/Apr/16 15/May/16 17/May/16 15/May/16 17/May/16
CON2360 Cable Pulling from Bay-2 (707) LCC to TRAFO+BF Set-II Panel 3 0% 23/Apr/16 26/Apr/16 17/May/16 19/May/16 17/May/16 19/May/16
CON2370 Cable Pulling from Bay-1 (706) LCC to TRAFO Set-I Panel 3 0% 26/Apr/16 28/Apr/16 21/May/16 23/May/16 21/May/16 23/May/16
CON2375 Cable Pulling from Bay-1 (706) LCC to TRAFO+BF Set-II Panel 3 0% 28/Apr/16 01/May/16 23/May/16 25/May/16 23/May/16 25/May/16
CON2260 Cable Pulling from BB-1A LCC to Protection Panel 3 0% 02/May/16 04/May/16 25/May/16 29/May/16 25/May/16 29/May/16
CON2270 Cable Pulling from BB-2A LCC to Protection Panel 3 0% 04/May/16 07/May/16 29/May/16 31/May/16 29/May/16 31/May/16
CON2280 Cable Pulling from BB-1B LCC to Protection Panel 3 0% 07/May/16 10/May/16 31/May/16 02/Jun/16 31/May/16 02/Jun/16
CON2290 Cable Pulling from BB-2B LCC to Protection Panel 3 0% 10/May/16 12/May/16 04/Jun/16 06/Jun/16 04/Jun/16 06/Jun/16
CON2300 Cable Pulling from Bus Coupler (705) LCC to BF Panel 3 0% 12/May/16 15/May/16 06/Jun/16 08/Jun/16 06/Jun/16 08/Jun/16
CON2310 Cable Pulling from Bus Section (704) LCC to BF Panel 3 0% 16/May/16 18/May/16 08/Jun/16 12/Jun/16 08/Jun/16 12/Jun/16
CON2320 Cable Pulling from Bus Section(703) LCC to BF Panel 3 0% 18/May/16 21/May/16 12/Jun/16 14/Jun/16 12/Jun/16 14/Jun/16
CON2200 Cable Pulling from Bay-4 (709) LCC to TRAFO Set-I Panel 3 0% 21/May/16 24/May/16 14/Jun/16 17/Jun/16 14/Jun/16 17/Jun/16
CON2210 Cable Pulling from Bay-4 (709) LCC to TRAFO+BF Set-II Panel 3 0% 24/May/16 26/May/16 18/Jun/16 20/Jun/16 18/Jun/16 20/Jun/16
CON2220 Cable Pulling from Bay-3 (708) LCC to TRAFO Set-I Panel 3 0% 26/May/16 29/May/16 20/Jun/16 22/Jun/16 20/Jun/16 22/Jun/16
CON2230 Cable Pulling from Bay-3 (708) LCC to TRAFO+BF Set-II Panel 3 0% 30/May/16 01/Jun/16 22/Jun/16 26/Jun/16 22/Jun/16 26/Jun/16
CON2240 Cable Pulling from Incommer (702) LCC to LP Set-I Panel 3 0% 01/Jun/16 04/Jun/16 26/Jun/16 28/Jun/16 26/Jun/16 28/Jun/16
CON2250 Cable Pulling from Incommer (702) LCC to LP+BF Set-II Panel 3 0% 04/Jun/16 07/Jun/16 28/Jun/16 01/Jul/16 28/Jun/16 01/Jul/16
Control Cable Termination
Term 55 0% 11/May/16 02/Jul/16 05/Jun/16 01/Aug/16
BUS System - A 54 0% 11/May/16 30/Jun/16 05/Jun/16 31/Jul/16
Control Cable Termination
Te - BUS System - A LCC Side 29 0% 14/May/16 09/Jun/16 06/Jun/16 09/Jul/16
CON2443 Cable Termination BB-1A LCC Side 17 0% 14/May/16 29/May/16 06/Jun/16 22/Jun/16 06/Jun/16 22/Jun/16
CON2455 Cable Termination BB-2A LCC Side 17 0% 14/May/16 30/May/16 07/Jun/16 23/Jun/16 07/Jun/16 23/Jun/16
CON2493 Cable Termination Bus Section (704) LCC Side 18 0% 18/May/16 04/Jun/16 12/Jun/16 28/Jun/16 12/Jun/16 28/Jun/16
CON5840 Cable Termination Bay-2 (707) LCC Side 18 0% 23/May/16 09/Jun/16 16/Jun/16 09/Jul/16 16/Jun/16 09/Jul/16
CON2395 Cable Termination Bay-1 (706) LCC Side 18 0% 23/May/16 09/Jun/16 16/Jun/16 09/Jul/16 16/Jun/16 09/Jul/16
CON2503 Cable Termination Bus Section (703) LCC Side 18 0% 23/May/16 09/Jun/16 16/Jun/16 09/Jul/16 16/Jun/16 09/Jul/16
CON2483 Cable Termination Bus Coupler (705) LCC Side 18 0% 23/May/16 09/Jun/16 16/Jun/16 09/Jul/16 16/Jun/16 09/Jul/16
CON2585 Cable Termination Incommer (701) LCC Side 18 0% 23/May/16 09/Jun/16 16/Jun/16 09/Jul/16 16/Jun/16 09/Jul/16
Control Cable Termination
Te - BUS System - A Protection Panels Side 54 0% 11/May/16 30/Jun/16 05/Jun/16 31/Jul/16
CON2383 Cable Termination Bay-1 (706) TRAFO Set-I Panel Side 18 0% 11/May/16 29/May/16 05/Jun/16 21/Jun/16 05/Jun/16 21/Jun/16
CON2830 Cable Termination Bay-2 (707) TRAFO+BF Set- II Panel Side 18 0% 11/May/16 29/May/16 05/Jun/16 21/Jun/16 05/Jun/16 21/Jun/16
CON2780 Cable Termination Bay-2 (707) TRAFO Set-I Panel Side 18 0% 11/May/16 29/May/16 05/Jun/16 21/Jun/16 05/Jun/16 21/Jun/16
CON2385 Cable Termination Bay-1 (706) TRAFO+BF Set- II Panel Side 18 0% 11/May/16 29/May/16 05/Jun/16 21/Jun/16 05/Jun/16 21/Jun/16
CON2580 Cable Termination Incommer (701) LP+BF Set-II Panel Side 18 0% 11/May/16 29/May/16 05/Jun/16 21/Jun/16 05/Jun/16 21/Jun/16
CON2570 Cable Termination Incommer (701) LP Set-I Panel Side 18 0% 11/May/16 29/May/16 05/Jun/16 21/Jun/16 05/Jun/16 21/Jun/16
CON2440 Cable Termination BB-1A BB-1A Protection Panel Side 17 0% 29/May/16 14/Jun/16 22/Jun/16 13/Jul/16 22/Jun/16 13/Jul/16
CON2450 Cable Termination BB-2A Protection Panel Side 17 0% 30/May/16 15/Jun/16 23/Jun/16 14/Jul/16 23/Jun/16 14/Jul/16
CON2500 Cable Termination Bus Section (703) BF Panel Side 17 0% 15/Jun/16 30/Jun/16 14/Jul/16 31/Jul/16 14/Jul/16 31/Jul/16
CON2480 Cable Termination Bus Coupler (705) BF Panel Side 17 0% 15/Jun/16 30/Jun/16 14/Jul/16 31/Jul/16 14/Jul/16 31/Jul/16
CON2490 Cable Termination Bus Section (704) BF Panel Side 17 0% 15/Jun/16 30/Jun/16 14/Jul/16 31/Jul/16 14/Jul/16 31/Jul/16
BUS System - B 41 0% 24/May/16 02/Jul/16 18/Jun/16 01/Aug/16
Control Cable Termination
Te - BUS System - B LCC Side 32 0% 30/May/16 28/Jun/16 23/Jun/16 28/Jul/16
CON2462 Cable Termination BB-1B LCC Side 17 0% 30/May/16 15/Jun/16 23/Jun/16 14/Jul/16 23/Jun/16 14/Jul/16
CON2472 Cable Termination BB-2B LCC Side 17 0% 30/May/16 15/Jun/16 23/Jun/16 14/Jul/16 23/Jun/16 14/Jul/16
CON2985 Cable Termination Incommer (702) LCC Side 18 0% 07/Jun/16 23/Jun/16 02/Jul/16 24/Jul/16 02/Jul/16 24/Jul/16

Page 5 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON5860 Cable Termination Bay-3 (708) LCC Side 17 0% 08/Jun/16 25/Jun/16 09/Jul/16 25/Jul/16 09/Jul/16 25/Jul/16
CON2406 Cable Termination Bay-4 (709) LCC Side 17 0% 13/Jun/16 28/Jun/16 12/Jul/16 28/Jul/16 12/Jul/16 28/Jul/16
Control Cable Termination
Te - BUS System - B Protection Panels Side 41 0% 24/May/16 02/Jul/16 18/Jun/16 01/Aug/16
CON2393 Cable Termination Bay-4 (709) TRAFO Set-I Panel Side 18 0% 24/May/16 09/Jun/16 18/Jun/16 10/Jul/16 18/Jun/16 10/Jul/16
CON2405 Cable Termination Bay-4 (709) TRAFO+BF Set- II Panel Side 18 0% 26/May/16 13/Jun/16 20/Jun/16 12/Jul/16 20/Jun/16 12/Jul/16
CON5570 Cable Termination Bay-3 (708) TRAFO Set-I Panel Side 18 0% 30/May/16 15/Jun/16 22/Jun/16 16/Jul/16 22/Jun/16 16/Jul/16
CON5590 Cable Termination Bay-3 (708) TRAFO+BF Set- II Panel Side 18 0% 01/Jun/16 18/Jun/16 26/Jun/16 18/Jul/16 26/Jun/16 18/Jul/16
CON2890 Cable Termination Incommer (702) LP Set-I Panel Side 17 0% 04/Jun/16 20/Jun/16 28/Jun/16 20/Jul/16 28/Jun/16 20/Jul/16
CON2980 Cable Termination Incommer (702) LP+BF Set-II Panel Side 17 0% 07/Jun/16 22/Jun/16 02/Jul/16 23/Jul/16 02/Jul/16 23/Jul/16
CON2460 Cable Termination BB-1B Protection Panel Side 18 0% 15/Jun/16 02/Jul/16 14/Jul/16 01/Aug/16 14/Jul/16 01/Aug/16
CON2470 Cable Termination BB-2B Protection Panel Side 18 0% 15/Jun/16 02/Jul/16 14/Jul/16 01/Aug/16 14/Jul/16 01/Aug/16
SS #4 PSA System Installation
I 76 0% 07/May/16 21/Jul/16 30/May/16 15/Aug/16
PSA Panels Installation
Installa 3 0% 07/May/16 09/May/16 30/May/16 02/Jun/16
CON3080 PSA Panel Installation @ Protection Systems Room 3 0% 07/May/16 09/May/16 30/May/16 02/Jun/16 30/May/16 02/Jun/16
CON3085 PSA Interface Panels Installation (If Requried) 3 0% 07/May/16 09/May/16 30/May/16 02/Jun/16 30/May/16 02/Jun/16
Fiber Optic Cables Laying & Termination 31 0% 09/May/16 07/Jun/16 02/Jun/16 30/Jun/16
CON3087 Mobilization of FO Subcontractor Supervisor (Vendor) 0 0% 09/May/16 02/Jun/16 Mobilization of FO Subcontractor
CON5580 FO&Instrum. Cables Pulling &Termination from PSA Panel to 230KV Relays(IEDs) 20 0% 10/May/16 29/May/16 02/Jun/16 21/Jun/16 02/Jun/16 21/Jun/16
CON5585 Cable Pulling &Termination from PSA Interface Panels to 230KV Relays (non-IEDs) 1 0% 11/May/16 12/May/16 05/Jun/16 06/Jun/16 05/Jun/16 06/Jun/16
CON5595 FO&Instrum. Cables Pulling &Termination from PSA Interface to PSA Panels 1 0% 29/May/16 29/May/16 21/Jun/16 22/Jun/16 21/Jun/16 22/Jun/16
CON5705 FO Cables Laying & Splicing between PSA Panels & BCUs 10 0% 29/May/16 07/Jun/16 21/Jun/16 30/Jun/16 21/Jun/16 30/Jun/16
BCUs Installation 32 0% 09/Jun/16 14/Jul/16 09/Jul/16 08/Aug/16
CON5675 BCU Installation & Termination @ LCC (701) 10 0% 09/Jun/16 19/Jun/16 09/Jul/16 18/Jul/16 09/Jul/16 18/Jul/16
CON5685 BCU Installation & Termination @ LCC (707) 10 0% 09/Jun/16 19/Jun/16 09/Jul/16 18/Jul/16 09/Jul/16 18/Jul/16
CON5695 BCU Installation & Termination @ LCC (706) 10 0% 09/Jun/16 19/Jun/16 09/Jul/16 18/Jul/16 09/Jul/16 18/Jul/16
CON5625 BCU Installation & Termination @ LCC (702) 10 0% 23/Jun/16 09/Jul/16 24/Jul/16 02/Aug/16 24/Jul/16 02/Aug/16
CON5615 BCU Installation & Termination @ LCC (708) 10 0% 25/Jun/16 10/Jul/16 25/Jul/16 03/Aug/16 25/Jul/16 03/Aug/16
CON5605 BCU Installation & Termination @ LCC (709) 10 0% 28/Jun/16 13/Jul/16 28/Jul/16 07/Aug/16 28/Jul/16 07/Aug/16
CON5645 BCU Installation & Termination @ LCC (705) 9 0% 30/Jun/16 14/Jul/16 31/Jul/16 08/Aug/16 31/Jul/16 08/Aug/16
CON5655 BCU Installation & Termination @ LCC (704) 9 0% 30/Jun/16 14/Jul/16 31/Jul/16 08/Aug/16 31/Jul/16 08/Aug/16
CON5665 BCU Installation & Termination @ LCC (703) 9 0% 30/Jun/16 14/Jul/16 31/Jul/16 08/Aug/16 31/Jul/16 08/Aug/16
PSA Sys. Pre-commissioning
Pre-comm ( Start up ) & Relay Configuration ( Pre-check ) @SS #4 73 0% 09/May/16 21/Jul/16 02/Jun/16 15/Aug/16
CON57010 Mobilization of PSA System Supervisor (Vendor) 0 0% 09/May/16 02/Jun/16 Mobilization of PSA System Supe
CON5709 Installation of 50" LCD Annunciator Screen and Cording to Automation Station 4 0% 10/May/16 14/May/16 02/Jun/16 07/Jun/16 02/Jun/16 07/Jun/16
CON5712 Availability of AC&DC 0 0% 25/May/16 19/Jun/16 Availability of AC&DC
CON5713 Pre-commissioning of Automation Station & Printer & LCD Screen 1 0% 30/May/16 31/May/16 19/Jun/16 19/Jun/16 19/Jun/16 19/Jun/16
CON5706 GPS Clock Antenna Installation & Linking to GPS Clock @ PSA Cabinet 4 0% 31/May/16 04/Jun/16 19/Jun/16 23/Jun/16 19/Jun/16 23/Jun/16
CON61040 SS #4 PSA System Ready To Start Internal Closed Loop Testing 0 0% 18/Jul/16 10/Aug/16 SS #4 PSA System Ready
CON5815 SS #4 PSA System Configuration Completed 0 0% 21/Jul/16 15/Aug/16 SS #4 PSA System Config
Busbar - A Relays Configuration ( Pre-check ) 5 0% 14/Jul/16 19/Jul/16 08/Aug/16 13/Aug/16
CON61020 Relay Configuration Pre-check for BB- A 1 0% 14/Jul/16 16/Jul/16 08/Aug/16 09/Aug/16 08/Aug/16 09/Aug/16
CON5715 Relay Configuration Pre-check for Line Feeder-1 1 0% 16/Jul/16 17/Jul/16 09/Aug/16 10/Aug/16 09/Aug/16 10/Aug/16
CON5725 Relay Configuration Pre-check for Transformer-701 1 0% 17/Jul/16 18/Jul/16 10/Aug/16 10/Aug/16 10/Aug/16 10/Aug/16
CON5755 Relay Configuration Pre-check for Transformer-703 1 0% 19/Jul/16 19/Jul/16 11/Aug/16 13/Aug/16 11/Aug/16 13/Aug/16
Busbar - B Relays Configuration ( Pre-check ) 5 0% 16/Jul/16 20/Jul/16 09/Aug/16 14/Aug/16
CON61030 Relay Configuration Pre-check for BB - B 1 0% 16/Jul/16 17/Jul/16 09/Aug/16 10/Aug/16 09/Aug/16 10/Aug/16
CON5735 Relay Configuration Pre-check for Line Feeder-2 1 0% 17/Jul/16 18/Jul/16 10/Aug/16 10/Aug/16 10/Aug/16 10/Aug/16
CON5745 Relay Configuration Pre-check for Transformer-702 1 0% 18/Jul/16 19/Jul/16 10/Aug/16 11/Aug/16 10/Aug/16 11/Aug/16
CON5765 Relay Configuration Pre-check for Transformer-704 1 0% 19/Jul/16 20/Jul/16 13/Aug/16 14/Aug/16 13/Aug/16 14/Aug/16
Interfacing FA, HV
HVAC & Battery Charger Monitoring Systems ( Pre-check ) 8 0% 14/Jul/16 21/Jul/16 08/Aug/16 15/Aug/16
CON5795 Fire Alarm Linking to Gateway @ PSA Cabinet t & Config. Pre-check 1 0% 14/Jul/16 16/Jul/16 08/Aug/16 08/Aug/16 08/Aug/16 08/Aug/16

Page 6 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON5805 HVAC Linking to Gateway @ PSA Cabinet t & Config. Pre-check 1 0% 14/Jul/16 16/Jul/16 13/Aug/16 14/Aug/16 13/Aug/16 14/Aug/16
CON5785 Battery Charger Monitoring & Alarm Linking to Gateway @ PSA Cabinet & Config. Pre-check 1 0% 20/Jul/16 21/Jul/16 14/Aug/16 15/Aug/16 14/Aug/16 15/Aug/16
SS #4 Communication
Communicatio Room - Installation of Data & Voice Telephone System 48 0% 07/May/16 20/Jun/16 30/May/16 20/Jul/16
SS #4 Comm. Panels
Pan Installation 7 0% 07/May/16 12/May/16 30/May/16 06/Jun/16
CON5540 FO Cables Patch Panels Installation (Rack 1 & 2) 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON5530 230V Telecom Power Panel Installation 2 0% 10/May/16 11/May/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
CON62220 Communication Panels Installation by Others (If Required) 0 0% 12/May/16 06/Jun/16 Communication Panels Installati
SS #4 FOC & Data Voice Inter-Connections 26 0% 31/May/16 20/Jun/16 19/Jun/16 20/Jul/16
CON61080 Mobilization of Communication System Supervisor (Vendor) 0 0% 31/May/16 19/Jun/16 Mobilization of Communication
CON61070 CAT6 Cables Network Pulling &Termination to VoIP Telephone (X2 & X8) 15 0% 02/Jun/16 16/Jun/16 22/Jun/16 12/Jul/16 22/Jun/16 12/Jul/16
CON6910 FO Cables Laying & Splicing between PSA Gateway Panel & FOC PP-1 (PoE Switch) (Rack1 4 0% 07/Jun/16 11/Jun/16 30/Jun/16 11/Jul/16 30/Jun/16 11/Jul/16
CON61090 Powering Communication Panel 2 0% 09/Jun/16 11/Jun/16 09/Jul/16 11/Jul/16 09/Jul/16 11/Jul/16
CON6920 FO Cables Laying & Splicing between PSA Gateway Panel & FOC PP-2 (UTP Patch Panel)(R 4 0% 11/Jun/16 14/Jun/16 11/Jul/16 14/Jul/16 11/Jul/16 14/Jul/16
CON61060 Connecting VoIP (X2 & X8) to Rack 2 2 0% 16/Jun/16 18/Jun/16 12/Jul/16 14/Jul/16 12/Jul/16 14/Jul/16
CON6930 FO Cables Laying & Splicing between FOC PP-1 & FOC PP-2 2 0% 14/Jun/16 16/Jun/16 14/Jul/16 16/Jul/16 14/Jul/16 16/Jul/16
CON62230 FO Cables Laying & Splicing between Wasit Lines Protection Panels & Panels Installed by O 4 0% 16/Jun/16 20/Jun/16 16/Jul/16 20/Jul/16 16/Jul/16 20/Jul/16
SS #4 Installation of Substation Auxiliaries 81 0% 07/May/16 09/Jul/16 30/May/16 20/Aug/16
SS #4 Equipment Room-
R Installation of AC / DC Systems 52 0% 07/May/16 23/Jun/16 30/May/16 24/Jul/16
CON3140 125VDC Panel Installation @ Protection Room 4 0% 07/May/16 10/May/16 30/May/16 02/Jun/16 30/May/16 02/Jun/16
CON3200 DC Battery Charger Installation 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON3250 Telecom Equip. Power Supply Inverter Installation @ Equipment Room 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON3850 400-230V Power Panel Installation 4 0% 07/May/16 10/May/16 30/May/16 02/Jun/16 30/May/16 02/Jun/16
CON3150 125VDC Panel Installation @ Equip. Room 4 0% 10/May/16 14/May/16 02/Jun/16 07/Jun/16 02/Jun/16 07/Jun/16
CON3860 400-230V Lighting Panel Installation 3 0% 10/May/16 12/May/16 02/Jun/16 06/Jun/16 02/Jun/16 06/Jun/16
CON3890 Lighting Control Planel Installation 2 0% 12/May/16 15/May/16 06/Jun/16 07/Jun/16 06/Jun/16 07/Jun/16
CON4110 480-400/230V Lighting / Power Dry Type Transformer Installation 3 0% 12/May/16 15/May/16 06/Jun/16 08/Jun/16 06/Jun/16 08/Jun/16
CON3380 Battery Back-up Supply for Emergency Lighting Installation 2 0% 14/May/16 15/May/16 07/Jun/16 08/Jun/16 07/Jun/16 08/Jun/16
CON6950 Maintenance & Tools Cupboard Mounting @GIS Room 2 0% 22/Jun/16 23/Jun/16 21/Jul/16 24/Jul/16 21/Jul/16 24/Jul/16
SS #4 Battery Room - Installation of Battery 81 0% 07/May/16 27/Jun/16 30/May/16 20/Aug/16
CON4310 Battery Support Frame Installation 3 0% 07/May/16 09/May/16 30/May/16 02/Jun/16 30/May/16 02/Jun/16
CON4410 Battery Rack (1) Installation 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON4590 Battery MCCB Box Installation 2 0% 08/May/16 10/May/16 01/Jun/16 02/Jun/16 01/Jun/16 02/Jun/16
CON4520 Battery Rack (2) Installation 2 0% 09/May/16 10/May/16 02/Jun/16 04/Jun/16 02/Jun/16 04/Jun/16
CON5610 Acid Filling 3 0% 23/May/16 25/May/16 16/Jul/16 18/Jul/16 16/Jul/16 18/Jul/16
CON5720 Battery Cells Linking 2 0% 25/May/16 28/May/16 19/Jul/16 20/Jul/16 19/Jul/16 20/Jul/16
CON6940 Tool Cupboard Mounting 2 0% 25/Jun/16 27/Jun/16 17/Aug/16 20/Aug/16 17/Aug/16 20/Aug/16
AC / DC Cables Pulling
Pu & Termination 48 0% 10/May/16 09/Jul/16 02/Jun/16 23/Jul/16
CON3095 AC Cables Pulling from 400-230V ACDB to Chargers & Termination 5 0% 10/May/16 15/May/16 02/Jun/16 07/Jun/16 02/Jun/16 07/Jun/16
CON3105 DC Cables Pulling From Chargers to Battery MCCB Box & Termination 3 0% 10/May/16 12/May/16 02/Jun/16 06/Jun/16 02/Jun/16 06/Jun/16
CON6430 DC Cables Pulling from Chargers to 125V DCDBs & Termination 4 0% 14/May/16 17/May/16 07/Jun/16 11/Jun/16 07/Jun/16 11/Jun/16
CON6440 DC Cables Pulling from 125V DCDB to 230KV GIS LCC & Termination 10 0% 14/May/16 23/May/16 07/Jun/16 16/Jun/16 07/Jun/16 16/Jun/16
CON6460 DC Cables Pulling from 125V DCDB to Protection Panels & Termination 15 0% 23/May/16 06/Jun/16 16/Jun/16 30/Jun/16 16/Jun/16 30/Jun/16
CON6490 DC Cables Pulling from 125V DCDB to PSA & IntefacePanels & Termination 2 0% 23/May/16 25/May/16 16/Jun/16 19/Jun/16 16/Jun/16 19/Jun/16
CON6650 AC Cables Pulling from 400-230V ACDB to Dry Type Transformers & Termination 3 0% 23/May/16 26/May/16 16/Jun/16 19/Jun/16 16/Jun/16 19/Jun/16
CON6680 AC Cables Pulling from 400-230V ACDB to Lighting Panel & Termination 7 0% 04/Jun/16 11/Jun/16 16/Jun/16 23/Jun/16 16/Jun/16 23/Jun/16
CON6670 AC Cables Pulling from 400-230V ACDB to Comm. Power Panel & Termination 3 0% 25/May/16 28/May/16 19/Jun/16 21/Jun/16 19/Jun/16 21/Jun/16
CON6660 AC Cables Pulling from Dry Type Transformer to Comm. Power Supply Inverter & Terminati 3 0% 06/Jun/16 09/Jun/16 30/Jun/16 09/Jul/16 30/Jun/16 09/Jul/16
CON61010 DC Supplied to All Relay & Control System 0 0% 09/Jun/16 09/Jul/16 DC Supplied to All Relay & Co
CON6690 DC Cables Pulling from 125V DCDB to Emergency Lighting Panel & Termination 7 0% 27/Jun/16 09/Jul/16 16/Jul/16 21/Jul/16 16/Jul/16 21/Jul/16
CON5730 DC Cables Pulling from MCCB Box to Battery & Termination 3 0% 28/May/16 30/May/16 20/Jul/16 23/Jul/16 20/Jul/16 23/Jul/16
CON69080 AC/DC Completed 0 0% 09/Jul/16 23/Jul/16 AC/DC Completed

Page 7 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
SS #4 Electromechanical
Electromecha 144 0.69% 31/Jan/16 25/Jul/16 31/Jan/16 A 13/Aug/16
S/S #4-GIS Room- O
Overhead Crane Installation & Commissioning 72 0.58% 13/Feb/16 08/May/16 13/Feb/16 A 01/Jun/16
CON4630 Runway Girder Beam Erection 9 5% 13/Feb/16 21/Feb/16 13/Feb/16 A 03/Apr/16 13/Feb/16 A 03/Apr/16
CON5550 Crane Rails Tack Welding. 4 0% 21/Feb/16 24/Feb/16 03/Apr/16 07/Apr/16 03/Apr/16 07/Apr/16
CON5560 Inspection of Rail Alignment 2 0% 22/Feb/16 24/Feb/16 05/Apr/16 07/Apr/16 05/Apr/16 07/Apr/16
CON6620 Loading of Crane Bridge & Carriage on Track 2 0% 21/Feb/16 22/Feb/16 07/Apr/16 09/Apr/16 07/Apr/16 09/Apr/16
CON5565 Crane Rails Welding 11 0% 24/Feb/16 06/Mar/16 07/Apr/16 17/Apr/16 07/Apr/16 17/Apr/16
CON6610 Inspection of Rails Welding 1 0% 07/Mar/16 07/Mar/16 18/Apr/16 19/Apr/16 18/Apr/16 19/Apr/16
CON6700 Installation of Busbar 3 0% 24/Apr/16 26/Apr/16 18/May/16 21/May/16 18/May/16 21/May/16
CON6710 Overhead Crane Isolator Installation 2 0% 27/Apr/16 28/Apr/16 21/May/16 23/May/16 21/May/16 23/May/16
CON6720 Temp. Power Supply Cables Pulling & Termination 3 0% 28/Apr/16 01/May/16 23/May/16 25/May/16 23/May/16 25/May/16
CON6730 Availability of Crane Pre-commissioning Supervisor (Vendor) 0 0% 02/May/16 25/May/16 Availability of Crane Pre-commiss
CON6740 General Checks & Limit Switches Installation 3 0% 02/May/16 04/May/16 25/May/16 29/May/16 25/May/16 29/May/16
CON6750 Pre-commissioning of Crane & Elec. & Mech.Components Check 2 0% 04/May/16 05/May/16 29/May/16 30/May/16 29/May/16 30/May/16
CON6760 Inspection & Testing of Crane Moves 1 0% 07/May/16 07/May/16 30/May/16 31/May/16 30/May/16 31/May/16
CON6770 Crane Loading Test 1 0% 07/May/16 08/May/16 31/May/16 01/Jun/16 31/May/16 01/Jun/16
CON6780 Crane Readiness for Operation 0 0% 08/May/16 01/Jun/16 Crane Readiness for Operation
S/S #4-Cable Ladder
Ladde / Trays 78 0% 17/Mar/16 29/May/16 11/Apr/16 22/Jun/16
CON6790 Marking @ Cable Vault 7 0% 17/Mar/16 24/Mar/16 11/Apr/16 17/Apr/16 11/Apr/16 17/Apr/16
CON6800 Installation of Cable Tray Supports @ Cable Vault 21 0% 24/Mar/16 12/Apr/16 18/Apr/16 07/May/16 18/Apr/16 07/May/16
CON6810 Installation of Cable Trays / Ladders @ Cable Vault 21 0% 26/Mar/16 14/Apr/16 19/Apr/16 09/May/16 19/Apr/16 09/May/16
CON6820 Marking @ GIS Room 4 0% 28/Apr/16 02/May/16 23/May/16 26/May/16 23/May/16 26/May/16
CON6830 Installation of Cable Tray Supports @ GIS Room 7 0% 02/May/16 09/May/16 26/May/16 02/Jun/16 26/May/16 02/Jun/16
CON6850 Marking @ Communication Room 4 0% 02/May/16 05/May/16 26/May/16 30/May/16 26/May/16 30/May/16
CON6880 Marking @ Mechanical Room 4 0% 07/May/16 10/May/16 30/May/16 02/Jun/16 30/May/16 02/Jun/16
CON6840 Installation of Cable Trays / Ladders @ GIS Room 7 0% 09/May/16 15/May/16 02/Jun/16 08/Jun/16 02/Jun/16 08/Jun/16
CON6890 Installation of Cable Tray Supports @ Mechanical Room 7 0% 10/May/16 16/May/16 02/Jun/16 09/Jun/16 02/Jun/16 09/Jun/16
CON6900 Installation of Cable Trays / Ladders @ Mechanical Room 7 0% 16/May/16 22/May/16 08/Jun/16 15/Jun/16 08/Jun/16 15/Jun/16
CON6860 Installation of Cable Tray Supports @ Communication Room 7 0% 16/May/16 23/May/16 09/Jun/16 16/Jun/16 09/Jun/16 16/Jun/16
CON6870 Installation of Cable Trays / Ladders @ Communication Room 7 0% 23/May/16 29/May/16 16/Jun/16 22/Jun/16 16/Jun/16 22/Jun/16
S/S #4 HVAC System (Sub-contracted) 125 0% 28/Mar/16 14/Jul/16 13/Apr/16 13/Aug/16
SS #4 HVAC Duct W Work 96 0% 28/Mar/16 17/Jun/16 13/Apr/16 17/Jul/16
SS #4 HVAC Duct Works Switchgear Level 53 0% 28/Apr/16 17/Jun/16 23/May/16 17/Jul/16
SS #4 Supply Air Duct Works Switchgear Level 40 0% 02/May/16 08/Jun/16 25/May/16 02/Jul/16
CON3115 Installation of Duct-1 Supports @ GIS Room 5 0% 02/May/16 05/May/16 25/May/16 30/May/16 25/May/16 30/May/16
CON3125 Main Supply Air Duct to GIS Room & T Connection Installation 5 0% 05/May/16 10/May/16 29/May/16 02/Jun/16 29/May/16 02/Jun/16
CON7060 Installation of Duct-2 Supports @ GIS Room 5 0% 07/May/16 10/May/16 30/May/16 04/Jun/16 30/May/16 04/Jun/16
CON6960 Duct-1 Installation @ GIS Room 7 0% 10/May/16 16/May/16 02/Jun/16 09/Jun/16 02/Jun/16 09/Jun/16
CON7095 Installation of Ducts Supports @ Mechanical Room 3 0% 11/May/16 14/May/16 04/Jun/16 07/Jun/16 04/Jun/16 07/Jun/16
CON6970 Supply Air Duct Connection to Protection Room 3 0% 16/May/16 19/May/16 09/Jun/16 12/Jun/16 09/Jun/16 12/Jun/16
CON6980 Supply Air Duct Connection to Equipment Room 3 0% 16/May/16 19/May/16 09/Jun/16 12/Jun/16 09/Jun/16 12/Jun/16
CON7070 Duct-2 Installation @ GIS Room 7 0% 16/May/16 23/May/16 09/Jun/16 16/Jun/16 09/Jun/16 16/Jun/16
CON6990 MF/S Dampers Installation Duct-1 3 0% 19/May/16 22/May/16 12/Jun/16 15/Jun/16 12/Jun/16 15/Jun/16
CON7000 Volume Dampers Installation Duct-1 3 0% 19/May/16 22/May/16 12/Jun/16 15/Jun/16 12/Jun/16 15/Jun/16
CON7080 MF/S Dampers Installation Duct-2 3 0% 23/May/16 25/May/16 16/Jun/16 19/Jun/16 16/Jun/16 19/Jun/16
CON7090 Volume Dampers Installation Duct-2 3 0% 23/May/16 25/May/16 16/Jun/16 19/Jun/16 16/Jun/16 19/Jun/16
CON7100 Supply Air Duct @ Mechanical Room 5 0% 23/May/16 28/May/16 16/Jun/16 21/Jun/16 16/Jun/16 21/Jun/16
CON7110 Supply Air Main Duct Connection to AHU-1 & AHU-2 5 0% 28/May/16 01/Jun/16 21/Jun/16 26/Jun/16 21/Jun/16 26/Jun/16
CON7120 MVD 1&2 Installation on Main Supply Air 4 0% 01/Jun/16 05/Jun/16 26/Jun/16 29/Jun/16 26/Jun/16 29/Jun/16
CON7122 Air Outlets Installation 3 0% 05/Jun/16 08/Jun/16 29/Jun/16 02/Jul/16 29/Jun/16 02/Jul/16
SS #4 Return & Fresh
F Air Duct Works Switchgear Level 53 0% 28/Apr/16 17/Jun/16 23/May/16 17/Jul/16

Page 8 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON7030 Return Air Ducts @ Protection Room 3 0% 28/Apr/16 01/May/16 23/May/16 25/May/16 23/May/16 25/May/16
CON7040 Return Air Ducts @ Equipment Room 3 0% 28/Apr/16 01/May/16 23/May/16 25/May/16 23/May/16 25/May/16
CON7130 Return Air Bell Mouth @ GIS Room 3 0% 28/Apr/16 01/May/16 23/May/16 25/May/16 23/May/16 25/May/16
CON7042 Return Air Ducts to Mechanical Room 5 0% 02/May/16 05/May/16 25/May/16 30/May/16 25/May/16 30/May/16
CON7135 MF/S Dampers Installation on Return Ducts 3 0% 25/May/16 29/May/16 19/Jun/16 21/Jun/16 19/Jun/16 21/Jun/16
CON7140 Return Air Main Duct Connection to AHU-1 & AHU-2 3 0% 28/May/16 30/May/16 21/Jun/16 23/Jun/16 21/Jun/16 23/Jun/16
CON7150 Volume Dampers 1&2 Installation 3 0% 30/May/16 02/Jun/16 23/Jun/16 26/Jun/16 23/Jun/16 26/Jun/16
CON7160 Fresh Air Connection to Outside 3 0% 02/Jun/16 05/Jun/16 26/Jun/16 29/Jun/16 26/Jun/16 29/Jun/16
CON7165 Motorized Volume Damper Installation 3 0% 05/Jun/16 08/Jun/16 29/Jun/16 02/Jul/16 29/Jun/16 02/Jul/16
CON7170 LEL Detector Installation 3 0% 08/Jun/16 11/Jun/16 02/Jul/16 11/Jul/16 02/Jul/16 11/Jul/16
CON7180 H2S Scrubber Installation 3 0% 11/Jun/16 13/Jun/16 11/Jul/16 13/Jul/16 11/Jul/16 13/Jul/16
CON7200 Fresh Air Inlet Bell Mouth w/Bird Screen Installation 4 0% 13/Jun/16 17/Jun/16 13/Jul/16 17/Jul/16 13/Jul/16 17/Jul/16
SS #4 HVAC Duct Works Cable Vault Level 95 0% 28/Mar/16 23/May/16 13/Apr/16 16/Jul/16
SS #4 Supply Air Duct Works Cable Vault Level 95 0% 28/Mar/16 23/May/16 13/Apr/16 16/Jul/16
CON3135 Installation of Supply Duct Supports @ Cable Vault 3 0% 28/Mar/16 30/Mar/16 13/Apr/16 16/Apr/16 13/Apr/16 16/Apr/16
CON3145 Main Supply Air Duct Installation 6 0% 30/Mar/16 05/Apr/16 16/Apr/16 21/Apr/16 16/Apr/16 21/Apr/16
CON7050 Duct Connection to Communication Room 3 0% 05/Apr/16 07/Apr/16 21/Apr/16 24/Apr/16 21/Apr/16 24/Apr/16
CON7330 Duct Connection to Battery Room 3 0% 05/Apr/16 07/Apr/16 21/Apr/16 24/Apr/16 21/Apr/16 24/Apr/16
CON7340 VD & AD Installation 3 0% 11/Apr/16 13/Apr/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
CON7350 MF/S Dampers Installation @ Communication Room 3 0% 11/Apr/16 13/Apr/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
CON7360 MF/S Dampers Installation @ Battery Room 3 0% 11/Apr/16 13/Apr/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
CON7105 Electrical Heater & Humidifier / Atomizer Installation 3 0% 13/Apr/16 16/Apr/16 06/Jun/16 08/Jun/16 06/Jun/16 08/Jun/16
CON7370 Installation of Split Handling Unit & Duct @ Air Lock 3 0% 17/May/16 19/May/16 10/Jul/16 13/Jul/16 10/Jul/16 13/Jul/16
CON7380 MF/S Dampers Installation on Air Lock Duct 3 0% 21/May/16 23/May/16 13/Jul/16 16/Jul/16 13/Jul/16 16/Jul/16
SS #4 Return Duct
Du Works Cable Vault Level 95 0% 28/Mar/16 23/May/16 13/Apr/16 16/Jul/16
CON7155 Installation of Return Duct Supports @ Cable Vault 3 0% 28/Mar/16 30/Mar/16 13/Apr/16 16/Apr/16 13/Apr/16 16/Apr/16
CON7195 Installation of Return Air Ducts @ Cable Vault 3 0% 30/Mar/16 03/Apr/16 16/Apr/16 18/Apr/16 16/Apr/16 18/Apr/16
CON7205 Return Air Ducts @ Communication Room 3 0% 02/May/16 04/May/16 25/May/16 29/May/16 25/May/16 29/May/16
CON7440 AD Installation on Return Duct @ Communication Room 3 0% 04/May/16 07/May/16 29/May/16 31/May/16 29/May/16 31/May/16
CON7460 Duct Risers Installation @ Mechanical Room 3 0% 07/May/16 10/May/16 31/May/16 02/Jun/16 31/May/16 02/Jun/16
CON7462 Air Duct Outlets Installation 3 0% 07/May/16 10/May/16 31/May/16 02/Jun/16 31/May/16 02/Jun/16
CON7450 Exhaust Fans Installation @ Battery Room 3 0% 21/May/16 23/May/16 13/Jul/16 16/Jul/16 13/Jul/16 16/Jul/16
SS #4 AHUs & ACCUs
ACC Installation 38 0% 27/Apr/16 30/May/16 06/Jun/16 17/Jul/16
CON7175 AHU-1 & 2 Mounting & Alighnement on Foundation @ Mechanical Room 10 0% 28/Apr/16 08/May/16 06/Jun/16 15/Jun/16 06/Jun/16 15/Jun/16
CON7190 Flixible Joints Installation and Connection to Supply & Return Ducts 6 0% 08/May/16 14/May/16 15/Jun/16 20/Jun/16 15/Jun/16 20/Jun/16
CON7210 ACCU-1 & 2 Installation on Outdoor Foundation & Alighnment 6 0% 27/Apr/16 03/May/16 20/Jun/16 25/Jun/16 20/Jun/16 25/Jun/16
CON7220 Connection Pipes to AHU-1 & 2 Installation 7 0% 08/May/16 15/May/16 25/Jun/16 02/Jul/16 25/Jun/16 02/Jul/16
CON7230 Drain Pipes Installation 6 0% 15/May/16 19/May/16 02/Jul/16 13/Jul/16 02/Jul/16 13/Jul/16
CON7240 Gas Filling 4 0% 15/May/16 18/May/16 02/Jul/16 11/Jul/16 02/Jul/16 11/Jul/16
CON7300 Main Compressors Check 4 0% 18/May/16 22/May/16 11/Jul/16 14/Jul/16 11/Jul/16 14/Jul/16
CON7390 Split Compressor Unit Installation w/ Hose Pipes to Air Lock & w/Power Supply 4 0% 21/May/16 24/May/16 13/Jul/16 17/Jul/16 13/Jul/16 17/Jul/16
CON7310 Min. Requi. of HVAC System for Temp. Operation 0 0% 30/May/16 14/Jul/16 Min. Requi. of HVAC System
SS #4 Devices & Power
P Supply 67 0% 07/May/16 14/Jul/16 06/Jun/16 13/Aug/16
CON7185 HVAC Control Panel Installation 3 0% 07/May/16 09/May/16 06/Jun/16 08/Jun/16 06/Jun/16 08/Jun/16
CON7280 AC Power Supply 3 0% 22/May/16 24/May/16 25/Jun/16 28/Jun/16 25/Jun/16 28/Jun/16
CON7290 HVAC Isolator Disconnect Switches Installation & Wiring 3 0% 25/May/16 28/May/16 28/Jun/16 30/Jun/16 28/Jun/16 30/Jun/16
CON7250 Instruments & Actuators Installation 10 0% 11/Jun/16 20/Jun/16 16/Jul/16 25/Jul/16 16/Jul/16 25/Jul/16
CON7260 Cables / Wires Pulling & Termination ( Devices Side ) 20 0% 20/Jun/16 14/Jul/16 25/Jul/16 13/Aug/16 25/Jul/16 13/Aug/16
CON7270 Cables / Wires Pulling & Termination ( Control Panel Side ) 20 0% 20/Jun/16 14/Jul/16 25/Jul/16 13/Aug/16 25/Jul/16 13/Aug/16
CON7320 HVAC System Ready for Testing 0 0% 14/Jul/16 13/Aug/16 HVAC System Ready for T
S/S #4-Fire Detection
Detectio & Alarm System (Sub-contracted) 123 0% 28/Mar/16 18/Jul/16 13/Apr/16 11/Aug/16

Page 9 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
S/S #4-Fire Detection
Detecti / Alarm Conduit Works 54 0% 28/Mar/16 09/May/16 13/Apr/16 02/Jun/16
CON7430 FA Conduits Installation @ Cable Vault 6 0% 28/Mar/16 03/Apr/16 13/Apr/16 18/Apr/16 13/Apr/16 18/Apr/16
CON7470 FA Conduits Installation @ Mechanical Room 4 0% 03/Apr/16 06/Apr/16 18/Apr/16 21/Apr/16 18/Apr/16 21/Apr/16
CON7480 FA Conduits Installation @ Battery Room 4 0% 06/Apr/16 10/Apr/16 23/Apr/16 26/Apr/16 23/Apr/16 26/Apr/16
CON7490 FA Conduits Installation @ Communication Room 4 0% 10/Apr/16 13/Apr/16 26/Apr/16 30/Apr/16 26/Apr/16 30/Apr/16
CON7400 FA Conduits Installation @ 230KV GIS Room 5 0% 28/Apr/16 03/May/16 23/May/16 28/May/16 23/May/16 28/May/16
CON7500 FA Conduits Installation @ S/S #4 External Walls 3 0% 28/Apr/16 01/May/16 23/May/16 25/May/16 23/May/16 25/May/16
CON7410 FA Conduits Installation @ Protection Room 3 0% 03/May/16 05/May/16 28/May/16 30/May/16 28/May/16 30/May/16
CON7420 FA Conduits Installation @ Equipment Room 3 0% 07/May/16 09/May/16 30/May/16 02/Jun/16 30/May/16 02/Jun/16
CON61270 Completion of Internal FA Conduits Installation 0 0% 09/May/16 02/Jun/16 Completion of Internal FA Condu
S/S #4-Fire Detection
Detecti / Alarm Wire Loops & Curcuits 33 0% 02/May/16 01/Jun/16 25/May/16 26/Jun/16
S/S #4-Fire Detec
Detection / Alarm Wire Pulling Loop-1 17 0% 09/May/16 24/May/16 02/Jun/16 18/Jun/16
CON7510 Beam Transmittal & Receivers Wires Pulling to LIM @ 230KV GIS Room 1 0% 09/May/16 10/May/16 02/Jun/16 02/Jun/16 02/Jun/16 02/Jun/16
CON7590 Manual Pull Stations Wire Pulling to LIM @ 230KV GIS Room 1 0% 10/May/16 10/May/16 02/Jun/16 04/Jun/16 02/Jun/16 04/Jun/16
CON7595 Smoke Detectors Wires Pulling to LIM @ Protection Room 1 0% 11/May/16 11/May/16 04/Jun/16 05/Jun/16 04/Jun/16 05/Jun/16
CON7605 Manual Pull Stations Wire Pulling to LIM @ Protection Room 1 0% 11/May/16 12/May/16 05/Jun/16 06/Jun/16 05/Jun/16 06/Jun/16
CON7607 Smoke Detectors Wires Pulling to LIM in PSA Cabinet @ Protection Room 1 0% 12/May/16 14/May/16 06/Jun/16 07/Jun/16 06/Jun/16 07/Jun/16
CON7615 Smoke Detectors Wires Pulling to LIM @ Equipment Room 1 0% 14/May/16 15/May/16 07/Jun/16 07/Jun/16 07/Jun/16 07/Jun/16
CON7625 Manual Pull Stations Wire Pulling to LIM @ Equipment Room 1 0% 15/May/16 15/May/16 07/Jun/16 08/Jun/16 07/Jun/16 08/Jun/16
CON7627 Smoke Detectors Wires Pulling to LIM @ Cable Vault 1 0% 16/May/16 16/May/16 08/Jun/16 09/Jun/16 08/Jun/16 09/Jun/16
CON7629 Manual Pull Stations Wire Pulling to LIM @ Cable Vault 1 0% 16/May/16 17/May/16 09/Jun/16 11/Jun/16 09/Jun/16 11/Jun/16
CON7635 Smoke & Flame Detectors Wires Pulling to LIM @ Mechanical Room 1 0% 17/May/16 18/May/16 11/Jun/16 12/Jun/16 11/Jun/16 12/Jun/16
CON7645 Manual Pull Stations Wire Pulling to LIM @ Mechanical Room 1 0% 18/May/16 19/May/16 12/Jun/16 12/Jun/16 12/Jun/16 12/Jun/16
CON7655 In HVAC Duct Smoke Detectors Wires Pulling to LIM @ Mechanical Room 1 0% 19/May/16 19/May/16 12/Jun/16 13/Jun/16 12/Jun/16 13/Jun/16
CON7665 Smoke Detectors Wires Pulling to LIM @ Battery Room 1 0% 19/May/16 19/May/16 12/Jun/16 13/Jun/16 12/Jun/16 13/Jun/16
CON7675 Manual Pull Stations Wire Pulling to LIM @ Battery Room 1 0% 21/May/16 21/May/16 13/Jun/16 14/Jun/16 13/Jun/16 14/Jun/16
CON7685 Smoke Detectors Wires Pulling to LIM @ Communication Room 1 0% 21/May/16 22/May/16 14/Jun/16 15/Jun/16 14/Jun/16 15/Jun/16
CON7695 Manual Pull Stations Wire Pulling to LIM @ Communication Room 1 0% 22/May/16 23/May/16 15/Jun/16 16/Jun/16 15/Jun/16 16/Jun/16
CON7705 Smoke Detectors Wires Pulling to LIM @ Air Lock Room 1 0% 23/May/16 24/May/16 16/Jun/16 16/Jun/16 16/Jun/16 16/Jun/16
CON7715 Manual Pull Stations Wire Pulling to LIM @ Air Lock Room 1 0% 24/May/16 24/May/16 16/Jun/16 18/Jun/16 16/Jun/16 18/Jun/16
S/S #4-Fire Detec
Detection / Alarm Notification Appliance Wire Pulling Curcuit-1 8 0% 25/May/16 01/Jun/16 18/Jun/16 26/Jun/16
CON7520 Wires Pulling from Control Panel to FA Bell @ 230KV GIS Room 1 0% 25/May/16 25/May/16 18/Jun/16 19/Jun/16 18/Jun/16 19/Jun/16
CON7617 Wires Pulling from Control Panel to FA Bell @ Protection Room 1 0% 25/May/16 26/May/16 19/Jun/16 20/Jun/16 19/Jun/16 20/Jun/16
CON7765 Wires Pulling from Control Panel to FA Bell @ Equipment Room 1 0% 26/May/16 28/May/16 20/Jun/16 21/Jun/16 20/Jun/16 21/Jun/16
CON7767 Wires Pulling from Control Panel to FA Bell @ Cable Vault 1 0% 28/May/16 29/May/16 21/Jun/16 21/Jun/16 21/Jun/16 21/Jun/16
CON7785 Wires Pulling from Control Panel to FA Bell @ Mechanical Room 1 0% 29/May/16 29/May/16 21/Jun/16 22/Jun/16 21/Jun/16 22/Jun/16
CON7815 Wires Pulling from Control Panel to FA Bell @ Battery Room 1 0% 30/May/16 30/May/16 22/Jun/16 23/Jun/16 22/Jun/16 23/Jun/16
CON7835 Wires Pulling from Control Panel to FA Bell @ Communication Room 1 0% 30/May/16 31/May/16 23/Jun/16 25/Jun/16 23/Jun/16 25/Jun/16
CON7855 Wires Pulling from Control Panel to FA Bell @ Air Lock Room 1 0% 31/May/16 01/Jun/16 25/Jun/16 26/Jun/16 25/Jun/16 26/Jun/16
CON61280 FA Wires Pulling Completion 0 0% 01/Jun/16 26/Jun/16 FA Wires Pulling Completion
S/S #4-Fire Detec
Detection / Alarm Notification Appliance Wire Pulling Curcuit-2 32 0% 02/May/16 31/May/16 25/May/16 25/Jun/16
CON7775 Wire Pulling from Control Panel to Horn, Beacon & Flashing Lights Strobes @ 3rd Bldg Side 3 0% 02/May/16 04/May/16 25/May/16 29/May/16 25/May/16 29/May/16
CON7637 Wire Pulling from Control Panel to Horn, Beacon & Flashing Lights Strobes @ 2nd Bldg Side 3 0% 02/May/16 04/May/16 25/May/16 29/May/16 25/May/16 29/May/16
CON7777 Wire Pulling from Control Panel to Horn, Beacon & Flashing Lights Strobes @ 4th Bldg Side 3 0% 02/May/16 04/May/16 25/May/16 29/May/16 25/May/16 29/May/16
CON7600 Wire Pulling from Control Panel to Horn, Beacon & Flashing Lights Strobes @ 1st Bldg Side 3 0% 29/May/16 31/May/16 21/Jun/16 25/Jun/16 21/Jun/16 25/Jun/16
S/S #4-Fire Detection
Detecti / Alarm Control Panel & Appliance Installation 123 0% 28/Mar/16 18/Jul/16 13/Apr/16 11/Aug/16
CON7647 LIM Installation @ Cable Vault 2 0% 28/Mar/16 29/Mar/16 13/Apr/16 14/Apr/16 13/Apr/16 14/Apr/16
CON7610 LIM Installation @ Equipment Room 2 0% 28/Apr/16 01/May/16 23/May/16 24/May/16 23/May/16 24/May/16
CON4210 Fire Alarm Control Panel Installation 2 0% 07/May/16 08/May/16 30/May/16 01/Jun/16 30/May/16 01/Jun/16
CON7725 Wire Pulling from LIM to FA Control Panel @ SWGR Level 5 0% 09/May/16 14/May/16 02/Jun/16 07/Jun/16 02/Jun/16 07/Jun/16
CON7735 Wire Pulling from LIM to FA Control Panel @ Cable Vault Level 5 0% 14/May/16 18/May/16 07/Jun/16 12/Jun/16 07/Jun/16 12/Jun/16

Page 10 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON7795 Wires Termination Of LIM @ Cable Vault 20 0% 01/Jun/16 20/Jun/16 26/Jun/16 20/Jul/16 26/Jun/16 20/Jul/16
CON7787 Wires Termination Of LIM @ Equipment Room 20 0% 01/Jun/16 20/Jun/16 26/Jun/16 20/Jul/16 26/Jun/16 20/Jul/16
CON7805 Wires Termination Of Control Panel @ Equipment Room 20 0% 20/Jun/16 14/Jul/16 20/Jul/16 08/Aug/16 20/Jul/16 08/Aug/16
CON7825 Installation & Termination of All Appliance @ GIS Level 4 0% 14/Jul/16 18/Jul/16 08/Aug/16 11/Aug/16 08/Aug/16 11/Aug/16
CON7845 Installation & Termination of All Appliance @ Cable Vault Level 4 0% 14/Jul/16 18/Jul/16 08/Aug/16 11/Aug/16 08/Aug/16 11/Aug/16
CON7865 Ready for Testing 0 0% 18/Jul/16 11/Aug/16 Ready for Testing
Hand Extinguishers 4 0% 12/Jul/16 16/Jul/16 06/Aug/16 09/Aug/16
CON7797 Installation of Extinguisher Brackets 2 0% 12/Jul/16 14/Jul/16 06/Aug/16 08/Aug/16 06/Aug/16 08/Aug/16
CON7875 Delivery & Mounting of Extinguishers 2 0% 14/Jul/16 16/Jul/16 08/Aug/16 09/Aug/16 08/Aug/16 09/Aug/16
S/S #4-Lighting 84 0% 28/Apr/16 25/Jul/16 16/May/16 08/Aug/16
S/S #4 Lighting & Small
S Power System Conduit Works 26 0% 28/Apr/16 26/May/16 16/May/16 08/Jun/16
CON7700 Lighting & Sockets Conduits Installation @ Cable Vault 10 0% 07/May/16 15/May/16 16/May/16 24/May/16 16/May/16 24/May/16
CON7670 Lighting & Sockets Conduits Installation @ 230KV GIS Room 10 0% 28/Apr/16 08/May/16 23/May/16 01/Jun/16 23/May/16 01/Jun/16
CON7740 Lighting & Sockets Conduits Installation @ S/S #4 External Walls 4 0% 28/Apr/16 02/May/16 23/May/16 26/May/16 23/May/16 26/May/16
CON7710 Lighting & Sockets Conduits Installation @ Mechanical Room 4 0% 16/May/16 19/May/16 25/May/16 29/May/16 25/May/16 29/May/16
CON7720 Lighting & Sockets Conduits Installation @ Battery Room 4 0% 19/May/16 23/May/16 29/May/16 01/Jun/16 29/May/16 01/Jun/16
CON7680 Lighting & Sockets Conduits Installation @ Protection Room 4 0% 08/May/16 11/May/16 01/Jun/16 05/Jun/16 01/Jun/16 05/Jun/16
CON7730 Lighting & Sockets Conduits Installation @ Communication Room 4 0% 23/May/16 26/May/16 01/Jun/16 05/Jun/16 01/Jun/16 05/Jun/16
CON7690 Lighting & Sockets Conduits Installation @ Equipment Room 4 0% 11/May/16 15/May/16 05/Jun/16 08/Jun/16 05/Jun/16 08/Jun/16
CON61290 Completion of Lighting Conduits Installation 0 0% 26/May/16 08/Jun/16 Completion of Lighting Conduits
S/S #4 Lighting & Small
S Power System Wires Pulling & Termination 52 0% 02/May/16 01/Jul/16 26/May/16 20/Jul/16
S/S #4 AC Lighting & Small Power System Wires Pulling & Termination Works 28 0% 02/May/16 08/Jun/16 26/May/16 21/Jun/16
CON7820 AC Lighting Wires Pulling & Termination @ S/S #4 External Walls 10 0% 02/May/16 11/May/16 26/May/16 05/Jun/16 26/May/16 05/Jun/16
CON7750 AC Lighting Wires Pulling & Termination @ 230KV GIS Room 5 0% 26/May/16 31/May/16 08/Jun/16 13/Jun/16 08/Jun/16 13/Jun/16
CON7780 AC Lighting Wires Pulling & Termination @ Cable Vault 5 0% 26/May/16 31/May/16 08/Jun/16 13/Jun/16 08/Jun/16 13/Jun/16
CON7760 AC Lighting Wires Pulling & Termination @ Protection Room 3 0% 31/May/16 02/Jun/16 13/Jun/16 16/Jun/16 13/Jun/16 16/Jun/16
CON7790 AC Lighting Wires Pulling & Termination @ Mechanical Room 3 0% 31/May/16 02/Jun/16 13/Jun/16 16/Jun/16 13/Jun/16 16/Jun/16
CON7770 AC Lighting Wires Pulling & Termination @ Equipment Room 3 0% 04/Jun/16 06/Jun/16 16/Jun/16 19/Jun/16 16/Jun/16 19/Jun/16
CON7800 AC Lighting Wires Pulling & Termination @ Battery Room 3 0% 04/Jun/16 06/Jun/16 16/Jun/16 19/Jun/16 16/Jun/16 19/Jun/16
CON7810 AC Lighting Wires Pulling & Termination @ Communication Room 3 0% 06/Jun/16 08/Jun/16 19/Jun/16 21/Jun/16 19/Jun/16 21/Jun/16
S/S #4 DC Lighting & Small Power System Wires Pulling & Termination Work s 52 0% 02/May/16 01/Jul/16 26/May/16 20/Jul/16
CON7900 DC Emergency Lighting Wires Pulling & Termination @ S/S #4 External Walls 6 0% 02/May/16 08/May/16 26/May/16 01/Jun/16 26/May/16 01/Jun/16
CON7830 DC Emergency Lighting Wires Pulling & Termination @ 230KV GIS Room 6 0% 06/Jun/16 12/Jun/16 19/Jun/16 25/Jun/16 19/Jun/16 25/Jun/16
CON7860 DC Emergency Lighting Wires Pulling & Termination @ Cable Vault 6 0% 08/Jun/16 14/Jun/16 21/Jun/16 27/Jun/16 21/Jun/16 27/Jun/16
CON7840 DC Emergency Lighting Wires Pulling & Termination @ Protection Room 6 0% 12/Jun/16 17/Jun/16 25/Jun/16 30/Jun/16 25/Jun/16 30/Jun/16
CON7870 DC Emergency Lighting Wires Pulling & Termination @ Mechanical Room 6 0% 14/Jun/16 20/Jun/16 27/Jun/16 09/Jul/16 27/Jun/16 09/Jul/16
CON7850 DC Emergency Lighting Wires Pulling & Termination @ Equipment Room 6 0% 18/Jun/16 22/Jun/16 30/Jun/16 11/Jul/16 30/Jun/16 11/Jul/16
CON7880 DC Emergency Lighting Wires Pulling & Termination @ Battery Room 6 0% 20/Jun/16 26/Jun/16 09/Jul/16 14/Jul/16 09/Jul/16 14/Jul/16
CON7890 DC Emergency Lighting Wires Pulling & Termination @ Communication Room 6 0% 26/Jun/16 01/Jul/16 14/Jul/16 20/Jul/16 14/Jul/16 20/Jul/16
S/S #4 Lighting Fixtures
Fixt & Power Access Sockets Installation 62 0% 11/May/16 25/Jul/16 05/Jun/16 08/Aug/16
S/S #4 Lighting Fixtures
Fix 46 0% 11/May/16 11/Jul/16 05/Jun/16 24/Jul/16
CON7980 AC & DC Emergency Lighting Fixtures Installation @ S/S #4 External Walls 4 0% 11/May/16 15/May/16 05/Jun/16 08/Jun/16 05/Jun/16 08/Jun/16
CON7910 AC & DC Emergency Lighting Fixtures Installation @ 230KV GIS Room 4 0% 12/Jun/16 15/Jun/16 25/Jun/16 28/Jun/16 25/Jun/16 28/Jun/16
CON7940 AC & DC Emergency Lighting Fixtures Installation @ Cable Vault 4 0% 14/Jun/16 18/Jun/16 27/Jun/16 30/Jun/16 27/Jun/16 30/Jun/16
CON7920 AC & DC Emergency Lighting Fixtures Installation @ Protection Room 4 0% 18/Jun/16 21/Jun/16 30/Jun/16 10/Jul/16 30/Jun/16 10/Jul/16
CON7950 AC & DC Emergency Lighting Fixtures Installation @ Mechanical Room 4 0% 20/Jun/16 23/Jun/16 09/Jul/16 12/Jul/16 09/Jul/16 12/Jul/16
CON7930 AC & DC Emergency Lighting Fixtures Installation @ Equipment Room 4 0% 22/Jun/16 27/Jun/16 11/Jul/16 16/Jul/16 11/Jul/16 16/Jul/16
CON7960 AC & DC Emergency Lighting Fixtures Installation @ Battery Room 4 0% 26/Jun/16 29/Jun/16 14/Jul/16 18/Jul/16 14/Jul/16 18/Jul/16
CON7970 AC & DC Emergency Lighting Fixtures Installation @ Communication Room 4 0% 02/Jul/16 11/Jul/16 20/Jul/16 24/Jul/16 20/Jul/16 24/Jul/16
S/S #4 Power Acc
Access Sockects 58 0% 16/May/16 25/Jul/16 08/Jun/16 08/Aug/16
CON8060 Power Access SocketsInstallation @ S/S #4 External Walls 4 0% 16/May/16 19/May/16 08/Jun/16 12/Jun/16 08/Jun/16 12/Jun/16

Page 11 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON7990 Power Access SocketsInstallation @ 230KV GIS Room 4 0% 27/Jun/16 30/Jun/16 16/Jul/16 19/Jul/16 16/Jul/16 19/Jul/16
CON8000 Power Access SocketsInstallation @ Protection Room 4 0% 30/Jun/16 10/Jul/16 19/Jul/16 23/Jul/16 19/Jul/16 23/Jul/16
CON8010 Power Access SocketsInstallation @ Equipment Room 4 0% 10/Jul/16 13/Jul/16 23/Jul/16 26/Jul/16 23/Jul/16 26/Jul/16
CON8020 Power Access SocketsInstallation @ Cable Vault 4 0% 11/Jul/16 14/Jul/16 24/Jul/16 27/Jul/16 24/Jul/16 27/Jul/16
CON8030 Power Access SocketsInstallation @ Mechanical Room 4 0% 14/Jul/16 18/Jul/16 27/Jul/16 31/Jul/16 27/Jul/16 31/Jul/16
CON8040 Power Access SocketsInstallation @ Battery Room 4 0% 18/Jul/16 21/Jul/16 31/Jul/16 03/Aug/16 31/Jul/16 03/Aug/16
CON8050 Power Access SocketsInstallation @ Communication Room 4 0% 21/Jul/16 25/Jul/16 03/Aug/16 08/Aug/16 03/Aug/16 08/Aug/16
S/S #4-Grounding & Earthing Work 80 14.81% 31/Jan/16 29/Jun/16 31/Jan/16 A 28/Jul/16
S/S #4-Bare Copper
Coppe Burried Mesh 4 54.55% 31/Jan/16 29/Jun/16 31/Jan/16 A 28/Jul/16
CON7650 Grounding Grid Link Inside Building Installation 0 100% 31/Jan/16 04/Feb/16 31/Jan/16 A 05/Feb/16 A 31/Jan/16 A 05/Feb/16 A
CON7640 Bare Copper Grounding Conductor Link to Burried Mesh 4 0% 25/Jun/16 29/Jun/16 25/Jul/16 28/Jul/16 25/Jul/16 28/Jul/16
S/S #4-Equipments Grounding 80 0% 14/Apr/16 28/Jun/16 09/May/16 28/Jul/16
CON7560 Copper Bus and Grounding of Cable Trays @ Cable Vault 15 0% 14/Apr/16 28/Apr/16 09/May/16 23/May/16 09/May/16 23/May/16
CON7540 Grounding Protection & PSA Panels @ Protection Room 4 0% 11/May/16 15/May/16 05/Jun/16 08/Jun/16 05/Jun/16 08/Jun/16
CON7570 Grounding of Mechanical Equips & Cable Trays@ Mechanical Room 5 0% 22/May/16 26/May/16 20/Jun/16 25/Jun/16 20/Jun/16 25/Jun/16
CON7535 Grounding of 230KV LCC @ 230KV GIS Room 5 0% 28/May/16 01/Jun/16 21/Jun/16 26/Jun/16 21/Jun/16 26/Jun/16
CON7620 Grounding of Panels & Cable Trays @ Communication Room 3 0% 30/May/16 01/Jun/16 22/Jun/16 26/Jun/16 22/Jun/16 26/Jun/16
CON7530 Grounding of 230KV GIS @ 230KV GIS Room 10 0% 07/Jun/16 16/Jun/16 02/Jul/16 17/Jul/16 02/Jul/16 17/Jul/16
CON7580 Grounding of Battery Supports @ Battery Room 4 0% 28/May/16 31/May/16 20/Jul/16 24/Jul/16 20/Jul/16 24/Jul/16
CON7550 Grounding Panels @ Equipment Room 5 0% 23/Jun/16 28/Jun/16 24/Jul/16 28/Jul/16 24/Jul/16 28/Jul/16
CON61300 Minimum Grounding to Be Ready for HV Testing 0 0% 28/Jun/16 28/Jul/16 Minimum Grounding to Be R
SS #4 Testing & Pre-Commissioning
Pre- (Sub-contracted) 77 0% 28/May/16 10/Aug/16 19/Jun/16 05/Sep/16
S/S #4- 230 KV GIS Testing & Pre-commissioning 58 0% 28/May/16 27/Jul/16 21/Jun/16 20/Aug/16
S/S #4- 230 KV GIS Mechanical Testing & Pre-commissioning 31 0% 13/Jun/16 18/Jul/16 12/Jul/16 10/Aug/16
CON61370 Timing Test of CBs & DSs 8 0% 13/Jun/16 20/Jun/16 12/Jul/16 20/Jul/16 12/Jul/16 20/Jul/16
CON61410 SF6 Due Point Test 3 0% 12/Jul/16 14/Jul/16 06/Aug/16 08/Aug/16 06/Aug/16 08/Aug/16
CON61420 SF6 Percentage Test 3 0% 12/Jul/16 14/Jul/16 06/Aug/16 08/Aug/16 06/Aug/16 08/Aug/16
CON61430 Gas Leakage Test 3 0% 14/Jul/16 18/Jul/16 08/Aug/16 10/Aug/16 08/Aug/16 10/Aug/16
S/S #4- 230 KV GIS Electrical Testing & Pre-commissioning 58 0% 28/May/16 27/Jul/16 21/Jun/16 20/Aug/16
CON61630 Mobilization of Testing Sub-contractor 0 0% 28/May/16 21/Jun/16 Mobilization of Testing Sub-con
CON61320 MCB & Auxiliary Relays & Heaters Test 10 0% 29/May/16 07/Jun/16 22/Jun/16 02/Jul/16 22/Jun/16 02/Jul/16
CON61380 Motors Current Tests 8 0% 30/May/16 06/Jun/16 23/Jun/16 30/Jun/16 23/Jun/16 30/Jun/16
CON61390 CTs Test 8 0% 31/May/16 07/Jun/16 23/Jun/16 02/Jul/16 23/Jun/16 02/Jul/16
CON61340 LCC Metering Test 4 0% 07/Jun/16 11/Jun/16 02/Jul/16 11/Jul/16 02/Jul/16 11/Jul/16
CON61400 VTs Test 8 0% 11/Jun/16 18/Jun/16 10/Jul/16 18/Jul/16 10/Jul/16 18/Jul/16
CON61360 Guages Test 4 0% 11/Jun/16 15/Jun/16 11/Jul/16 14/Jul/16 11/Jul/16 14/Jul/16
CON61350 Annunciator Test 4 0% 11/Jun/16 15/Jun/16 11/Jul/16 14/Jul/16 11/Jul/16 14/Jul/16
CON61330 Contact Resistance Including CBs & BB 3 0% 14/Jul/16 18/Jul/16 08/Aug/16 10/Aug/16 08/Aug/16 10/Aug/16
CON61310 DS Insulation Tests ( Meggering ) 4 0% 18/Jul/16 21/Jul/16 10/Aug/16 15/Aug/16 10/Aug/16 15/Aug/16
CON61440 Earthing Switches Insulation Test 4 0% 18/Jul/16 21/Jul/16 10/Aug/16 15/Aug/16 10/Aug/16 15/Aug/16
CON61450 230KV GIS High Voltage Test 6 0% 21/Jul/16 27/Jul/16 15/Aug/16 20/Aug/16 15/Aug/16 20/Aug/16
S/S #4- 230 KV Protection
Prot Testing & Pre-commissioning 72 0% 28/May/16 08/Aug/16 21/Jun/16 01/Sep/16
S/S #4- 230 KV GIS Scheme & Function Check 20 0% 18/Jun/16 12/Jul/16 18/Jul/16 06/Aug/16
S/S #4- 230 KV GIS
GI Internal Scheme Check 18 0% 18/Jun/16 11/Jul/16 18/Jul/16 03/Aug/16
CON61770 Bay-1 Outgoing (706) Internal Scheme Check 2 0% 18/Jun/16 20/Jun/16 18/Jul/16 20/Jul/16 18/Jul/16 20/Jul/16
CON61780 Bay-2 Outgoing (707) Internal Scheme Check 2 0% 20/Jun/16 22/Jun/16 20/Jul/16 21/Jul/16 20/Jul/16 21/Jul/16
CON61790 Incommer (701) Internal Scheme Check 2 0% 22/Jun/16 23/Jun/16 21/Jul/16 24/Jul/16 21/Jul/16 24/Jul/16
CON61800 Bus Tie (703) Internal Scheme Check 2 0% 23/Jun/16 26/Jun/16 24/Jul/16 25/Jul/16 24/Jul/16 25/Jul/16
CON61810 Bus Coupler (705) Internal Scheme Check 2 0% 26/Jun/16 27/Jun/16 26/Jul/16 27/Jul/16 26/Jul/16 27/Jul/16
CON61820 Bus Tie (704) Internal Scheme Check 2 0% 27/Jun/16 29/Jun/16 27/Jul/16 30/Jul/16 27/Jul/16 30/Jul/16
CON61830 Bay-3 Outgoing (708) Internal Scheme Check 2 0% 29/Jun/16 01/Jul/16 30/Jul/16 31/Jul/16 30/Jul/16 31/Jul/16

Page 12 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON61850 Incommer (702) Internal Scheme Check 2 0% 02/Jul/16 09/Jul/16 31/Jul/16 02/Aug/16 31/Jul/16 02/Aug/16
CON61840 Bay-4 Outgoing (709) Internal Scheme Check 2 0% 09/Jul/16 11/Jul/16 02/Aug/16 03/Aug/16 02/Aug/16 03/Aug/16
S/S #4- 230 KV GI
GIS Operation & Function Test 18 0% 20/Jun/16 12/Jul/16 20/Jul/16 06/Aug/16
CON61860 Bay-1 Outgoing (706) Function Test 2 0% 20/Jun/16 22/Jun/16 20/Jul/16 21/Jul/16 20/Jul/16 21/Jul/16
CON61870 Bay-2 Outgoing (707) Function Test 2 0% 22/Jun/16 23/Jun/16 21/Jul/16 24/Jul/16 21/Jul/16 24/Jul/16
CON61880 Incommer (701) Function Test 2 0% 23/Jun/16 26/Jun/16 24/Jul/16 25/Jul/16 24/Jul/16 25/Jul/16
CON61890 Bus Tie (703) Function Test 2 0% 26/Jun/16 27/Jun/16 26/Jul/16 27/Jul/16 26/Jul/16 27/Jul/16
CON61900 Bus Coupler (705) Function Test 2 0% 27/Jun/16 29/Jun/16 27/Jul/16 30/Jul/16 27/Jul/16 30/Jul/16
CON61910 Bus Tie (704) Function Test 2 0% 29/Jun/16 01/Jul/16 30/Jul/16 31/Jul/16 30/Jul/16 31/Jul/16
CON61920 Bay-3 Outgoing (708) Function Test 2 0% 02/Jul/16 09/Jul/16 31/Jul/16 02/Aug/16 31/Jul/16 02/Aug/16
CON61940 Incommer (702) Function Test 2 0% 09/Jul/16 11/Jul/16 02/Aug/16 03/Aug/16 02/Aug/16 03/Aug/16
CON61930 Bay-4 Outgoing (709) Function Test 2 0% 11/Jul/16 12/Jul/16 04/Aug/16 06/Aug/16 04/Aug/16 06/Aug/16
S/S #4- 230 KV Auxiliary
Aux & Main Protection Relays Testing 44 0% 28/May/16 14/Jul/16 21/Jun/16 07/Aug/16
CON61490 Auxiliary Relays & MCBs Test 15 0% 28/May/16 11/Jun/16 21/Jun/16 11/Jul/16 21/Jun/16 11/Jul/16
CON61470 AVR Relay Acceptance Test 8 0% 28/May/16 05/Jun/16 21/Jun/16 28/Jun/16 21/Jun/16 28/Jun/16
CON1545 Distance / Line Diffrential Relays Acceptance Tests 8 0% 28/May/16 05/Jun/16 21/Jun/16 28/Jun/16 21/Jun/16 28/Jun/16
CON61480 Transformer Diffrential Relay Acceptance Test 8 0% 05/Jun/16 12/Jun/16 28/Jun/16 12/Jul/16 28/Jun/16 12/Jul/16
CON1585 HV & LV REF Relay Test 8 0% 05/Jun/16 12/Jun/16 28/Jun/16 12/Jul/16 28/Jun/16 12/Jul/16
CON61500 HV & LV Neutral O/C Protection Acceptance Test 8 0% 12/Jun/16 20/Jun/16 12/Jul/16 19/Jul/16 12/Jul/16 19/Jul/16
CON61510 O/C Relay Acceptance Test 8 0% 12/Jun/16 20/Jun/16 12/Jul/16 19/Jul/16 12/Jul/16 19/Jul/16
CON61520 Over Flux Acceptance Testing 6 0% 20/Jun/16 25/Jun/16 19/Jul/16 25/Jul/16 19/Jul/16 25/Jul/16
CON1615 BCUs Acceptance Test 5 0% 10/Jul/16 14/Jul/16 02/Aug/16 07/Aug/16 02/Aug/16 07/Aug/16
S/S #4- 230 KV Protection
Pro Relays Setting 56 0% 12/Jun/16 08/Aug/16 12/Jul/16 01/Sep/16
CON1645 Power Transformers Relays Final Settings 20 0% 12/Jun/16 30/Jun/16 12/Jul/16 31/Jul/16 12/Jul/16 31/Jul/16
CON61640 Availability of Line Parameters (by Others) 0 0% 18/Jul/16 11/Aug/16 Availability of Line Paramet
CON61650 Preparation of LP Relays Final Settings & Approval 13 0% 18/Jul/16 30/Jul/16 11/Aug/16 23/Aug/16 11/Aug/16 23/Aug/16
CON61570 LP Relays Final Settings Upload 10 0% 31/Jul/16 08/Aug/16 23/Aug/16 01/Sep/16 23/Aug/16 01/Sep/16
S/S #4- 230 KV Protection
Pro Scheme Check 46 0% 09/Jun/16 27/Jul/16 09/Jul/16 21/Aug/16
CON61670 CT Loop Ckeck 4 0% 11/Jul/16 14/Jul/16 04/Aug/16 08/Aug/16 04/Aug/16 08/Aug/16
CON61680 VT Loop Check 4 0% 14/Jul/16 18/Jul/16 08/Aug/16 11/Aug/16 08/Aug/16 11/Aug/16
S/S #4- 230 KV Pr
Protection Bus System-A Scheme Check 41 0% 09/Jun/16 23/Jul/16 09/Jul/16 16/Aug/16
CON61960 Line-1 Line Protection Set-I & II + CBF Scheme Check 2 0% 09/Jun/16 11/Jun/16 09/Jul/16 11/Jul/16 09/Jul/16 11/Jul/16
CON61950 Transformer (701) Set-I & II + CBF Scheme Check 2 0% 25/Jun/16 27/Jun/16 25/Jul/16 27/Jul/16 25/Jul/16 27/Jul/16
CON61970 Transformer (703) Set-I & II + CBF Scheme Check 2 0% 27/Jun/16 29/Jun/16 27/Jul/16 28/Jul/16 27/Jul/16 28/Jul/16
CON62010 Bus Section (703) CBF Scheme Check 2 0% 30/Jun/16 09/Jul/16 31/Jul/16 01/Aug/16 31/Jul/16 01/Aug/16
CON61990 Bus Coupler (705) CBF Scheme Check 2 0% 09/Jul/16 10/Jul/16 01/Aug/16 03/Aug/16 01/Aug/16 03/Aug/16
CON62000 Bus Section (704) CBF Scheme Check 2 0% 10/Jul/16 12/Jul/16 03/Aug/16 06/Aug/16 03/Aug/16 06/Aug/16
CON61550 BB Differential (System A) 5 0% 18/Jul/16 23/Jul/16 11/Aug/16 16/Aug/16 11/Aug/16 16/Aug/16
S/S #4- 230 KV Pr
Protection Bus System-B Scheme Check 17 0% 12/Jul/16 27/Jul/16 06/Aug/16 21/Aug/16
CON62020 Line-2 Line Protection Set-I & II + CBF Scheme Check 2 0% 12/Jul/16 14/Jul/16 06/Aug/16 07/Aug/16 06/Aug/16 07/Aug/16
CON62030 Transformer (702) Set-I & II + CBF Scheme Check 2 0% 14/Jul/16 16/Jul/16 07/Aug/16 09/Aug/16 07/Aug/16 09/Aug/16
CON62050 Transformer (704) Set-I & II + CBF Scheme Check 2 0% 16/Jul/16 18/Jul/16 09/Aug/16 10/Aug/16 09/Aug/16 10/Aug/16
CON62080 BB Differential (System B) 5 0% 23/Jul/16 27/Jul/16 16/Aug/16 21/Aug/16 16/Aug/16 21/Aug/16
S/S #4- 230 KV PSA System Testing 72 0% 31/May/16 07/Aug/16 19/Jun/16 31/Aug/16
CON62190 Hardware Start up Test 1 0% 31/May/16 01/Jun/16 19/Jun/16 20/Jun/16 19/Jun/16 20/Jun/16
CON62090 Line-1 Line Feeder Internal Closed Loop (Source to PSA @ SS#4) 2 0% 18/Jul/16 19/Jul/16 10/Aug/16 13/Aug/16 10/Aug/16 13/Aug/16
CON62100 Transformer (701) Feeder Internal Closed Loop (Source to PSA @ SS#4) 2 0% 19/Jul/16 21/Jul/16 13/Aug/16 15/Aug/16 13/Aug/16 15/Aug/16
CON62110 BB Diffrintial Relays Closed Loop (Source to PSA @ SS#4) 2 0% 27/Jul/16 30/Jul/16 21/Aug/16 22/Aug/16 21/Aug/16 22/Aug/16
CON62120 Transformer (702) Feeder Internal Closed Loop (Source to PSA @ SS#4) 2 0% 30/Jul/16 31/Jul/16 23/Aug/16 24/Aug/16 23/Aug/16 24/Aug/16
CON62160 Line-2 Feeder Internal Closed Loop (Source to PSA @ SS#4) 2 0% 31/Jul/16 02/Aug/16 24/Aug/16 27/Aug/16 24/Aug/16 27/Aug/16
CON62170 Transformer (704) Feeder Internal Closed Loop (Source to PSA @ SS#4) 2 0% 02/Aug/16 03/Aug/16 27/Aug/16 28/Aug/16 27/Aug/16 28/Aug/16

Page 13 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON62180 Transformer (703) Feeder Internal Closed Loop (Source to PSA @ SS#4) 2 0% 04/Aug/16 06/Aug/16 28/Aug/16 30/Aug/16 28/Aug/16 30/Aug/16
CON62200 HVAC & FA & Battery Chargers Signals Testing 1 0% 06/Aug/16 07/Aug/16 30/Aug/16 31/Aug/16 30/Aug/16 31/Aug/16
CON62210 SS #4 PSA System Ready for Integration w/ Existing Abu Ali Facility System 0 0% 07/Aug/16 31/Aug/16 SS #4 PSA System Read
S/S #4- Communication
Communica Testing 13 0% 11/Jun/16 23/Jun/16 11/Jul/16 24/Jul/16
CON62250 Communication Panels Check 2 0% 11/Jun/16 13/Jun/16 11/Jul/16 13/Jul/16 11/Jul/16 13/Jul/16
CON62270 CAT6 VoIP Interconnections Check 2 0% 18/Jun/16 20/Jun/16 14/Jul/16 16/Jul/16 14/Jul/16 16/Jul/16
CON62260 FO Cables Interconnections Check 4 0% 20/Jun/16 23/Jun/16 20/Jul/16 24/Jul/16 20/Jul/16 24/Jul/16
CON61050 S/S #4 Ready for Connecting Rack 1 with FOC ( Data & Voive and PSA) Going to DCO 0 0% 23/Jun/16 24/Jul/16 S/S #4 Ready for Connectin
CON62240 S/S #4 Communication Ready for Connecting Wasit for Line-1 & 2 Protection 0 0% 23/Jun/16 24/Jul/16 S/S #4 Communication Read
S/S #4- Auxiliaries Te
Testing & Pre-commissioning 33 0% 11/Jun/16 30/Jul/16 11/Jul/16 11/Aug/16
CON62330 AC Panels Acceptance & Check 2 0% 11/Jun/16 13/Jun/16 11/Jul/16 13/Jul/16 11/Jul/16 13/Jul/16
CON62280 DC Panels Acceptance & Check 2 0% 13/Jun/16 15/Jun/16 13/Jul/16 14/Jul/16 13/Jul/16 14/Jul/16
CON62340 AC Circuit Review & Check 4 0% 09/Jul/16 12/Jul/16 24/Jul/16 27/Jul/16 24/Jul/16 27/Jul/16
CON62290 DC Circuit Review & Check 4 0% 09/Jul/16 12/Jul/16 24/Jul/16 27/Jul/16 24/Jul/16 27/Jul/16
CON62310 Mobilization of Battery & Charger Supervisor (Vendor) 0 0% 12/Jul/16 27/Jul/16 Mobilization of Battery & Cha
CON62300 Battery Charging 4 0% 13/Jul/16 17/Jul/16 28/Jul/16 01/Aug/16 28/Jul/16 01/Aug/16
CON62320 Battery Discharge Test 4 0% 17/Jul/16 20/Jul/16 01/Aug/16 04/Aug/16 01/Aug/16 04/Aug/16
CON62350 Lighting Panels Acceptance & Check 1 0% 26/Jul/16 26/Jul/16 08/Aug/16 08/Aug/16 08/Aug/16 08/Aug/16
CON62360 S/S #4 Lighting System Testing 3 0% 26/Jul/16 30/Jul/16 08/Aug/16 11/Aug/16 08/Aug/16 11/Aug/16
S/S #4- Electromech
Electromechanical Systems Testing & Pre-commissioning 27 0% 14/Jul/16 10/Aug/16 11/Aug/16 05/Sep/16
CON62380 S/S #4 Fire Alarm Testing 25 0% 18/Jul/16 10/Aug/16 11/Aug/16 04/Sep/16 11/Aug/16 04/Sep/16
CON62370 S/S #4 HVAC System Testing 25 0% 14/Jul/16 07/Aug/16 13/Aug/16 05/Sep/16 13/Aug/16 05/Sep/16
13.8kV Substation #5-Abu
#5-A Ali Plant 191 28.09% 16/Apr/15 16/Aug/16 16/Apr/15 A 22/Sep/16
SS #5 Civil Construction
Construc (Sub-contracted) 104 73.47% 16/Apr/15 18/May/16 16/Apr/15 A 25/Jun/16
SS #5 Cast-In-Situ RC
R Works 10 97.98% 16/Apr/15 14/May/16 16/Apr/15 A 20/Jun/16
SS #5 Foundation 0 100% 16/Apr/15 15/Nov/15 16/Apr/15 A 15/Nov/15 A
CON63500 Excavation 0 100% 16/Apr/15 18/May/15 16/Apr/15 A 18/May/15 A 16/Apr/15 A 18/May/15 A
CON63510 Work Cavity Dewatering ( If Required ) 0 100% 16/Apr/15 18/May/15 16/Apr/15 A 18/May/15 A 16/Apr/15 A 18/May/15 A
CON63520 Cavity Side Courtains & supports ( If Required ) 0 100% 16/Apr/15 18/May/15 16/Apr/15 A 18/May/15 A 16/Apr/15 A 18/May/15 A
CON63290 Backfilling , Compaction and Leveling 0 100% 24/May/15 25/May/15 24/May/15 A 26/May/15 A 24/May/15 A 26/May/15 A
CON63260 Lean Concrete 0 100% 31/May/15 31/May/15 31/May/15 A 31/May/15 A 31/May/15 A 31/May/15 A
CON68410 Foundation Formwork 0 100% 03/Jun/15 09/Jun/15 03/Jun/15 A 10/Jun/15 A 03/Jun/15 A 10/Jun/15 A
CON68400 REBARS of Building Foundation 0 100% 04/Jun/15 09/Jun/15 04/Jun/15 A 10/Jun/15 A 04/Jun/15 A 10/Jun/15 A
CON68420 Grade Beam Column Necks REBARS , Forms & Casting 0 100% 07/Jun/15 29/Jul/15 07/Jun/15 A 30/Jul/15 A 07/Jun/15 A 30/Jul/15 A
CON68430 Check & Casting of Foundation 0 100% 11/Jun/15 13/Jun/15 11/Jun/15 A 13/Jun/15 A 11/Jun/15 A 13/Jun/15 A
CON68440 Curing of Building Foundation 0 100% 14/Jun/15 16/Jun/15 14/Jun/15 A 17/Jun/15 A 14/Jun/15 A 17/Jun/15 A
CON68450 Removal of Formwork 0 100% 03/Aug/15 04/Aug/15 03/Aug/15 A 05/Aug/15 A 03/Aug/15 A 05/Aug/15 A
CON63350 Water Proofing Works 0 100% 05/Nov/15 15/Nov/15 05/Nov/15 A 15/Nov/15 A 05/Nov/15 A 15/Nov/15 A
SS #5 Building Roo
Rooms 10 94.43% 05/Aug/15 14/May/16 05/Aug/15 A 20/Jun/16
CON63270 SWGR Room Columns REBARS 0 100% 05/Aug/15 27/Aug/15 05/Aug/15 A 29/Aug/15 A 05/Aug/15 A 29/Aug/15 A
CON68590 SWGR Room Columns Formwork 0 100% 05/Aug/15 27/Aug/15 05/Aug/15 A 29/Aug/15 A 05/Aug/15 A 29/Aug/15 A
CON68620 Rooms Columns REBARS & Form Work 0 100% 05/Aug/15 27/Aug/15 05/Aug/15 A 29/Aug/15 A 05/Aug/15 A 29/Aug/15 A
CON68600 SWGR Room Check & Casting of Columns 0 100% 30/Aug/15 30/Aug/15 30/Aug/15 A 30/Aug/15 A 30/Aug/15 A 30/Aug/15 A
CON68610 SWGR Room Curing & Formwork Removal of Columns 0 100% 01/Sep/15 03/Sep/15 01/Sep/15 A 05/Sep/15 A 01/Sep/15 A 05/Sep/15 A
CON67350 Beams RCC Casting & Curing & Removal of Formwork 0 100% 05/Sep/15 19/Oct/15 05/Sep/15 A 19/Oct/15 A 05/Sep/15 A 19/Oct/15 A
CON68660 Building Foundation Water Proofing 0 100% 02/Nov/15 15/Nov/15 02/Nov/15 A 15/Nov/15 A 02/Nov/15 A 15/Nov/15 A
CON63420 Backfilling ,AHUs Foundations RC of Mechanical Room & SWGR SOG 0 100% 15/Nov/15 26/Nov/15 15/Nov/15 A 28/Nov/15 A 15/Nov/15 A 28/Nov/15 A
CON63280 Backfilling & Compaction Works Around Foundations 0 100% 22/Nov/15 24/Nov/15 22/Nov/15 A 25/Nov/15 A 22/Nov/15 A 25/Nov/15 A
CON68670 WalkWays RCC 10 0% 05/May/16 14/May/16 11/Jun/16 20/Jun/16 11/Jun/16 20/Jun/16
Pre-Cast Columns, Beams,
B Panels, TT Slabs & Parapets Erection 0 100% 28/Nov/15 15/Feb/16 28/Nov/15 A 11/Mar/16 A
CON63300 SWGR Room Pre-cast Concrete Double T Slab 0 100% 28/Nov/15 23/Jan/16 28/Nov/15 A 24/Jan/16 A 28/Nov/15 A 24/Jan/16 A

Page 14 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON63370 Internal Walls 0 100% 10/Dec/15 10/Dec/15 10/Dec/15 A 12/Dec/15 A 10/Dec/15 A 12/Dec/15 A
CON63190 SWGR Room Pre-Cast Panels Erection & Alignement 0 100% 24/Dec/15 15/Feb/16 24/Dec/15 A 11/Mar/16 A 24/Dec/15 A 11/Mar/16 A
CON63400 Comm. & Battery Room Walls Panels Erection 0 100% 29/Dec/15 13/Jan/16 29/Dec/15 A 14/Jan/16 A 29/Dec/15 A 14/Jan/16 A
CON63430 Mech. Room Walls Panels Erection 0 100% 02/Jan/16 06/Jan/16 02/Jan/16 A 07/Jan/16 A 02/Jan/16 A 07/Jan/16 A
Finishing - Completi
Completion of Works 104 13.11% 16/Feb/16 18/May/16 16/Feb/16 A 25/Jun/16
CON63440 Panel Base Plates Installation & Grouting 0 100% 16/Feb/16 20/Feb/16 16/Feb/16 A 10/Mar/16 A 16/Feb/16 A 10/Mar/16 A
CON63250 Sealant & Putty Application of Internal Walls 20 10% 16/Feb/16 09/Mar/16 16/Feb/16 A 07/Apr/16 16/Feb/16 A 07/Apr/16
CON63310 Screed & Roof Water Proofing Works 15 50% 16/Feb/16 03/Mar/16 27/Feb/16 A 07/Apr/16 27/Feb/16 A 07/Apr/16
CON63340 Scuppers & Drain Pipes Erection 5 0% 18/Feb/16 23/Feb/16 26/Mar/16 29/Mar/16 26/Mar/16 29/Mar/16
CON63230 Supply & Installation of Doors & Hardwares 5 0% 10/Mar/16 14/Mar/16 09/Apr/16 12/Apr/16 09/Apr/16 12/Apr/16
CON63320 Flood Test 4 0% 03/Mar/16 07/Mar/16 09/Apr/16 12/Apr/16 09/Apr/16 12/Apr/16
CON63210 Painting Works @ Building 18 0% 07/Mar/16 24/Mar/16 12/Apr/16 28/Apr/16 12/Apr/16 28/Apr/16
CON63330 Thermal Insulation 20 0% 07/Mar/16 26/Mar/16 12/Apr/16 01/May/16 12/Apr/16 01/May/16
CON63220 Floor Finishing Works, Self Level & Epoxy Coating 16 0% 16/Mar/16 31/Mar/16 21/Apr/16 05/May/16 21/Apr/16 05/May/16
CON63470 Roof Access Ladders Erection. 5 0% 26/Mar/16 30/Mar/16 01/May/16 05/May/16 01/May/16 05/May/16
CON63240 External Finishing Works (Touch Up) 5 0% 15/May/16 18/May/16 20/Jun/16 25/Jun/16 20/Jun/16 25/Jun/16
SS #5 Electrical Installation
Insta 101 0% 31/Mar/16 10/Jul/16 07/May/16 14/Aug/16
SS #5 13.8KV SWGR
SWG Room - Installation of 13.8KV SWGR 72 0% 31/Mar/16 01/Jun/16 07/May/16 18/Jul/16
13.8KV SWGR Mechanical
Mec Installation 72 0% 31/Mar/16 01/Jun/16 07/May/16 18/Jul/16
CON63530 Mobilization of 13.8KV SWGR Supervisor ( Vendor ) 0 0% 31/Mar/16 07/May/16 Mobilization of 13.8KV SWGR Sup
CON63540 Floor and Base Plate Alignment Check 2 0% 31/Mar/16 03/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON63550 Opening Box & Arrangement of Material & Equipment 3 0% 02/Apr/16 04/Apr/16 07/May/16 10/May/16 07/May/16 10/May/16
CON63560 Transfer of SWGR Cubicles to Room 3 0% 04/Apr/16 07/Apr/16 10/May/16 12/May/16 10/May/16 12/May/16
CON63570 Positioning & Alignment & Installation of CBs 4 0% 07/Apr/16 11/Apr/16 12/May/16 16/May/16 12/May/16 16/May/16
CON63580 CTs Installation 2 0% 11/Apr/16 13/Apr/16 16/May/16 18/May/16 16/May/16 18/May/16
CON63600 Installation of BB-A & Alignment 2 0% 11/Apr/16 13/Apr/16 16/May/16 18/May/16 16/May/16 18/May/16
CON63610 Installation of BB-B & Alignment 2 0% 13/Apr/16 14/Apr/16 18/May/16 19/May/16 18/May/16 19/May/16
CON63630 VTs Installation 2 0% 14/Apr/16 17/Apr/16 21/May/16 22/May/16 21/May/16 22/May/16
CON64000 BB VT Installation 2 0% 17/Apr/16 18/Apr/16 22/May/16 24/May/16 22/May/16 24/May/16
CON63730 Bolt Tightening Check 3 0% 18/Apr/16 21/Apr/16 24/May/16 26/May/16 24/May/16 26/May/16
CON63740 Rack in/out Mechanisms Installation & Adjusting 3 0% 18/Apr/16 21/Apr/16 24/May/16 26/May/16 24/May/16 26/May/16
CON63670 Contact Resistance Check (Internal) & Repair if Required 2 0% 21/Apr/16 23/Apr/16 26/May/16 29/May/16 26/May/16 29/May/16
CON64030 Readiness to Start SWGR Mechanical Pre-commisioning 0 0% 23/Apr/16 29/May/16 Readiness to Start SWGR Mech
CON64010 Readiness for HV Test 0 0% 01/Jun/16 18/Jul/16 Readiness for HV Test
13.8KV SWGR Electrical
Elec Installation 20 0% 11/Apr/16 30/Apr/16 16/May/16 04/Jun/16
CON63960 Control Cables Looping & Termination 20 0% 11/Apr/16 30/Apr/16 16/May/16 04/Jun/16 16/May/16 04/Jun/16
CON63970 CT Looping 10 0% 20/Apr/16 30/Apr/16 25/May/16 04/Jun/16 25/May/16 04/Jun/16
CON63980 VT Looping 10 0% 20/Apr/16 30/Apr/16 25/May/16 04/Jun/16 25/May/16 04/Jun/16
CON64020 Readiness to Start SWGR Electrical Pre-commisioning 0 0% 30/Apr/16 04/Jun/16 Readiness to Start SWGR Elect
SS #5 13.8KV SWGR
SWG Room - Installation of Protection Systems 73 0% 31/Mar/16 08/Jun/16 07/May/16 19/Jul/16
Panels Installation 8 0% 31/Mar/16 09/Apr/16 07/May/16 14/May/16
CON64130 TRAFO (701) AVR & RTCC Panels Installation 2 0% 31/Mar/16 03/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON64190 TRAFO (702) AVR & RTCC Panels Installation 2 0% 03/Apr/16 04/Apr/16 08/May/16 10/May/16 08/May/16 10/May/16
CON64140 TRAFO (703) AVR & RTCC Panels Installation 2 0% 04/Apr/16 06/Apr/16 10/May/16 11/May/16 10/May/16 11/May/16
CON64150 TRAFO (704) AVR & RTCC Panels Installation 2 0% 06/Apr/16 09/Apr/16 11/May/16 14/May/16 11/May/16 14/May/16
Control & Instrumentation
Instrumen Cable Pulling 10 0% 11/Apr/16 20/Apr/16 16/May/16 25/May/16
CON64510 Cable Pulling from SWGR to TRAFO (701) AVR & RTCC Panels 5 0% 11/Apr/16 16/Apr/16 16/May/16 21/May/16 16/May/16 21/May/16
CON64570 Cable Pulling from SWGR to TRAFO (702) AVR & RTCC Panels 5 0% 16/Apr/16 20/Apr/16 21/May/16 25/May/16 21/May/16 25/May/16
Control Cable Termination
Term 57 0% 16/Apr/16 08/Jun/16 21/May/16 19/Jul/16
BUS System - A 36 0% 16/Apr/16 19/May/16 21/May/16 23/Jun/16
CON65010 Cable Termination TRAFO (701) AVR & RTCC Panels Side 21 0% 16/Apr/16 05/May/16 21/May/16 09/Jun/16 21/May/16 09/Jun/16

Page 15 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON65030 Cable Termination TRAFO (701) SWGR Side 21 0% 30/Apr/16 19/May/16 04/Jun/16 23/Jun/16 04/Jun/16 23/Jun/16
BUS System - B 36 0% 05/May/16 08/Jun/16 09/Jun/16 19/Jul/16
CON65110 Cable Termination TRAFO (702) AVR & RTCC Panels Side 21 0% 05/May/16 25/May/16 09/Jun/16 29/Jun/16 09/Jun/16 29/Jun/16
CON65120 Cable Termination TRAFO (702) SWGR Side 21 0% 19/May/16 08/Jun/16 23/Jun/16 19/Jul/16 23/Jun/16 19/Jul/16
SS #5 PSA System Installation
I 101 0% 31/Mar/16 10/Jul/16 07/May/16 14/Aug/16
PSA Panels Installation
Installa 12 0% 31/Mar/16 12/Apr/16 07/May/16 17/May/16
CON64320 PSA Panel Installation 2 0% 31/Mar/16 03/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON64340 PSA Interface Panels Installation ( Not Required ) 1 0% 31/Mar/16 02/Apr/16 07/May/16 07/May/16 07/May/16 07/May/16
CON68760 BCUs Installation ( Not Required ) 1 0% 11/Apr/16 12/Apr/16 16/May/16 17/May/16 16/May/16 17/May/16
Fiber Optic Cables Laying & Termination 22 0% 30/Apr/16 21/May/16 04/Jun/16 25/Jun/16
CON64710 Cable Pulling &Termination from PSA Interface Panels to 13.8KV Relays (non-IEDs) 1 0% 30/Apr/16 01/May/16 04/Jun/16 05/Jun/16 04/Jun/16 05/Jun/16
CON64840 Availability of FO Subcontractor Supervisor (Vendor) 0 0% 30/Apr/16 04/Jun/16 Availability of FO Subcontractor
CON68770 BCUs Internal Termination 1 0% 30/Apr/16 01/May/16 04/Jun/16 05/Jun/16 04/Jun/16 05/Jun/16
CON64700 FO&Instrum. Cables Pulling &Termination from PSA Panel to 13.8KV Relays(IEDs) 10 0% 01/May/16 10/May/16 05/Jun/16 14/Jun/16 05/Jun/16 14/Jun/16
CON64720 FO&Instrum. Cables Pulling &Termination from PSA Interface to PSA Panels 1 0% 10/May/16 11/May/16 14/Jun/16 15/Jun/16 14/Jun/16 15/Jun/16
CON64820 FO Cables Laying & Splicing between PSA Panels & BCUs 10 0% 11/May/16 21/May/16 15/Jun/16 25/Jun/16 15/Jun/16 25/Jun/16
PSA Sys. Pre-commissioning
Pre-comm ( Start Up ) & Relay Configuration ( Pre-check ) @SS #5 69 0% 01/May/16 10/Jul/16 05/Jun/16 14/Aug/16
CON65700 Availability of PSA System Supervisor (Vendor) 0 0% 01/May/16 05/Jun/16 Availability of PSA System Super
CON65670 Workstation Installation & Cording to PSA Cabinet 4 0% 02/May/16 05/May/16 06/Jun/16 09/Jun/16 06/Jun/16 09/Jun/16
CON65660 Availability of AC&DC 0 0% 18/May/16 22/Jun/16 Availability of AC&DC
CON65680 Pre-commissioning of Automation Station & Printer & LCD Screen 1 0% 18/May/16 19/May/16 22/Jun/16 23/Jun/16 22/Jun/16 23/Jun/16
CON65620 GPS Clock Antenna Installation & Linking to GPS Clock @ PSA Cabinet 4 0% 19/May/16 23/May/16 23/Jun/16 27/Jun/16 23/Jun/16 27/Jun/16
CON67430 SS #5 PSA System Ready To Start Internal Closed Loop Testing 0 0% 25/May/16 29/Jun/16 SS #5 PSA System Ready To
CON65690 SS #5 PSA System Configuration Completed 0 0% 10/Jul/16 14/Aug/16 SS #5 PSA System Config
Busbar - A Relays Configuration ( Pre-check ) 21 0% 21/May/16 08/Jun/16 25/Jun/16 20/Jul/16
CON67410 Relay Configuration Pre-check for BB- A 1 0% 21/May/16 21/May/16 25/Jun/16 26/Jun/16 25/Jun/16 26/Jun/16
CON68780 Relay Configuration Pre-check for Transformer (701) Incommer 1 0% 21/May/16 22/May/16 26/Jun/16 27/Jun/16 26/Jun/16 27/Jun/16
CON68790 Relay Configuration Pre-check for S/S #5 Auxiliary TFR (301) Feeder 1 0% 22/May/16 23/May/16 27/Jun/16 27/Jun/16 27/Jun/16 27/Jun/16
CON68820 Relay Configuration Pre-check for S/S #1 Auxiliary TFR (301) Feeder 1 0% 25/May/16 25/May/16 29/Jun/16 30/Jun/16 29/Jun/16 30/Jun/16
CON68840 Relay Configuration Pre-check for S/S #3 SWGR Building Incom. No.1 Feeder 1 0% 26/May/16 28/May/16 02/Jul/16 02/Jul/16 02/Jul/16 02/Jul/16
CON68810 Relay Configuration Pre-check for Arabiyah Field Feeder 1 0% 30/May/16 30/May/16 10/Jul/16 11/Jul/16 10/Jul/16 11/Jul/16
CON68800 Relay Configuration Pre-check for Berri Field Potential Project Feeder 1 0% 30/May/16 31/May/16 11/Jul/16 11/Jul/16 11/Jul/16 11/Jul/16
CON68830 Relay Configuration Pre-check for Offshore Wells TP 1 Feeder 1 0% 31/May/16 01/Jun/16 12/Jul/16 12/Jul/16 12/Jul/16 12/Jul/16
CON68860 Relay Configuration Pre-check for CGT Van Feeder 1 0% 02/Jun/16 04/Jun/16 13/Jul/16 14/Jul/16 13/Jul/16 14/Jul/16
CON68850 Relay Configuration Pre-check for S/S #2 Auxiliary TFR (301) Feeder 1 0% 04/Jun/16 04/Jun/16 14/Jul/16 16/Jul/16 14/Jul/16 16/Jul/16
CON68870 Relay Configuration Pre-check for Spare Feeder 1 0% 08/Jun/16 08/Jun/16 19/Jul/16 20/Jul/16 19/Jul/16 20/Jul/16
Busbar - B Relays Configuration ( Pre-check ) 19 0% 21/May/16 08/Jun/16 26/Jun/16 19/Jul/16
CON67420 Relay Configuration Pre-check for BB - B 1 0% 21/May/16 22/May/16 26/Jun/16 27/Jun/16 26/Jun/16 27/Jun/16
CON68890 Relay Configuration Pre-check for Transformer (702) Incommer 1 0% 23/May/16 24/May/16 27/Jun/16 28/Jun/16 27/Jun/16 28/Jun/16
CON68900 Relay Configuration Pre-check for S/S #5 Auxiliary TFR (302) Feeder 1 0% 24/May/16 25/May/16 28/Jun/16 29/Jun/16 28/Jun/16 29/Jun/16
CON68930 Relay Configuration Pre-check for S/S #1 Auxiliary TFR (302) Feeder 1 0% 25/May/16 26/May/16 30/Jun/16 01/Jul/16 30/Jun/16 01/Jul/16
CON68940 Relay Configuration Pre-check for S/S #3 SWGR Building Incom. No.2 Feeder 1 0% 28/May/16 29/May/16 02/Jul/16 09/Jul/16 02/Jul/16 09/Jul/16
CON68910 Relay Configuration Pre-check for Karan Field Potential Project Feeder 1 0% 29/May/16 30/May/16 09/Jul/16 10/Jul/16 09/Jul/16 10/Jul/16
CON68950 Relay Configuration Pre-check for Offshore Wells TP 3 Feeder 1 0% 01/Jun/16 02/Jun/16 12/Jul/16 13/Jul/16 12/Jul/16 13/Jul/16
CON68960 Relay Configuration Pre-check for S/S #2 Auxiliary TFR (302) Feeder 1 0% 04/Jun/16 05/Jun/16 16/Jul/16 16/Jul/16 16/Jul/16 16/Jul/16
CON68920 Relay Configuration Pre-check for Berri Field Potential Project Feeder 1 0% 05/Jun/16 06/Jun/16 17/Jul/16 17/Jul/16 17/Jul/16 17/Jul/16
CON68970 Relay Configuration Pre-check for New Admin. Building Feeder 1 0% 06/Jun/16 07/Jun/16 17/Jul/16 18/Jul/16 17/Jul/16 18/Jul/16
CON68980 Relay Configuration Pre-check for Spare Feeder 1 0% 07/Jun/16 08/Jun/16 18/Jul/16 19/Jul/16 18/Jul/16 19/Jul/16
Interfacing FA, HV
HVAC & Battery Charger Monitoring Systems ( Pre-check ) 27 0% 08/Jun/16 10/Jul/16 20/Jul/16 14/Aug/16
CON65630 AC & DC System Battery Charger Monitoring & Alarm Linking to Gateway @ PSA Cabinett & 1 0% 08/Jun/16 09/Jun/16 20/Jul/16 20/Jul/16 20/Jul/16 20/Jul/16
CON65640 Fire Alarm Linking to Gateway @ PSA Cabinett & Config. Pre-check 1 0% 20/Jun/16 21/Jun/16 01/Aug/16 01/Aug/16 01/Aug/16 01/Aug/16

Page 16 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON65650 HVAC Linking to Gateway @ PSA Cabinett & Config. Pre-check 1 0% 09/Jul/16 10/Jul/16 14/Aug/16 14/Aug/16 14/Aug/16 14/Aug/16
SS #5 Communication
Communicatio Room - Installation of Data & Voice Telephone System 74 0% 04/Apr/16 13/Jun/16 10/May/16 24/Jul/16
SS #5 Comm. Panels
Pan Installation 11 0% 04/Apr/16 01/May/16 10/May/16 19/May/16
CON64490 230V Telecom Power Panel Installation 2 0% 04/Apr/16 06/Apr/16 10/May/16 11/May/16 10/May/16 11/May/16
CON64500 FO Cables Patch Panels Installation (Rack 1 & 2) 2 0% 30/Apr/16 01/May/16 18/May/16 19/May/16 18/May/16 19/May/16
SS #5 FOC & Data Voice Inter-Connections 26 0% 19/May/16 13/Jun/16 23/Jun/16 24/Jul/16
CON67470 Availability of Communication System Supervisor (Vendor) 0 0% 19/May/16 23/Jun/16 Availability of Communication S
CON65710 FO Cables Laying & Splicing between PSA Gateway Panel & FOC PP-1 (PoE Switch) (Rack1 8 0% 21/May/16 28/May/16 25/Jun/16 02/Jul/16 25/Jun/16 02/Jul/16
CON67460 CAT6 Cables Network Pulling &Termination to VoIP Telephone (X2 & X6) 20 0% 21/May/16 08/Jun/16 26/Jun/16 20/Jul/16 26/Jun/16 20/Jul/16
CON67480 Powering Communication Panel 4 0% 21/May/16 25/May/16 26/Jun/16 29/Jun/16 26/Jun/16 29/Jun/16
CON65720 FO Cables Laying & Splicing between PSA Gateway Panel & FOC PP-2 (UTP Patch Panel)(R 8 0% 28/May/16 04/Jun/16 02/Jul/16 16/Jul/16 02/Jul/16 16/Jul/16
CON65730 FO Cables Laying & Splicing between FOC PP-1 & FOC PP-2 4 0% 04/Jun/16 08/Jun/16 16/Jul/16 19/Jul/16 16/Jul/16 19/Jul/16
CON67450 Connecting VoIP (X2 & X6) to Rack 2 4 0% 08/Jun/16 13/Jun/16 20/Jul/16 24/Jul/16 20/Jul/16 24/Jul/16
SS #5 Installation of Substation Auxiliaries 73 0% 31/Mar/16 01/Jun/16 07/May/16 18/Jul/16
SS #5 13.8KV SWGR
SWG Room - Installation of AC / DC Systems 14 0% 31/Mar/16 13/Apr/16 07/May/16 19/May/16
CON64330 125VDC Panel Installation 4 0% 31/Mar/16 04/Apr/16 07/May/16 10/May/16 07/May/16 10/May/16
CON64360 DC Battery Charger Installation 4 0% 31/Mar/16 04/Apr/16 07/May/16 10/May/16 07/May/16 10/May/16
CON64370 Telecom Equip. Power Supply Inverter Installation 4 0% 31/Mar/16 04/Apr/16 07/May/16 10/May/16 07/May/16 10/May/16
CON64390 400-230V Power Panel Installation 4 0% 31/Mar/16 04/Apr/16 07/May/16 10/May/16 07/May/16 10/May/16
CON65750 Maintenance & Tools Cupboard Mounting 2 0% 31/Mar/16 03/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON69000 408V SWGR Panels Installation 4 0% 31/Mar/16 04/Apr/16 07/May/16 10/May/16 07/May/16 10/May/16
CON64350 125VDC Panel Installation 6 0% 04/Apr/16 10/Apr/16 10/May/16 15/May/16 10/May/16 15/May/16
CON64400 400-230V Lighting Panel Installation 5 0% 04/Apr/16 09/Apr/16 10/May/16 15/May/16 10/May/16 15/May/16
CON69010 MCC Panels Installation 4 0% 04/Apr/16 09/Apr/16 10/May/16 14/May/16 10/May/16 14/May/16
CON64410 Lighting Control Planel Installation 4 0% 09/Apr/16 13/Apr/16 15/May/16 18/May/16 15/May/16 18/May/16
CON64420 480-400/230V Lighting / Power Dry Type Transformer Installation 4 0% 09/Apr/16 13/Apr/16 15/May/16 18/May/16 15/May/16 18/May/16
CON64380 Battery Back-up Supply for Emergency Lighting Installation 4 0% 10/Apr/16 13/Apr/16 16/May/16 19/May/16 16/May/16 19/May/16
SS #5 Battery Room - Installation of Battery 73 0% 31/Mar/16 01/Jun/16 07/May/16 18/Jul/16
CON64440 Battery Support Frame Installation 4 0% 31/Mar/16 04/Apr/16 07/May/16 10/May/16 07/May/16 10/May/16
CON64450 Battery Rack (1) Installation 3 0% 31/Mar/16 04/Apr/16 07/May/16 09/May/16 07/May/16 09/May/16
CON64460 Battery Rack (2) Installation 3 0% 04/Apr/16 07/Apr/16 10/May/16 12/May/16 10/May/16 12/May/16
CON64470 Battery MCCB Box Installation 3 0% 04/Apr/16 07/Apr/16 10/May/16 12/May/16 10/May/16 12/May/16
CON65230 Acid Filling 3 0% 24/May/16 28/May/16 10/Jul/16 13/Jul/16 10/Jul/16 13/Jul/16
CON65240 Battery Cells Linking 3 0% 28/May/16 30/May/16 13/Jul/16 16/Jul/16 13/Jul/16 16/Jul/16
CON65740 Tool Cupboard Mounting 3 0% 30/May/16 01/Jun/16 16/Jul/16 18/Jul/16 16/Jul/16 18/Jul/16
AC / DC Cables Pulling
Pu & Termination 62 0% 11/Apr/16 01/Jun/16 16/May/16 18/Jul/16
CON65270 DC Cables Pulling From Chargers to Battery MCCB Box & Termination 3 0% 11/Apr/16 13/Apr/16 16/May/16 19/May/16 16/May/16 19/May/16
CON69020 AC Cables Pulling from 480V SWGR to MCC & Termination 4 0% 11/Apr/16 14/Apr/16 16/May/16 19/May/16 16/May/16 19/May/16
CON69030 AC Cables Pulling from MCC to 400-230V ACDB & Termination 4 0% 11/Apr/16 14/Apr/16 16/May/16 19/May/16 16/May/16 19/May/16
CON69040 DC Cables Pulling from 125V DCDB to 480V SWGR Panels & Termination 3 0% 11/Apr/16 13/Apr/16 16/May/16 19/May/16 16/May/16 19/May/16
CON64830 AC Cables Pulling from 400-230V ACDB to Chargers & Termination 5 0% 11/Apr/16 16/Apr/16 16/May/16 21/May/16 16/May/16 21/May/16
CON65260 DC Cables Pulling from Chargers to 125V DCDBs & Termination 4 0% 11/Apr/16 14/Apr/16 16/May/16 19/May/16 16/May/16 19/May/16
CON65280 DC Cables Pulling from 125V DCDB to 13.8KV SWGR Cubicles & Termination 10 0% 23/Apr/16 02/May/16 29/May/16 07/Jun/16 29/May/16 07/Jun/16
CON65290 DC Cables Pulling from 125V DCDB to Protection Panels & Termination 15 0% 02/May/16 16/May/16 07/Jun/16 21/Jun/16 07/Jun/16 21/Jun/16
CON65320 AC Cables Pulling from 400-230V ACDB to Dry Type Transformers & Termination 3 0% 02/May/16 05/May/16 07/Jun/16 09/Jun/16 07/Jun/16 09/Jun/16
CON69060 AC LV Cables Between S/S #4 & 5 Pulling & Termination Both Sides 10 0% 04/May/16 14/May/16 11/Jun/16 20/Jun/16 11/Jun/16 20/Jun/16
CON65300 DC Cables Pulling from 125V DCDB to PSA & IntefacePanels & Termination 2 0% 16/May/16 18/May/16 21/Jun/16 22/Jun/16 21/Jun/16 22/Jun/16
CON65310 AC Cables Pulling from 400-230V ACDB to Comm. Power Panel & Termination 3 0% 18/May/16 21/May/16 22/Jun/16 26/Jun/16 22/Jun/16 26/Jun/16
CON65330 AC Cables Pulling from Dry Type Transformer to Comm. Power Supply Inverter & Terminati 3 0% 18/May/16 21/May/16 22/Jun/16 26/Jun/16 22/Jun/16 26/Jun/16
CON65340 AC Cables Pulling from 400-230V ACDB to Lighting Panel & Termination 7 0% 18/May/16 24/May/16 25/Jun/16 30/Jun/16 25/Jun/16 30/Jun/16
CON65350 DC Cables Pulling from 125V DCDB to Emergency Lighting Panel & Termination 7 0% 18/May/16 24/May/16 25/Jun/16 30/Jun/16 25/Jun/16 30/Jun/16

Page 17 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON69050 AC LV Cables from Auxil. TFRs and Termination to 480V SWGR 3 0% 29/May/16 31/May/16 10/Jul/16 13/Jul/16 10/Jul/16 13/Jul/16
CON65250 DC Cables Pulling from MCCB Box to Battery & Termination 3 0% 30/May/16 01/Jun/16 16/Jul/16 18/Jul/16 16/Jul/16 18/Jul/16
CON67400 DC Supplied to All Relay & Control System 0 0% 01/Jun/16 18/Jul/16 DC Supplied to All Relay & C
CON69070 AC/DC Completed 0 0% 01/Jun/16 18/Jul/16 AC/DC Completed
SS #5 Electromechanical
Electromecha 108 0% 24/Mar/16 11/Jul/16 28/Apr/16 13/Aug/16
S/S #5-Cable Ladder
Ladde / Trays 29 0% 24/Mar/16 20/Apr/16 28/Apr/16 25/May/16
CON65530 Marking @ SWGR Room 4 0% 24/Mar/16 28/Mar/16 28/Apr/16 02/May/16 28/Apr/16 02/May/16
CON65540 Installation of Cable Tray Supports @ SWGR Room 10 0% 26/Mar/16 04/Apr/16 01/May/16 10/May/16 01/May/16 10/May/16
CON65550 Installation of Cable Trays / Ladders @ SWGR Room 15 0% 28/Mar/16 11/Apr/16 02/May/16 16/May/16 02/May/16 16/May/16
CON65560 Marking @ Communication Room 2 0% 28/Mar/16 30/Mar/16 02/May/16 04/May/16 02/May/16 04/May/16
CON65590 Marking @ Mechanical Room 2 0% 30/Mar/16 31/Mar/16 04/May/16 05/May/16 04/May/16 05/May/16
CON65600 Installation of Cable Tray Supports @ Mechanical Room 5 0% 04/Apr/16 09/Apr/16 10/May/16 15/May/16 10/May/16 15/May/16
CON65570 Installation of Cable Tray Supports @ Communication Room 5 0% 09/Apr/16 13/Apr/16 15/May/16 19/May/16 15/May/16 19/May/16
CON65610 Installation of Cable Trays / Ladders @ Mechanical Room 5 0% 11/Apr/16 16/Apr/16 16/May/16 21/May/16 16/May/16 21/May/16
CON65580 Installation of Cable Trays / Ladders @ Communication Room 5 0% 16/Apr/16 20/Apr/16 21/May/16 25/May/16 21/May/16 25/May/16
S/S #5 HVAC System (Sub-contracted) 108 0% 24/Mar/16 09/Jul/16 28/Apr/16 13/Aug/16
SS #5 HVAC Duct W Work 95 0% 24/Mar/16 21/Jun/16 28/Apr/16 01/Aug/16
SS #5 HVAC Duct Works Switchgear Level 95 0% 24/Mar/16 21/Jun/16 28/Apr/16 01/Aug/16
SS #5 Supply Air Duct Works Switchgear Level 74 0% 24/Mar/16 01/Jun/16 28/Apr/16 12/Jul/16
CON65760 Installation of Duct Supports @ SWGR Room 7 0% 24/Mar/16 30/Mar/16 28/Apr/16 05/May/16 28/Apr/16 05/May/16
CON65790 Main Supply Air Duct to SWGR Room & T Connection Installation 10 0% 26/Mar/16 04/Apr/16 30/Apr/16 09/May/16 30/Apr/16 09/May/16
CON65970 Installation of Ducts Supports @ Mechanical Room 6 0% 30/Mar/16 05/Apr/16 05/May/16 10/May/16 05/May/16 10/May/16
CON65770 Supply Duct Installation @ SWGR Room 20 0% 04/Apr/16 23/Apr/16 09/May/16 28/May/16 09/May/16 28/May/16
CON65820 Volume Dampers Installation 3 0% 23/Apr/16 25/Apr/16 28/May/16 30/May/16 28/May/16 30/May/16
CON65892 Supply Air Connection to Battery RoomRoom 7 0% 25/Apr/16 02/May/16 30/May/16 06/Jun/16 30/May/16 06/Jun/16
CON65810 MF/S Dampers Installation 6 0% 23/Apr/16 27/Apr/16 06/Jun/16 11/Jun/16 06/Jun/16 11/Jun/16
CON65890 Supply Air Connection to Communication Room 7 0% 02/May/16 08/May/16 06/Jun/16 13/Jun/16 06/Jun/16 13/Jun/16
CON65900 Supply Air Main Duct Connection to AHU-1 & AHU-2 10 0% 08/May/16 17/May/16 13/Jun/16 22/Jun/16 13/Jun/16 22/Jun/16
CON65910 MVD 1&2 Installation on Main Supply Air 8 0% 17/May/16 25/May/16 22/Jun/16 29/Jun/16 22/Jun/16 29/Jun/16
CON65912 Air Outlet Installation 8 0% 25/May/16 01/Jun/16 29/Jun/16 12/Jul/16 29/Jun/16 12/Jul/16
SS #5 Return & Fresh
F Air Duct Works Switchgear Level 88 0% 30/Mar/16 21/Jun/16 05/May/16 01/Aug/16
CON65920 Return Air Ducts @ SWGR Room 8 0% 30/Mar/16 07/Apr/16 05/May/16 12/May/16 05/May/16 12/May/16
CON66140 MF/S Dampers Installation on return Ducts 6 0% 07/Apr/16 13/Apr/16 31/May/16 05/Jun/16 31/May/16 05/Jun/16
CON65922 Return Air Ducts @ Mechanical Room 15 0% 13/Apr/16 27/Apr/16 06/Jun/16 20/Jun/16 06/Jun/16 20/Jun/16
CON65930 Return Air Main Duct Connection to AHU-1 & AHU-2 3 0% 08/May/16 11/May/16 13/Jun/16 15/Jun/16 13/Jun/16 15/Jun/16
CON65940 Volume Dampers Installation 6 0% 11/May/16 16/May/16 15/Jun/16 21/Jun/16 15/Jun/16 21/Jun/16
CON65924 Return Air Ducts @ Communication Room 8 0% 27/Apr/16 04/May/16 20/Jun/16 27/Jun/16 20/Jun/16 27/Jun/16
CON65950 Fresh Air Connection to Outside 6 0% 16/May/16 22/May/16 21/Jun/16 27/Jun/16 21/Jun/16 27/Jun/16
CON65990 Motorized Volume Damper Installation 6 0% 22/May/16 28/May/16 27/Jun/16 02/Jul/16 27/Jun/16 02/Jul/16
CON69120 Exhaust Fans Installation @ Battery Room 8 0% 05/May/16 12/May/16 27/Jun/16 10/Jul/16 27/Jun/16 10/Jul/16
CON65992 Air Outlet Installation 6 0% 28/May/16 02/Jun/16 02/Jul/16 13/Jul/16 02/Jul/16 13/Jul/16
CON65960 LEL Detector Installation 6 0% 02/Jun/16 08/Jun/16 13/Jul/16 19/Jul/16 13/Jul/16 19/Jul/16
CON65980 H2S Scrubber Installation 6 0% 08/Jun/16 13/Jun/16 19/Jul/16 25/Jul/16 19/Jul/16 25/Jul/16
CON66000 Fresh Air Inlet Bell Mouth w/Bird Screen Installation 8 0% 13/Jun/16 21/Jun/16 25/Jul/16 01/Aug/16 25/Jul/16 01/Aug/16
SS #5 AHUs & ACCUs
ACC Installation 28 0% 13/Apr/16 11/May/16 06/Jun/16 02/Jul/16
CON66020 ACCU-1 & 2 Installation on Outdoor Foundation & Alighnment 6 0% 13/Apr/16 19/Apr/16 06/Jun/16 11/Jun/16 06/Jun/16 11/Jun/16
CON66050 AHU-1 & 2 Mounting & Alighnement on Foundation @ Mechanical Room 10 0% 13/Apr/16 23/Apr/16 06/Jun/16 15/Jun/16 06/Jun/16 15/Jun/16
CON66010 Flixible Joints Installation and Connection to Supply & Return Ducts 6 0% 23/Apr/16 28/Apr/16 15/Jun/16 20/Jun/16 15/Jun/16 20/Jun/16
CON66030 Connection Pipes to AHU-1 & 2 Installation 10 0% 23/Apr/16 02/May/16 15/Jun/16 24/Jun/16 15/Jun/16 24/Jun/16
CON66040 Drain Pipes Installation 6 0% 02/May/16 08/May/16 25/Jun/16 29/Jun/16 25/Jun/16 29/Jun/16
CON66060 Gas Filling 4 0% 02/May/16 05/May/16 25/Jun/16 28/Jun/16 25/Jun/16 28/Jun/16

Page 18 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON66130 Main Compressors Check 4 0% 05/May/16 09/May/16 28/Jun/16 02/Jul/16 28/Jun/16 02/Jul/16
CON66150 Min. Requi. of HVAC System for Temp. Operation 0 0% 11/May/16 02/Jul/16 Min. Requi. of HVAC System f
SS #5 Devices & Power
P Supply 68 0% 13/Apr/16 09/Jul/16 06/Jun/16 13/Aug/16
CON66110 HVAC Control Panel Installation 2 0% 13/Apr/16 16/Apr/16 06/Jun/16 07/Jun/16 06/Jun/16 07/Jun/16
CON66100 AC Power Supply 2 0% 23/Apr/16 25/Apr/16 15/Jun/16 16/Jun/16 15/Jun/16 16/Jun/16
CON66120 HVAC Isolator Disconnect Switches Installation & Wiring 2 0% 07/May/16 08/May/16 16/Jun/16 19/Jun/16 16/Jun/16 19/Jun/16
CON66070 Instruments & Actuators Installation 7 0% 08/Jun/16 14/Jun/16 19/Jul/16 25/Jul/16 19/Jul/16 25/Jul/16
CON66080 Cables / Wires Pulling & Termination ( Devices Side ) 20 0% 14/Jun/16 09/Jul/16 26/Jul/16 13/Aug/16 26/Jul/16 13/Aug/16
CON66090 Cables / Wires Pulling & Termination ( Control Panel Side ) 20 0% 14/Jun/16 09/Jul/16 26/Jul/16 13/Aug/16 26/Jul/16 13/Aug/16
CON66160 HVAC System Ready for Testing 0 0% 09/Jul/16 13/Aug/16 HVAC System Ready for T
S/S #5-Fire Detection
Detectio & Alarm System (Sub-contracted) 97 0% 24/Mar/16 22/Jun/16 28/Apr/16 02/Aug/16
S/S #5-Fire Detection
Detecti / Alarm Conduit Works 65 0% 24/Mar/16 28/May/16 28/Apr/16 28/Jun/16
CON66340 FA Conduits Installation @ SWGR Room 5 0% 24/Mar/16 29/Mar/16 28/Apr/16 03/May/16 28/Apr/16 03/May/16
CON66380 FA Conduits Installation @ Mechanical Room 3 0% 24/Mar/16 27/Mar/16 28/Apr/16 01/May/16 28/Apr/16 01/May/16
CON66390 FA Conduits Installation @ Battery Room 3 0% 27/Mar/16 30/Mar/16 02/May/16 04/May/16 02/May/16 04/May/16
CON66400 FA Conduits Installation @ Communication Room 3 0% 30/Mar/16 02/Apr/16 04/May/16 07/May/16 04/May/16 07/May/16
CON67490 Completion of Internal FA Conduits Installation 0 0% 02/Apr/16 07/May/16 Completion of Internal FA Conduits
CON69130 Direct Burried FA Conduits for TFR (702) @ Transformers Yard 3 0% 21/Apr/16 24/Apr/16 22/May/16 24/May/16 22/May/16 24/May/16
CON69250 Direct Burried FA Conduits for TFR (701) @ Transformers Yard 3 0% 02/May/16 04/May/16 22/May/16 24/May/16 22/May/16 24/May/16
CON69260 Direct Burried FA Conduits for TFR (704) @ Transformers Yard 3 0% 14/May/16 16/May/16 01/Jun/16 04/Jun/16 01/Jun/16 04/Jun/16
CON69270 Direct Burried FA Conduits for TFR (703) @ Transformers Yard 3 0% 24/May/16 28/May/16 13/Jun/16 15/Jun/16 13/Jun/16 15/Jun/16
CON66410 FA Conduits Installation @ S/S #5 External Walls 3 0% 19/May/16 22/May/16 25/Jun/16 28/Jun/16 25/Jun/16 28/Jun/16
S/S #5-Fire Detection
Detecti / Alarm Wire Loops & Curcuits 75 0% 02/Apr/16 08/Jun/16 07/May/16 21/Jul/16
S/S #5-Fire Detec
Detection / Alarm Wire Pulling Loop-1 40 0% 02/Apr/16 09/May/16 07/May/16 13/Jun/16
CON66420 Beam Transmittal & Receivers Wires Pulling to LIM @ SWGR Room 5 0% 02/Apr/16 06/Apr/16 07/May/16 11/May/16 07/May/16 11/May/16
CON66480 Smoke & Flame Detectors Wires Pulling to LIM @ Mechanical Room 5 0% 02/Apr/16 06/Apr/16 07/May/16 11/May/16 07/May/16 11/May/16
CON66440 Manual Pull Stations Wire Pulling to LIM @ SWGR Room 5 0% 06/Apr/16 11/Apr/16 11/May/16 16/May/16 11/May/16 16/May/16
CON66490 Manual Pull Stations Wire Pulling to LIM @ Mechanical Room 5 0% 06/Apr/16 11/Apr/16 11/May/16 16/May/16 11/May/16 16/May/16
CON66500 In HVAC Duct Smoke Detectors Wires Pulling to LIM @ Mechanical Room 5 0% 11/Apr/16 16/Apr/16 16/May/16 21/May/16 16/May/16 21/May/16
CON66510 Smoke Detectors Wires Pulling to LIM @ Battery Room 5 0% 11/Apr/16 16/Apr/16 16/May/16 21/May/16 16/May/16 21/May/16
CON66520 Manual Pull Stations Wire Pulling to LIM @ Battery Room 5 0% 16/Apr/16 20/Apr/16 21/May/16 25/May/16 21/May/16 25/May/16
CON66530 Smoke Detectors Wires Pulling to LIM @ Communication Room 5 0% 20/Apr/16 25/Apr/16 25/May/16 30/May/16 25/May/16 30/May/16
CON66540 Manual Pull Stations Wire Pulling to LIM @ Communication Room 5 0% 25/Apr/16 30/Apr/16 30/May/16 04/Jun/16 30/May/16 04/Jun/16
CON66550 Smoke Detectors Wires Pulling to LIM @ Air Lock Room 5 0% 30/Apr/16 04/May/16 04/Jun/16 08/Jun/16 04/Jun/16 08/Jun/16
CON66560 Manual Pull Stations Wire Pulling to LIM @ Air Lock Room 5 0% 04/May/16 09/May/16 08/Jun/16 13/Jun/16 08/Jun/16 13/Jun/16
S/S #5-Fire Detec
Detection / Alarm Wire Pulling Loop-2 38 0% 14/May/16 08/Jun/16 11/Jun/16 21/Jul/16
CON59530 Control Cable Pulling From TFR (704) to FAJB 5 0% 18/May/16 23/May/16 11/Jun/16 15/Jun/16 11/Jun/16 15/Jun/16
CON59600 Control Cable Pulling From TFR (703) to FAJB 5 0% 29/May/16 02/Jun/16 18/Jun/16 22/Jun/16 18/Jun/16 22/Jun/16
CON59390 Control Cable Pulling From TFR (702) to FAJB 5 0% 14/May/16 18/May/16 20/Jun/16 24/Jun/16 20/Jun/16 24/Jun/16
CON59460 Control Cable Pulling From TFR (701) to FAJB 5 0% 14/May/16 18/May/16 20/Jun/16 24/Jun/16 20/Jun/16 24/Jun/16
CON60770 Control Cable Pulling From Auxi. TFRs to FAJB 5 0% 04/Jun/16 08/Jun/16 17/Jul/16 21/Jul/16 17/Jul/16 21/Jul/16
S/S #5-Fire Detec
Detection / Alarm Notification Appliance Wire Pulling Curcuit-1 45 0% 02/Apr/16 14/May/16 07/May/16 18/Jun/16
CON66640 Wires Pulling from Control Panel to FA Bell @ Mechanical Room 5 0% 02/Apr/16 06/Apr/16 07/May/16 11/May/16 07/May/16 11/May/16
CON66650 Wires Pulling from Control Panel to FA Bell @ Battery Room 5 0% 06/Apr/16 11/Apr/16 11/May/16 16/May/16 11/May/16 16/May/16
CON66660 Wires Pulling from Control Panel to FA Bell @ Communication Room 5 0% 11/Apr/16 16/Apr/16 16/May/16 21/May/16 16/May/16 21/May/16
CON66670 Wires Pulling from Control Panel to FA Bell @ Air Lock Room 5 0% 16/Apr/16 20/Apr/16 21/May/16 25/May/16 21/May/16 25/May/16
CON66620 Wires Pulling from Control Panel to FA Bell @ SWGR Room 5 0% 09/May/16 14/May/16 13/Jun/16 18/Jun/16 13/Jun/16 18/Jun/16
CON67500 FA Wires Pulling Completion 0 0% 14/May/16 18/Jun/16 FA Wires Pulling Completion
S/S #5-Fire Detec
Detection / Alarm Notification Appliance Wire Pulling Curcuit-2 5 0% 22/May/16 26/May/16 28/Jun/16 09/Jul/16
CON66700 Wire Pulling from Control Panel to Horn, Beacon & Flashing Lights Strobes @ 1st Bldg Side 5 0% 22/May/16 26/May/16 28/Jun/16 09/Jul/16 28/Jun/16 09/Jul/16
CON66710 Wire Pulling from Control Panel to Horn, Beacon & Flashing Lights Strobes @ 3rd Bldg Side 5 0% 22/May/16 26/May/16 28/Jun/16 09/Jul/16 28/Jun/16 09/Jul/16

Page 19 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON66720 Wire Pulling from Control Panel to Horn, Beacon & Flashing Lights Strobes @ 2nd Bldg Side 5 0% 22/May/16 26/May/16 28/Jun/16 09/Jul/16 28/Jun/16 09/Jul/16
CON66730 Wire Pulling from Control Panel to Horn, Beacon & Flashing Lights Strobes @ 4th Bldg Side 5 0% 22/May/16 26/May/16 28/Jun/16 09/Jul/16 28/Jun/16 09/Jul/16
S/S #5-Fire Detection
Detecti / Alarm Control Panel & Appliance Installation 97 0% 24/Mar/16 22/Jun/16 28/Apr/16 02/Aug/16
CON66740 LIM Installation @ SWGR Room 2 0% 24/Mar/16 26/Mar/16 28/Apr/16 01/May/16 28/Apr/16 01/May/16
CON64430 Fire Alarm Control Panel Installation 2 0% 31/Mar/16 03/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON66580 Wire Pulling from LIM to FA Control Panel @ SWGR Room 5 0% 03/Apr/16 07/Apr/16 08/May/16 12/May/16 08/May/16 12/May/16
CON66770 Wires Termination Of LIM @ SWGR Room 15 0% 14/May/16 28/May/16 18/Jun/16 02/Jul/16 18/Jun/16 02/Jul/16
CON66780 Wires Termination Of Control Panel @ SWGR Room 25 0% 28/May/16 20/Jun/16 09/Jul/16 01/Aug/16 09/Jul/16 01/Aug/16
CON69280 Wire Pulling &Termination from FAJB to FA Control Panel @ SWGR Room 5 0% 08/Jun/16 13/Jun/16 21/Jul/16 26/Jul/16 21/Jul/16 26/Jul/16
CON59540 Flame Detector Installation @ TFR (704) 1 0% 13/Jun/16 14/Jun/16 26/Jul/16 27/Jul/16 26/Jul/16 27/Jul/16
CON66790 Installation & Termination of All Appliance @ S/S #5 4 0% 16/Jun/16 20/Jun/16 28/Jul/16 01/Aug/16 28/Jul/16 01/Aug/16
CON59400 Flame Detector Installation @ TFR (702) 1 0% 20/Jun/16 21/Jun/16 01/Aug/16 01/Aug/16 01/Aug/16 01/Aug/16
CON59470 Flame Detector Installation @ TFR (701) 1 0% 20/Jun/16 21/Jun/16 01/Aug/16 01/Aug/16 01/Aug/16 01/Aug/16
CON59610 Flame Detector Installation @ TFR (703) 1 0% 20/Jun/16 21/Jun/16 01/Aug/16 01/Aug/16 01/Aug/16 01/Aug/16
CON60780 Flame Detector Installation @ Auxi. TFRs 1 0% 20/Jun/16 21/Jun/16 01/Aug/16 01/Aug/16 01/Aug/16 01/Aug/16
CON66810 Ready for Testing 0 0% 22/Jun/16 02/Aug/16 Ready for Testing
Hand Extinguishers 4 0% 18/Jun/16 22/Jun/16 30/Jul/16 02/Aug/16
CON66830 Installation of Extinguisher Brackets 2 0% 18/Jun/16 20/Jun/16 30/Jul/16 01/Aug/16 30/Jul/16 01/Aug/16
CON66820 Delivery & Mounting of Extinguishers 2 0% 20/Jun/16 22/Jun/16 01/Aug/16 02/Aug/16 01/Aug/16 02/Aug/16
S/S #5-Lighting 70 0% 24/Mar/16 26/May/16 28/Apr/16 09/Jul/16
S/S #5 Lighting & Small
S Power System Conduit Works 64 0% 24/Mar/16 21/May/16 28/Apr/16 27/Jun/16
CON66990 Lighting & Sockets Conduits Installation @ Mechanical Room 2 0% 24/Mar/16 26/Mar/16 28/Apr/16 01/May/16 28/Apr/16 01/May/16
CON66950 Lighting & Sockets Conduits Installation @ SWGR Room 4 0% 24/Mar/16 28/Mar/16 28/Apr/16 02/May/16 28/Apr/16 02/May/16
CON67000 Lighting & Sockets Conduits Installation @ Battery Room 2 0% 26/Mar/16 28/Mar/16 01/May/16 02/May/16 01/May/16 02/May/16
CON67010 Lighting & Sockets Conduits Installation @ Communication Room 2 0% 28/Mar/16 30/Mar/16 02/May/16 04/May/16 02/May/16 04/May/16
CON67510 Completion of Lighting Internal Conduits Installation 0 0% 30/Mar/16 04/May/16 Completion of Lighting Internal Con
CON67020 Lighting & Sockets Conduits Installation @ S/S #5 External Walls 2 0% 19/May/16 21/May/16 25/Jun/16 27/Jun/16 25/Jun/16 27/Jun/16
S/S #5 Lighting & Small
S Power System Wires Pulling & Termination 60 0% 30/Mar/16 23/May/16 04/May/16 29/Jun/16
S/S #5 AC Lighting & Small Power System Wires Pulling & Termination Works 60 0% 30/Mar/16 23/May/16 04/May/16 29/Jun/16
CON67030 AC Lighting Wires Pulling & Termination @ SWGR Room 2 0% 30/Mar/16 31/Mar/16 04/May/16 05/May/16 04/May/16 05/May/16
CON67070 AC Lighting Wires Pulling & Termination @ Mechanical Room 2 0% 30/Mar/16 31/Mar/16 04/May/16 05/May/16 04/May/16 05/May/16
CON67080 AC Lighting Wires Pulling & Termination @ Battery Room 2 0% 31/Mar/16 03/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON67090 AC Lighting Wires Pulling & Termination @ Communication Room 2 0% 03/Apr/16 04/Apr/16 08/May/16 10/May/16 08/May/16 10/May/16
CON67100 AC Lighting Wires Pulling & Termination @ S/S #5 External Walls 2 0% 21/May/16 23/May/16 27/Jun/16 29/Jun/16 27/Jun/16 29/Jun/16
S/S #5 DC Lighting & Small Power System Wires Pulling & Termination Work s 60 0% 30/Mar/16 23/May/16 04/May/16 29/Jun/16
CON67110 DC Emergency Lighting Wires Pulling & Termination @ SWGR Room 2 0% 30/Mar/16 31/Mar/16 04/May/16 05/May/16 04/May/16 05/May/16
CON67150 DC Emergency Lighting Wires Pulling & Termination @ Mechanical Room 2 0% 30/Mar/16 31/Mar/16 04/May/16 05/May/16 04/May/16 05/May/16
CON67160 DC Emergency Lighting Wires Pulling & Termination @ Battery Room 2 0% 31/Mar/16 03/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON67170 DC Emergency Lighting Wires Pulling & Termination @ Communication Room 2 0% 03/Apr/16 04/Apr/16 08/May/16 10/May/16 08/May/16 10/May/16
CON67180 DC Emergency Lighting Wires Pulling & Termination @ S/S #5 External Walls 2 0% 21/May/16 23/May/16 27/Jun/16 29/Jun/16 27/Jun/16 29/Jun/16
S/S #5 Lighting Fixtures
Fixt & Power Access Sockets Installation 62 0% 31/Mar/16 26/May/16 07/May/16 09/Jul/16
S/S #5 Lighting Fixtures
Fix 60 0% 31/Mar/16 24/May/16 07/May/16 30/Jun/16
CON67190 AC & DC Emergency Lighting Fixtures Installation @ SWGR Room 2 0% 31/Mar/16 03/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON67230 AC & DC Emergency Lighting Fixtures Installation @ Mechanical Room 2 0% 31/Mar/16 03/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON67240 AC & DC Emergency Lighting Fixtures Installation @ Battery Room 2 0% 03/Apr/16 04/Apr/16 08/May/16 10/May/16 08/May/16 10/May/16
CON67250 AC & DC Emergency Lighting Fixtures Installation @ Communication Room 2 0% 04/Apr/16 06/Apr/16 10/May/16 11/May/16 10/May/16 11/May/16
CON67260 AC & DC Emergency Lighting Fixtures Installation @ S/S #5 External Walls 2 0% 23/May/16 24/May/16 29/Jun/16 30/Jun/16 29/Jun/16 30/Jun/16
S/S #5 Power Acc
Access Sockects 60 0% 03/Apr/16 26/May/16 08/May/16 09/Jul/16
CON67270 Power Access SocketsInstallation @ SWGR Room 2 0% 03/Apr/16 04/Apr/16 08/May/16 10/May/16 08/May/16 10/May/16
CON67310 Power Access SocketsInstallation @ Mechanical Room 2 0% 03/Apr/16 04/Apr/16 08/May/16 10/May/16 08/May/16 10/May/16
CON67320 Power Access SocketsInstallation @ Battery Room 2 0% 04/Apr/16 06/Apr/16 10/May/16 11/May/16 10/May/16 11/May/16

Page 20 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON67330 Power Access SocketsInstallation @ Communication Room 2 0% 06/Apr/16 09/Apr/16 11/May/16 14/May/16 11/May/16 14/May/16
CON67340 Power Access SocketsInstallation @ S/S #5 External Walls 2 0% 24/May/16 26/May/16 30/Jun/16 09/Jul/16 30/Jun/16 09/Jul/16
S/S #5-Grounding & Earthing Work 98 0% 24/Mar/16 11/Jul/16 28/Apr/16 04/Aug/16
S/S #5-Bare Copper
Coppe Burried Mesh 98 0% 24/Mar/16 11/Jul/16 28/Apr/16 04/Aug/16
CON66930 Grounding Grid Link Inside Building Installation 6 0% 24/Mar/16 30/Mar/16 28/Apr/16 04/May/16 28/Apr/16 04/May/16
CON66920 Bare Copper Grounding Conductor Link to Burried Mesh 4 0% 02/Jul/16 11/Jul/16 01/Aug/16 04/Aug/16 01/Aug/16 04/Aug/16
S/S #5-Equipments Grounding 50 0% 23/Apr/16 01/Jun/16 26/May/16 18/Jul/16
CON66900 Grounding of Panels & Cable Trays @ Communication Room 1 0% 02/May/16 03/May/16 26/May/16 28/May/16 26/May/16 28/May/16
CON66910 Grounding of Protection & Control Panels @ SWGR Room 10 0% 23/Apr/16 02/May/16 28/May/16 06/Jun/16 28/May/16 06/Jun/16
CON66840 Grounding of 13.8KV SWGR @ SWGR Room 4 0% 30/Apr/16 03/May/16 04/Jun/16 08/Jun/16 04/Jun/16 08/Jun/16
CON66880 Grounding of Mechanical Equips & Cable Trays@ Mechanical Room 2 0% 23/Apr/16 25/Apr/16 15/Jun/16 16/Jun/16 15/Jun/16 16/Jun/16
CON66890 Grounding of Battery Supports @ Battery Room 1 0% 31/May/16 01/Jun/16 17/Jul/16 18/Jul/16 17/Jul/16 18/Jul/16
CON67520 Minimum Grounding to Be Ready for HV Testing 0 0% 01/Jun/16 18/Jul/16 Minimum Grounding to Be Re
SS #5 Testing & Pre-Commissioning
Pre- (Sub-contracted) 117 0% 23/Apr/16 16/Aug/16 29/May/16 22/Sep/16
S/S #5- 13.8 KV SWGR
SW Testing & Pre-commissioning 72 0% 23/Apr/16 17/Jul/16 29/May/16 10/Aug/16
S/S #5- 13.8KV SW
SWGR Mechanical Testing & Pre-commissioning 10 0% 23/Apr/16 02/May/16 29/May/16 07/Jun/16
CON67570 CBs & DSs Mechanism Checks 10 0% 23/Apr/16 02/May/16 29/May/16 07/Jun/16 29/May/16 07/Jun/16
S/S #5- 13.8KV SWGR
SW Electrical Testing & Pre-commissioning 65 0% 30/Apr/16 17/Jul/16 04/Jun/16 10/Aug/16
CON67530 Contact Resistance Including CBs & BB 4 0% 30/Apr/16 03/May/16 04/Jun/16 08/Jun/16 04/Jun/16 08/Jun/16
CON67800 Availability of Testing Sub-contractor 0 0% 30/Apr/16 04/Jun/16 Availability of Testing Sub-contra
CON67620 MCB & Auxiliary Relays & Heaters Test 4 0% 01/May/16 04/May/16 05/Jun/16 08/Jun/16 05/Jun/16 08/Jun/16
CON67580 Motors Current Tests 4 0% 02/May/16 05/May/16 06/Jun/16 09/Jun/16 06/Jun/16 09/Jun/16
CON67650 CTs Test 4 0% 02/May/16 07/May/16 07/Jun/16 11/Jun/16 07/Jun/16 11/Jun/16
CON67540 DS Insulation Tests ( Meggering ) 2 0% 03/May/16 05/May/16 08/Jun/16 09/Jun/16 08/Jun/16 09/Jun/16
CON67610 Earthing Switches Insulation Test 2 0% 03/May/16 05/May/16 08/Jun/16 09/Jun/16 08/Jun/16 09/Jun/16
CON67630 Metering Test 2 0% 04/May/16 07/May/16 08/Jun/16 11/Jun/16 08/Jun/16 11/Jun/16
CON67600 Guages Test 2 0% 07/May/16 08/May/16 11/Jun/16 13/Jun/16 11/Jun/16 13/Jun/16
CON67640 Annunciator Test 2 0% 07/May/16 08/May/16 11/Jun/16 13/Jun/16 11/Jun/16 13/Jun/16
CON67660 VTs Test 4 0% 07/May/16 10/May/16 11/Jun/16 14/Jun/16 11/Jun/16 14/Jun/16
CON67670 13.8KV SWGR High Voltage Test 6 0% 11/Jul/16 17/Jul/16 04/Aug/16 10/Aug/16 04/Aug/16 10/Aug/16
S/S #5- 13.8 KV Protection
Pro Testing & Pre-commissioning 104 0% 30/Apr/16 10/Aug/16 04/Jun/16 17/Sep/16
S/S #5- 13.8KV SW
SWGR Scheme & Function Check 93 0% 10/May/16 10/Aug/16 14/Jun/16 17/Sep/16
S/S #5- 13.8KV SW
SWGR Internal Scheme Check 90 0% 10/May/16 08/Aug/16 14/Jun/16 13/Sep/16
S/S #5- 13.8KV S
SWGR Bus System- A Internal Scheme Check 75 0% 10/May/16 25/Jul/16 14/Jun/16 29/Aug/16
CON69290 BB- A Scheme Check 5 0% 10/May/16 15/May/16 14/Jun/16 19/Jun/16 14/Jun/16 19/Jun/16
CON69300 Transformer (701) Incommer Scheme Check 5 0% 15/May/16 19/May/16 19/Jun/16 23/Jun/16 19/Jun/16 23/Jun/16
CON69310 S/S #5 Auxiliary TFR (301) Feeder Scheme Check 5 0% 19/May/16 24/May/16 23/Jun/16 28/Jun/16 23/Jun/16 28/Jun/16
CON69320 S/S #1 Auxiliary TFR (301) Feeder Scheme Check 5 0% 24/May/16 29/May/16 28/Jun/16 09/Jul/16 28/Jun/16 09/Jul/16
CON69330 S/S #3 SWGR Building Incom. No.1 Feeder Scheme Check 5 0% 02/Jun/16 07/Jun/16 13/Jul/16 18/Jul/16 13/Jul/16 18/Jul/16
CON69340 Arabiyah Field Feeder Scheme Check 5 0% 16/Jun/16 21/Jun/16 27/Jul/16 01/Aug/16 27/Jul/16 01/Aug/16
CON69350 Berri Field Potential Project Feeder Scheme Check 5 0% 21/Jun/16 26/Jun/16 01/Aug/16 06/Aug/16 01/Aug/16 06/Aug/16
CON69360 Offshore Wells TP 1 Feeder Scheme Check 5 0% 26/Jun/16 30/Jun/16 06/Aug/16 10/Aug/16 06/Aug/16 10/Aug/16
CON69370 CGT Van Feeder Scheme Check 5 0% 11/Jul/16 16/Jul/16 15/Aug/16 20/Aug/16 15/Aug/16 20/Aug/16
CON69380 S/S #2 Auxiliary TFR (301) Feeder Scheme Check 5 0% 16/Jul/16 20/Jul/16 20/Aug/16 24/Aug/16 20/Aug/16 24/Aug/16
CON69390 Spare Feeder Scheme Check 5 0% 20/Jul/16 25/Jul/16 24/Aug/16 29/Aug/16 24/Aug/16 29/Aug/16
S/S #5- 13.8KV S
SWGR Bus System- B Internal Scheme Check 85 0% 15/May/16 08/Aug/16 19/Jun/16 13/Sep/16
CON69400 BB - B Scheme Check 5 0% 15/May/16 19/May/16 19/Jun/16 23/Jun/16 19/Jun/16 23/Jun/16
CON69410 Transformer (702) Incommer Scheme Check 5 0% 19/May/16 24/May/16 23/Jun/16 28/Jun/16 23/Jun/16 28/Jun/16
CON69420 S/S #5 Auxiliary TFR (302) Feeder Scheme Check 5 0% 29/May/16 02/Jun/16 09/Jul/16 13/Jul/16 09/Jul/16 13/Jul/16
CON69430 S/S #1 Auxiliary TFR (302) Feeder Scheme Check 5 0% 29/May/16 02/Jun/16 09/Jul/16 13/Jul/16 09/Jul/16 13/Jul/16
CON69440 S/S #3 SWGR Building Incom. No.2 Feeder Scheme Check 5 0% 07/Jun/16 12/Jun/16 18/Jul/16 23/Jul/16 18/Jul/16 23/Jul/16
CON69450 Karan Field Potential Project Feeder Scheme Check 5 0% 12/Jun/16 16/Jun/16 23/Jul/16 27/Jul/16 23/Jul/16 27/Jul/16

Page 21 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON69460 Offshore Wells TP 3 Feeder Scheme Check 5 0% 30/Jun/16 11/Jul/16 10/Aug/16 15/Aug/16 10/Aug/16 15/Aug/16
CON69470 S/S #2 Auxiliary TFR (302) Feeder Scheme Check 5 0% 20/Jul/16 25/Jul/16 24/Aug/16 29/Aug/16 24/Aug/16 29/Aug/16
CON69480 Berri Field Potential Project Feeder Scheme Check 5 0% 25/Jul/16 30/Jul/16 29/Aug/16 03/Sep/16 29/Aug/16 03/Sep/16
CON69490 New Admin. Building Feeder Scheme Check 5 0% 30/Jul/16 03/Aug/16 03/Sep/16 08/Sep/16 03/Sep/16 08/Sep/16
CON69500 Spare Feeder Scheme Check 5 0% 03/Aug/16 08/Aug/16 08/Sep/16 13/Sep/16 08/Sep/16 13/Sep/16
S/S #5- 13.8KV SW
SWGR Operation & Function Test 83 0% 19/May/16 10/Aug/16 23/Jun/16 17/Sep/16
S/S #5- 13.8KV S
SWGR Bus System- A Function Test 68 0% 19/May/16 27/Jul/16 23/Jun/16 31/Aug/16
CON69510 BB- A Function Test 3 0% 19/May/16 22/May/16 23/Jun/16 27/Jun/16 23/Jun/16 27/Jun/16
CON69520 Transformer (701) Incommer Function Test 3 0% 22/May/16 25/May/16 27/Jun/16 29/Jun/16 27/Jun/16 29/Jun/16
CON69530 S/S #5 Auxiliary TFR (301) Feeder Function Test 3 0% 25/May/16 28/May/16 29/Jun/16 02/Jul/16 29/Jun/16 02/Jul/16
CON69540 S/S #1 Auxiliary TFR (301) Feeder Function Test 3 0% 29/May/16 31/May/16 09/Jul/16 11/Jul/16 09/Jul/16 11/Jul/16
CON69550 S/S #3 SWGR Building Incom. No.1 Feeder Function Test 3 0% 07/Jun/16 09/Jun/16 18/Jul/16 20/Jul/16 18/Jul/16 20/Jul/16
CON69560 Arabiyah Field Feeder Function Test 3 0% 21/Jun/16 23/Jun/16 01/Aug/16 03/Aug/16 01/Aug/16 03/Aug/16
CON69570 Berri Field Potential Project Feeder Function Test 3 0% 26/Jun/16 28/Jun/16 06/Aug/16 08/Aug/16 06/Aug/16 08/Aug/16
CON69580 Offshore Wells TP 1 Feeder Function Test 3 0% 30/Jun/16 09/Jul/16 10/Aug/16 13/Aug/16 10/Aug/16 13/Aug/16
CON69590 CGT Van Feeder Function Test 3 0% 16/Jul/16 18/Jul/16 20/Aug/16 22/Aug/16 20/Aug/16 22/Aug/16
CON69600 S/S #2 Auxiliary TFR (301) Feeder Function Test 3 0% 20/Jul/16 23/Jul/16 24/Aug/16 27/Aug/16 24/Aug/16 27/Aug/16
CON69610 Spare Feeder Function Test 3 0% 25/Jul/16 27/Jul/16 29/Aug/16 31/Aug/16 29/Aug/16 31/Aug/16
S/S #5- 13.8KV S
SWGR Bus System- B Function Test 83 0% 19/May/16 10/Aug/16 23/Jun/16 17/Sep/16
CON69620 BB - B Function Test 3 0% 19/May/16 22/May/16 23/Jun/16 27/Jun/16 23/Jun/16 27/Jun/16
CON69630 Transformer (702) Incommer Function Test 3 0% 24/May/16 26/May/16 28/Jun/16 01/Jul/16 28/Jun/16 01/Jul/16
CON69640 S/S #5 Auxiliary TFR (302) Feeder Function Test 3 0% 02/Jun/16 05/Jun/16 13/Jul/16 16/Jul/16 13/Jul/16 16/Jul/16
CON69650 S/S #1 Auxiliary TFR (302) Feeder Function Test 3 0% 02/Jun/16 05/Jun/16 13/Jul/16 16/Jul/16 13/Jul/16 16/Jul/16
CON69660 S/S #3 SWGR Building Incom. No.2 Feeder Function Test 3 0% 12/Jun/16 14/Jun/16 23/Jul/16 25/Jul/16 23/Jul/16 25/Jul/16
CON69670 Karan Field Potential Project Feeder Function Test 3 0% 16/Jun/16 19/Jun/16 27/Jul/16 30/Jul/16 27/Jul/16 30/Jul/16
CON69680 Offshore Wells TP 3 Feeder Function Test 3 0% 11/Jul/16 13/Jul/16 15/Aug/16 17/Aug/16 15/Aug/16 17/Aug/16
CON69690 S/S #2 Auxiliary TFR (302) Feeder Function Test 3 0% 25/Jul/16 27/Jul/16 29/Aug/16 31/Aug/16 29/Aug/16 31/Aug/16
CON69700 Berri Field Potential Project Feeder Function Test 3 0% 30/Jul/16 01/Aug/16 03/Sep/16 06/Sep/16 03/Sep/16 06/Sep/16
CON69710 New Admin. Building Feeder Function Test 3 0% 03/Aug/16 06/Aug/16 08/Sep/16 11/Sep/16 08/Sep/16 11/Sep/16
CON69720 Spare Feeder Function Test 3 0% 08/Aug/16 10/Aug/16 13/Sep/16 17/Sep/16 13/Sep/16 17/Sep/16
S/S #5- 13.8KV Auxiliary
Aux & Main Protection Relays Testing 28 0% 30/Apr/16 25/May/16 04/Jun/16 30/Jun/16
CON67680 Auxiliary Relays & MCBs Test 8 0% 30/Apr/16 07/May/16 04/Jun/16 12/Jun/16 04/Jun/16 12/Jun/16
CON67690 AVR Relay Acceptance Test 8 0% 30/Apr/16 07/May/16 04/Jun/16 12/Jun/16 04/Jun/16 12/Jun/16
CON67770 HV & LV REF Relay Test 6 0% 30/Apr/16 05/May/16 04/Jun/16 09/Jun/16 04/Jun/16 09/Jun/16
CON67780 BCUs Acceptance Test 6 0% 02/May/16 08/May/16 07/Jun/16 13/Jun/16 07/Jun/16 13/Jun/16
CON67720 O/C Relay Acceptance Test 6 0% 05/May/16 11/May/16 09/Jun/16 15/Jun/16 09/Jun/16 15/Jun/16
CON67700 Transformer Diffrential Relay Acceptance Test 8 0% 07/May/16 15/May/16 12/Jun/16 19/Jun/16 12/Jun/16 19/Jun/16
CON67710 HV & LV Neutral O/C Protection Acceptance Test 6 0% 15/May/16 21/May/16 19/Jun/16 25/Jun/16 19/Jun/16 25/Jun/16
CON67730 Over Flux Acceptance Testing 6 0% 21/May/16 25/May/16 25/Jun/16 30/Jun/16 25/Jun/16 30/Jun/16
S/S #5- 13.8KV Protection
Pro Relays Setting 21 0% 15/May/16 04/Jun/16 19/Jun/16 14/Jul/16
CON67790 Power Transformers Relays Final Settings ( 702 ) & ( 701 ) 21 0% 15/May/16 04/Jun/16 19/Jun/16 14/Jul/16 19/Jun/16 14/Jul/16
S/S #5- 13.8KV Protection
Pro Scheme Check 49 0% 30/Apr/16 14/Jun/16 04/Jun/16 25/Jul/16
CON67830 CT Loop Ckeck 6 0% 30/Apr/16 05/May/16 04/Jun/16 09/Jun/16 04/Jun/16 09/Jun/16
CON67840 VT Loop Check 6 0% 05/May/16 11/May/16 09/Jun/16 15/Jun/16 09/Jun/16 15/Jun/16
S/S #5- 13.8KV Pr
Protection Bus System-A Scheme Check 13 0% 21/May/16 01/Jun/16 25/Jun/16 12/Jul/16
CON67750 BB Differential (System A) 7 0% 21/May/16 26/May/16 25/Jun/16 01/Jul/16 25/Jun/16 01/Jul/16
CON68080 Transformer (701) AVR & RTCC Scheme Check 7 0% 25/May/16 01/Jun/16 30/Jun/16 12/Jul/16 30/Jun/16 12/Jul/16
S/S #5- 13.8KV Pr
Protection Bus System-B Scheme Check 20 0% 26/May/16 14/Jun/16 02/Jul/16 25/Jul/16
CON68090 BB Differential (System B) 7 0% 26/May/16 02/Jun/16 02/Jul/16 13/Jul/16 02/Jul/16 13/Jul/16
CON68120 Transformer (702) AVR & RTCC Scheme Check 7 0% 08/Jun/16 14/Jun/16 19/Jul/16 25/Jul/16 19/Jul/16 25/Jul/16
S/S #5- 13.8 KV PSA System Testing 89 0% 19/May/16 16/Aug/16 23/Jun/16 22/Sep/16

Page 22 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON68200 Hardware Start up Test 1 0% 19/May/16 21/May/16 23/Jun/16 25/Jun/16 23/Jun/16 25/Jun/16
CON68220 SS #5 PSA System Ready for Integration w/ Existing Abu Ali Facility System 0 0% 16/Aug/16 22/Sep/16 SS #5 PSA System Rea
Busbar - A Internal Closed Loop 72 0% 02/Jun/16 14/Aug/16 13/Jul/16 20/Sep/16
CON69820 BB- A Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 02/Jun/16 04/Jun/16 13/Jul/16 16/Jul/16 13/Jul/16 16/Jul/16
CON69850 Transformer (701) Incommer Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 04/Jun/16 06/Jun/16 16/Jul/16 17/Jul/16 16/Jul/16 17/Jul/16
CON69860 S/S #5 Auxiliary TFR (301) Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 06/Jun/16 08/Jun/16 17/Jul/16 19/Jul/16 17/Jul/16 19/Jul/16
CON69890 S/S #1 Auxiliary TFR (301) Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 18/Jun/16 20/Jun/16 30/Jul/16 31/Jul/16 30/Jul/16 31/Jul/16
CON69910 S/S #3 SWGR Building Incom. No.1 Feeder Internal Closed Loop ( from Source to PSA S/S 2 0% 22/Jun/16 23/Jun/16 02/Aug/16 03/Aug/16 02/Aug/16 03/Aug/16
CON69880 Arabiyah Field Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 27/Jun/16 29/Jun/16 08/Aug/16 09/Aug/16 08/Aug/16 09/Aug/16
CON69870 Berri Field Potential Project Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 29/Jun/16 02/Jul/16 09/Aug/16 11/Aug/16 09/Aug/16 11/Aug/16
CON69900 Offshore Wells TP 1 Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 09/Jul/16 11/Jul/16 14/Aug/16 15/Aug/16 14/Aug/16 15/Aug/16
CON69930 CGT Van Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 18/Jul/16 20/Jul/16 23/Aug/16 24/Aug/16 23/Aug/16 24/Aug/16
CON69920 S/S #2 Auxiliary TFR (301) Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 23/Jul/16 25/Jul/16 28/Aug/16 29/Aug/16 28/Aug/16 29/Aug/16
CON69940 Spare Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 13/Aug/16 14/Aug/16 19/Sep/16 20/Sep/16 19/Sep/16 20/Sep/16
Busbar - B Interna
Internal Closed Loop 68 0% 04/Jun/16 13/Aug/16 16/Jul/16 19/Sep/16
CON69830 BB - B Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 04/Jun/16 06/Jun/16 16/Jul/16 17/Jul/16 16/Jul/16 17/Jul/16
CON69950 Transformer (702) Incommer Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 14/Jun/16 16/Jun/16 26/Jul/16 27/Jul/16 26/Jul/16 27/Jul/16
CON69960 S/S #5 Auxiliary TFR (302) Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 16/Jun/16 18/Jun/16 27/Jul/16 30/Jul/16 27/Jul/16 30/Jul/16
CON69990 S/S #1 Auxiliary TFR (302) Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 20/Jun/16 22/Jun/16 31/Jul/16 02/Aug/16 31/Jul/16 02/Aug/16
CON70000 S/S #3 SWGR Building Incom. No.2 Feeder Internal Closed Loop ( from Source to PSA S/S 2 0% 23/Jun/16 26/Jun/16 04/Aug/16 06/Aug/16 04/Aug/16 06/Aug/16
CON69970 Karan Field Potential Project Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 26/Jun/16 27/Jun/16 06/Aug/16 08/Aug/16 06/Aug/16 08/Aug/16
CON70010 Offshore Wells TP 3 Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 13/Jul/16 16/Jul/16 18/Aug/16 20/Aug/16 18/Aug/16 20/Aug/16
CON70020 S/S #2 Auxiliary TFR (302) Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 27/Jul/16 30/Jul/16 01/Sep/16 03/Sep/16 01/Sep/16 03/Sep/16
CON69980 Berri Field Potential Project Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 01/Aug/16 03/Aug/16 06/Sep/16 08/Sep/16 06/Sep/16 08/Sep/16
CON70030 New Admin. Building Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 06/Aug/16 08/Aug/16 11/Sep/16 13/Sep/16 11/Sep/16 13/Sep/16
CON70040 Spare Feeder Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 10/Aug/16 13/Aug/16 17/Sep/16 19/Sep/16 17/Sep/16 19/Sep/16
Interfacing FA, HVAC
HVA & Battery Charger Monitoring Systems Internal Closed Loop 2 0% 14/Aug/16 16/Aug/16 20/Sep/16 22/Sep/16
CON69740 AC & DC System Battery Charger Monitoring & Alarm Internal Closed Loop ( from Source to 2 0% 14/Aug/16 16/Aug/16 20/Sep/16 22/Sep/16 20/Sep/16 22/Sep/16
CON69750 Fire Alarm Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 14/Aug/16 16/Aug/16 20/Sep/16 22/Sep/16 20/Sep/16 22/Sep/16
CON69760 HVAC Internal Closed Loop ( from Source to PSA S/S #5 ) 2 0% 14/Aug/16 16/Aug/16 20/Sep/16 22/Sep/16 20/Sep/16 22/Sep/16
S/S #5- Communication
Communica Testing 22 0% 25/May/16 14/Jun/16 29/Jun/16 25/Jul/16
CON68260 Communication Panels Check 2 0% 25/May/16 26/May/16 29/Jun/16 01/Jul/16 29/Jun/16 01/Jul/16
CON68270 FO Cables Interconnections Check 4 0% 08/Jun/16 12/Jun/16 19/Jul/16 23/Jul/16 19/Jul/16 23/Jul/16
CON67440 S/S #5 Ready for Connecting Rack 1 with FOC ( Data & Voive and PSA) Going to DCO 0 0% 13/Jun/16 24/Jul/16 S/S #5 Ready for Connectin
CON68280 CAT6 VoIP Interconnections Check 2 0% 13/Jun/16 14/Jun/16 24/Jul/16 25/Jul/16 24/Jul/16 25/Jul/16
S/S #5- Auxiliaries Te
Testing & Pre-commissioning 21 0% 02/Jun/16 21/Jun/16 19/Jul/16 07/Aug/16
CON68340 AC Panels Acceptance & Check 2 0% 02/Jun/16 04/Jun/16 19/Jul/16 20/Jul/16 19/Jul/16 20/Jul/16
CON68290 DC Panels Acceptance & Check 2 0% 04/Jun/16 06/Jun/16 20/Jul/16 23/Jul/16 20/Jul/16 23/Jul/16
CON68300 DC Circuit Review & Check 4 0% 06/Jun/16 09/Jun/16 23/Jul/16 26/Jul/16 23/Jul/16 26/Jul/16
CON68350 AC Circuit Review & Check 4 0% 06/Jun/16 09/Jun/16 23/Jul/16 26/Jul/16 23/Jul/16 26/Jul/16
CON68320 Availability of Battery & Charger Supervisor (Vendor) 0 0% 09/Jun/16 26/Jul/16 Availability of Battery & Char
CON68310 Battery Charging 4 0% 11/Jun/16 14/Jun/16 27/Jul/16 31/Jul/16 27/Jul/16 31/Jul/16
CON68330 Battery Discharge Test 4 0% 14/Jun/16 18/Jun/16 31/Jul/16 03/Aug/16 31/Jul/16 03/Aug/16
CON68360 Lighting Panels Acceptance & Check 1 0% 18/Jun/16 19/Jun/16 03/Aug/16 04/Aug/16 03/Aug/16 04/Aug/16
CON68370 S/S #5 Lighting System Testing 3 0% 19/Jun/16 21/Jun/16 04/Aug/16 07/Aug/16 04/Aug/16 07/Aug/16
S/S #5- Electromech
Electromechanical Systems Testing & Pre-commissioning 37 0% 22/Jun/16 01/Aug/16 02/Aug/16 06/Sep/16
CON68390 S/S #5 Fire Alarm Testing 25 0% 22/Jun/16 21/Jul/16 02/Aug/16 25/Aug/16 02/Aug/16 25/Aug/16
CON68380 S/S #5 HVAC System Testing 25 0% 09/Jul/16 01/Aug/16 14/Aug/16 06/Sep/16 14/Aug/16 06/Sep/16
Power Transformers Yard
Y 180 37.38% 06/May/15 17/Aug/16 06/May/15 A 11/Sep/16
Power Transformers Yard - Civil Construction (Sub-contracted) 106 66.59% 06/May/15 30/May/16 06/May/15 A 27/Jun/16
Power Transformer Foundations 30 92.98% 06/May/15 27/Mar/16 06/May/15 A 03/May/16

Page 23 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
Power Transformer (702) Foundation 5 92.69% 06/May/15 28/Feb/16 06/May/15 A 10/Apr/16
CON4640 Excavation 0 100% 06/May/15 13/May/15 06/May/15 A 13/May/15 A 06/May/15 A 13/May/15 A
CON4650 Compacting & Leveling 0 100% 20/May/15 28/May/15 20/May/15 A 30/May/15 A 20/May/15 A 30/May/15 A
CON4660 Lean Concrete 0 100% 31/May/15 03/Jun/15 31/May/15 A 03/Jun/15 A 31/May/15 A 03/Jun/15 A
CON4680 REBARS of (702) Foundation & Pedistals 0 100% 27/Jun/15 12/Jul/15 27/Jun/15 A 12/Jul/15 A 27/Jun/15 A 12/Jul/15 A
CON4690 Foundation Formwork 0 100% 28/Jun/15 13/Jul/15 28/Jun/15 A 13/Jul/15 A 28/Jun/15 A 13/Jul/15 A
CON4700 Check Before Casting 0 100% 13/Jul/15 13/Jul/15 13/Jul/15 A 13/Jul/15 A 13/Jul/15 A 13/Jul/15 A
CON4710 Casting of (702) Foundation 0 100% 13/Jul/15 14/Jul/15 13/Jul/15 A 14/Jul/15 A 13/Jul/15 A 14/Jul/15 A
CON4720 Curing of Foundation (702) 0 100% 14/Jul/15 20/Jul/15 14/Jul/15 A 20/Jul/15 A 14/Jul/15 A 20/Jul/15 A
CON4740 Removal of Formwork 0 100% 20/Jul/15 23/Jul/15 20/Jul/15 A 23/Jul/15 A 20/Jul/15 A 23/Jul/15 A
CON4730 Pedistals Formwork 0 100% 11/Aug/15 22/Sep/15 11/Aug/15 A 27/Sep/15 A 11/Aug/15 A 27/Sep/15 A
CON4750 REBARS of Walls 0 100% 11/Aug/15 22/Sep/15 11/Aug/15 A 27/Sep/15 A 11/Aug/15 A 27/Sep/15 A
CON4760 Formwork of Walls 0 100% 17/Aug/15 22/Sep/15 17/Aug/15 A 27/Sep/15 A 17/Aug/15 A 27/Sep/15 A
CON4770 Check Before Casting 0 100% 28/Sep/15 29/Sep/15 28/Sep/15 A 29/Sep/15 A 28/Sep/15 A 29/Sep/15 A
CON4780 Casting of (702) Foundation Walls & Pedistals 0 100% 28/Sep/15 29/Sep/15 28/Sep/15 A 29/Sep/15 A 28/Sep/15 A 29/Sep/15 A
CON4790 Curing 0 100% 29/Sep/15 01/Oct/15 29/Sep/15 A 01/Oct/15 A 29/Sep/15 A 01/Oct/15 A
CON4800 Removal of Formwork 0 100% 03/Oct/15 05/Oct/15 03/Oct/15 A 05/Oct/15 A 03/Oct/15 A 05/Oct/15 A
CON4830 Finishing ( Cocrete Repair ) 0 100% 06/Oct/15 11/Oct/15 06/Oct/15 A 12/Oct/15 A 06/Oct/15 A 12/Oct/15 A
CON4670 Water Proofing 0 100% 22/Oct/15 24/Oct/15 22/Oct/15 A 24/Oct/15 A 22/Oct/15 A 24/Oct/15 A
CON4810 Water Proofing Work 0 100% 22/Oct/15 24/Oct/15 22/Oct/15 A 24/Oct/15 A 22/Oct/15 A 24/Oct/15 A
CON4820 Backfilling Compacting Around (702) Foundation 0 100% 07/Nov/15 07/Nov/15 07/Nov/15 A 07/Nov/15 A 07/Nov/15 A 07/Nov/15 A
CON4840 Steel Grating Installation 5 0% 18/Feb/16 28/Feb/16 05/Apr/16 10/Apr/16 05/Apr/16 10/Apr/16
Power Transformer (701) Foundation 5 93.07% 07/May/15 08/Mar/16 07/May/15 A 14/Apr/16
CON4870 Excavation 0 100% 07/May/15 13/May/15 07/May/15 A 13/May/15 A 07/May/15 A 13/May/15 A
CON4880 Compacting & Leveling 0 100% 20/May/15 28/May/15 20/May/15 A 30/May/15 A 20/May/15 A 30/May/15 A
CON4890 Lean Concrete 0 100% 31/May/15 03/Jun/15 31/May/15 A 03/Jun/15 A 31/May/15 A 03/Jun/15 A
CON4910 REBARS of (701) Foundation & Pedistals 0 100% 27/Jun/15 12/Jul/15 27/Jun/15 A 12/Jul/15 A 27/Jun/15 A 12/Jul/15 A
CON4920 Foundation Formwork 0 100% 28/Jun/15 13/Jul/15 28/Jun/15 A 13/Jul/15 A 28/Jun/15 A 13/Jul/15 A
CON4930 Check Before Casting 0 100% 13/Jul/15 13/Jul/15 13/Jul/15 A 13/Jul/15 A 13/Jul/15 A 13/Jul/15 A
CON4940 Casting of (701) Foundation 0 100% 13/Jul/15 14/Jul/15 13/Jul/15 A 14/Jul/15 A 13/Jul/15 A 14/Jul/15 A
CON4950 Curing of Foundation (701) 0 100% 14/Jul/15 20/Jul/15 14/Jul/15 A 20/Jul/15 A 14/Jul/15 A 20/Jul/15 A
CON4970 Removal of Formwork 0 100% 20/Jul/15 22/Jul/15 20/Jul/15 A 23/Jul/15 A 20/Jul/15 A 23/Jul/15 A
CON4960 Pedistals Formwork 0 100% 11/Aug/15 22/Sep/15 11/Aug/15 A 28/Sep/15 A 11/Aug/15 A 28/Sep/15 A
CON4980 REBARS of Walls 0 100% 11/Aug/15 22/Sep/15 11/Aug/15 A 28/Sep/15 A 11/Aug/15 A 28/Sep/15 A
CON4990 Formwork of Walls 0 100% 17/Aug/15 22/Sep/15 17/Aug/15 A 28/Sep/15 A 17/Aug/15 A 28/Sep/15 A
CON5000 Check Before Casting 0 100% 28/Sep/15 29/Sep/15 28/Sep/15 A 29/Sep/15 A 28/Sep/15 A 29/Sep/15 A
CON5010 Casting of (701) Foundation Walls & Pedistals 0 100% 29/Sep/15 30/Sep/15 29/Sep/15 A 30/Sep/15 A 29/Sep/15 A 30/Sep/15 A
CON5020 Curing 0 100% 30/Sep/15 03/Oct/15 30/Sep/15 A 03/Oct/15 A 30/Sep/15 A 03/Oct/15 A
CON5030 Removal of Formwork 0 100% 03/Oct/15 05/Oct/15 03/Oct/15 A 05/Oct/15 A 03/Oct/15 A 05/Oct/15 A
CON5060 Finishing ( Cocrete Repair ) 0 100% 06/Oct/15 11/Oct/15 06/Oct/15 A 12/Oct/15 A 06/Oct/15 A 12/Oct/15 A
CON4900 Water Proofing Below Foundation 0 100% 26/Oct/15 27/Oct/15 26/Oct/15 A 27/Oct/15 A 26/Oct/15 A 27/Oct/15 A
CON5040 Water Proofing Work 0 100% 28/Oct/15 29/Oct/15 28/Oct/15 A 30/Oct/15 A 28/Oct/15 A 30/Oct/15 A
CON5050 Backfilling Compacting Around (701) Foundation 0 100% 07/Nov/15 07/Nov/15 07/Nov/15 A 07/Nov/15 A 07/Nov/15 A 07/Nov/15 A
CON5070 Steel Grating Installation 5 0% 28/Feb/16 08/Mar/16 10/Apr/16 14/Apr/16 10/Apr/16 14/Apr/16
Power Transformer (704) Foundation 10 93.07% 09/May/15 17/Mar/16 08/May/15 A 24/Apr/16
CON5100 Excavation 0 100% 09/May/15 16/May/15 08/May/15 A 16/May/15 A 08/May/15 A 16/May/15 A
CON5110 Compacting & Leveling 0 100% 20/May/15 28/May/15 20/May/15 A 30/May/15 A 20/May/15 A 30/May/15 A
CON5120 Lean Concrete 0 100% 31/May/15 31/May/15 31/May/15 A 31/May/15 A 31/May/15 A 31/May/15 A
CON5140 REBARS of (704) Foundation & Pedistals 0 100% 27/Jun/15 12/Jul/15 27/Jun/15 A 12/Jul/15 A 27/Jun/15 A 12/Jul/15 A
CON5150 Foundation Formwork 0 100% 28/Jun/15 13/Jul/15 28/Jun/15 A 13/Jul/15 A 28/Jun/15 A 13/Jul/15 A
CON5160 Check Before Casting 0 100% 13/Jul/15 13/Jul/15 13/Jul/15 A 13/Jul/15 A 13/Jul/15 A 13/Jul/15 A

Page 24 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON5170 Casting of (704) Foundation 0 100% 13/Jul/15 14/Jul/15 13/Jul/15 A 14/Jul/15 A 13/Jul/15 A 14/Jul/15 A
CON5180 Curing of Foundation (704) 0 100% 14/Jul/15 20/Jul/15 14/Jul/15 A 20/Jul/15 A 14/Jul/15 A 20/Jul/15 A
CON5200 Removal of Formwork 0 100% 20/Jul/15 22/Jul/15 20/Jul/15 A 23/Jul/15 A 20/Jul/15 A 23/Jul/15 A
CON5190 Pedistals Formwork 0 100% 11/Aug/15 29/Sep/15 11/Aug/15 A 29/Sep/15 A 11/Aug/15 A 29/Sep/15 A
CON5210 REBARS of Walls 0 100% 11/Aug/15 29/Sep/15 11/Aug/15 A 29/Sep/15 A 11/Aug/15 A 29/Sep/15 A
CON5220 Formwork of Walls 0 100% 17/Aug/15 29/Sep/15 17/Aug/15 A 29/Sep/15 A 17/Aug/15 A 29/Sep/15 A
CON5230 Check Before Casting 0 100% 30/Sep/15 30/Sep/15 30/Sep/15 A 30/Sep/15 A 30/Sep/15 A 30/Sep/15 A
CON5240 Casting of (704) Foundation Walls & Pedistals 0 100% 30/Sep/15 30/Sep/15 30/Sep/15 A 30/Sep/15 A 30/Sep/15 A 30/Sep/15 A
CON5250 Curing 0 100% 30/Sep/15 04/Oct/15 30/Sep/15 A 04/Oct/15 A 30/Sep/15 A 04/Oct/15 A
CON5260 Removal of Formwork 0 100% 04/Oct/15 05/Oct/15 04/Oct/15 A 05/Oct/15 A 04/Oct/15 A 05/Oct/15 A
CON5290 Finishing ( Cocrete Repair ) 0 100% 06/Oct/15 11/Oct/15 06/Oct/15 A 12/Oct/15 A 06/Oct/15 A 12/Oct/15 A
CON5130 Water Proofing Below Foundation 0 100% 07/Nov/15 08/Nov/15 07/Nov/15 A 08/Nov/15 A 07/Nov/15 A 08/Nov/15 A
CON5270 Water Proofing Work 0 100% 07/Nov/15 08/Nov/15 07/Nov/15 A 08/Nov/15 A 07/Nov/15 A 08/Nov/15 A
CON5280 Backfilling Compacting Around (704) Foundation 0 100% 08/Nov/15 09/Nov/15 08/Nov/15 A 09/Nov/15 A 08/Nov/15 A 09/Nov/15 A
CON5300 Steel Grating Installation 10 0% 08/Mar/16 17/Mar/16 14/Apr/16 24/Apr/16 14/Apr/16 24/Apr/16
Power Transformer (703) Foundation 10 93.07% 16/May/15 27/Mar/16 16/May/15 A 03/May/16
CON5330 Excavation 0 100% 16/May/15 17/May/15 16/May/15 A 17/May/15 A 16/May/15 A 17/May/15 A
CON5340 Compacting & Leveling 0 100% 20/May/15 28/May/15 20/May/15 A 28/May/15 A 20/May/15 A 28/May/15 A
CON5350 Lean Concrete 0 100% 31/May/15 31/May/15 31/May/15 A 31/May/15 A 31/May/15 A 31/May/15 A
CON5370 REBARS of (703) Foundation & Pedistals 0 100% 27/Jun/15 12/Jul/15 27/Jun/15 A 12/Jul/15 A 27/Jun/15 A 12/Jul/15 A
CON5380 Foundation Formwork 0 100% 28/Jun/15 13/Jul/15 28/Jun/15 A 13/Jul/15 A 28/Jun/15 A 13/Jul/15 A
CON5390 Check Before Casting 0 100% 13/Jul/15 13/Jul/15 13/Jul/15 A 13/Jul/15 A 13/Jul/15 A 13/Jul/15 A
CON5400 Casting of (703) Foundation 0 100% 13/Jul/15 14/Jul/15 13/Jul/15 A 14/Jul/15 A 13/Jul/15 A 14/Jul/15 A
CON5410 Curing of Foundation (703) 0 100% 14/Jul/15 20/Jul/15 14/Jul/15 A 20/Jul/15 A 14/Jul/15 A 20/Jul/15 A
CON5430 Removal of Formwork 0 100% 20/Jul/15 22/Jul/15 20/Jul/15 A 23/Jul/15 A 20/Jul/15 A 23/Jul/15 A
CON5420 Pedistals Formwork 0 100% 11/Aug/15 29/Sep/15 11/Aug/15 A 29/Sep/15 A 11/Aug/15 A 29/Sep/15 A
CON5440 REBARS of Walls 0 100% 11/Aug/15 29/Sep/15 11/Aug/15 A 29/Sep/15 A 11/Aug/15 A 29/Sep/15 A
CON5450 Formwork of Walls 0 100% 17/Aug/15 29/Sep/15 17/Aug/15 A 29/Sep/15 A 17/Aug/15 A 29/Sep/15 A
CON5460 Check Before Casting 0 100% 30/Sep/15 30/Sep/15 30/Sep/15 A 30/Sep/15 A 30/Sep/15 A 30/Sep/15 A
CON5470 Casting of (703) Foundation Walls & Pedistals 0 100% 30/Sep/15 01/Oct/15 30/Sep/15 A 01/Oct/15 A 30/Sep/15 A 01/Oct/15 A
CON5480 Curing 0 100% 01/Oct/15 04/Oct/15 01/Oct/15 A 04/Oct/15 A 01/Oct/15 A 04/Oct/15 A
CON5490 Removal of Formwork 0 100% 04/Oct/15 05/Oct/15 04/Oct/15 A 05/Oct/15 A 04/Oct/15 A 05/Oct/15 A
CON5520 Finishing ( Cocrete Repair ) 0 100% 06/Oct/15 11/Oct/15 06/Oct/15 A 12/Oct/15 A 06/Oct/15 A 12/Oct/15 A
CON5360 Water Proofing Below Foundation 0 100% 08/Nov/15 09/Nov/15 08/Nov/15 A 09/Nov/15 A 08/Nov/15 A 09/Nov/15 A
CON5500 Water Proofing Work 0 100% 08/Nov/15 10/Nov/15 08/Nov/15 A 10/Nov/15 A 08/Nov/15 A 10/Nov/15 A
CON5510 Backfilling Compacting Around (703) Foundation 0 100% 10/Nov/15 10/Nov/15 10/Nov/15 A 10/Nov/15 A 10/Nov/15 A 10/Nov/15 A
CON5600 Steel Grating Installation 10 0% 17/Mar/16 27/Mar/16 24/Apr/16 03/May/16 24/Apr/16 03/May/16
Fire Walls Construction
Construc 0 100% 20/May/15 20/Mar/16 20/May/15 A 06/Mar/16 A
Fire Wall Between (702)
( & (701) 0 100% 20/May/15 01/Mar/16 20/May/15 A 03/Mar/16 A
CON5650 Excavation 0 100% 20/May/15 20/May/15 20/May/15 A 20/May/15 A 20/May/15 A 20/May/15 A
CON5660 Compacting & Leveling 0 100% 20/May/15 28/May/15 20/May/15 A 28/May/15 A 20/May/15 A 28/May/15 A
CON5670 Lean Concrete 0 100% 31/May/15 31/May/15 31/May/15 A 31/May/15 A 31/May/15 A 31/May/15 A
CON5680 Water Proofing Below Foundation 0 100% 07/Jul/15 07/Jul/15 07/Jul/15 A 07/Jul/15 A 07/Jul/15 A 07/Jul/15 A
CON5690 REBARS of Foundation 0 100% 07/Jul/15 15/Aug/15 07/Jul/15 A 16/Aug/15 A 07/Jul/15 A 16/Aug/15 A
CON5700 Foundation Formwork 0 100% 08/Jul/15 15/Aug/15 08/Jul/15 A 16/Aug/15 A 08/Jul/15 A 16/Aug/15 A
CON5710 Check Before Casting 0 100% 30/Aug/15 30/Aug/15 30/Aug/15 A 30/Aug/15 A 30/Aug/15 A 30/Aug/15 A
CON5740 Casting of Foundation 0 100% 30/Aug/15 31/Aug/15 30/Aug/15 A 31/Aug/15 A 30/Aug/15 A 31/Aug/15 A
CON5750 Curing of Foundation 0 100% 31/Aug/15 02/Sep/15 31/Aug/15 A 02/Sep/15 A 31/Aug/15 A 02/Sep/15 A
CON5752 Removal of Formwork 0 100% 03/Sep/15 03/Sep/15 03/Sep/15 A 03/Sep/15 A 03/Sep/15 A 03/Sep/15 A
CON5760 Scafolding Erection 0 100% 04/Oct/15 07/Oct/15 04/Oct/15 A 07/Oct/15 A 04/Oct/15 A 07/Oct/15 A
CON5780 Wall First Part Form Work 0 100% 05/Oct/15 11/Oct/15 05/Oct/15 A 11/Oct/15 A 05/Oct/15 A 11/Oct/15 A

Page 25 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON5770 Wall REBARS 0 100% 07/Oct/15 08/Oct/15 07/Oct/15 A 08/Oct/15 A 07/Oct/15 A 08/Oct/15 A
CON5790 Check Before Casting 0 100% 13/Oct/15 13/Oct/15 13/Oct/15 A 13/Oct/15 A 13/Oct/15 A 13/Oct/15 A
CON5800 Casting 0 100% 13/Oct/15 14/Oct/15 13/Oct/15 A 14/Oct/15 A 13/Oct/15 A 14/Oct/15 A
CON5810 Curing 0 100% 14/Oct/15 17/Oct/15 14/Oct/15 A 17/Oct/15 A 14/Oct/15 A 17/Oct/15 A
CON5820 Wall REBARS Completion 0 100% 15/Oct/15 28/Nov/15 15/Oct/15 A 29/Nov/15 A 15/Oct/15 A 29/Nov/15 A
CON5830 Wall Second Part Form Work 0 100% 17/Oct/15 30/Nov/15 17/Oct/15 A 30/Nov/15 A 17/Oct/15 A 30/Nov/15 A
CON5870 Check Before Casting 0 100% 19/Oct/15 01/Dec/15 19/Oct/15 A 01/Dec/15 A 19/Oct/15 A 01/Dec/15 A
CON5756 Water Proofing Work 0 100% 28/Nov/15 28/Nov/15 28/Nov/15 A 28/Nov/15 A 28/Nov/15 A 28/Nov/15 A
CON5757 Backfilling & Compaction 0 100% 28/Nov/15 29/Nov/15 28/Nov/15 A 29/Nov/15 A 28/Nov/15 A 29/Nov/15 A
CON5880 Casting 0 100% 01/Dec/15 01/Dec/15 01/Dec/15 A 01/Dec/15 A 01/Dec/15 A 01/Dec/15 A
CON5890 Curing 0 100% 02/Dec/15 05/Dec/15 02/Dec/15 A 05/Dec/15 A 02/Dec/15 A 05/Dec/15 A
CON5900 Formwork Removal 0 100% 05/Dec/15 06/Dec/15 05/Dec/15 A 06/Dec/15 A 05/Dec/15 A 06/Dec/15 A
CON5930 Finishing ( Cocrete Repair ) & Painting 0 100% 21/Feb/16 01/Mar/16 21/Feb/16 A 03/Mar/16 A 21/Feb/16 A 03/Mar/16 A
Fire Wall Between (701)
( & (704) 0 100% 20/May/15 10/Mar/16 20/May/15 A 06/Mar/16 A
CON1040 Excavation 0 100% 20/May/15 21/May/15 20/May/15 A 21/May/15 A 20/May/15 A 21/May/15 A
CON1050 Compacting & Leveling 0 100% 20/May/15 28/May/15 20/May/15 A 28/May/15 A 20/May/15 A 28/May/15 A
CON1060 Lean Concrete 0 100% 31/May/15 31/May/15 31/May/15 A 31/May/15 A 31/May/15 A 31/May/15 A
CON1070 Water Proofing Below Foundation 0 100% 07/Jul/15 07/Jul/15 07/Jul/15 A 07/Jul/15 A 07/Jul/15 A 07/Jul/15 A
CON1080 REBARS of Foundation 0 100% 07/Jul/15 15/Aug/15 07/Jul/15 A 16/Aug/15 A 07/Jul/15 A 16/Aug/15 A
CON1090 Foundation Formwork 0 100% 08/Jul/15 15/Aug/15 08/Jul/15 A 16/Aug/15 A 08/Jul/15 A 16/Aug/15 A
CON1100 Check Before Casting 0 100% 30/Aug/15 30/Aug/15 30/Aug/15 A 30/Aug/15 A 30/Aug/15 A 30/Aug/15 A
CON1110 Casting of Foundation 0 100% 30/Aug/15 31/Aug/15 30/Aug/15 A 31/Aug/15 A 30/Aug/15 A 31/Aug/15 A
CON1120 Curing of Foundation 0 100% 31/Aug/15 02/Sep/15 31/Aug/15 A 02/Sep/15 A 31/Aug/15 A 02/Sep/15 A
CON1130 Removal of Formwork 0 100% 03/Sep/15 03/Sep/15 03/Sep/15 A 03/Sep/15 A 03/Sep/15 A 03/Sep/15 A
CON1160 Scafolding Erection 0 100% 04/Oct/15 07/Oct/15 04/Oct/15 A 07/Oct/15 A 04/Oct/15 A 07/Oct/15 A
CON1180 Wall First Part Form Work 0 100% 05/Oct/15 11/Oct/15 05/Oct/15 A 11/Oct/15 A 05/Oct/15 A 11/Oct/15 A
CON1170 Wall REBARS 0 100% 07/Oct/15 08/Oct/15 07/Oct/15 A 08/Oct/15 A 07/Oct/15 A 08/Oct/15 A
CON1190 Check Before Casting 0 100% 13/Oct/15 13/Oct/15 13/Oct/15 A 13/Oct/15 A 13/Oct/15 A 13/Oct/15 A
CON1200 Casting 0 100% 13/Oct/15 14/Oct/15 13/Oct/15 A 14/Oct/15 A 13/Oct/15 A 14/Oct/15 A
CON1210 Curing 0 100% 14/Oct/15 17/Oct/15 14/Oct/15 A 17/Oct/15 A 14/Oct/15 A 17/Oct/15 A
CON12201 Wall REBARS Completion 0 100% 15/Oct/15 29/Nov/15 15/Oct/15 A 29/Nov/15 A 15/Oct/15 A 29/Nov/15 A
CON1230 Wall Second Part Form Work 0 100% 17/Oct/15 30/Nov/15 17/Oct/15 A 30/Nov/15 A 17/Oct/15 A 30/Nov/15 A
CON1140 Water Proofing Work 0 100% 28/Nov/15 29/Nov/15 28/Nov/15 A 29/Nov/15 A 28/Nov/15 A 29/Nov/15 A
CON1150 Backfilling & Compaction 0 100% 29/Nov/15 30/Nov/15 29/Nov/15 A 30/Nov/15 A 29/Nov/15 A 30/Nov/15 A
CON1240 Check Before Casting 0 100% 30/Nov/15 01/Dec/15 30/Nov/15 A 01/Dec/15 A 30/Nov/15 A 01/Dec/15 A
CON12502 Casting 0 100% 01/Dec/15 01/Dec/15 01/Dec/15 A 01/Dec/15 A 01/Dec/15 A 01/Dec/15 A
CON12601 Curing 0 100% 02/Dec/15 05/Dec/15 02/Dec/15 A 05/Dec/15 A 02/Dec/15 A 05/Dec/15 A
CON1270 Formwork Removal 0 100% 05/Dec/15 06/Dec/15 05/Dec/15 A 06/Dec/15 A 05/Dec/15 A 06/Dec/15 A
CON1280 Finishing ( Cocrete Repair ) & Painting 0 100% 01/Mar/16 10/Mar/16 24/Feb/16 A 06/Mar/16 A 24/Feb/16 A 06/Mar/16 A
Fire Wall Between (704)
( & (703) 0 100% 21/May/15 20/Mar/16 21/May/15 A 06/Mar/16 A
CON12901 Excavation 0 100% 21/May/15 21/May/15 21/May/15 A 21/May/15 A 21/May/15 A 21/May/15 A
CON13001 Compacting & Leveling 0 100% 21/May/15 28/May/15 21/May/15 A 28/May/15 A 21/May/15 A 28/May/15 A
CON13101 Lean Concrete 0 100% 31/May/15 31/May/15 31/May/15 A 31/May/15 A 31/May/15 A 31/May/15 A
CON13201 Water Proofing Below Foundation 0 100% 07/Jul/15 07/Jul/15 07/Jul/15 A 07/Jul/15 A 07/Jul/15 A 07/Jul/15 A
CON13301 REBARS of Foundation 0 100% 07/Jul/15 15/Aug/15 07/Jul/15 A 16/Aug/15 A 07/Jul/15 A 16/Aug/15 A
CON13401 Foundation Formwork 0 100% 08/Jul/15 15/Aug/15 08/Jul/15 A 16/Aug/15 A 08/Jul/15 A 16/Aug/15 A
CON13501 Check Before Casting 0 100% 30/Aug/15 30/Aug/15 30/Aug/15 A 30/Aug/15 A 30/Aug/15 A 30/Aug/15 A
CON13601 Casting of Foundation 0 100% 30/Aug/15 31/Aug/15 30/Aug/15 A 31/Aug/15 A 30/Aug/15 A 31/Aug/15 A
CON13701 Curing of Foundation 0 100% 31/Aug/15 02/Sep/15 31/Aug/15 A 02/Sep/15 A 31/Aug/15 A 02/Sep/15 A
CON13801 Removal of Formwork 0 100% 03/Sep/15 03/Sep/15 03/Sep/15 A 03/Sep/15 A 03/Sep/15 A 03/Sep/15 A
CON14101 Scafolding Erection 0 100% 04/Oct/15 07/Oct/15 04/Oct/15 A 07/Oct/15 A 04/Oct/15 A 07/Oct/15 A

Page 26 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON1430 Wall First Part Form Work 0 100% 05/Oct/15 11/Oct/15 05/Oct/15 A 11/Oct/15 A 05/Oct/15 A 11/Oct/15 A
CON1420 Wall REBARS 0 100% 07/Oct/15 08/Oct/15 07/Oct/15 A 08/Oct/15 A 07/Oct/15 A 08/Oct/15 A
CON1440 Check Before Casting 0 100% 13/Oct/15 13/Oct/15 13/Oct/15 A 13/Oct/15 A 13/Oct/15 A 13/Oct/15 A
CON1450 Casting 0 100% 13/Oct/15 14/Oct/15 13/Oct/15 A 14/Oct/15 A 13/Oct/15 A 14/Oct/15 A
CON1460 Curing 0 100% 14/Oct/15 17/Oct/15 14/Oct/15 A 17/Oct/15 A 14/Oct/15 A 17/Oct/15 A
CON1470 Wall REBARS Completion 0 100% 15/Oct/15 29/Nov/15 15/Oct/15 A 29/Nov/15 A 15/Oct/15 A 29/Nov/15 A
CON1480 Wall Second Part Form Work 0 100% 17/Oct/15 30/Nov/15 17/Oct/15 A 30/Nov/15 A 17/Oct/15 A 30/Nov/15 A
CON13901 Water Proofing Work 0 100% 29/Nov/15 30/Nov/15 29/Nov/15 A 30/Nov/15 A 29/Nov/15 A 30/Nov/15 A
CON1490 Check Before Casting 0 100% 30/Nov/15 01/Dec/15 30/Nov/15 A 01/Dec/15 A 30/Nov/15 A 01/Dec/15 A
CON14001 Backfilling & Compaction 0 100% 30/Nov/15 01/Dec/15 30/Nov/15 A 01/Dec/15 A 30/Nov/15 A 01/Dec/15 A
CON1500 Casting 0 100% 01/Dec/15 01/Dec/15 01/Dec/15 A 01/Dec/15 A 01/Dec/15 A 01/Dec/15 A
CON1510 Curing 0 100% 02/Dec/15 05/Dec/15 02/Dec/15 A 05/Dec/15 A 02/Dec/15 A 05/Dec/15 A
CON1520 Formwork Removal 0 100% 05/Dec/15 06/Dec/15 05/Dec/15 A 06/Dec/15 A 05/Dec/15 A 06/Dec/15 A
CON1530 Finishing ( Cocrete Repair ) & Painting 0 100% 10/Mar/16 20/Mar/16 24/Feb/16 A 06/Mar/16 A 24/Feb/16 A 06/Mar/16 A
NGR Foundations 13 0% 15/Mar/16 28/Mar/16 21/Mar/16 02/Apr/16
CON20701 Excavation 1 0% 15/Mar/16 16/Mar/16 21/Mar/16 21/Mar/16 21/Mar/16 21/Mar/16
CON20801 REBARS & Formwork 2 0% 16/Mar/16 19/Mar/16 21/Mar/16 23/Mar/16 21/Mar/16 23/Mar/16
CON20901 Anchor Bolts Planting and Alignment 1 0% 20/Mar/16 20/Mar/16 24/Mar/16 24/Mar/16 24/Mar/16 24/Mar/16
CON21001 Check Before Casting 1 0% 20/Mar/16 21/Mar/16 26/Mar/16 26/Mar/16 26/Mar/16 26/Mar/16
CON21101 Casting 1 0% 21/Mar/16 22/Mar/16 26/Mar/16 27/Mar/16 26/Mar/16 27/Mar/16
CON21201 Curing 3 0% 22/Mar/16 24/Mar/16 27/Mar/16 29/Mar/16 27/Mar/16 29/Mar/16
CON21301 Water Proofing Works 1 0% 24/Mar/16 26/Mar/16 30/Mar/16 30/Mar/16 30/Mar/16 30/Mar/16
CON21501 NGR Support Frames Erection 1 0% 24/Mar/16 26/Mar/16 30/Mar/16 30/Mar/16 30/Mar/16 30/Mar/16
CON21401 Backfilling & Compacting 1 0% 26/Mar/16 27/Mar/16 30/Mar/16 31/Mar/16 30/Mar/16 31/Mar/16
CON21601 Conctrete Repair 1 0% 27/Mar/16 28/Mar/16 31/Mar/16 02/Apr/16 31/Mar/16 02/Apr/16
S/S #5 Auxiliary Transformers
Tran Foundation 2 84.48% 25/Feb/16 15/Mar/16 27/Feb/16 A 22/Mar/16
CON1540 Excavation 0 100% 25/Feb/16 25/Feb/16 27/Feb/16 A 28/Feb/16 A 27/Feb/16 A 28/Feb/16 A
CON1550 Compacting & Leveling 0 100% 25/Feb/16 25/Feb/16 28/Feb/16 A 29/Feb/16 A 28/Feb/16 A 29/Feb/16 A
CON1560 Lean Concrete 0 100% 25/Feb/16 27/Feb/16 29/Feb/16 A 01/Mar/16 A 29/Feb/16 A 01/Mar/16 A
CON1570 Water Proofing Below Foundation 0 100% 27/Feb/16 28/Feb/16 01/Mar/16 A 02/Mar/16 A 01/Mar/16 A 02/Mar/16 A
CON1590 Foundation Formwork 0 100% 29/Feb/16 01/Mar/16 02/Mar/16 A 03/Mar/16 A 02/Mar/16 A 03/Mar/16 A
CON1580 REBARS of Auxiliary Transformers Foundation & Pedistals 0 100% 28/Feb/16 29/Feb/16 02/Mar/16 A 03/Mar/16 A 02/Mar/16 A 03/Mar/16 A
CON1600 Check Before Casting 0 100% 01/Mar/16 02/Mar/16 06/Mar/16 A 06/Mar/16 A 06/Mar/16 A 06/Mar/16 A
CON1610 Casting of Auxiliary Transformers Foundation 0 100% 02/Mar/16 03/Mar/16 07/Mar/16 A 07/Mar/16 A 07/Mar/16 A 07/Mar/16 A
CON1620 Curing of Foundation 0 100% 03/Mar/16 06/Mar/16 07/Mar/16 A 09/Mar/16 A 07/Mar/16 A 09/Mar/16 A
CON1630 Pedistals Formwork 0 100% 05/Mar/16 06/Mar/16 07/Mar/16 A 09/Mar/16 A 07/Mar/16 A 09/Mar/16 A
CON1650 REBARS of Fire Wall 0 100% 06/Mar/16 07/Mar/16 08/Mar/16 A 09/Mar/16 A 08/Mar/16 A 09/Mar/16 A
CON1660 Formwork of Wall 0 100% 07/Mar/16 08/Mar/16 09/Mar/16 A 10/Mar/16 A 09/Mar/16 A 10/Mar/16 A
CON1640 Removal of Foundation Formwork 0 100% 06/Mar/16 07/Mar/16 09/Mar/16 A 10/Mar/16 A 09/Mar/16 A 10/Mar/16 A
CON1670 Check Before Casting 0 100% 08/Mar/16 09/Mar/16 10/Mar/16 A 10/Mar/16 A 10/Mar/16 A 10/Mar/16 A
CON1680 Casting of Auxiliary Transformers Fire Wall & Pedistals 0 100% 09/Mar/16 09/Mar/16 13/Mar/16 A 13/Mar/16 A 13/Mar/16 A 13/Mar/16 A
CON1690 Curing 0 100% 10/Mar/16 13/Mar/16 14/Mar/16 A 17/Mar/16 A 14/Mar/16 A 17/Mar/16 A
CON1700 Removal of Formwork 0 100% 13/Mar/16 14/Mar/16 19/Mar/16 A 20/Mar/16 A 19/Mar/16 A 20/Mar/16 A
CON1710 Water Proofing Work 1 0% 14/Mar/16 14/Mar/16 21/Mar/16 21/Mar/16 21/Mar/16 21/Mar/16
CON1730 Finishing ( Cocrete Repair ) 2 0% 14/Mar/16 15/Mar/16 21/Mar/16 22/Mar/16 21/Mar/16 22/Mar/16
CON1720 Backfilling Compacting Around Auxiliary Transformers Foundation 1 0% 15/Mar/16 15/Mar/16 21/Mar/16 22/Mar/16 21/Mar/16 22/Mar/16
Power Transformers Yard - Concrete Encased PVC Cable Duct Banks 58 0% 28/Mar/16 21/May/16 04/May/16 27/Jun/16
HV Cables DB From S/S #4 to Power Transformes w/ Manholes 22 0% 28/Mar/16 17/Apr/16 04/May/16 24/May/16
CON1740 HV Cables Main Trench From S/S #4 to Power Transformes w/ Manholes 10 0% 28/Mar/16 06/Apr/16 04/May/16 12/May/16 04/May/16 12/May/16
CON1750 HV Cables Branch Trench Portion from Manhole to (702) Foundation 10 0% 06/Apr/16 16/Apr/16 14/May/16 22/May/16 14/May/16 22/May/16
CON1760 HV Cables Branch Trench Portion from Manhole to (701) Foundation 10 0% 06/Apr/16 16/Apr/16 14/May/16 22/May/16 14/May/16 22/May/16

Page 27 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON1770 HV Cables Branch Trench Portion from Manhole to (704) Foundation 10 0% 06/Apr/16 16/Apr/16 14/May/16 22/May/16 14/May/16 22/May/16
CON1780 HV Cables Branch Trench Portion from Manhole to (703) Foundation 10 0% 06/Apr/16 16/Apr/16 14/May/16 22/May/16 14/May/16 22/May/16
CON1920 Backfilling Compacting 7 0% 11/Apr/16 17/Apr/16 18/May/16 24/May/16 18/May/16 24/May/16
Control & LV Cables DB From S/S #4 to S/S #5 & #1 w/ Handholes 22 0% 16/Apr/16 05/May/16 23/May/16 12/Jun/16
CON1800 Control & LV Cables Main DB From S/S #4 to S/S #5 & #1 w/ Handholes 15 0% 16/Apr/16 30/Apr/16 23/May/16 05/Jun/16 23/May/16 05/Jun/16
CON1810 Control & LV Cables from Manhole to S/S #5 Four Branches DB Portions 5 0% 30/Apr/16 04/May/16 06/Jun/16 10/Jun/16 06/Jun/16 10/Jun/16
CON1820 MV & LV Cables from Manhole to S/S #5 Two Branches DB Portions 5 0% 30/Apr/16 04/May/16 06/Jun/16 10/Jun/16 06/Jun/16 10/Jun/16
CON1830 MV & LV Cables from Manhole to S/S #1 Branch DB Portion 5 0% 30/Apr/16 04/May/16 06/Jun/16 10/Jun/16 06/Jun/16 10/Jun/16
CON1860 Control & LV Cables from Manhole to (704) Foundation Branch DB Portion 5 0% 30/Apr/16 04/May/16 06/Jun/16 10/Jun/16 06/Jun/16 10/Jun/16
CON1870 Control & LV Cables from Manhole to (703) Foundation Branch DB Portion 5 0% 30/Apr/16 04/May/16 06/Jun/16 10/Jun/16 06/Jun/16 10/Jun/16
CON1930 Backfilling Compacting 5 0% 01/May/16 05/May/16 07/Jun/16 12/Jun/16 07/Jun/16 12/Jun/16
Control & LV Cables DB From S/S #5 to (702) & (701) Foundations w/ Handholes 16 0% 30/Apr/16 14/May/16 06/Jun/16 20/Jun/16
CON1880 Control & LV Cables Main DB From S/S #5 to (702) & (701) Foundations w/ Handholes 10 0% 30/Apr/16 09/May/16 06/Jun/16 15/Jun/16 06/Jun/16 15/Jun/16
CON1890 Control & LV Cables from Manhole to (702) Foundation Branch DB Portion 5 0% 09/May/16 14/May/16 15/Jun/16 20/Jun/16 15/Jun/16 20/Jun/16
CON1900 Control & LV Cables from Manhole to (701) Foundation Branch DB Portion 5 0% 09/May/16 14/May/16 15/Jun/16 20/Jun/16 15/Jun/16 20/Jun/16
CON1940 Backfilling Compacting 3 0% 11/May/16 14/May/16 18/Jun/16 20/Jun/16 18/Jun/16 20/Jun/16
Control & LV Cables DB From S/S #5 to Auxiliary Transformer Foundation 7 0% 15/May/16 21/May/16 20/Jun/16 27/Jun/16
CON1910 Control & LV Cables DB From S/S #5 to Auxiliary Transformer Foundation 6 0% 15/May/16 19/May/16 20/Jun/16 26/Jun/16 20/Jun/16 26/Jun/16
CON1950 Backfilling Compacting 1 0% 19/May/16 21/May/16 26/Jun/16 27/Jun/16 26/Jun/16 27/Jun/16
Cable Bus Support Foundations
F 99 43.25% 21/Nov/15 30/May/16 21/Nov/15 A 21/Jun/16
CON1970 REBARS & Formwork 0 100% 21/Nov/15 20/Dec/15 21/Nov/15 A 21/Dec/15 A 21/Nov/15 A 21/Dec/15 A
CON1990 Check Before Casting 0 100% 19/Dec/15 19/Dec/15 19/Dec/15 A 19/Dec/15 A 19/Dec/15 A 19/Dec/15 A
CON2000 Casting 0 100% 20/Dec/15 20/Dec/15 20/Dec/15 A 20/Dec/15 A 20/Dec/15 A 20/Dec/15 A
CON2010 Curing 0 100% 20/Dec/15 22/Dec/15 20/Dec/15 A 23/Dec/15 A 20/Dec/15 A 23/Dec/15 A
CON1960 Excavation 10 45% 21/May/16 23/May/16 27/Feb/16 A 29/Mar/16 27/Feb/16 A 29/Mar/16
CON20201 Placing of Pre-casted Foundations & Water Proofing Works 9 0% 23/May/16 24/May/16 26/Mar/16 03/Apr/16 26/Mar/16 03/Apr/16
CON20301 Backfilling & Compacting 9 0% 24/May/16 25/May/16 28/Mar/16 05/Apr/16 28/Mar/16 05/Apr/16
CON2055 Conctrete Repair 9 0% 25/May/16 28/May/16 30/Mar/16 07/Apr/16 30/Mar/16 07/Apr/16
CON1980 Anchor Bolts Planting and Alignment 3 0% 23/May/16 25/May/16 13/Jun/16 16/Jun/16 13/Jun/16 16/Jun/16
CON20501 Cable Bus Supports Installation & Alignment 4 0% 25/May/16 29/May/16 16/Jun/16 20/Jun/16 16/Jun/16 20/Jun/16
CON20601 Grouting 1 0% 29/May/16 30/May/16 20/Jun/16 21/Jun/16 20/Jun/16 21/Jun/16
Power Transformers Yard - Electrical Installation 130 3.34% 09/Jan/16 20/Jul/16 09/Jan/16 A 14/Aug/16
Power Transformer ( 702) Installation 128 3.41% 09/Jan/16 19/Jul/16 09/Jan/16 A 11/Aug/16
CON57810 Arrival to Site of Heavy Transportation Subcontractor Team 0 100% 09/Jan/16 09/Jan/16 A Arrival to Site of Heavy Transportation Subco
CON57830 Arrival to Site of Transformer (702) 0 100% 09/Jan/16 09/Jan/16 A Arrival to Site of Transformer (702)
CON57840 Offloading of Transformer (702) on Foundation 0 100% 14/Jan/16 14/Jan/16 14/Jan/16 A 15/Jan/16 A 14/Jan/16 A 15/Jan/16 A
CON57845 Alighnment of Transformer (702) 0 100% 16/Jan/16 16/Jan/16 15/Jan/16 A 16/Jan/16 A 15/Jan/16 A 16/Jan/16 A
CON57850 Mobilization of Transformer Installation Supervisor (Vendor) 0 0% 20/Mar/16 09/Apr/16 Mobilization of Transformer Installatio
CON57860 Box Opening & Preparation for Work 3 0% 20/Mar/16 23/Mar/16 09/Apr/16 11/Apr/16 09/Apr/16 11/Apr/16
CON57880 Supports of Radiator Banks Installation 2 0% 23/Mar/16 24/Mar/16 11/Apr/16 13/Apr/16 11/Apr/16 13/Apr/16
CON57890 Radiator Banks Installation 2 0% 24/Mar/16 27/Mar/16 13/Apr/16 14/Apr/16 13/Apr/16 14/Apr/16
CON57895 Cable Heads Installation 2 0% 27/Mar/16 28/Mar/16 14/Apr/16 17/Apr/16 14/Apr/16 17/Apr/16
CON57900 Oil Reservoir Installation 1 0% 29/Mar/16 29/Mar/16 17/Apr/16 18/Apr/16 17/Apr/16 18/Apr/16
CON57897 Cable Supports Installation 2 0% 29/Mar/16 30/Mar/16 17/Apr/16 18/Apr/16 17/Apr/16 18/Apr/16
CON57910 Oil Pipes Connections Installation 4 0% 29/Mar/16 02/Apr/16 18/Apr/16 21/Apr/16 18/Apr/16 21/Apr/16
CON57920 Phase Bushings Installation 2 0% 03/Apr/16 04/Apr/16 21/Apr/16 23/Apr/16 21/Apr/16 23/Apr/16
CON57925 Neutral Bushing Installation 1 0% 04/Apr/16 05/Apr/16 23/Apr/16 24/Apr/16 23/Apr/16 24/Apr/16
CON57930 Instrumentations & Guages Installation 2 0% 05/Apr/16 06/Apr/16 24/Apr/16 26/Apr/16 24/Apr/16 26/Apr/16
CON57940 Installation of Radiator Cooling Fans 3 0% 07/Apr/16 10/Apr/16 26/Apr/16 28/Apr/16 26/Apr/16 28/Apr/16
CON57950 Wiring of Fans & Instrumentations to Marchaling Box 4 0% 10/Apr/16 13/Apr/16 28/Apr/16 02/May/16 28/Apr/16 02/May/16
CON58050 Arrival of Power Cables Termination Subcontractor 0 0% 02/May/16 08/Jun/16 Arrival of Power Cables Termina

Page 28 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
Power Transformer (702) Vacuming & Oil Filling 12 0% 07/Apr/16 18/Apr/16 26/Apr/16 07/May/16
CON58100 Vacuming of Power Transformer (702) 5 0% 07/Apr/16 11/Apr/16 26/Apr/16 01/May/16 26/Apr/16 01/May/16
CON58110 Oil Filling of Power Transformer (702) 5 0% 12/Apr/16 16/Apr/16 01/May/16 05/May/16 01/May/16 05/May/16
CON58120 Transformer (702) Ready for Testing 0 0% 16/Apr/16 05/May/16 Transformer (702) Ready for Testin
CON58130 Vacuming & Oil Filling Of Cable Heads, Getting Ready for HV Test of Power Cables 2 0% 17/Apr/16 18/Apr/16 05/May/16 07/May/16 05/May/16 07/May/16
Transformer (702) - 230KV Power Cables Pulling & Termination 36 0% 16/Apr/16 01/Jun/16 23/May/16 25/Jun/16
CON57960 Red Phase Power Cable Pulling 3 0% 16/Apr/16 18/Apr/16 23/May/16 25/May/16 23/May/16 25/May/16
CON57970 Yellow Phase Power Cable Pulling 3 0% 18/Apr/16 20/Apr/16 25/May/16 28/May/16 25/May/16 28/May/16
CON57980 Blue Phase Power Cable Pulling 3 0% 21/Apr/16 24/Apr/16 28/May/16 31/May/16 28/May/16 31/May/16
CON57990 Termination of Red Phase Transformer (702) Side 2 0% 02/May/16 04/May/16 08/Jun/16 10/Jun/16 08/Jun/16 10/Jun/16
CON58000 Termination of Yellow Phase Transformer (702) Side 2 0% 04/May/16 05/May/16 11/Jun/16 12/Jun/16 11/Jun/16 12/Jun/16
CON58010 Termination of Blue Phase Transformer (702) Side 2 0% 05/May/16 08/May/16 12/Jun/16 14/Jun/16 12/Jun/16 14/Jun/16
CON58020 Termination of Red Phase GIS Side 2 0% 26/May/16 28/May/16 19/Jun/16 21/Jun/16 19/Jun/16 21/Jun/16
CON58030 Termination of Yellow Phase GIS Side 2 0% 28/May/16 30/May/16 21/Jun/16 23/Jun/16 21/Jun/16 23/Jun/16
CON58040 Termination of Blue Phase GIS Side 2 0% 30/May/16 01/Jun/16 23/Jun/16 25/Jun/16 23/Jun/16 25/Jun/16
Transformer (702) - 13.8KV Power Cable Bus Installation & Termination 42 0% 06/Jun/16 19/Jul/16 27/Jun/16 11/Aug/16
CON70050 Preparation & Aliginment of Cable Bus for TFR (702) 2 0% 06/Jun/16 07/Jun/16 27/Jun/16 29/Jun/16 27/Jun/16 29/Jun/16
CON70070 13.8KV Power Cable Bus Erection Transformer (702) Side 2 0% 07/Jun/16 09/Jun/16 29/Jun/16 01/Jul/16 29/Jun/16 01/Jul/16
CON70060 13.8KV Power Cable Bus Erection SWGR Side 2 0% 17/Jul/16 19/Jul/16 10/Aug/16 11/Aug/16 10/Aug/16 11/Aug/16
Transformer (702) - NGR Installation & HV Cables Bonding 6 0% 01/Jun/16 06/Jun/16 25/Jun/16 30/Jun/16
CON59080 Installation of NGR 1 0% 01/Jun/16 01/Jun/16 25/Jun/16 26/Jun/16 25/Jun/16 26/Jun/16
CON59090 Bonding Cables & NGR Cables Pulling & Termination to NGR 3 0% 01/Jun/16 05/Jun/16 26/Jun/16 28/Jun/16 26/Jun/16 28/Jun/16
CON59100 Termination to Transformer ( 702 ) 1 0% 05/Jun/16 06/Jun/16 28/Jun/16 29/Jun/16 28/Jun/16 29/Jun/16
CON59110 Bonding Cables Termination to GIS Side 1 0% 06/Jun/16 06/Jun/16 29/Jun/16 30/Jun/16 29/Jun/16 30/Jun/16
Transformer (702) - Control Cables Pulling & Termination 23 0% 14/May/16 04/Jun/16 20/Jun/16 17/Jul/16
CON58060 Control Cable Pulling From TRAFO Set-I &II to Transformer (702) Marchaling Box 2 0% 14/May/16 15/May/16 20/Jun/16 21/Jun/16 20/Jun/16 21/Jun/16
CON58070 Control Cable Termination Set-I &II Panel Side 7 0% 15/May/16 22/May/16 21/Jun/16 28/Jun/16 21/Jun/16 28/Jun/16
CON68680 Control Cable Pulling From AVR & RTCC Panels to Transformer (702) Marchaling Box 2 0% 15/May/16 17/May/16 21/Jun/16 23/Jun/16 21/Jun/16 23/Jun/16
CON68690 Control Cable Termination AVR & RTCC Panels Side 7 0% 22/May/16 28/May/16 28/Jun/16 10/Jul/16 28/Jun/16 10/Jul/16
CON58090 Control Cable Termination Transformer-(702) Side 7 0% 29/May/16 04/Jun/16 10/Jul/16 17/Jul/16 10/Jul/16 17/Jul/16
Power Transformer ( 701) Installation 125 3.49% 09/Jan/16 19/Jul/16 09/Jan/16 A 11/Aug/16
CON58150 Arrival to Site of Transformer (701) 0 100% 09/Jan/16 09/Jan/16 A Arrival to Site of Transformer (701)
CON58160 Offloading of Transformer (701) on Foundation 0 100% 16/Jan/16 17/Jan/16 16/Jan/16 A 18/Jan/16 A 16/Jan/16 A 18/Jan/16 A
CON58170 Alighnment of Transformer (701) 0 100% 17/Jan/16 18/Jan/16 17/Jan/16 A 19/Jan/16 A 17/Jan/16 A 19/Jan/16 A
CON58180 Supports of Radiator Banks Installation 2 0% 23/Mar/16 24/Mar/16 11/Apr/16 13/Apr/16 11/Apr/16 13/Apr/16
CON58190 Radiator Banks Installation 2 0% 24/Mar/16 27/Mar/16 13/Apr/16 14/Apr/16 13/Apr/16 14/Apr/16
CON58200 Cable Heads Installation 2 0% 27/Mar/16 28/Mar/16 14/Apr/16 17/Apr/16 14/Apr/16 17/Apr/16
CON58220 Oil Reservoir Installation 1 0% 29/Mar/16 29/Mar/16 17/Apr/16 18/Apr/16 17/Apr/16 18/Apr/16
CON58210 Cable Supports Installation 2 0% 29/Mar/16 30/Mar/16 17/Apr/16 18/Apr/16 17/Apr/16 18/Apr/16
CON58230 Oil Pipes Connections Installation 4 0% 29/Mar/16 02/Apr/16 18/Apr/16 21/Apr/16 18/Apr/16 21/Apr/16
CON58240 Phase Bushings Installation 2 0% 03/Apr/16 04/Apr/16 21/Apr/16 23/Apr/16 21/Apr/16 23/Apr/16
CON58250 Neutral Bushing Installation 1 0% 04/Apr/16 05/Apr/16 23/Apr/16 24/Apr/16 23/Apr/16 24/Apr/16
CON58260 Instrumentations & Guages Installation 2 0% 05/Apr/16 06/Apr/16 24/Apr/16 26/Apr/16 24/Apr/16 26/Apr/16
CON58270 Installation of Radiator Cooling Fans 3 0% 07/Apr/16 10/Apr/16 26/Apr/16 28/Apr/16 26/Apr/16 28/Apr/16
CON58280 Wiring of Fans & Instrumentations to Marchaling Box 4 0% 10/Apr/16 13/Apr/16 28/Apr/16 02/May/16 28/Apr/16 02/May/16
Power Transformer (701) Vacuming & Oil Filling 12 0% 18/Apr/16 30/Apr/16 07/May/16 18/May/16
CON58290 Vacuming of Power Transformer (701) 5 0% 18/Apr/16 23/Apr/16 07/May/16 11/May/16 07/May/16 11/May/16
CON58300 Oil Filling of Power Transformer (701) 5 0% 23/Apr/16 27/Apr/16 11/May/16 16/May/16 11/May/16 16/May/16
CON58310 Transformer (701) Ready for Testing 0 0% 27/Apr/16 16/May/16 Transformer (701) Ready for Test
CON58320 Vacuming & Oil Filling Of Cable Heads, Getting Ready for HV Test of Power Cables 2 0% 27/Apr/16 30/Apr/16 16/May/16 18/May/16 16/May/16 18/May/16
Transformer (701) - 230KV Power Cables Pulling & Termination 35 0% 24/Apr/16 08/Jun/16 31/May/16 09/Jul/16

Page 29 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON58340 Red Phase Power Cable Pulling 3 0% 24/Apr/16 26/Apr/16 31/May/16 02/Jun/16 31/May/16 02/Jun/16
CON58350 Yellow Phase Power Cable Pulling 3 0% 26/Apr/16 30/Apr/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
CON58360 Blue Phase Power Cable Pulling 3 0% 30/Apr/16 02/May/16 06/Jun/16 08/Jun/16 06/Jun/16 08/Jun/16
CON58370 Termination of Red Phase Transformer (701) Side 2 0% 01/Jun/16 02/Jun/16 25/Jun/16 27/Jun/16 25/Jun/16 27/Jun/16
CON58380 Termination of Yellow Phase Transformer (701) Side 2 0% 02/Jun/16 05/Jun/16 27/Jun/16 28/Jun/16 27/Jun/16 28/Jun/16
CON58400 Termination of Red Phase GIS Side 2 0% 02/Jun/16 05/Jun/16 27/Jun/16 28/Jun/16 27/Jun/16 28/Jun/16
CON58390 Termination of Blue Phase Transformer (701) Side 2 0% 05/Jun/16 06/Jun/16 28/Jun/16 30/Jun/16 28/Jun/16 30/Jun/16
CON58410 Termination of Yellow Phase GIS Side 2 0% 05/Jun/16 06/Jun/16 28/Jun/16 30/Jun/16 28/Jun/16 30/Jun/16
CON58420 Termination of Blue Phase GIS Side 2 0% 06/Jun/16 08/Jun/16 30/Jun/16 09/Jul/16 30/Jun/16 09/Jul/16
Transformer (701) - 13.8KV Power Cable Bus Installation & Termination 34 0% 13/Jun/16 19/Jul/16 11/Jul/16 11/Aug/16
CON70080 Preparation & Aliginment of Cable Bus for TFR (701) 2 0% 13/Jun/16 15/Jun/16 11/Jul/16 12/Jul/16 11/Jul/16 12/Jul/16
CON70100 13.8KV Power Cable Bus Erection Transformer (701) Side 2 0% 15/Jun/16 16/Jun/16 12/Jul/16 14/Jul/16 12/Jul/16 14/Jul/16
CON70090 13.8KV Power Cable Bus Erection SWGR Side 2 0% 17/Jul/16 19/Jul/16 10/Aug/16 11/Aug/16 10/Aug/16 11/Aug/16
Transformer (701) - NGR Installation & HV Cables Bonding 6 0% 08/Jun/16 14/Jun/16 09/Jul/16 13/Jul/16
CON59120 Installation of NGR 1 0% 08/Jun/16 09/Jun/16 09/Jul/16 09/Jul/16 09/Jul/16 09/Jul/16
CON59130 Bonding Cables & NGR Cables Pulling & Termination to NGR 3 0% 09/Jun/16 12/Jun/16 09/Jul/16 12/Jul/16 09/Jul/16 12/Jul/16
CON59140 Termination to Transformer ( 701 ) 1 0% 12/Jun/16 13/Jun/16 12/Jul/16 13/Jul/16 12/Jul/16 13/Jul/16
CON59150 Bonding Cables Termination to GIS Side 1 0% 13/Jun/16 14/Jun/16 13/Jul/16 13/Jul/16 13/Jul/16 13/Jul/16
Transformer (701) - Control Cables Pulling & Termination 20 0% 14/May/16 01/Jun/16 20/Jun/16 13/Jul/16
CON58430 Control Cable Pulling From TRAFO Set-I &II to Transformer (701) Marchaling Box 2 0% 14/May/16 15/May/16 20/Jun/16 21/Jun/16 20/Jun/16 21/Jun/16
CON58440 Control Cable Termination Set-I &II Panel Side 6 0% 15/May/16 21/May/16 21/Jun/16 27/Jun/16 21/Jun/16 27/Jun/16
CON68700 Control Cable Pulling From AVR & RTCC Panels to Transformer (701) Marchaling Box 2 0% 15/May/16 17/May/16 21/Jun/16 23/Jun/16 21/Jun/16 23/Jun/16
CON68710 Control Cable Termination AVR & RTCC Panels Side 6 0% 21/May/16 26/May/16 27/Jun/16 09/Jul/16 27/Jun/16 09/Jul/16
CON58450 Control Cable Termination Transformer-(701) Side 6 0% 26/May/16 01/Jun/16 09/Jul/16 13/Jul/16 09/Jul/16 13/Jul/16
Power Transformer ( 704) Installation 103 3.58% 23/Jan/16 25/Jun/16 23/Jan/16 A 21/Jul/16
CON58460 Arrival to Site of Transformer (704) 0 100% 23/Jan/16 23/Jan/16 A Arrival to Site of Transformer (704)
CON58470 Offloading of Transformer (704) on Foundation 0 100% 23/Jan/16 23/Jan/16 23/Jan/16 A 24/Jan/16 A 23/Jan/16 A 24/Jan/16 A
CON58480 Alighnment of Transformer (704) 0 100% 24/Jan/16 24/Jan/16 24/Jan/16 A 25/Jan/16 A 24/Jan/16 A 25/Jan/16 A
CON58490 Supports of Radiator Banks Installation 2 0% 23/Mar/16 24/Mar/16 11/Apr/16 13/Apr/16 11/Apr/16 13/Apr/16
CON58500 Radiator Banks Installation 2 0% 24/Mar/16 27/Mar/16 13/Apr/16 14/Apr/16 13/Apr/16 14/Apr/16
CON58510 Cable Heads Installation 2 0% 27/Mar/16 28/Mar/16 24/Apr/16 25/Apr/16 24/Apr/16 25/Apr/16
CON58530 Oil Reservoir Installation 1 0% 29/Mar/16 29/Mar/16 26/Apr/16 26/Apr/16 26/Apr/16 26/Apr/16
CON58520 Cable Supports Installation 2 0% 29/Mar/16 30/Mar/16 26/Apr/16 27/Apr/16 26/Apr/16 27/Apr/16
CON58540 Oil Pipes Connections Installation 4 0% 29/Mar/16 02/Apr/16 26/Apr/16 30/Apr/16 26/Apr/16 30/Apr/16
CON58550 Phase Bushings Installation 2 0% 03/Apr/16 04/Apr/16 01/May/16 02/May/16 01/May/16 02/May/16
CON58560 Neutral Bushing Installation 1 0% 04/Apr/16 05/Apr/16 02/May/16 03/May/16 02/May/16 03/May/16
CON58570 Instrumentations & Guages Installation 2 0% 05/Apr/16 06/Apr/16 03/May/16 04/May/16 03/May/16 04/May/16
CON58580 Installation of Radiator Cooling Fans 3 0% 07/Apr/16 10/Apr/16 05/May/16 08/May/16 05/May/16 08/May/16
CON58590 Wiring of Fans & Instrumentations to Marchaling Box 4 0% 10/Apr/16 13/Apr/16 08/May/16 11/May/16 08/May/16 11/May/16
Power Transformer (704) Vacuming & Oil Filling 12 0% 30/Apr/16 10/May/16 18/May/16 30/May/16
CON58600 Vacuming of Power Transformer (704) 5 0% 30/Apr/16 04/May/16 18/May/16 23/May/16 18/May/16 23/May/16
CON58610 Oil Filling of Power Transformer (704) 5 0% 04/May/16 09/May/16 23/May/16 28/May/16 23/May/16 28/May/16
CON58620 Transformer (704) Ready for Testing 0 0% 09/May/16 28/May/16 Transformer (704) Ready for Tes
CON58630 Vacuming & Oil Filling Of Cable Heads, Getting Ready for HV Test of Power Cables 2 0% 09/May/16 10/May/16 28/May/16 30/May/16 28/May/16 30/May/16
Transformer (704) - 230KV Power Cables Pulling & Termination 40 0% 26/Apr/16 15/Jun/16 02/Jun/16 16/Jul/16
CON58650 Red Phase Power Cable Pulling 3 0% 26/Apr/16 30/Apr/16 02/Jun/16 05/Jun/16 02/Jun/16 05/Jun/16
CON58660 Yellow Phase Power Cable Pulling 3 0% 30/Apr/16 02/May/16 06/Jun/16 08/Jun/16 06/Jun/16 08/Jun/16
CON58670 Blue Phase Power Cable Pulling 3 0% 02/May/16 04/May/16 08/Jun/16 11/Jun/16 08/Jun/16 11/Jun/16
CON58680 Termination of Red Phase Transformer (704) Side 2 0% 08/Jun/16 11/Jun/16 09/Jul/16 10/Jul/16 09/Jul/16 10/Jul/16
CON58690 Termination of Yellow Phase Transformer (704) Side 2 0% 11/Jun/16 12/Jun/16 10/Jul/16 12/Jul/16 10/Jul/16 12/Jul/16
CON58710 Termination of Red Phase GIS Side 2 0% 11/Jun/16 12/Jun/16 10/Jul/16 12/Jul/16 10/Jul/16 12/Jul/16

Page 30 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON58700 Termination of Blue Phase Transformer (704) Side 2 0% 12/Jun/16 14/Jun/16 12/Jul/16 13/Jul/16 12/Jul/16 13/Jul/16
CON58720 Termination of Yellow Phase GIS Side 2 0% 12/Jun/16 14/Jun/16 12/Jul/16 13/Jul/16 12/Jul/16 13/Jul/16
CON58730 Termination of Blue Phase GIS Side 2 0% 14/Jun/16 15/Jun/16 13/Jul/16 16/Jul/16 13/Jul/16 16/Jul/16
Transformer (704) - 13.8KV Power Cable Bus Installation & Termination 4 0% 21/Jun/16 25/Jun/16 18/Jul/16 21/Jul/16
CON70110 Preparation & Aliginment of Cable Bus for TFR (704) 2 0% 21/Jun/16 22/Jun/16 18/Jul/16 20/Jul/16 18/Jul/16 20/Jul/16
CON70130 13.8KV Power Cable Bus Erection Transformer (704) Side 2 0% 22/Jun/16 25/Jun/16 20/Jul/16 21/Jul/16 20/Jul/16 21/Jul/16
Transformer (704) - NGR Installation & HV Cables Bonding 6 0% 15/Jun/16 21/Jun/16 16/Jul/16 21/Jul/16
CON59160 Installation of NGR 1 0% 15/Jun/16 16/Jun/16 16/Jul/16 17/Jul/16 16/Jul/16 17/Jul/16
CON59170 Bonding Cables & NGR Cables Pulling & Termination to NGR 3 0% 16/Jun/16 20/Jun/16 17/Jul/16 19/Jul/16 17/Jul/16 19/Jul/16
CON59180 Termination to Transformer ( 704 ) 1 0% 20/Jun/16 20/Jun/16 19/Jul/16 20/Jul/16 19/Jul/16 20/Jul/16
CON59190 Bonding Cable Termination to GIS Side 1 0% 20/Jun/16 21/Jun/16 20/Jul/16 21/Jul/16 20/Jul/16 21/Jul/16
Transformer (704) - Control Cables Pulling & Termination 20 0% 04/May/16 24/May/16 11/Jun/16 29/Jun/16
CON58740 Control Cable Pulling From TRAFO Set-I &II to Transformer (704) Marchaling Box @ S/S #4 2 0% 04/May/16 05/May/16 11/Jun/16 12/Jun/16 11/Jun/16 12/Jun/16
CON58750 Control Cable Termination Set-I &II Panel Side @ S/S #4 6 0% 08/May/16 14/May/16 12/Jun/16 18/Jun/16 12/Jun/16 18/Jun/16
CON68720 Control Cable Pulling From AVR & RTCC Panels to Transformer (704) Marchaling Box @ S 2 0% 05/May/16 08/May/16 12/Jun/16 14/Jun/16 12/Jun/16 14/Jun/16
CON68730 Control Cable Termination AVR & RTCC Panels Side @ S/S #5 6 0% 14/May/16 19/May/16 18/Jun/16 23/Jun/16 18/Jun/16 23/Jun/16
CON58760 Control Cable Termination Transformer-(704) Side 6 0% 19/May/16 24/May/16 23/Jun/16 29/Jun/16 23/Jun/16 29/Jun/16
Power Transformer ( 703) Installation 111 3.62% 23/Jan/16 02/Jul/16 23/Jan/16 A 30/Jul/16
CON58770 Arrival to Site of Transformer (703) 0 100% 23/Jan/16 23/Jan/16 A Arrival to Site of Transformer (703)
CON58780 Offloading of Transformer (703) on Foundation 0 100% 24/Jan/16 25/Jan/16 24/Jan/16 A 26/Jan/16 A 24/Jan/16 A 26/Jan/16 A
CON58790 Alighnment of Transformer (703) 0 100% 26/Jan/16 26/Jan/16 26/Jan/16 A 27/Jan/16 A 26/Jan/16 A 27/Jan/16 A
CON58800 Supports of Radiator Banks Installation 2 0% 23/Mar/16 24/Mar/16 11/Apr/16 13/Apr/16 11/Apr/16 13/Apr/16
CON58810 Radiator Banks Installation 2 0% 24/Mar/16 27/Mar/16 13/Apr/16 14/Apr/16 13/Apr/16 14/Apr/16
CON58820 Cable Heads Installation 2 0% 27/Mar/16 28/Mar/16 03/May/16 04/May/16 03/May/16 04/May/16
CON58840 Oil Reservoir Installation 1 0% 29/Mar/16 29/Mar/16 05/May/16 05/May/16 05/May/16 05/May/16
CON58830 Cable Supports Installation 2 0% 29/Mar/16 30/Mar/16 05/May/16 07/May/16 05/May/16 07/May/16
CON58850 Oil Pipes Connections Installation 4 0% 29/Mar/16 02/Apr/16 05/May/16 09/May/16 05/May/16 09/May/16
CON58860 Phase Bushings Installation 2 0% 03/Apr/16 04/Apr/16 10/May/16 11/May/16 10/May/16 11/May/16
CON58870 Neutral Bushing Installation 1 0% 04/Apr/16 05/Apr/16 11/May/16 12/May/16 11/May/16 12/May/16
CON58880 Instrumentations & Guages Installation 2 0% 05/Apr/16 06/Apr/16 12/May/16 14/May/16 12/May/16 14/May/16
CON58890 Installation of Radiator Cooling Fans 3 0% 07/Apr/16 10/Apr/16 15/May/16 17/May/16 15/May/16 17/May/16
CON58900 Wiring of Fans & Instrumentations to Marchaling Box 4 0% 10/Apr/16 13/Apr/16 17/May/16 21/May/16 17/May/16 21/May/16
Power Transformer (703) Vacuming & Oil Filling 12 0% 10/May/16 22/May/16 30/May/16 09/Jun/16
CON58910 Vacuming of Power Transformer (703) 5 0% 10/May/16 15/May/16 30/May/16 04/Jun/16 30/May/16 04/Jun/16
CON58920 Oil Filling of Power Transformer (703) 5 0% 15/May/16 19/May/16 04/Jun/16 08/Jun/16 04/Jun/16 08/Jun/16
CON58930 Transformer (703) Ready for Testing 0 0% 19/May/16 08/Jun/16 Transformer (703) Ready for Te
CON58940 Vacuming & Oil Filling Of Cable Heads, Getting Ready for HV Test of Power Cables 2 0% 19/May/16 22/May/16 08/Jun/16 09/Jun/16 08/Jun/16 09/Jun/16
Transformer (703) - 230KV Power Cables Pulling & Termination 45 0% 30/Apr/16 23/Jun/16 06/Jun/16 23/Jul/16
CON58960 Red Phase Power Cable Pulling 3 0% 30/Apr/16 02/May/16 06/Jun/16 08/Jun/16 06/Jun/16 08/Jun/16
CON58970 Yellow Phase Power Cable Pulling 3 0% 02/May/16 04/May/16 08/Jun/16 11/Jun/16 08/Jun/16 11/Jun/16
CON58980 Blue Phase Power Cable Pulling 3 0% 05/May/16 08/May/16 11/Jun/16 14/Jun/16 11/Jun/16 14/Jun/16
CON58990 Termination of Red Phase Transformer (703) Side 2 0% 15/Jun/16 18/Jun/16 16/Jul/16 18/Jul/16 16/Jul/16 18/Jul/16
CON59000 Termination of Yellow Phase Transformer (703) Side 2 0% 18/Jun/16 20/Jun/16 18/Jul/16 19/Jul/16 18/Jul/16 19/Jul/16
CON59020 Termination of Red Phase GIS Side 2 0% 18/Jun/16 20/Jun/16 18/Jul/16 19/Jul/16 18/Jul/16 19/Jul/16
CON59010 Termination of Blue Phase Transformer (703) Side 2 0% 20/Jun/16 21/Jun/16 19/Jul/16 21/Jul/16 19/Jul/16 21/Jul/16
CON59030 Termination of Yellow Phase GIS Side 2 0% 20/Jun/16 21/Jun/16 19/Jul/16 21/Jul/16 19/Jul/16 21/Jul/16
CON59040 Termination of Blue Phase GIS Side 2 0% 21/Jun/16 23/Jun/16 21/Jul/16 23/Jul/16 21/Jul/16 23/Jul/16
Transformer (703) - 13.8KV Power Cable Bus Installation & Termination 4 0% 28/Jun/16 02/Jul/16 26/Jul/16 30/Jul/16
CON70140 Preparation & Aliginment of Cable Bus for TFR (703) 2 0% 28/Jun/16 30/Jun/16 26/Jul/16 27/Jul/16 26/Jul/16 27/Jul/16
CON70150 13.8KV Power Cable Bus Erection SWGR Side 2 0% 30/Jun/16 02/Jul/16 27/Jul/16 30/Jul/16 27/Jul/16 30/Jul/16
CON70160 13.8KV Power Cable Erection Transformer (703) Side 2 0% 30/Jun/16 02/Jul/16 27/Jul/16 30/Jul/16 27/Jul/16 30/Jul/16

Page 31 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
Transformer (703) - NGR Installation & HV Cables Bonding 6 0% 23/Jun/16 29/Jun/16 23/Jul/16 28/Jul/16
CON59200 Installation of NGR 1 0% 23/Jun/16 25/Jun/16 23/Jul/16 24/Jul/16 23/Jul/16 24/Jul/16
CON59210 Bonding Cables & NGR Cables Pulling & Termination to NGR 3 0% 25/Jun/16 27/Jun/16 24/Jul/16 27/Jul/16 24/Jul/16 27/Jul/16
CON59220 Termination to Transformer ( 703 ) 1 0% 27/Jun/16 28/Jun/16 27/Jul/16 27/Jul/16 27/Jul/16 27/Jul/16
CON59230 Bonding Cables Termination to GIS Side 1 0% 28/Jun/16 29/Jun/16 27/Jul/16 28/Jul/16 27/Jul/16 28/Jul/16
Transformer (703) - Control Cables Pulling & Termination 20 0% 04/May/16 29/May/16 11/Jun/16 29/Jun/16
CON59050 Control Cable Pulling From TRAFO Set-I &II to Transformer (703) Marchaling Box 2 0% 04/May/16 05/May/16 11/Jun/16 12/Jun/16 11/Jun/16 12/Jun/16
CON59060 Control Cable Termination Set-I &II Panel Side 6 0% 11/May/16 17/May/16 12/Jun/16 18/Jun/16 12/Jun/16 18/Jun/16
CON68740 Control Cable Pulling From AVR & RTCC Panels to Transformer (703) Marchaling Box 2 0% 05/May/16 08/May/16 12/Jun/16 14/Jun/16 12/Jun/16 14/Jun/16
CON68750 Control Cable Termination AVR & RTCC Panels Side 6 0% 17/May/16 23/May/16 18/Jun/16 23/Jun/16 18/Jun/16 23/Jun/16
CON59070 Control Cable Termination Transformer-(703) Side 6 0% 23/May/16 29/May/16 23/Jun/16 29/Jun/16 23/Jun/16 29/Jun/16
Auxiliary Transformers
Transforme 118 0% 12/Apr/16 20/Jul/16 19/Apr/16 14/Aug/16
CON60690 Placing of Auxiliary Transformers on Foundation 2 0% 12/Apr/16 14/Apr/16 19/Apr/16 21/Apr/16 19/Apr/16 21/Apr/16
CON60700 MV Power Cables Pulling & Termination (Auxi. TFR Side) 4 0% 21/May/16 24/May/16 27/Jun/16 30/Jun/16 27/Jun/16 30/Jun/16
CON60710 LV Power Cables Pulling & Termination (Auxi. TFR Side) 4 0% 24/May/16 28/May/16 30/Jun/16 10/Jul/16 30/Jun/16 10/Jul/16
CON60720 Control Cables Pulling & Termination (Auxi. TFR Side) 4 0% 29/May/16 01/Jun/16 10/Jul/16 13/Jul/16 10/Jul/16 13/Jul/16
CON69100 Control Cables Termination (13.8KV SWGR Side) 4 0% 01/Jun/16 05/Jun/16 18/Jul/16 21/Jul/16 18/Jul/16 21/Jul/16
CON69110 Control Cables Termination (480V SWGR Side) 4 0% 02/Jun/16 06/Jun/16 19/Jul/16 23/Jul/16 19/Jul/16 23/Jul/16
CON69090 MV Power Cables Termination (SWGRSide) 4 0% 17/Jul/16 20/Jul/16 10/Aug/16 14/Aug/16 10/Aug/16 14/Aug/16
Power Transformers Yard - Electromechanical Works 108 0% 14/Apr/16 14/Jul/16 23/Apr/16 08/Aug/16
Power Transformers Yard -Cable Bus Installation 94 0% 14/Apr/16 28/Jun/16 23/Apr/16 25/Jul/16
CON60790 Auxiliary Transformers Cable Bus Installation 2 0% 14/Apr/16 16/Apr/16 23/Apr/16 25/Apr/16 23/Apr/16 25/Apr/16
CON59240 Transformer (702) Cable Bus Installation 8 0% 29/May/16 06/Jun/16 20/Jun/16 27/Jun/16 20/Jun/16 27/Jun/16
CON59250 Transformer (701) Cable Bus Installation 8 0% 06/Jun/16 13/Jun/16 27/Jun/16 11/Jul/16 27/Jun/16 11/Jul/16
CON59260 Transformer (704) Cable Bus Installation 8 0% 13/Jun/16 21/Jun/16 11/Jul/16 18/Jul/16 11/Jul/16 18/Jul/16
CON59270 Transformer (703) Cable Bus Installation 8 0% 21/Jun/16 28/Jun/16 18/Jul/16 25/Jul/16 18/Jul/16 25/Jul/16
Power Transformers Yard -Fire Fighting / Fire Alarm Water Spray System (Sub-contracted) 57 0% 18/Apr/16 04/Jun/16 19/May/16 17/Jul/16
Power Transformer (702) Water Spray System Installation 10 0% 18/Apr/16 27/Apr/16 19/May/16 29/May/16
CON59350 Sprinklers & Detectors Frame Support Installation For Transformer (702) 2 0% 18/Apr/16 20/Apr/16 19/May/16 21/May/16 19/May/16 21/May/16
CON59360 Conduits Installation 1 0% 20/Apr/16 20/Apr/16 21/May/16 22/May/16 21/May/16 22/May/16
CON59370 Pipes Installation 2 0% 21/Apr/16 23/Apr/16 22/May/16 24/May/16 22/May/16 24/May/16
CON59380 Transormer (702) Deluge Valve Installation 3 0% 23/Apr/16 25/Apr/16 24/May/16 26/May/16 24/May/16 26/May/16
CON59410 Sprinklers Installation 2 0% 26/Apr/16 27/Apr/16 26/May/16 29/May/16 26/May/16 29/May/16
Power Transformer (701) Water Spray System Installation 10 0% 30/Apr/16 09/May/16 19/May/16 29/May/16
CON59420 Sprinklers & Detectors Frame Support Installation For Transformer (701) 2 0% 30/Apr/16 01/May/16 19/May/16 21/May/16 19/May/16 21/May/16
CON59430 Conduits Installation 1 0% 01/May/16 02/May/16 21/May/16 22/May/16 21/May/16 22/May/16
CON59440 Pipes Installation 2 0% 02/May/16 04/May/16 22/May/16 24/May/16 22/May/16 24/May/16
CON59450 Transormer (701) Deluge Valve Installation 3 0% 04/May/16 07/May/16 24/May/16 26/May/16 24/May/16 26/May/16
CON59480 Sprinklers Installation 2 0% 07/May/16 09/May/16 26/May/16 29/May/16 26/May/16 29/May/16
Power Transformer (704) Water Spray System Installation 10 0% 10/May/16 19/May/16 30/May/16 08/Jun/16
CON59490 Sprinklers & Detectors Frame Support Installation For Transformer (704) 2 0% 10/May/16 12/May/16 30/May/16 31/May/16 30/May/16 31/May/16
CON59500 Conduits Installation 1 0% 12/May/16 14/May/16 31/May/16 01/Jun/16 31/May/16 01/Jun/16
CON59510 Pipes Installation 2 0% 14/May/16 15/May/16 01/Jun/16 04/Jun/16 01/Jun/16 04/Jun/16
CON59520 Transormer (704) Deluge Valve Installation 3 0% 15/May/16 18/May/16 04/Jun/16 06/Jun/16 04/Jun/16 06/Jun/16
CON59550 Sprinklers Installation 2 0% 18/May/16 19/May/16 06/Jun/16 08/Jun/16 06/Jun/16 08/Jun/16
Power Transformer (703) Water Spray System Installation 10 0% 22/May/16 31/May/16 09/Jun/16 19/Jun/16
CON59560 Sprinklers & Detectors Frame Support Installation For Transformer (703) 2 0% 22/May/16 23/May/16 09/Jun/16 12/Jun/16 09/Jun/16 12/Jun/16
CON59570 Conduits Installation 1 0% 24/May/16 24/May/16 12/Jun/16 13/Jun/16 12/Jun/16 13/Jun/16
CON59580 Pipes Installation 2 0% 24/May/16 26/May/16 13/Jun/16 14/Jun/16 13/Jun/16 14/Jun/16
CON59590 Transformer (703) Deluge Valve Installation 3 0% 26/May/16 29/May/16 14/Jun/16 18/Jun/16 14/Jun/16 18/Jun/16
CON59620 Sprinklers Installation 2 0% 29/May/16 31/May/16 18/Jun/16 19/Jun/16 18/Jun/16 19/Jun/16
Power Transformers
Transformer Yard - Auxiliary Transformers Fire Alarm Installation 3 0% 01/Jun/16 04/Jun/16 14/Jul/16 17/Jul/16

Page 32 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON60730 Detectors Frame Support Installation For Auxiliary Transformers 2 0% 01/Jun/16 02/Jun/16 14/Jul/16 16/Jul/16 14/Jul/16 16/Jul/16
CON60740 Conduits Installation 1 0% 02/Jun/16 04/Jun/16 16/Jul/16 17/Jul/16 16/Jul/16 17/Jul/16
Power Transformers Yard -Lighting 32 0% 02/May/16 21/May/16 26/May/16 25/Jun/16
CON59280 Yard - Lighting & Small Power Ducts Fixation on Fire Walls 2 0% 02/May/16 04/May/16 26/May/16 29/May/16 26/May/16 29/May/16
CON59290 Wires Pulling to Lighting Panel 2 0% 14/May/16 15/May/16 20/Jun/16 21/Jun/16 20/Jun/16 21/Jun/16
CON59300 Lighting Fixtures Installation 2 0% 16/May/16 17/May/16 21/Jun/16 23/Jun/16 21/Jun/16 23/Jun/16
CON59310 Sockets Installation 2 0% 19/May/16 21/May/16 23/Jun/16 25/Jun/16 23/Jun/16 25/Jun/16
Earthing & Grounding
Groundin 12 0% 28/Jun/16 14/Jul/16 27/Jul/16 08/Aug/16
CON59320 Earthing of Transformers Body 4 0% 28/Jun/16 02/Jul/16 27/Jul/16 01/Aug/16 27/Jul/16 01/Aug/16
CON59325 Earthing of Auxiliary Transformers Body 2 0% 02/Jul/16 10/Jul/16 01/Aug/16 02/Aug/16 01/Aug/16 02/Aug/16
CON59330 Earthing of Cable Bus 4 0% 10/Jul/16 13/Jul/16 02/Aug/16 06/Aug/16 02/Aug/16 06/Aug/16
CON59340 Earthing of Fire Fighting Sprinklers Frames & Pipes & Valves 2 0% 13/Jul/16 14/Jul/16 06/Aug/16 08/Aug/16 06/Aug/16 08/Aug/16
Power Transformers Yard - Testing & Pre-commissioning (Sub-contracted) 131 0% 17/Apr/16 17/Aug/16 05/May/16 11/Sep/16
Power Transformer ( 702) Testing 117 0% 17/Apr/16 03/Aug/16 05/May/16 28/Aug/16
Power Transformer ( 702) Electrical & Mechanical Testing 6 0% 17/Apr/16 21/Apr/16 05/May/16 11/May/16
CON62400 TFR (702) Visual Inspection 1 0% 17/Apr/16 17/Apr/16 05/May/16 07/May/16 05/May/16 07/May/16
CON62410 TFR (702) Pressure Test 2 0% 17/Apr/16 18/Apr/16 05/May/16 07/May/16 05/May/16 07/May/16
CON62460 TFR (702) Temperature Sensor Calibration 1 0% 17/Apr/16 18/Apr/16 07/May/16 07/May/16 07/May/16 07/May/16
CON62480 TFR (702) Cooling System Test 1 0% 17/Apr/16 18/Apr/16 07/May/16 07/May/16 07/May/16 07/May/16
CON62490 TFR (702) Fan & OLTC Motor Current Test 1 0% 17/Apr/16 18/Apr/16 07/May/16 07/May/16 07/May/16 07/May/16
CON62430 TFR (702) Ratio,Phase Relation, Magnetizing Current & Polarizing Index 1 0% 18/Apr/16 19/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON62470 TFR (702) Oil Breakdown Test 1 0% 18/Apr/16 19/Apr/16 07/May/16 08/May/16 07/May/16 08/May/16
CON62440 TFR (702) TFR Impedence 1 0% 19/Apr/16 20/Apr/16 08/May/16 09/May/16 08/May/16 09/May/16
CON62450 TFR (702) Tan Delta 1 0% 20/Apr/16 20/Apr/16 09/May/16 10/May/16 09/May/16 10/May/16
CON62500 TFR (702) Core & Winding Insulation Test 1 0% 21/Apr/16 21/Apr/16 10/May/16 11/May/16 10/May/16 11/May/16
Power Transformer ( 702) Protection & Control Testing 46 0% 04/Jun/16 03/Aug/16 17/Jul/16 28/Aug/16
CON62390 TFR (702) MCBs & Auxiliary Relays Testing 1 0% 11/Jun/16 12/Jun/16 17/Jul/16 18/Jul/16 17/Jul/16 18/Jul/16
CON62420 TFR (702) Bushing CT Test 1 0% 04/Jun/16 05/Jun/16 17/Jul/16 18/Jul/16 17/Jul/16 18/Jul/16
CON62510 TFR (702) Scheme & Function Test 4 0% 16/Jul/16 19/Jul/16 09/Aug/16 13/Aug/16 09/Aug/16 13/Aug/16
CON70220 TFR (702) Closed Loop S/S #5 4 0% 19/Jul/16 24/Jul/16 13/Aug/16 16/Aug/16 13/Aug/16 16/Aug/16
CON70210 TFR (702) Closed Loop S/S #4 4 0% 31/Jul/16 03/Aug/16 24/Aug/16 28/Aug/16 24/Aug/16 28/Aug/16
Power Transformer ( 701) Testing 94 0% 27/Apr/16 25/Jul/16 16/May/16 18/Aug/16
Power Transformer ( 701) Electrical & Mechanical Testing 6 0% 27/Apr/16 03/May/16 16/May/16 22/May/16
CON62520 TFR (701) Visual Inspection 1 0% 27/Apr/16 28/Apr/16 16/May/16 17/May/16 16/May/16 17/May/16
CON62530 TFR (701) Pressure Test 2 0% 27/Apr/16 30/Apr/16 16/May/16 18/May/16 16/May/16 18/May/16
CON62540 TFR (701) Teperature Sensor Calibration 1 0% 28/Apr/16 30/Apr/16 17/May/16 18/May/16 17/May/16 18/May/16
CON62550 TFR (701) Cooling System Test 1 0% 28/Apr/16 30/Apr/16 17/May/16 18/May/16 17/May/16 18/May/16
CON62560 TFR (701) Fan & OLTC Motor Current Test 1 0% 28/Apr/16 30/Apr/16 17/May/16 18/May/16 17/May/16 18/May/16
CON62570 TFR (701) Ratio,Phase Relation, Magnetizing Current & Polarizing Index 1 0% 30/Apr/16 30/Apr/16 18/May/16 19/May/16 18/May/16 19/May/16
CON62580 TFR (701) Oil Breakdown Test 1 0% 30/Apr/16 30/Apr/16 18/May/16 19/May/16 18/May/16 19/May/16
CON62590 TFR (701) TFR Impedence 1 0% 01/May/16 01/May/16 19/May/16 21/May/16 19/May/16 21/May/16
CON62600 TFR (701) Tan Delta 1 0% 01/May/16 02/May/16 21/May/16 21/May/16 21/May/16 21/May/16
CON62610 TFR (701) Core & Winding Insulation Test 1 0% 02/May/16 03/May/16 21/May/16 22/May/16 21/May/16 22/May/16
Power Transformer ( 701) Protection & Control Testing 38 0% 01/Jun/16 25/Jul/16 14/Jul/16 18/Aug/16
CON62630 TFR (701) MCBs & Auxiliary Relays Testing 1 0% 11/Jun/16 12/Jun/16 14/Jul/16 14/Jul/16 14/Jul/16 14/Jul/16
CON62620 TFR (701) Bushing CT Test 1 0% 01/Jun/16 01/Jun/16 14/Jul/16 14/Jul/16 14/Jul/16 14/Jul/16
CON62640 TFR (701) Scheme & Function Test 4 0% 27/Jun/16 30/Jun/16 27/Jul/16 31/Jul/16 27/Jul/16 31/Jul/16
CON70250 TFR (701) Closed Loop S/S #5 4 0% 30/Jun/16 10/Jul/16 31/Jul/16 03/Aug/16 31/Jul/16 03/Aug/16
CON70240 TFR (701) Closed Loop S/S #4 4 0% 21/Jul/16 25/Jul/16 15/Aug/16 18/Aug/16 15/Aug/16 18/Aug/16
Power Transformer ( 704) Testing 105 0% 09/May/16 15/Aug/16 28/May/16 10/Sep/16
Power Transformer ( 704) Electrical & Mechanical Testing 6 0% 09/May/16 14/May/16 28/May/16 02/Jun/16
CON62650 TFR (704) Visual Inspection 2 0% 09/May/16 10/May/16 28/May/16 30/May/16 28/May/16 30/May/16

Page 33 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON62660 TFR (704) Pressure Test 2 0% 09/May/16 10/May/16 28/May/16 30/May/16 28/May/16 30/May/16
CON62670 TFR (704) Teperature Sensor Calibration 1 0% 10/May/16 10/May/16 29/May/16 30/May/16 29/May/16 30/May/16
CON62680 TFR (704) Cooling System Test 1 0% 10/May/16 10/May/16 29/May/16 30/May/16 29/May/16 30/May/16
CON62700 TFR (704) Ratio,Phase Relation, Magnetizing Current & Polarizing Index 1 0% 10/May/16 11/May/16 30/May/16 30/May/16 30/May/16 30/May/16
CON62710 TFR (704) Oil Breakdown Test 1 0% 10/May/16 11/May/16 30/May/16 30/May/16 30/May/16 30/May/16
CON62690 TFR (704) Fan & OLTC Motor Current Test 1 0% 10/May/16 11/May/16 30/May/16 30/May/16 30/May/16 30/May/16
CON62720 TFR (704) TFR Impedence 1 0% 11/May/16 12/May/16 30/May/16 31/May/16 30/May/16 31/May/16
CON62730 TFR (704) Tan Delta 1 0% 12/May/16 14/May/16 31/May/16 01/Jun/16 31/May/16 01/Jun/16
CON62740 TFR (704) Core & Winding Insulation Test 1 0% 14/May/16 14/May/16 01/Jun/16 02/Jun/16 01/Jun/16 02/Jun/16
Power Transformer ( 704) Protection & Control Testing 71 0% 25/May/16 15/Aug/16 29/Jun/16 10/Sep/16
CON62750 TFR (704) Bushing CT Test 1 0% 25/May/16 25/May/16 29/Jun/16 29/Jun/16 29/Jun/16 29/Jun/16
CON62760 TFR (704) MCBs & Auxiliary Relays Testing 1 0% 11/Jun/16 12/Jun/16 11/Jul/16 12/Jul/16 11/Jul/16 12/Jul/16
CON62770 TFR (704) Scheme & Function Test 4 0% 18/Jul/16 21/Jul/16 10/Aug/16 15/Aug/16 10/Aug/16 15/Aug/16
CON70270 TFR (704) Closed Loop S/S #4 4 0% 04/Aug/16 08/Aug/16 28/Aug/16 31/Aug/16 28/Aug/16 31/Aug/16
CON70280 TFR (704) Closed Loop S/S #5 4 0% 08/Aug/16 11/Aug/16 01/Sep/16 05/Sep/16 01/Sep/16 05/Sep/16
CON70290 TFR (704) Closed Loop with PMC 4 0% 11/Aug/16 15/Aug/16 05/Sep/16 10/Sep/16 05/Sep/16 10/Sep/16
Power Transformer ( 703) Testing 95 0% 19/May/16 17/Aug/16 08/Jun/16 11/Sep/16
Power Transformer ( 703) Electrical & Mechanical Testing 6 0% 19/May/16 25/May/16 08/Jun/16 13/Jun/16
CON62780 TFR (703) Visual Inspection 1 0% 19/May/16 21/May/16 08/Jun/16 08/Jun/16 08/Jun/16 08/Jun/16
CON62790 TFR (703) Pressure Test 2 0% 19/May/16 22/May/16 08/Jun/16 09/Jun/16 08/Jun/16 09/Jun/16
CON62800 TFR (703) Teperature Sensor Calibration 1 0% 21/May/16 22/May/16 08/Jun/16 09/Jun/16 08/Jun/16 09/Jun/16
CON62810 TFR (703) Cooling System Test 1 0% 21/May/16 22/May/16 08/Jun/16 09/Jun/16 08/Jun/16 09/Jun/16
CON62820 TFR (703) Fan & OLTC Motor Current Test 1 0% 21/May/16 22/May/16 08/Jun/16 09/Jun/16 08/Jun/16 09/Jun/16
CON62840 TFR (703) Oil Breakdown Test 1 0% 22/May/16 23/May/16 09/Jun/16 11/Jun/16 09/Jun/16 11/Jun/16
CON62830 TFR (703) Ratio,Phase Relation, Magnetizing Current & Polarizing Index 1 0% 22/May/16 23/May/16 09/Jun/16 11/Jun/16 09/Jun/16 11/Jun/16
CON62850 TFR (703) TFR Impedence 1 0% 23/May/16 23/May/16 11/Jun/16 12/Jun/16 11/Jun/16 12/Jun/16
CON62860 TFR (703) Tan Delta 1 0% 24/May/16 24/May/16 12/Jun/16 13/Jun/16 12/Jun/16 13/Jun/16
CON62870 TFR (703) Core & Winding Insulation Test 1 0% 24/May/16 25/May/16 13/Jun/16 13/Jun/16 13/Jun/16 13/Jun/16
Power Transformer ( 703) Protection & Control Testing 73 0% 29/May/16 17/Aug/16 29/Jun/16 11/Sep/16
CON62880 TFR (703) Bushing CT Test 1 0% 29/May/16 29/May/16 29/Jun/16 29/Jun/16 29/Jun/16 29/Jun/16
CON62890 TFR (703) MCBs & Auxiliary Relays Testing 1 0% 11/Jun/16 12/Jun/16 11/Jul/16 12/Jul/16 11/Jul/16 12/Jul/16
CON62900 TFR (703) Scheme & Function Test 4 0% 29/Jun/16 09/Jul/16 28/Jul/16 01/Aug/16 28/Jul/16 01/Aug/16
CON70300 TFR (703) Closed Loop S/S #4 4 0% 06/Aug/16 09/Aug/16 30/Aug/16 03/Sep/16 30/Aug/16 03/Sep/16
CON70310 TFR (703) Closed Loop S/S #5 4 0% 09/Aug/16 13/Aug/16 03/Sep/16 07/Sep/16 03/Sep/16 07/Sep/16
CON70320 TFR (703) Closed Loop with PMC 4 0% 14/Aug/16 17/Aug/16 07/Sep/16 11/Sep/16 07/Sep/16 11/Sep/16
Power Transformer Yard - Miscellaneous Tests 51 0% 21/May/16 24/Jul/16 25/Jun/16 17/Aug/16
CON70190 Power Transformers Yard Lighting Review & Check 1 0% 21/May/16 22/May/16 25/Jun/16 26/Jun/16 25/Jun/16 26/Jun/16
CON70180 Delauge System Tests 4 0% 26/Jun/16 29/Jun/16 20/Jul/16 24/Jul/16 20/Jul/16 24/Jul/16
CON70420 230KV Power Cables High Potential Test 6 0% 29/Jun/16 10/Jul/16 28/Jul/16 03/Aug/16 28/Jul/16 03/Aug/16
CON67360 Discharge, Link & Refill Of Cable Heads TFR(702), after HV Test of Power Cables 2 0% 10/Jul/16 12/Jul/16 03/Aug/16 06/Aug/16 03/Aug/16 06/Aug/16
CON67370 Discharge, Link & Refill Of Cable Heads TFR(701), after HV Test of Power Cables 2 0% 12/Jul/16 14/Jul/16 06/Aug/16 07/Aug/16 06/Aug/16 07/Aug/16
CON67380 Discharge, Link & Refill Of Cable Heads TFR(704), after HV Test of Power Cables 2 0% 14/Jul/16 16/Jul/16 07/Aug/16 09/Aug/16 07/Aug/16 09/Aug/16
CON67390 Discharge, Link & Refill Of Cable Heads TFR(703), after HV Test of Power Cables 2 0% 16/Jul/16 18/Jul/16 09/Aug/16 10/Aug/16 09/Aug/16 10/Aug/16
CON70170 Auxiliary TFRs Testing 3 0% 20/Jul/16 24/Jul/16 14/Aug/16 16/Aug/16 14/Aug/16 16/Aug/16
CON70200 Power Transformers Yard Earthing Review & Check 1 0% 24/Jul/16 24/Jul/16 16/Aug/16 17/Aug/16 16/Aug/16 17/Aug/16
Existing DCS Sys. Mod
Modification ( by HONEYWELL ) 117 0% 09/Apr/16 31/Jul/16 03/May/16 27/Aug/16
Instrumentation Cable Duct Portion from S/S/ #4 & S/S #5 to PIB #2 16 0% 09/Apr/16 24/Apr/16 03/May/16 18/May/16
CON59760 Excavation 2 0% 09/Apr/16 11/Apr/16 03/May/16 05/May/16 03/May/16 05/May/16
CON59770 Manholes Casting 5 0% 11/Apr/16 16/Apr/16 05/May/16 10/May/16 05/May/16 10/May/16
CON59780 Laying of PVC Pipes & Concrete Casting 5 0% 16/Apr/16 20/Apr/16 10/May/16 15/May/16 10/May/16 15/May/16
CON59790 Backfilling & Compaction 1 0% 20/Apr/16 21/Apr/16 15/May/16 15/May/16 15/May/16 15/May/16

Page 34 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON59800 Instrumentation Cables Laying from S/S #4 & #5 to PIB#2 3 0% 21/Apr/16 24/Apr/16 15/May/16 18/May/16 15/May/16 18/May/16
DCS Modification Work
Wo @ PIB #2 101 0% 24/Apr/16 31/Jul/16 18/May/16 27/Aug/16
CON73445 Avilability of HONEYWELL Supervisor 0 0% 24/Apr/16 18/May/16 Avilability of HONEYWELL Superv
CON60470 Installation of Hardware Required for DCS Sys. Modifications by HONEYWELL 3 0% 25/Apr/16 27/Apr/16 19/May/16 22/May/16 19/May/16 22/May/16
CON60500 Configuration Required for DCS Sys Modification 4 0% 27/Apr/16 01/May/16 22/May/16 25/May/16 22/May/16 25/May/16
CON60510 Termination of Cables from S/S#4 & S/S #5 to @ PIB #2 ( GAS Detection & Battery Temp & C 2 0% 27/Apr/16 30/Apr/16 22/May/16 24/May/16 22/May/16 24/May/16
CON60520 DCS System Completion of Configuration & Modifications Testing. W/ S/S #4 4 0% 27/Jul/16 31/Jul/16 22/Aug/16 25/Aug/16 22/Aug/16 25/Aug/16
CON73475 DCS System Completion of Configuration & Modifications Testing. W/ S/S #5 4 0% 18/Jul/16 21/Jul/16 23/Aug/16 27/Aug/16 23/Aug/16 27/Aug/16
Instrumentation Work / Integration of PSA System w/ Existing 171 2.7% 02/Feb/16 08/Aug/16 02/Feb/16 A 01/Sep/16
PSA System - Control
Contro Cables & FO Cables Network & Pedistals 152 6.02% 02/Feb/16 21/Jul/16 02/Feb/16 A 15/Aug/16
FO Cable Duct Portion
Porti from S/S/ #4 to PMC 78 0% 30/Mar/16 12/Jun/16 24/Apr/16 11/Jul/16
CON59882 Excavation 10 0% 30/Mar/16 09/Apr/16 24/Apr/16 03/May/16 24/Apr/16 03/May/16
CON59902 Laying of PVC Pipes & Concrete Casting 15 0% 30/Mar/16 13/Apr/16 24/Apr/16 08/May/16 24/Apr/16 08/May/16
CON59892 Manholes & Pedistals Base Casting In Place 15 0% 13/Apr/16 27/Apr/16 08/May/16 22/May/16 08/May/16 22/May/16
CON59912 Backfilling & Compaction 6 0% 27/Apr/16 03/May/16 22/May/16 28/May/16 22/May/16 28/May/16
CON59932 Pedistals Installation & Cable Splicing 10 0% 02/Jun/16 12/Jun/16 26/Jun/16 11/Jul/16 26/Jun/16 11/Jul/16
CON59922 FO Cables Laying 4 0% 07/Jun/16 11/Jun/16 30/Jun/16 11/Jul/16 30/Jun/16 11/Jul/16
FO Cable Duct Portion
Porti from S/S/ #5 to PMC 127 16.18% 02/Feb/16 22/Jun/16 02/Feb/16 A 23/Jul/16
CON59880 Excavation 10 85% 02/Feb/16 24/Feb/16 02/Feb/16 A 29/Mar/16 02/Feb/16 A 29/Mar/16
CON59900 Laying of PVC Pipes & Concrete Casting 10 70% 25/Feb/16 09/Mar/16 29/Feb/16 A 29/Mar/16 29/Feb/16 A 29/Mar/16
CON59890 Manholes & Pedistals Base Casting In Place 15 0% 25/Feb/16 09/Mar/16 30/Mar/16 12/Apr/16 30/Mar/16 12/Apr/16
CON59910 Backfilling & Compaction 6 0% 12/Jun/16 17/Jun/16 11/Jul/16 17/Jul/16 11/Jul/16 17/Jul/16
CON59930 Pedistals Installation & Cable Splicing 10 0% 13/Jun/16 22/Jun/16 13/Jul/16 23/Jul/16 13/Jul/16 23/Jul/16
CON59920 FO Cables Laying 5 0% 18/Jun/16 22/Jun/16 17/Jul/16 21/Jul/16 17/Jul/16 21/Jul/16
FO Cable Duct Portion
Porti from S/S/ #4 to S/S #5 31 0% 18/Jun/16 21/Jul/16 17/Jul/16 15/Aug/16
CON59820 Excavation 10 0% 18/Jun/16 27/Jun/16 17/Jul/16 26/Jul/16 17/Jul/16 26/Jul/16
CON59830 Manholes & Pedistals Base Casting In Place 15 0% 27/Jun/16 16/Jul/16 26/Jul/16 09/Aug/16 26/Jul/16 09/Aug/16
CON59840 Laying of PVC Pipes & Concrete Casting 15 0% 27/Jun/16 16/Jul/16 26/Jul/16 09/Aug/16 26/Jul/16 09/Aug/16
CON59850 Backfilling & Compaction 6 0% 12/Jul/16 17/Jul/16 04/Aug/16 10/Aug/16 04/Aug/16 10/Aug/16
CON59870 Pedistals Installation & Cable Splicing 6 0% 17/Jul/16 21/Jul/16 09/Aug/16 15/Aug/16 09/Aug/16 15/Aug/16
CON59860 FO Cables Laying 4 0% 17/Jul/16 20/Jul/16 10/Aug/16 14/Aug/16 10/Aug/16 14/Aug/16
Instrumentation Work
Works @ PMC Building 43 0% 20/Jun/16 08/Aug/16 24/Jul/16 01/Sep/16
CON60360 FOC Patch Panels Installation @ PMC 7 0% 20/Jun/16 27/Jun/16 24/Jul/16 30/Jul/16 24/Jul/16 30/Jul/16
CON60370 Managed Etherne Switches Installation @PMC 7 0% 27/Jun/16 09/Jul/16 31/Jul/16 06/Aug/16 31/Jul/16 06/Aug/16
CON60380 Fire Alarm Panel Installation @PMC 4 0% 16/Jul/16 19/Jul/16 08/Aug/16 13/Aug/16 08/Aug/16 13/Aug/16
Integration of S/S #4 29 0% 12/Jul/16 08/Aug/16 06/Aug/16 01/Sep/16
CON60390 FO Cables Laying & Splicing to connect Existing PSA System @PMC 10 0% 12/Jul/16 21/Jul/16 06/Aug/16 15/Aug/16 06/Aug/16 15/Aug/16
CON60402 Connection of FOC from S/S #4 to FOC/PP 4 0% 21/Jul/16 25/Jul/16 15/Aug/16 18/Aug/16 15/Aug/16 18/Aug/16
CON60410 Configuration of S/S #4 @PMC Servers & Workstations 15 0% 26/Jul/16 08/Aug/16 18/Aug/16 01/Sep/16 18/Aug/16 01/Sep/16
CON60420 S/S #4 PSA System Ready for Closed Loop Testing 0 0% 08/Aug/16 01/Sep/16 S/S #4 PSA System Read
Integration of S/S #5 14 0% 17/Jul/16 30/Jul/16 10/Aug/16 23/Aug/16
CON60430 FO Cables Laying & Splicing to connect Existing PSA System @PMC 5 0% 17/Jul/16 21/Jul/16 10/Aug/16 15/Aug/16 10/Aug/16 15/Aug/16
CON60440 Connection of FOC from S/S #5 to FOC/PP 2 0% 21/Jul/16 24/Jul/16 15/Aug/16 17/Aug/16 15/Aug/16 17/Aug/16
CON60450 Configuration of S/S #5 @PMC Servers & Workstations 7 0% 24/Jul/16 30/Jul/16 17/Aug/16 23/Aug/16 17/Aug/16 23/Aug/16
CON60460 S/S #5 PSA System Ready for Closed Loop Testing 0 0% 30/Jul/16 23/Aug/16 S/S #5 PSA System Read
Communication Work / Inter-connection of Data Voice System w/ Existing 221 4.23% 27/Jun/16 27/Sep/16 15/Mar/16 A 22/Oct/16
Data Voice Network - FO Cables & Pedistals 181 7.9% 27/Jun/16 18/Aug/16 15/Mar/16 A 12/Sep/16
FO Cable Duct Portion
Porti from S/S/ #4 to Manhole #02 41 0% 27/Jun/16 09/Aug/16 26/Jul/16 03/Sep/16
CON60000 Excavation 10 0% 27/Jun/16 11/Jul/16 26/Jul/16 04/Aug/16 26/Jul/16 04/Aug/16
CON60010 Manholes & Pedistals Base Casting In Place 15 0% 12/Jul/16 25/Jul/16 04/Aug/16 18/Aug/16 04/Aug/16 18/Aug/16
CON60020 Laying of PVC Pipes & Concrete Casting 15 0% 12/Jul/16 25/Jul/16 04/Aug/16 18/Aug/16 04/Aug/16 18/Aug/16

Page 35 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON60030 Backfilling & Compaction 6 0% 21/Jul/16 26/Jul/16 14/Aug/16 20/Aug/16 14/Aug/16 20/Aug/16
CON60040 FO Cables Laying 4 0% 26/Jul/16 30/Jul/16 20/Aug/16 23/Aug/16 20/Aug/16 23/Aug/16
CON60050 Pedistals Installation & Cable Splicing 10 0% 31/Jul/16 09/Aug/16 24/Aug/16 03/Sep/16 24/Aug/16 03/Sep/16
FO Cable Duct Portion
Porti from S/S #5 to Nearest Pedistal 36 0% 12/Jul/16 14/Aug/16 04/Aug/16 08/Sep/16
CON59940 Excavation 10 0% 12/Jul/16 20/Jul/16 04/Aug/16 14/Aug/16 04/Aug/16 14/Aug/16
CON59960 Laying of PVC Pipes & Concrete Casting 15 0% 21/Jul/16 03/Aug/16 14/Aug/16 28/Aug/16 14/Aug/16 28/Aug/16
CON59970 Backfilling & Compaction 6 0% 31/Jul/16 04/Aug/16 23/Aug/16 29/Aug/16 23/Aug/16 29/Aug/16
CON59980 FO Cables Laying 4 0% 09/Aug/16 13/Aug/16 03/Sep/16 07/Sep/16 03/Sep/16 07/Sep/16
CON59990 Cable Splicing 4 0% 10/Aug/16 14/Aug/16 04/Sep/16 08/Sep/16 04/Sep/16 08/Sep/16
FO Cable Duct Portion
Porti from New Proposed Outdoor Enclosure to Nearest Pedistal 181 26.49% 21/Jul/16 18/Aug/16 15/Mar/16 A 12/Sep/16
CON60060 Excavation 0 100% 21/Jul/16 30/Jul/16 15/Mar/16 A 20/Mar/16 A 15/Mar/16 A 20/Mar/16 A
CON60080 Laying of PVC Pipes & Concrete Casting 15 0% 31/Jul/16 13/Aug/16 21/Mar/16 03/Apr/16 21/Mar/16 03/Apr/16
CON60090 Backfilling & Compaction 6 0% 09/Aug/16 14/Aug/16 30/Mar/16 04/Apr/16 30/Mar/16 04/Apr/16
CON60100 FO Cables Laying 4 0% 14/Aug/16 17/Aug/16 07/Sep/16 11/Sep/16 07/Sep/16 11/Sep/16
CON60110 Cable Splicing 4 0% 15/Aug/16 18/Aug/16 08/Sep/16 12/Sep/16 08/Sep/16 12/Sep/16
Data Voice System Works
W @ Abu Ali DCO Building 79 0% 09/Jul/16 27/Sep/16 06/Aug/16 22/Oct/16
CON60530 FOC Patch Panels Installation @ DCO 2 0% 09/Jul/16 11/Jul/16 06/Aug/16 08/Aug/16 06/Aug/16 08/Aug/16
CON60540 Installation of Transceivers in existing JUNIPER MX-480 @ DCO 2 0% 11/Jul/16 12/Jul/16 08/Aug/16 09/Aug/16 08/Aug/16 09/Aug/16
CON60650 Configuration @ DCO 6 0% 12/Jul/16 18/Jul/16 09/Aug/16 15/Aug/16 09/Aug/16 15/Aug/16
Linking of S/S #4 8 0% 18/Jul/16 25/Jul/16 15/Aug/16 22/Aug/16
CON60550 Inter-connection FO Cables @ DCO 4 0% 18/Jul/16 21/Jul/16 15/Aug/16 18/Aug/16 15/Aug/16 18/Aug/16
CON60560 S/S #4 FO Cales Connection to FOC/PP @ DCO 2 0% 21/Jul/16 24/Jul/16 18/Aug/16 21/Aug/16 18/Aug/16 21/Aug/16
CON61100 S/S #4 FO Cales Connection to FOC/PP @ S/S #4 2 0% 24/Jul/16 25/Jul/16 21/Aug/16 22/Aug/16 21/Aug/16 22/Aug/16
CON60570 S/S #4 Connection Established & Ready for Test @ DCO 0 0% 25/Jul/16 22/Aug/16 S/S #4 Connection Estab
Linking of S/S #5 21 0% 26/Jul/16 17/Aug/16 23/Aug/16 12/Sep/16
CON60580 Inter-connection FO Cables @ DCO 4 0% 26/Jul/16 30/Jul/16 23/Aug/16 27/Aug/16 23/Aug/16 27/Aug/16
CON60590 S/S #5 FO Cales Connection to FOC/PP @ DCO 2 0% 14/Aug/16 16/Aug/16 08/Sep/16 10/Sep/16 08/Sep/16 10/Sep/16
CON61110 S/S #4 FO Cales Connection to FOC/PP @ S/S #5 2 0% 16/Aug/16 17/Aug/16 10/Sep/16 12/Sep/16 10/Sep/16 12/Sep/16
CON60600 S/S #5 Connection Established & Ready for Test @ DCO 0 0% 17/Aug/16 12/Sep/16 S/S #5 Connection Esta
Linking of S/S #1 10 0% 18/Aug/16 27/Aug/16 12/Sep/16 22/Sep/16
CON61220 Inter-connection FO Cables @ DCO 4 0% 18/Aug/16 22/Aug/16 12/Sep/16 17/Sep/16 12/Sep/16 17/Sep/16
CON61230 S/S #1 FO Cales Connection to FOC/PP @ DCO 2 0% 22/Aug/16 23/Aug/16 17/Sep/16 18/Sep/16 17/Sep/16 18/Sep/16
CON61260 Cutting Existing FOC & New Splicing @ S/S #1 2 0% 23/Aug/16 25/Aug/16 19/Sep/16 20/Sep/16 19/Sep/16 20/Sep/16
CON61250 S/S #1 FO Cales Connection to FOC/PP @ S/S #1 2 0% 25/Aug/16 27/Aug/16 20/Sep/16 22/Sep/16 20/Sep/16 22/Sep/16
CON61240 S/S #1 Connection Established & Ready for Test @ DCO 0 0% 27/Aug/16 22/Sep/16 S/S #1 Connection Est
New Proposed Outdoor
Outd Enclosure Installation @ Pipe Line RTU 30 0% 28/Aug/16 27/Sep/16 22/Sep/16 22/Oct/16
CON60610 Outdoor Enclosure Erection 6 0% 28/Aug/16 01/Sep/16 22/Sep/16 28/Sep/16 22/Sep/16 28/Sep/16
CON60620 FOC Patch Panel Installation & Power Connection@ Outdoor Enclosure 6 0% 01/Sep/16 08/Sep/16 28/Sep/16 04/Oct/16 28/Sep/16 04/Oct/16
CON60630 Connection of FO Cables @ Outdoor Enclosure 4 0% 08/Sep/16 12/Sep/16 04/Oct/16 08/Oct/16 04/Oct/16 08/Oct/16
CON60640 Connection Established & Ready for Test @ DCO 0 0% 12/Sep/16 08/Oct/16 Connection Establishe
CON73440 Configuration & Connection Testing @ @DCO 4 0% 22/Sep/16 27/Sep/16 18/Oct/16 22/Oct/16 18/Oct/16 22/Oct/16
Energizing & Final Testing
Tes S/S #4, #5 & Power Transformers 93 0% 26/Jul/16 24/Oct/16 20/Aug/16 17/Nov/16
Energizing & Final Te
Testing S/S #4 49 0% 26/Jul/16 11/Sep/16 20/Aug/16 08/Oct/16
CON70350 Readiness @ Wasit for End to End @ Waist (by Others) 0 0% 27/Jul/16 20/Aug/16 Readiness @ Wasit for E
CON70390 Testing Connection S/S #4 with DCO @ DCO 4 0% 26/Jul/16 30/Jul/16 23/Aug/16 27/Aug/16 23/Aug/16 27/Aug/16
CON70400 Testing Connection S/S #4 with DCO @ Dhahran 4 0% 30/Jul/16 02/Aug/16 27/Aug/16 30/Aug/16 27/Aug/16 30/Aug/16
CON70340 Wasit Line-1 End to End Test 2 0% 08/Aug/16 09/Aug/16 01/Sep/16 03/Sep/16 01/Sep/16 03/Sep/16
CON70380 Testing Connection S/S #4 with PMC @ PMC 4 0% 09/Aug/16 13/Aug/16 01/Sep/16 06/Sep/16 01/Sep/16 06/Sep/16
CON70330 230KV BB Stability Test 10 0% 09/Aug/16 18/Aug/16 03/Sep/16 13/Sep/16 03/Sep/16 13/Sep/16
CON70360 Wasit Line-2 End to End Test 2 0% 09/Aug/16 11/Aug/16 03/Sep/16 05/Sep/16 03/Sep/16 05/Sep/16
CON70410 Readiness for 230KV GIS Energizing BB-B Through Wasit Line-2 0 0% 11/Sep/16 08/Oct/16 Readiness for 230KV

Page 36 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON70370 Readiness for 230KV GIS Energizing BB-A Through Wasit Line-1 0 0% 11/Sep/16 08/Oct/16 Readiness for 230KV
S/S #4 Final Closed Loop with PMC & DCO & Dhahran 24 0% 18/Aug/16 11/Sep/16 13/Sep/16 08/Oct/16
CON70430 Line-1 Line Feeder Final Closed Loop (Source to PMC) 3 0% 18/Aug/16 22/Aug/16 13/Sep/16 17/Sep/16 13/Sep/16 17/Sep/16
CON70440 Transformer (701) Feeder Final Closed Loop (Source to PMC) 3 0% 22/Aug/16 24/Aug/16 17/Sep/16 19/Sep/16 17/Sep/16 19/Sep/16
CON70450 BB Diffrintial Relays Closed Loop (Source to PMC) 3 0% 24/Aug/16 27/Aug/16 20/Sep/16 22/Sep/16 20/Sep/16 22/Sep/16
CON70460 Transformer (702) Feeder Final Closed Loop (Source to PMC) 3 0% 28/Aug/16 30/Aug/16 22/Sep/16 26/Sep/16 22/Sep/16 26/Sep/16
CON70470 Line-2 Feeder Final Closed Loop (Source to PMC) 3 0% 30/Aug/16 01/Sep/16 26/Sep/16 28/Sep/16 26/Sep/16 28/Sep/16
CON70480 Transformer (704) Feeder Final Closed Loop (Source to PMC) 3 0% 01/Sep/16 05/Sep/16 29/Sep/16 02/Oct/16 29/Sep/16 02/Oct/16
CON70490 Transformer (703) Feeder Final Closed Loop (Source to PMC) 3 0% 05/Sep/16 08/Sep/16 02/Oct/16 04/Oct/16 02/Oct/16 04/Oct/16
CON70500 HVAC & FA & Battery Chargers Signals Testing 3 0% 08/Sep/16 11/Sep/16 04/Oct/16 08/Oct/16 04/Oct/16 08/Oct/16
Power Transformers ( 702), (701) Energizing & Final Testing 7 0% 15/Sep/16 22/Sep/16 11/Oct/16 18/Oct/16
CON70260 TFR (701) Closed Loop with PMC 3 0% 15/Sep/16 19/Sep/16 11/Oct/16 13/Oct/16 11/Oct/16 13/Oct/16
CON70510 Readiness for TFR (701) Energizing 0 0% 19/Sep/16 13/Oct/16 Readiness for TFR (7
CON70230 TFR (702) Closed Loop with PMC 3 0% 20/Sep/16 22/Sep/16 15/Oct/16 18/Oct/16 15/Oct/16 18/Oct/16
CON70520 Readiness for TFR (702) Energizing 0 0% 22/Sep/16 18/Oct/16 Readiness for TFR (
Energizing & Final Te
Testing S/S #5 69 0% 16/Aug/16 24/Oct/16 12/Sep/16 17/Nov/16
CON70540 Testing Connection S/S #5 with DCO @ DCO 4 0% 18/Aug/16 22/Aug/16 12/Sep/16 17/Sep/16 12/Sep/16 17/Sep/16
CON70550 Testing Connection S/S #5 with DCO @ Dhahran 4 0% 22/Aug/16 25/Aug/16 17/Sep/16 20/Sep/16 17/Sep/16 20/Sep/16
CON70530 Testing Connection S/S #5 with PMC @ PMC 4 0% 16/Aug/16 20/Aug/16 22/Sep/16 27/Sep/16 22/Sep/16 27/Sep/16
CON70810 Readiness for 13.8KV SWGR S/S #5 Energizing 0 0% 24/Oct/16 17/Nov/16 Readiness for 13.8
S/S #5 Final Closed Loop with PMC & DCO & Dhahran 44 0% 11/Sep/16 24/Oct/16 08/Oct/16 17/Nov/16
13.8KV Busbar - A Final Closed Loop 42 0% 11/Sep/16 23/Oct/16 08/Oct/16 15/Nov/16
CON70590 BB- A FinalClosed Loop ( from Source to PMC ) 2 0% 11/Sep/16 13/Sep/16 08/Oct/16 09/Oct/16 08/Oct/16 09/Oct/16
CON70610 Transformer (701) Incommer FinalClosed Loop ( from Source to PMC ) 2 0% 13/Sep/16 15/Sep/16 09/Oct/16 11/Oct/16 09/Oct/16 11/Oct/16
CON70620 S/S #5 Auxiliary TFR (301) Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 15/Sep/16 18/Sep/16 11/Oct/16 13/Oct/16 11/Oct/16 13/Oct/16
CON70650 S/S #1 Auxiliary TFR (301) Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 21/Sep/16 24/Sep/16 17/Oct/16 18/Oct/16 17/Oct/16 18/Oct/16
CON70670 S/S #3 SWGR Building Incom. No.1 Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 26/Sep/16 28/Sep/16 20/Oct/16 23/Oct/16 20/Oct/16 23/Oct/16
CON70640 Arabiyah Field Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 02/Oct/16 04/Oct/16 26/Oct/16 27/Oct/16 26/Oct/16 27/Oct/16
CON70630 Berri Field Potential Project Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 04/Oct/16 05/Oct/16 27/Oct/16 30/Oct/16 27/Oct/16 30/Oct/16
CON70660 Offshore Wells TP 1 Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 05/Oct/16 08/Oct/16 30/Oct/16 01/Nov/16 30/Oct/16 01/Nov/16
CON70690 CGT Van Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 09/Oct/16 11/Oct/16 02/Nov/16 05/Nov/16 02/Nov/16 05/Nov/16
CON70680 S/S #2 Auxiliary TFR (301) Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 11/Oct/16 13/Oct/16 05/Nov/16 06/Nov/16 05/Nov/16 06/Nov/16
CON70700 Spare Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 20/Oct/16 23/Oct/16 14/Nov/16 15/Nov/16 14/Nov/16 15/Nov/16
13.8KV Busbar - B Final Closed Loop 38 0% 13/Sep/16 20/Oct/16 09/Oct/16 14/Nov/16
CON70600 BB - B FinalClosed Loop ( from Source to PMC ) 2 0% 13/Sep/16 15/Sep/16 09/Oct/16 11/Oct/16 09/Oct/16 11/Oct/16
CON70710 Transformer (702) Incommer FinalClosed Loop ( from Source to PMC ) 2 0% 18/Sep/16 19/Sep/16 13/Oct/16 15/Oct/16 13/Oct/16 15/Oct/16
CON70720 S/S #5 Auxiliary TFR (302) Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 20/Sep/16 21/Sep/16 15/Oct/16 17/Oct/16 15/Oct/16 17/Oct/16
CON70750 S/S #1 Auxiliary TFR (302) Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 24/Sep/16 26/Sep/16 18/Oct/16 20/Oct/16 18/Oct/16 20/Oct/16
CON70760 S/S #3 SWGR Building Incom. No.2 Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 28/Sep/16 29/Sep/16 23/Oct/16 24/Oct/16 23/Oct/16 24/Oct/16
CON70730 Karan Field Potential Project Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 29/Sep/16 02/Oct/16 24/Oct/16 26/Oct/16 24/Oct/16 26/Oct/16
CON70770 Offshore Wells TP 3 Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 08/Oct/16 09/Oct/16 01/Nov/16 02/Nov/16 01/Nov/16 02/Nov/16
CON70780 S/S #2 Auxiliary TFR (302) Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 13/Oct/16 15/Oct/16 06/Nov/16 08/Nov/16 06/Nov/16 08/Nov/16
CON70740 Berri Field Potential Project Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 15/Oct/16 17/Oct/16 08/Nov/16 10/Nov/16 08/Nov/16 10/Nov/16
CON70790 New Admin. Building Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 17/Oct/16 18/Oct/16 10/Nov/16 12/Nov/16 10/Nov/16 12/Nov/16
CON70800 Spare Feeder FinalClosed Loop ( from Source to PMC ) 2 0% 18/Oct/16 20/Oct/16 12/Nov/16 14/Nov/16 12/Nov/16 14/Nov/16
S/S #5 Interfacing F
FA, HVAC & Battery Charger Monitoring Systems Final Closed Loop 2 0% 23/Oct/16 24/Oct/16 15/Nov/16 17/Nov/16
CON70560 AC & DC System Battery Charger Monitoring & Alarm FinalClosed Loop ( from Source to PM 2 0% 23/Oct/16 24/Oct/16 15/Nov/16 17/Nov/16 15/Nov/16 17/Nov/16
CON70580 HVAC Final Closed Loop ( from Source to PMC ) 2 0% 23/Oct/16 24/Oct/16 15/Nov/16 17/Nov/16 15/Nov/16 17/Nov/16
CON70570 Fire Alarm FinalClosed Loop ( from Source to PMC ) 2 0% 23/Oct/16 24/Oct/16 15/Nov/16 17/Nov/16 15/Nov/16 17/Nov/16
Switchover of Non-motor
Non-mo Loads form Existing S/S #1 to New S/S #5 215 0% 18/Jun/16 16/Jan/17 21/Jul/16 09/Feb/17
S/S #1 Auxi. Transformers
Transfor Feeders 144 0% 18/Jun/16 10/Nov/16 21/Jul/16 05/Dec/16

Page 37 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
S/S #1 Auxi. Transformers
Transfo Feeder (301) 134 0% 18/Jun/16 01/Nov/16 21/Jul/16 26/Nov/16
S/S #1 Auxi. Transf
Transformers Feeder (301) Works Prior to Switchover 17 0% 18/Jun/16 10/Jul/16 21/Jul/16 06/Aug/16
CON70820 13.8KV Power Cable Pulling from S/S #5 to S/S #1 Auxiliary TFR (301) 6 0% 18/Jun/16 23/Jun/16 21/Jul/16 27/Jul/16 21/Jul/16 27/Jul/16
CON70830 Power Cables Lugs Installation Both Sides 4 0% 23/Jun/16 27/Jun/16 27/Jul/16 31/Jul/16 27/Jul/16 31/Jul/16
CON70840 Control Cables Pulling from S/S #5 13.8KV SWGR Feeder to S/S#1 480V SWGR 4 0% 23/Jun/16 27/Jun/16 27/Jul/16 31/Jul/16 27/Jul/16 31/Jul/16
CON70850 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 27/Jun/16 28/Jun/16 31/Jul/16 01/Aug/16 31/Jul/16 01/Aug/16
CON71120 13.8KV Power Cables Meggering 2 0% 27/Jun/16 29/Jun/16 31/Jul/16 01/Aug/16 31/Jul/16 01/Aug/16
CON70860 Termination of 13.8KV Power Cables @ S/S #5 Feeder 4 0% 28/Jun/16 02/Jul/16 01/Aug/16 04/Aug/16 01/Aug/16 04/Aug/16
CON70870 Termination of Control Cables @ S/S #5 Feeder 6 0% 28/Jun/16 10/Jul/16 01/Aug/16 06/Aug/16 01/Aug/16 06/Aug/16
S/S #1 Auxi. Transf
Transformers Feeder (301) Switchover 9 0% 24/Oct/16 01/Nov/16 17/Nov/16 26/Nov/16
CON71000 Open Feeder CBs & Rackout @ S/S #1 13.8KV SWGR & Power Cable Discharge & Ground 1 0% 24/Oct/16 25/Oct/16 17/Nov/16 19/Nov/16 17/Nov/16 19/Nov/16
CON71010 Disconnect Existing 13.8KV Power Cable from TFR (301) @ S/S #1 1 0% 25/Oct/16 26/Oct/16 19/Nov/16 20/Nov/16 19/Nov/16 20/Nov/16
CON71020 Disconnect Existing Control Cables Between Existing SWGR CB & 480V SWGR 1 0% 26/Oct/16 27/Oct/16 20/Nov/16 20/Nov/16 20/Nov/16 20/Nov/16
CON71030 Terminate New 13.8KV Cables @ S/S #1 Auxi. TFR (301) 1 0% 26/Oct/16 27/Oct/16 20/Nov/16 20/Nov/16 20/Nov/16 20/Nov/16
CON71040 Termination of Control Cables @ S/S #1 480V SWGR 2 0% 27/Oct/16 29/Oct/16 20/Nov/16 22/Nov/16 20/Nov/16 22/Nov/16
CON71050 Scheme Check 2 0% 29/Oct/16 31/Oct/16 22/Nov/16 24/Nov/16 22/Nov/16 24/Nov/16
CON71060 PSA Configuration @ S/S #1 1 0% 29/Oct/16 30/Oct/16 22/Nov/16 23/Nov/16 22/Nov/16 23/Nov/16
CON71070 PSA Configuration @ S/S #5 1 0% 29/Oct/16 30/Oct/16 22/Nov/16 23/Nov/16 22/Nov/16 23/Nov/16
CON71080 S/S #1 480V SWGR Bus Tie Shutdown & Final Testing & Closed Loop with PMC 1 0% 31/Oct/16 01/Nov/16 24/Nov/16 24/Nov/16 24/Nov/16 24/Nov/16
CON71090 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 01/Nov/16 01/Nov/16 24/Nov/16 26/Nov/16 24/Nov/16 26/Nov/16
CON71100 Close 480V Bus Tie & CB Feeder @ S/S #1 1 0% 01/Nov/16 01/Nov/16 24/Nov/16 26/Nov/16 24/Nov/16 26/Nov/16
CON71110 S/S #1 Auxi. TFR (301) Switchover to S/S #5 Completed 0 0% 01/Nov/16 26/Nov/16 S/S #1 Auxi. TFR
S/S #1 Auxi. Transformers
Transfo Feeder (302) 121 0% 19/Jul/16 10/Nov/16 11/Aug/16 05/Dec/16
S/S #1 Auxi. Transf
Transformers Feeder (302) Works Prior to Switchover 17 0% 19/Jul/16 03/Aug/16 11/Aug/16 28/Aug/16
CON71130 13.8KV Power Cable Pulling from S/S #5 to S/S #1 Auxiliary TFR (302) 6 0% 19/Jul/16 24/Jul/16 11/Aug/16 17/Aug/16 11/Aug/16 17/Aug/16
CON71140 Power Cables Lugs Installation Both Sides 4 0% 24/Jul/16 28/Jul/16 17/Aug/16 21/Aug/16 17/Aug/16 21/Aug/16
CON71150 Control Cables Pulling from S/S #5 13.8KV SWGR Feeder to S/S#1 480V SWGR 4 0% 24/Jul/16 28/Jul/16 17/Aug/16 21/Aug/16 17/Aug/16 21/Aug/16
CON71160 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 28/Jul/16 28/Jul/16 21/Aug/16 22/Aug/16 21/Aug/16 22/Aug/16
CON71170 13.8KV Power Cables Meggering 2 0% 28/Jul/16 30/Jul/16 21/Aug/16 23/Aug/16 21/Aug/16 23/Aug/16
CON71180 Termination of 13.8KV Power Cables @ S/S #5 Feeder 4 0% 28/Jul/16 02/Aug/16 22/Aug/16 25/Aug/16 22/Aug/16 25/Aug/16
CON71190 Termination of Control Cables @ S/S #5 Feeder 6 0% 28/Jul/16 03/Aug/16 22/Aug/16 28/Aug/16 22/Aug/16 28/Aug/16
S/S #1 Auxi. Transf
Transformers Feeder (302) Switchover 9 0% 02/Nov/16 10/Nov/16 27/Nov/16 05/Dec/16
CON71200 Open Feeder CBs & Rackout @ S/S #1 13.8KV SWGR & Power Cable Discharge & Ground 1 0% 02/Nov/16 03/Nov/16 27/Nov/16 28/Nov/16 27/Nov/16 28/Nov/16
CON71210 Disconnect Existing 13.8KV Power Cable from TFR (302) @ S/S #1 1 0% 03/Nov/16 05/Nov/16 28/Nov/16 29/Nov/16 28/Nov/16 29/Nov/16
CON71220 Disconnect Existing Control Cables Between Existing SWGR CB & 480V SWGR 1 0% 05/Nov/16 06/Nov/16 29/Nov/16 29/Nov/16 29/Nov/16 29/Nov/16
CON71230 Terminate New 13.8KV Cables @ S/S #1 Auxi. TFR (302) 1 0% 05/Nov/16 06/Nov/16 29/Nov/16 29/Nov/16 29/Nov/16 29/Nov/16
CON71240 Termination of Control Cables @ S/S #1 480V SWGR 2 0% 06/Nov/16 07/Nov/16 29/Nov/16 01/Dec/16 29/Nov/16 01/Dec/16
CON71250 Scheme Check 2 0% 07/Nov/16 09/Nov/16 01/Dec/16 04/Dec/16 01/Dec/16 04/Dec/16
CON71260 PSA Configuration @ S/S #1 1 0% 07/Nov/16 08/Nov/16 01/Dec/16 03/Dec/16 01/Dec/16 03/Dec/16
CON71270 PSA Configuration @ S/S #5 1 0% 07/Nov/16 08/Nov/16 01/Dec/16 03/Dec/16 01/Dec/16 03/Dec/16
CON71280 S/S #1 480V SWGR Bus Tie Shutdown & Final Testing & Closed Loop with PMC 1 0% 09/Nov/16 10/Nov/16 04/Dec/16 04/Dec/16 04/Dec/16 04/Dec/16
CON71290 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 10/Nov/16 10/Nov/16 04/Dec/16 05/Dec/16 04/Dec/16 05/Dec/16
CON71300 Close 480V Bus Tie & CB Feeder @ S/S #1 1 0% 10/Nov/16 10/Nov/16 04/Dec/16 05/Dec/16 04/Dec/16 05/Dec/16
CON71310 S/S #1 Auxi. TFR (302) Switchover to S/S #5 Completed 0 0% 10/Nov/16 05/Dec/16 S/S #1 Auxi. TFR
S/S #3 SWGR Building
Buildin Incom. No.1&2 Feeders 118 0% 03/Aug/16 24/Nov/16 28/Aug/16 18/Dec/16
S/S #3 SWGR Buildi
Building Incom. No.1 Feeder 111 0% 03/Aug/16 17/Nov/16 28/Aug/16 12/Dec/16
S/S #3 SWGR Building
Build Incom. No.1 Feeder Works prior to Switchover 14 0% 03/Aug/16 16/Aug/16 28/Aug/16 11/Sep/16
CON71510 13.8KV Power Cable Pulling from S/S #5 to Splice Point @ S/S #1 6 0% 03/Aug/16 09/Aug/16 28/Aug/16 03/Sep/16 28/Aug/16 03/Sep/16
CON71520 Power Cables Lugs Installation & Preparation for Cables Splicing 4 0% 09/Aug/16 13/Aug/16 03/Sep/16 06/Sep/16 03/Sep/16 06/Sep/16
CON71540 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 09/Aug/16 10/Aug/16 03/Sep/16 04/Sep/16 03/Sep/16 04/Sep/16
CON71560 Termination of 13.8KV Power Cables @ S/S #5 Feeder 4 0% 13/Aug/16 16/Aug/16 06/Sep/16 11/Sep/16 06/Sep/16 11/Sep/16

Page 38 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
S/S #3 SWGR Building
Build Incom. No.1 Feeder Switchover 6 0% 12/Nov/16 17/Nov/16 06/Dec/16 12/Dec/16
CON71580 Open Feeder CBs & Rackout @ S/S #3 13.8KV SWGR & Power Cable Discharge & Ground 1 0% 12/Nov/16 13/Nov/16 06/Dec/16 07/Dec/16 06/Dec/16 07/Dec/16
CON71590 Disconnect Existing 13.8KV Power Cable from 13.8KV SWGR & Pull to Splice Pint @ S/S #1 1 0% 13/Nov/16 14/Nov/16 07/Dec/16 08/Dec/16 07/Dec/16 08/Dec/16
CON71640 PSA Configuration @ S/S #1 1 0% 13/Nov/16 14/Nov/16 07/Dec/16 08/Dec/16 07/Dec/16 08/Dec/16
CON71650 PSA Configuration @ S/S #3 1 0% 13/Nov/16 14/Nov/16 07/Dec/16 08/Dec/16 07/Dec/16 08/Dec/16
CON71610 Splice & Terminate 13.8KV Cables @ S/S #1Splice Point 1 0% 14/Nov/16 15/Nov/16 08/Dec/16 08/Dec/16 08/Dec/16 08/Dec/16
CON71620 13.8KV Power Cables Meggering After Splicing 1 0% 15/Nov/16 15/Nov/16 08/Dec/16 10/Dec/16 08/Dec/16 10/Dec/16
CON71660 S/S #3 13.8V SWGR Bus Tie Shutdown & Final Testing & Closed Loop with PMC 1 0% 15/Nov/16 16/Nov/16 10/Dec/16 11/Dec/16 10/Dec/16 11/Dec/16
CON71670 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 16/Nov/16 17/Nov/16 11/Dec/16 12/Dec/16 11/Dec/16 12/Dec/16
CON71680 Close 13.8KV SWGR Bus Tie & CB Feeder @ S/S #3 1 0% 16/Nov/16 17/Nov/16 11/Dec/16 12/Dec/16 11/Dec/16 12/Dec/16
CON71690 S/S #3 Building Incom. No.1 Switchover to S/S #5 Completed 0 0% 17/Nov/16 12/Dec/16 S/S #3 Building I
S/S #3 SWGR Buildi
Building Incom. No.2 Feeder 104 0% 16/Aug/16 24/Nov/16 11/Sep/16 18/Dec/16
S/S #3 SWGR Building
Build Incom. No.2 Feeder Works prior to Switchover 6 0% 16/Aug/16 22/Aug/16 11/Sep/16 17/Sep/16
CON71700 13.8KV Power Cable Pulling from S/S #5 to Splice Point @ S/S #1 3 0% 16/Aug/16 20/Aug/16 11/Sep/16 14/Sep/16 11/Sep/16 14/Sep/16
CON71710 Power Cables Lugs Installation & Preparation for Cables Splicing 2 0% 20/Aug/16 21/Aug/16 14/Sep/16 15/Sep/16 14/Sep/16 15/Sep/16
CON71720 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 20/Aug/16 21/Aug/16 14/Sep/16 14/Sep/16 14/Sep/16 14/Sep/16
CON71730 Termination of 13.8KV Power Cables @ S/S #5 Feeder 1 0% 21/Aug/16 22/Aug/16 15/Sep/16 17/Sep/16 15/Sep/16 17/Sep/16
S/S #3 SWGR Building
Build Incom. No.2 Feeder Switchover 6 0% 19/Nov/16 24/Nov/16 13/Dec/16 18/Dec/16
CON71740 Open Feeder CBs & Rackout @ S/S #3 13.8KV SWGR & Power Cable Discharge & Ground 1 0% 19/Nov/16 20/Nov/16 13/Dec/16 13/Dec/16 13/Dec/16 13/Dec/16
CON71750 Disconnect Existing 13.8KV Power Cable from 13.8KV SWGR & Pull to Splice Pint @ S/S #1 1 0% 20/Nov/16 20/Nov/16 13/Dec/16 14/Dec/16 13/Dec/16 14/Dec/16
CON71760 PSA Configuration @ S/S #1 1 0% 20/Nov/16 20/Nov/16 13/Dec/16 14/Dec/16 13/Dec/16 14/Dec/16
CON71770 PSA Configuration @ S/S #3 1 0% 20/Nov/16 20/Nov/16 13/Dec/16 14/Dec/16 13/Dec/16 14/Dec/16
CON71780 Splice & Terminate 13.8KV Cables @ S/S #1Splice Point 1 0% 20/Nov/16 21/Nov/16 14/Dec/16 15/Dec/16 14/Dec/16 15/Dec/16
CON71790 13.8KV Power Cables Meggering After Splicing 1 0% 21/Nov/16 22/Nov/16 15/Dec/16 17/Dec/16 15/Dec/16 17/Dec/16
CON71800 S/S #3 13.8V SWGR Bus Tie Shutdown & Final Testing & Closed Loop with PMC 1 0% 22/Nov/16 23/Nov/16 17/Dec/16 18/Dec/16 17/Dec/16 18/Dec/16
CON71810 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 23/Nov/16 24/Nov/16 18/Dec/16 18/Dec/16 18/Dec/16 18/Dec/16
CON71820 Close 13.8KV SWGR Bus Tie & CB Feeder @ S/S #3 1 0% 23/Nov/16 24/Nov/16 18/Dec/16 18/Dec/16 18/Dec/16 18/Dec/16
CON71830 S/S #3 Building Incom. No.2 Switchover to S/S #5 Completed 0 0% 24/Nov/16 18/Dec/16 S/S #3 Building
Karan Field Feeder 107 0% 22/Aug/16 03/Dec/16 17/Sep/16 27/Dec/16
Karan Field Feeder Works Pirior to Switchover 14 0% 22/Aug/16 05/Sep/16 17/Sep/16 02/Oct/16
CON71840 13.8KV Power Cable Pulling from S/S #5 to Splice Point @ S/S #1 6 0% 22/Aug/16 28/Aug/16 17/Sep/16 24/Sep/16 17/Sep/16 24/Sep/16
CON71860 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 28/Aug/16 29/Aug/16 24/Sep/16 24/Sep/16 24/Sep/16 24/Sep/16
CON71980 New FO Cable Pulling from S/S #5 to S/S #1 Existing Splice Enclosure 4 0% 28/Aug/16 31/Aug/16 24/Sep/16 27/Sep/16 24/Sep/16 27/Sep/16
CON72020 Preparation of Diesel Genset @ Karan 6 0% 28/Aug/16 03/Sep/16 24/Sep/16 29/Sep/16 24/Sep/16 29/Sep/16
CON71850 Power Cables Lugs Installation & Preparation for Cables Splicing 4 0% 28/Aug/16 31/Aug/16 24/Sep/16 27/Sep/16 24/Sep/16 27/Sep/16
CON71870 Termination of 13.8KV Power Cables @ S/S #5 Feeder 4 0% 31/Aug/16 05/Sep/16 27/Sep/16 02/Oct/16 27/Sep/16 02/Oct/16
CON71990 Termination of New FO Cable to S/S #5 13.8KV SWGR 3 0% 31/Aug/16 04/Sep/16 27/Sep/16 01/Oct/16 27/Sep/16 01/Oct/16
Karan Field Feeder Switchover Works 8 0% 24/Nov/16 03/Dec/16 19/Dec/16 27/Dec/16
CON71880 Open Feeder CBs & Rackout @ Karan & Power Cable Discharge & Grounding 1 0% 24/Nov/16 26/Nov/16 19/Dec/16 20/Dec/16 19/Dec/16 20/Dec/16
CON72030 Connecting Diesel Genset to Load Side @ Karan 1 0% 26/Nov/16 27/Nov/16 20/Dec/16 21/Dec/16 20/Dec/16 21/Dec/16
CON71890 Disconnect Existing 13.8KV Power Cable from 13.8KV SWGR & Pull to Splice Pint @ S/S #1 1 0% 27/Nov/16 28/Nov/16 21/Dec/16 22/Dec/16 21/Dec/16 22/Dec/16
CON72010 Disconnect Existing FO Cable @ S/S #1 Existing Splice Enclosure 1 0% 27/Nov/16 28/Nov/16 21/Dec/16 22/Dec/16 21/Dec/16 22/Dec/16
CON71920 Splice & Terminate 13.8KV Cables @ S/S #1Splice Point 1 0% 28/Nov/16 29/Nov/16 22/Dec/16 22/Dec/16 22/Dec/16 22/Dec/16
CON72000 Termination of FO Cable @ S/S #1 Existing Splice Enclosure 1 0% 28/Nov/16 29/Nov/16 22/Dec/16 22/Dec/16 22/Dec/16 22/Dec/16
CON71930 13.8KV Power Cables Meggering After Splicing 1 0% 29/Nov/16 29/Nov/16 22/Dec/16 24/Dec/16 22/Dec/16 24/Dec/16
CON71900 PSA Configuration @ S/S #1 1 0% 29/Nov/16 29/Nov/16 22/Dec/16 24/Dec/16 22/Dec/16 24/Dec/16
CON71910 PSA Configuration @ S/S #5 1 0% 29/Nov/16 29/Nov/16 22/Dec/16 24/Dec/16 22/Dec/16 24/Dec/16
CON71940 Final Testing & Closed Loop with PMC 1 0% 29/Nov/16 30/Nov/16 24/Dec/16 25/Dec/16 24/Dec/16 25/Dec/16
CON71960 Close CB Feeder @ Karan 1 0% 30/Nov/16 01/Dec/16 25/Dec/16 26/Dec/16 25/Dec/16 26/Dec/16
CON72040 Diconnecting Diesel Genset from Load Side @ Karan 1 0% 30/Nov/16 01/Dec/16 25/Dec/16 26/Dec/16 25/Dec/16 26/Dec/16
CON71950 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 01/Dec/16 03/Dec/16 26/Dec/16 27/Dec/16 26/Dec/16 27/Dec/16

Page 39 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON71970 Karan Feeder Switchover to S/S #5 Completed 0 0% 03/Dec/16 27/Dec/16 Karan Feeder S
Arabiyah Field Feeder
Feede 103 0% 04/Sep/16 11/Dec/16 01/Oct/16 04/Jan/17
Arabiyah Field Feed
Feeder Works Prior to Switchover 14 0% 04/Sep/16 18/Sep/16 01/Oct/16 13/Oct/16
CON72050 13.8KV Power Cable Pulling from S/S #5 to Splice Point @ S/S #1 6 0% 04/Sep/16 10/Sep/16 01/Oct/16 06/Oct/16 01/Oct/16 06/Oct/16
CON72060 Power Cables Lugs Installation & Preparation for Cables Splicing 4 0% 10/Sep/16 14/Sep/16 06/Oct/16 10/Oct/16 06/Oct/16 10/Oct/16
CON72070 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 10/Sep/16 11/Sep/16 06/Oct/16 06/Oct/16 06/Oct/16 06/Oct/16
CON72080 New FO Cable Pulling from S/S #5 to S/S #1 Existing Splice Enclosure 4 0% 10/Sep/16 14/Sep/16 06/Oct/16 10/Oct/16 06/Oct/16 10/Oct/16
CON72090 Preparation of Diesel Genset @ Arabiyah 6 0% 10/Sep/16 15/Sep/16 06/Oct/16 11/Oct/16 06/Oct/16 11/Oct/16
CON72100 Termination of 13.8KV Power Cables @ S/S #5 Feeder 4 0% 14/Sep/16 18/Sep/16 10/Oct/16 13/Oct/16 10/Oct/16 13/Oct/16
CON72110 Termination of New FO Cable to S/S #5 13.8KV SWGR 3 0% 14/Sep/16 17/Sep/16 10/Oct/16 12/Oct/16 10/Oct/16 12/Oct/16
Arabiyah Field Feeder
Feed Switchover 8 0% 04/Dec/16 11/Dec/16 27/Dec/16 04/Jan/17
CON72120 Open Feeder CBs & Rackout @ Arabiyah & Power Cable Discharge & Grounding 1 0% 04/Dec/16 04/Dec/16 27/Dec/16 28/Dec/16 27/Dec/16 28/Dec/16
CON72130 Connecting Diesel Genset to Load Side @ Arabiyah 1 0% 04/Dec/16 05/Dec/16 28/Dec/16 29/Dec/16 28/Dec/16 29/Dec/16
CON72140 Disconnect Existing 13.8KV Power Cable from 13.8KV SWGR & Pull to Splice Pint @ S/S #1 1 0% 05/Dec/16 06/Dec/16 29/Dec/16 31/Dec/16 29/Dec/16 31/Dec/16
CON72150 Disconnect Existing FO Cable @ S/S #1 Existing Splice Enclosure 1 0% 05/Dec/16 06/Dec/16 29/Dec/16 31/Dec/16 29/Dec/16 31/Dec/16
CON72160 Splice & Terminate 13.8KV Cables @ S/S #1Splice Point 1 0% 06/Dec/16 07/Dec/16 31/Dec/16 01/Jan/17 31/Dec/16 01/Jan/17
CON72170 Termination of FO Cable @ S/S #1 Existing Splice Enclosure 1 0% 06/Dec/16 07/Dec/16 31/Dec/16 01/Jan/17 31/Dec/16 01/Jan/17
CON72180 13.8KV Power Cables Meggering After Splicing 1 0% 07/Dec/16 08/Dec/16 01/Jan/17 01/Jan/17 01/Jan/17 01/Jan/17
CON72190 PSA Configuration @ S/S #1 1 0% 07/Dec/16 08/Dec/16 01/Jan/17 01/Jan/17 01/Jan/17 01/Jan/17
CON72200 PSA Configuration @ S/S #5 1 0% 07/Dec/16 08/Dec/16 01/Jan/17 01/Jan/17 01/Jan/17 01/Jan/17
CON72210 Final Testing & Closed Loop with PMC 1 0% 08/Dec/16 08/Dec/16 01/Jan/17 02/Jan/17 01/Jan/17 02/Jan/17
CON72220 Close CB Feeder @ Arabiyah 1 0% 08/Dec/16 10/Dec/16 02/Jan/17 03/Jan/17 02/Jan/17 03/Jan/17
CON72230 Diconnecting Diesel Genset from Load Side @ Arabiyah 1 0% 08/Dec/16 10/Dec/16 02/Jan/17 03/Jan/17 02/Jan/17 03/Jan/17
CON72240 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 10/Dec/16 11/Dec/16 03/Jan/17 04/Jan/17 03/Jan/17 04/Jan/17
CON72250 Arabiyah Feeder Switchover to S/S #5 Completed 0 0% 11/Dec/16 04/Jan/17 Arabiyah Feed
Berri Field Feeders Switchover
S 101 0% 17/Sep/16 21/Dec/16 12/Oct/16 15/Jan/17
TP 1 Incom. Feeder 100 0% 17/Sep/16 20/Dec/16 12/Oct/16 14/Jan/17
TP 1 Incom. Feeder
Feede Works Prior to Switchover 21 0% 17/Sep/16 08/Oct/16 12/Oct/16 01/Nov/16
CON72260 13.8KV Power Cable Pulling from S/S #5 to S/S #1 Splice Point for TP 1 6 0% 17/Sep/16 24/Sep/16 12/Oct/16 18/Oct/16 12/Oct/16 18/Oct/16
CON72270 Power Cables Lugs Installation & Preparation for Splicing 4 0% 24/Sep/16 27/Sep/16 18/Oct/16 22/Oct/16 18/Oct/16 22/Oct/16
CON72280 Control Cables Pulling from S/S #5 13.8KV SWGR Feeder to S/S#1 Existing Marshaling Cab 4 0% 24/Sep/16 27/Sep/16 18/Oct/16 22/Oct/16 18/Oct/16 22/Oct/16
CON72290 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 27/Sep/16 28/Sep/16 22/Oct/16 23/Oct/16 22/Oct/16 23/Oct/16
CON72310 Termination of 13.8KV Power Cables @ S/S #5 Feeder 4 0% 28/Sep/16 02/Oct/16 23/Oct/16 26/Oct/16 23/Oct/16 26/Oct/16
CON72320 Termination of Control Cables @ S/S #5 Feeder 4 0% 28/Sep/16 02/Oct/16 23/Oct/16 26/Oct/16 23/Oct/16 26/Oct/16
CON72460 TP 2 Modification to Normally Open Scheme 6 0% 02/Oct/16 08/Oct/16 26/Oct/16 01/Nov/16 26/Oct/16 01/Nov/16
TP 1 Incom. Feeder
Feede Switchover 9 0% 12/Dec/16 20/Dec/16 05/Jan/17 14/Jan/17
CON72330 Open Feeder CBs & Rackout @ S/S #1 13.8KV SWGR & Power Cable Discharge & Ground 1 0% 12/Dec/16 13/Dec/16 05/Jan/17 05/Jan/17 05/Jan/17 05/Jan/17
CON72340 Disconnect Existing 13.8KV Power Cable from CB @ S/S #1 1 0% 13/Dec/16 13/Dec/16 05/Jan/17 07/Jan/17 05/Jan/17 07/Jan/17
CON72350 Disconnect Existing Control Cables Between Existing SWGR CB & Marshaling Cabinet 1 0% 13/Dec/16 14/Dec/16 07/Jan/17 08/Jan/17 07/Jan/17 08/Jan/17
CON72360 Splice & Terminate 13.8KV Cables @ S/S #1Splice Point 1 0% 13/Dec/16 14/Dec/16 07/Jan/17 08/Jan/17 07/Jan/17 08/Jan/17
CON72450 13.8KV Power Cables Meggering After Splicing 1 0% 14/Dec/16 15/Dec/16 08/Jan/17 09/Jan/17 08/Jan/17 09/Jan/17
CON72370 Termination of Control Cables @ S/S #1 Marshaling Cabinet 2 0% 14/Dec/16 17/Dec/16 08/Jan/17 10/Jan/17 08/Jan/17 10/Jan/17
CON72380 Scheme Check 2 0% 17/Dec/16 18/Dec/16 10/Jan/17 11/Jan/17 10/Jan/17 11/Jan/17
CON72390 PSA Configuration @ S/S #1 1 0% 17/Dec/16 18/Dec/16 10/Jan/17 10/Jan/17 10/Jan/17 10/Jan/17
CON72400 PSA Configuration @ S/S #5 1 0% 17/Dec/16 18/Dec/16 10/Jan/17 10/Jan/17 10/Jan/17 10/Jan/17
CON72410 Shutdown of TP 1 Final Testing & Closed Loop with PMC 1 0% 18/Dec/16 19/Dec/16 11/Jan/17 12/Jan/17 11/Jan/17 12/Jan/17
CON72420 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 19/Dec/16 20/Dec/16 12/Jan/17 14/Jan/17 12/Jan/17 14/Jan/17
CON72430 Close CB Feeder @ S/S #1 1 0% 19/Dec/16 20/Dec/16 12/Jan/17 14/Jan/17 12/Jan/17 14/Jan/17
CON72440 TP 1 Feeder Switchover to S/S #5 Completed 0 0% 20/Dec/16 14/Jan/17 TP 1 Feeder
TP 3 Incom. Feeder 95 0% 24/Sep/16 21/Dec/16 18/Oct/16 15/Jan/17
TP 3 Incom. Feeder
Feede Works Prior to Switchover 20 0% 24/Sep/16 12/Oct/16 18/Oct/16 06/Nov/16

Page 40 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON72470 13.8KV Power Cable Pulling from S/S #5 to S/S #1 Splice Point for TP 3 6 0% 24/Sep/16 29/Sep/16 18/Oct/16 24/Oct/16 18/Oct/16 24/Oct/16
CON72480 Power Cables Lugs Installation & Preparation for Splicing 4 0% 29/Sep/16 03/Oct/16 24/Oct/16 27/Oct/16 24/Oct/16 27/Oct/16
CON72490 Control Cables Pulling from S/S #5 13.8KV SWGR Feeder to S/S#1 Existing Marshaling Cab 4 0% 29/Sep/16 03/Oct/16 24/Oct/16 27/Oct/16 24/Oct/16 27/Oct/16
CON72500 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 03/Oct/16 04/Oct/16 27/Oct/16 29/Oct/16 27/Oct/16 29/Oct/16
CON72520 Termination of 13.8KV Power Cables @ S/S #5 Feeder 3 0% 04/Oct/16 06/Oct/16 29/Oct/16 31/Oct/16 29/Oct/16 31/Oct/16
CON72530 Termination of Control Cables @ S/S #5 Feeder 3 0% 04/Oct/16 06/Oct/16 29/Oct/16 31/Oct/16 29/Oct/16 31/Oct/16
CON72540 TP 2 Modification to Normally Open Scheme 6 0% 06/Oct/16 12/Oct/16 31/Oct/16 06/Nov/16 31/Oct/16 06/Nov/16
TP 3 Incom. Feeder
Feede Switchover 11 0% 11/Dec/16 21/Dec/16 04/Jan/17 15/Jan/17
CON72550 Open Feeder CBs & Rackout @ S/S #1 13.8KV SWGR & Power Cable Discharge & Ground 1 0% 11/Dec/16 12/Dec/16 04/Jan/17 05/Jan/17 04/Jan/17 05/Jan/17
CON72560 Disconnect Existing 13.8KV Power Cable from CB @ S/S #1 1 0% 12/Dec/16 13/Dec/16 05/Jan/17 05/Jan/17 05/Jan/17 05/Jan/17
CON72570 Disconnect Existing Control Cables Between Existing SWGR CB & Marshaling Cabinet 1 0% 13/Dec/16 13/Dec/16 05/Jan/17 07/Jan/17 05/Jan/17 07/Jan/17
CON72580 Splice & Terminate 13.8KV Cables @ S/S #1Splice Point 1 0% 13/Dec/16 13/Dec/16 05/Jan/17 07/Jan/17 05/Jan/17 07/Jan/17
CON72590 Termination of Control Cables @ S/S #1 Marshaling Cabinet 2 0% 13/Dec/16 15/Dec/16 07/Jan/17 09/Jan/17 07/Jan/17 09/Jan/17
CON72600 13.8KV Power Cables Meggering After Splicing 1 0% 13/Dec/16 14/Dec/16 07/Jan/17 08/Jan/17 07/Jan/17 08/Jan/17
CON72610 Scheme Check 2 0% 15/Dec/16 18/Dec/16 09/Jan/17 10/Jan/17 09/Jan/17 10/Jan/17
CON72620 PSA Configuration @ S/S #1 1 0% 15/Dec/16 17/Dec/16 09/Jan/17 10/Jan/17 09/Jan/17 10/Jan/17
CON72630 PSA Configuration @ S/S #5 1 0% 15/Dec/16 17/Dec/16 09/Jan/17 10/Jan/17 09/Jan/17 10/Jan/17
CON72640 Shutdown of TP 3 Final Testing & Closed Loop with PMC 1 0% 18/Dec/16 19/Dec/16 11/Jan/17 12/Jan/17 11/Jan/17 12/Jan/17
CON72650 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 19/Dec/16 20/Dec/16 12/Jan/17 14/Jan/17 12/Jan/17 14/Jan/17
CON72680 Open Modified CB Feeder @ TP 2 1 0% 19/Dec/16 20/Dec/16 12/Jan/17 14/Jan/17 12/Jan/17 14/Jan/17
CON72660 Close CB Feeder @ S/S #1 1 0% 20/Dec/16 21/Dec/16 14/Jan/17 15/Jan/17 14/Jan/17 15/Jan/17
CON72670 TP 1, TP 2 & TP 3 Feeders Energized Switchover to S/S #5 Completed 0 0% 21/Dec/16 15/Jan/17 TP 1, TP 2 & T
F31 CGT VAN Feeder
Feede Switchover 83 0% 12/Oct/16 28/Dec/16 06/Nov/16 22/Jan/17
F31 CGT VAN Feeder
Feed Works Prior to Switchover 16 0% 12/Oct/16 27/Oct/16 06/Nov/16 21/Nov/16
CON72690 13.8KV Power Cable Pulling from S/S #5 to Splice Point @ S/S #1 6 0% 12/Oct/16 18/Oct/16 06/Nov/16 12/Nov/16 06/Nov/16 12/Nov/16
CON72700 Power Cables Lugs Installation & Preparation for Cables Splicing 4 0% 18/Oct/16 22/Oct/16 12/Nov/16 15/Nov/16 12/Nov/16 15/Nov/16
CON72710 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 18/Oct/16 19/Oct/16 12/Nov/16 13/Nov/16 12/Nov/16 13/Nov/16
CON72720 Termination of 13.8KV Power Cables @ S/S #5 Feeder 6 0% 22/Oct/16 27/Oct/16 15/Nov/16 21/Nov/16 15/Nov/16 21/Nov/16
F31 CGT VAN Feeder
Feed Switchover 7 0% 22/Dec/16 28/Dec/16 15/Jan/17 22/Jan/17
CON72830 Open Main Incom.@ CGT Control Room & Power Cable Discharge & Grounding 1 0% 22/Dec/16 22/Dec/16 15/Jan/17 16/Jan/17 15/Jan/17 16/Jan/17
CON72730 Open Feeder CB & Rackout @ S/S #1 13.8KV SWGR & Power Cable Discharge & Groundin 1 0% 22/Dec/16 24/Dec/16 16/Jan/17 17/Jan/17 16/Jan/17 17/Jan/17
CON72740 Disconnect Existing 13.8KV Power Cable from 13.8KV SWGR & Pull to Splice Pint @ S/S #1 1 0% 24/Dec/16 25/Dec/16 17/Jan/17 18/Jan/17 17/Jan/17 18/Jan/17
CON72750 PSA Configuration @ S/S #1 1 0% 24/Dec/16 25/Dec/16 17/Jan/17 18/Jan/17 17/Jan/17 18/Jan/17
CON72760 PSA Configuration @ S/S #5 1 0% 24/Dec/16 25/Dec/16 17/Jan/17 18/Jan/17 17/Jan/17 18/Jan/17
CON72770 Splice & Terminate 13.8KV Cables @ S/S #1Splice Point 1 0% 25/Dec/16 26/Dec/16 18/Jan/17 19/Jan/17 18/Jan/17 19/Jan/17
CON72780 13.8KV Power Cables Meggering After Splicing 1 0% 26/Dec/16 27/Dec/16 19/Jan/17 19/Jan/17 19/Jan/17 19/Jan/17
CON72790 Final Testing & Closed Loop with PMC 1 0% 27/Dec/16 27/Dec/16 19/Jan/17 21/Jan/17 19/Jan/17 21/Jan/17
CON72800 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 27/Dec/16 28/Dec/16 21/Jan/17 22/Jan/17 21/Jan/17 22/Jan/17
CON72810 Close CB Feeder @ S/S 1 & CGT 1 0% 27/Dec/16 28/Dec/16 21/Jan/17 22/Jan/17 21/Jan/17 22/Jan/17
CON72820 S/S #3 Building Incom. No.1 Switchover to S/S #5 Completed 0 0% 28/Dec/16 22/Jan/17 S/S #3 Buildin
S/S #2 Feeders Switchover
Switc 87 0% 27/Oct/16 16/Jan/17 21/Nov/16 09/Feb/17
S/S #2 Feeder Incom.
Incom No1 77 0% 27/Oct/16 07/Jan/17 21/Nov/16 31/Jan/17
S/S #2 Feeder Incom.
Inco No1 Works Prior to Switchover 15 0% 27/Oct/16 10/Nov/16 21/Nov/16 05/Dec/16
CON72840 13.8KV Power Cable Pulling from S/S #5 to S/S #1 Splice Point 6 0% 27/Oct/16 02/Nov/16 21/Nov/16 27/Nov/16 21/Nov/16 27/Nov/16
CON72850 Power Cables Lugs Installation & Preparation for Splicing 4 0% 02/Nov/16 06/Nov/16 27/Nov/16 30/Nov/16 27/Nov/16 30/Nov/16
CON72860 Control Cables Pulling from S/S #5 13.8KV SWGR Feeder to S/S#1 New Splice Enclosure 4 0% 02/Nov/16 06/Nov/16 27/Nov/16 30/Nov/16 27/Nov/16 30/Nov/16
CON73040 Installation of New Control Splice Enclosure 4 0% 02/Nov/16 06/Nov/16 27/Nov/16 30/Nov/16 27/Nov/16 30/Nov/16
CON72870 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 06/Nov/16 07/Nov/16 30/Nov/16 01/Dec/16 30/Nov/16 01/Dec/16
CON72880 Termination of 13.8KV Power Cables @ S/S #5 Feeder 4 0% 07/Nov/16 10/Nov/16 01/Dec/16 05/Dec/16 01/Dec/16 05/Dec/16
CON72890 Termination of Control Cables @ S/S #5 Feeder & New Splice Enclosure S/S #1 4 0% 07/Nov/16 10/Nov/16 01/Dec/16 05/Dec/16 01/Dec/16 05/Dec/16
S/S #2 Feeder Incom.
Inco No1 Switchover 9 0% 29/Dec/16 07/Jan/17 23/Jan/17 31/Jan/17

Page 41 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON72910 Open Feeder CBs & Rackout @ S/S #1 13.8KV SWGR & Power Cable Discharge & Ground 1 0% 29/Dec/16 31/Dec/16 23/Jan/17 24/Jan/17 23/Jan/17 24/Jan/17
CON72920 Disconnect Existing 13.8KV Power Cable from CB @ S/S #1 1 0% 31/Dec/16 01/Jan/17 24/Jan/17 24/Jan/17 24/Jan/17 24/Jan/17
CON72930 Disconnect Existing Control Cables 1 0% 01/Jan/17 01/Jan/17 24/Jan/17 25/Jan/17 24/Jan/17 25/Jan/17
CON72940 Splice & Terminate 13.8KV Cables @ S/S #1Splice Point 1 0% 01/Jan/17 01/Jan/17 24/Jan/17 25/Jan/17 24/Jan/17 25/Jan/17
CON72960 13.8KV Power Cables Meggering After Splicing 1 0% 01/Jan/17 02/Jan/17 25/Jan/17 26/Jan/17 25/Jan/17 26/Jan/17
CON72950 Termination of Control Cables @ S/S #1New Splice Cabinet 2 0% 01/Jan/17 03/Jan/17 25/Jan/17 28/Jan/17 25/Jan/17 28/Jan/17
CON72970 Scheme Check 2 0% 03/Jan/17 05/Jan/17 28/Jan/17 29/Jan/17 28/Jan/17 29/Jan/17
CON72980 PSA Configuration @ S/S #1 1 0% 03/Jan/17 04/Jan/17 28/Jan/17 29/Jan/17 28/Jan/17 29/Jan/17
CON72990 PSA Configuration @ S/S #5 1 0% 03/Jan/17 04/Jan/17 28/Jan/17 29/Jan/17 28/Jan/17 29/Jan/17
CON73000 Testing & Closed Loop with PMC 1 0% 05/Jan/17 05/Jan/17 29/Jan/17 30/Jan/17 29/Jan/17 30/Jan/17
CON73010 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 05/Jan/17 07/Jan/17 30/Jan/17 31/Jan/17 30/Jan/17 31/Jan/17
CON73020 Close CB Feeder @ S/S #1 1 0% 05/Jan/17 07/Jan/17 30/Jan/17 31/Jan/17 30/Jan/17 31/Jan/17
CON73030 S/S #2 Incom. No. 1 Feeder Switchover to S/S #5 Completed 0 0% 07/Jan/17 31/Jan/17 S/S #2 Incom
S/S #2 Feeder Incom.
Incom No2 72 0% 10/Nov/16 16/Jan/17 05/Dec/16 09/Feb/17
S/S #2 Feeder Inco
Incom. No2 Works Prior to Switchover 15 0% 10/Nov/16 24/Nov/16 05/Dec/16 19/Dec/16
CON73050 13.8KV Power Cable Pulling from S/S #5 to S/S #1 Splice Point 6 0% 10/Nov/16 16/Nov/16 05/Dec/16 11/Dec/16 05/Dec/16 11/Dec/16
CON73060 Power Cables Lugs Installation & Preparation for Splicing 4 0% 16/Nov/16 20/Nov/16 11/Dec/16 14/Dec/16 11/Dec/16 14/Dec/16
CON73070 Control Cables Pulling from S/S #5 13.8KV SWGR Feeder to S/S#1 New Splice Enclosure 4 0% 16/Nov/16 20/Nov/16 11/Dec/16 14/Dec/16 11/Dec/16 14/Dec/16
CON73080 Installation of New Control Splice Enclosure 4 0% 16/Nov/16 20/Nov/16 11/Dec/16 14/Dec/16 11/Dec/16 14/Dec/16
CON73090 Open Feeder CB & Rackout @ S/S#5 & Power Cable Grounding 1 0% 20/Nov/16 21/Nov/16 14/Dec/16 15/Dec/16 14/Dec/16 15/Dec/16
CON73100 Termination of 13.8KV Power Cables @ S/S #5 Feeder 4 0% 21/Nov/16 24/Nov/16 15/Dec/16 19/Dec/16 15/Dec/16 19/Dec/16
CON73110 Termination of Control Cables @ S/S #5 Feeder & New Splice Enclosure S/S #1 4 0% 21/Nov/16 24/Nov/16 15/Dec/16 19/Dec/16 15/Dec/16 19/Dec/16
S/S #2 Feeder Incom.
Inco No2 Works Switchover 9 0% 08/Jan/17 16/Jan/17 01/Feb/17 09/Feb/17
CON73120 Open Feeder CBs & Rackout @ S/S #1 13.8KV SWGR & Power Cable Discharge & Ground 1 0% 08/Jan/17 09/Jan/17 01/Feb/17 02/Feb/17 01/Feb/17 02/Feb/17
CON73130 Disconnect Existing 13.8KV Power Cable from CB @ S/S #1 1 0% 09/Jan/17 10/Jan/17 02/Feb/17 02/Feb/17 02/Feb/17 02/Feb/17
CON73140 Disconnect Existing Control Cables 1 0% 10/Jan/17 10/Jan/17 02/Feb/17 04/Feb/17 02/Feb/17 04/Feb/17
CON73150 Splice & Terminate 13.8KV Cables @ S/S #1Splice Point 1 0% 10/Jan/17 10/Jan/17 02/Feb/17 04/Feb/17 02/Feb/17 04/Feb/17
CON73160 Termination of Control Cables @ S/S #1New Splice Cabinet 2 0% 10/Jan/17 12/Jan/17 04/Feb/17 06/Feb/17 04/Feb/17 06/Feb/17
CON73170 13.8KV Power Cables Meggering After Splicing 1 0% 10/Jan/17 11/Jan/17 04/Feb/17 05/Feb/17 04/Feb/17 05/Feb/17
CON73180 Scheme Check 2 0% 12/Jan/17 15/Jan/17 06/Feb/17 07/Feb/17 06/Feb/17 07/Feb/17
CON73190 PSA Configuration @ S/S #1 1 0% 12/Jan/17 14/Jan/17 06/Feb/17 07/Feb/17 06/Feb/17 07/Feb/17
CON73200 PSA Configuration @ S/S #5 1 0% 12/Jan/17 14/Jan/17 06/Feb/17 07/Feb/17 06/Feb/17 07/Feb/17
CON73210 Testing & Closed Loop with PMC 1 0% 15/Jan/17 15/Jan/17 07/Feb/17 08/Feb/17 07/Feb/17 08/Feb/17
CON73220 Remove Grounding & Close 13.8KV CB Feeder @ S/S #5 1 0% 15/Jan/17 16/Jan/17 08/Feb/17 09/Feb/17 08/Feb/17 09/Feb/17
CON73230 Close CB Feeder @ S/S #1 1 0% 15/Jan/17 16/Jan/17 08/Feb/17 09/Feb/17 08/Feb/17 09/Feb/17
CON73240 S/S #2 Incom. No. 2 Feeder Switchover to S/S #5 Completed 0 0% 16/Jan/17 09/Feb/17 S/S #2 Inco
Cutover of Existing S/S #1 Power Transformer & Replacement w/ New Transformers (704) & (703) 81 0% 24/Nov/16 07/Feb/17 19/Dec/16 04/Mar/17
S/S #1 Replacement of Existing Power Transformer w/ New Power Transformer (704) 69 0% 24/Nov/16 28/Jan/17 19/Dec/16 21/Feb/17
S/S #1- Power Transformer
Trans (704) Prior activities to Cutover 10 0% 24/Nov/16 04/Dec/16 19/Dec/16 28/Dec/16
CON64530 Cable Pulling from SWGR S/S #1 to TRAFO (704) AVR & RTCC Panels S/S #5 5 0% 24/Nov/16 29/Nov/16 19/Dec/16 24/Dec/16 19/Dec/16 24/Dec/16
CON65160 Cable Termination TRAFO (704) AVR & RTCC Panels Side S/S #5 5 0% 29/Nov/16 04/Dec/16 24/Dec/16 28/Dec/16 24/Dec/16 28/Dec/16
CON73250 Cable Termination @ TRAFO ( 704) Marshaling Box 3 0% 29/Nov/16 01/Dec/16 24/Dec/16 26/Dec/16 24/Dec/16 26/Dec/16
S/S #1- Cutover to R
Replace Existing Transformer w/ Power Transformer (704) 12 0% 16/Jan/17 28/Jan/17 09/Feb/17 21/Feb/17
CON73300 Disconnect All Existing Control Cables 1 0% 16/Jan/17 17/Jan/17 09/Feb/17 11/Feb/17 09/Feb/17 11/Feb/17
CON73310 Shut Down of Existing Transformer to be Replaced 0 0% 16/Jan/17 09/Feb/17 Shut Down
CON65180 Internal Scheme Modification & Cable Termination TRAFO (704) SWGR Side S/S #1 5 0% 17/Jan/17 22/Jan/17 11/Feb/17 15/Feb/17 11/Feb/17 15/Feb/17
CON70120 13.8KV Power Cable Bus Erection SWGR Side 2 0% 17/Jan/17 19/Jan/17 11/Feb/17 12/Feb/17 11/Feb/17 12/Feb/17
CON68110 Transformer (704) Scheme Check 5 0% 22/Jan/17 26/Jan/17 15/Feb/17 20/Feb/17 15/Feb/17 20/Feb/17
CON73260 Relay Setting 5 0% 22/Jan/17 26/Jan/17 15/Feb/17 20/Feb/17 15/Feb/17 20/Feb/17
CON73270 PSA Configuration @ S/S #1 5 0% 22/Jan/17 26/Jan/17 15/Feb/17 20/Feb/17 15/Feb/17 20/Feb/17
CON73465 PSA Configuration @PMC 5 0% 22/Jan/17 26/Jan/17 15/Feb/17 20/Feb/17 15/Feb/17 20/Feb/17

Page 42 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON73280 TFR (704) Closed Loop with PMC 1 0% 26/Jan/17 28/Jan/17 20/Feb/17 21/Feb/17 20/Feb/17 21/Feb/17
CON73290 TFR (704) Energizing 0 0% 28/Jan/17 21/Feb/17 TFR (704)
S/S #1-Replacement of Existing Power Transformer w/ New Power Transformer (703) 76 0% 29/Nov/16 07/Feb/17 24/Dec/16 04/Mar/17
S/S #1- Power Transformer
Trans (703) Prior activities to Cutover 10 0% 29/Nov/16 08/Dec/16 24/Dec/16 02/Jan/17
CON64520 Cable Pulling from SWGR S/S #1 to TRAFO (703) AVR & RTCC Panels S/S #5 5 0% 29/Nov/16 04/Dec/16 24/Dec/16 28/Dec/16 24/Dec/16 28/Dec/16
CON64910 Cable Termination TRAFO (703) AVR & RTCC Panels Side S/S #5 5 0% 04/Dec/16 08/Dec/16 28/Dec/16 02/Jan/17 28/Dec/16 02/Jan/17
CON65020 Cable Termination @ TRAFO ( 703) Marshaling Box 3 0% 04/Dec/16 06/Dec/16 28/Dec/16 31/Dec/16 28/Dec/16 31/Dec/16
S/S #1- Cutover to R
Replace Existing Transformer w/ Power Transformer (703) 12 0% 28/Jan/17 07/Feb/17 21/Feb/17 04/Mar/17
CON73330 Disconnect All Existing Control Cables 1 0% 28/Jan/17 29/Jan/17 21/Feb/17 21/Feb/17 21/Feb/17 21/Feb/17
CON73340 Shutdown of Existing Transformer to be Replaced 0 0% 28/Jan/17 21/Feb/17 Shutdown
CON73350 Internal Scheme Modification & Cable Termination TRAFO (703) SWGR Side S/S #1 5 0% 29/Jan/17 02/Feb/17 21/Feb/17 26/Feb/17 21/Feb/17 26/Feb/17
CON73320 13.8KV Power Cable Bus Erection SWGR Side 2 0% 29/Jan/17 30/Jan/17 21/Feb/17 23/Feb/17 21/Feb/17 23/Feb/17
CON73370 Relay Setting 5 0% 02/Feb/17 07/Feb/17 26/Feb/17 02/Mar/17 26/Feb/17 02/Mar/17
CON73380 PSA Configuration @ S/S #1 5 0% 02/Feb/17 07/Feb/17 26/Feb/17 02/Mar/17 26/Feb/17 02/Mar/17
CON73470 PSA Configuration @ PMC 5 0% 02/Feb/17 07/Feb/17 26/Feb/17 02/Mar/17 26/Feb/17 02/Mar/17
CON68070 Transformer (703) Scheme Check 5 0% 02/Feb/17 07/Feb/17 26/Feb/17 02/Mar/17 26/Feb/17 02/Mar/17
CON73390 TFR (703) Closed Loop with PMC 1 0% 07/Feb/17 07/Feb/17 02/Mar/17 04/Mar/17 02/Mar/17 04/Mar/17
CON73400 TFR (703) Energizing 0 0% 07/Feb/17 04/Mar/17 TFR (703
General Systems & Outdoor
O Works 210 40.42% 15/Apr/15 26/Sep/16 15/Apr/15 A 11/Oct/16
General Outdoor Civil Works 210 50.4% 15/Apr/15 26/Sep/16 15/Apr/15 A 11/Oct/16
Civil Construction of Oily Water Tank 25 96.79% 15/Apr/15 24/Feb/16 15/Apr/15 A 12/Apr/16
Site Preparation for Tank Construction 0 100% 15/Apr/15 04/Nov/15 15/Apr/15 A 05/Nov/15 A
CON21701 Excavation 1st (1.5M) 0 100% 15/Apr/15 27/Apr/15 15/Apr/15 A 27/Apr/15 A 15/Apr/15 A 27/Apr/15 A
CON21901 Driving Sheet Piles 0 100% 30/Jun/15 29/Jul/15 30/Jun/15 A 30/Jul/15 A 30/Jun/15 A 30/Jul/15 A
CON21801 Construction Cavity Temp. Deawtering Sys. Implementation & 2nd Excavation 0 100% 05/Aug/15 17/Sep/15 05/Aug/15 A 19/Sep/15 A 05/Aug/15 A 19/Sep/15 A
CON22001 Compacting and Leveling 0 100% 20/Sep/15 04/Nov/15 20/Sep/15 A 05/Nov/15 A 20/Sep/15 A 05/Nov/15 A
Tank Foundation 0 100% 07/Nov/15 01/Dec/15 07/Nov/15 A 01/Dec/15 A
CON22101 Lean Concrete 0 100% 07/Nov/15 07/Nov/15 07/Nov/15 A 07/Nov/15 A 07/Nov/15 A 07/Nov/15 A
CON22201 Water Proofing Below Foundation 0 100% 07/Nov/15 09/Nov/15 07/Nov/15 A 09/Nov/15 A 07/Nov/15 A 09/Nov/15 A
CON22301 REBARS of Foundation 0 100% 09/Nov/15 23/Nov/15 09/Nov/15 A 23/Nov/15 A 09/Nov/15 A 23/Nov/15 A
CON22401 Form Wrok of Foundation 0 100% 11/Nov/15 24/Nov/15 11/Nov/15 A 24/Nov/15 A 11/Nov/15 A 24/Nov/15 A
CON22501 Check Before Casting 0 100% 25/Nov/15 25/Nov/15 25/Nov/15 A 25/Nov/15 A 25/Nov/15 A 25/Nov/15 A
CON22601 Casting 0 100% 28/Nov/15 28/Nov/15 28/Nov/15 A 28/Nov/15 A 28/Nov/15 A 28/Nov/15 A
CON22701 Curing 0 100% 28/Nov/15 01/Dec/15 28/Nov/15 A 01/Dec/15 A 28/Nov/15 A 01/Dec/15 A
CON2275 Removal of Formwork 0 100% 01/Dec/15 01/Dec/15 01/Dec/15 A 01/Dec/15 A 01/Dec/15 A 01/Dec/15 A
Tank Walls & Top Slab
S 0 100% 28/Nov/15 20/Feb/16 28/Nov/15 A 05/Mar/16 A
CON22801 REBARS of Side Columns & Walls 0 100% 28/Nov/15 07/Dec/15 28/Nov/15 A 07/Dec/15 A 28/Nov/15 A 07/Dec/15 A
CON22901 Formwork of Side Columns & Walls 0 100% 30/Nov/15 09/Dec/15 30/Nov/15 A 09/Dec/15 A 30/Nov/15 A 09/Dec/15 A
CON23401 REBAR of Internal Columns 0 100% 07/Dec/15 09/Dec/15 07/Dec/15 A 09/Dec/15 A 07/Dec/15 A 09/Dec/15 A
CON23501 Formwork of Internal Columns 0 100% 08/Dec/15 10/Dec/15 08/Dec/15 A 10/Dec/15 A 08/Dec/15 A 10/Dec/15 A
CON23001 Check Before Casting 0 100% 07/Jan/16 07/Jan/16 07/Jan/16 A 07/Jan/16 A 07/Jan/16 A 07/Jan/16 A
CON23601 Check Internal Columns before Casting 0 100% 07/Jan/16 07/Jan/16 07/Jan/16 A 07/Jan/16 A 07/Jan/16 A 07/Jan/16 A
CON23101 Casting of Side Columns & Walls 0 100% 09/Jan/16 09/Jan/16 09/Jan/16 A 09/Jan/16 A 09/Jan/16 A 09/Jan/16 A
CON23201 Curing of Side Columns & Walls 0 100% 09/Jan/16 11/Jan/16 09/Jan/16 A 12/Jan/16 A 09/Jan/16 A 12/Jan/16 A
CON23701 Curing Internal Columns 0 100% 09/Jan/16 11/Jan/16 09/Jan/16 A 12/Jan/16 A 09/Jan/16 A 12/Jan/16 A
CON23301 Formwork Removal 0 100% 12/Jan/16 23/Jan/16 12/Jan/16 A 24/Jan/16 A 12/Jan/16 A 24/Jan/16 A
CON2390 Scafolding for Tank Top Slab 0 100% 14/Jan/16 07/Feb/16 14/Jan/16 A 08/Feb/16 A 14/Jan/16 A 08/Feb/16 A
CON2400 Formwork of Top Slab 0 100% 03/Feb/16 11/Feb/16 03/Feb/16 A 13/Feb/16 A 03/Feb/16 A 13/Feb/16 A
CON2410 REBARS of Top Slab & Beam 0 100% 06/Feb/16 13/Feb/16 06/Feb/16 A 14/Feb/16 A 06/Feb/16 A 14/Feb/16 A
CON2420 Embeding Air Vent and Inlet Pipe Flange 0 100% 14/Feb/16 14/Feb/16 14/Feb/16 A 14/Feb/16 A 14/Feb/16 A 14/Feb/16 A
CON2430 Check before Casting 0 100% 15/Feb/16 15/Feb/16 15/Feb/16 A 15/Feb/16 A 15/Feb/16 A 15/Feb/16 A

Page 43 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON24401 Casting of Top Slab 0 100% 16/Feb/16 16/Feb/16 16/Feb/16 A 16/Feb/16 A 16/Feb/16 A 16/Feb/16 A
CON24501 Curing of Top Slab 0 100% 16/Feb/16 16/Feb/16 16/Feb/16 A 16/Feb/16 A 16/Feb/16 A 16/Feb/16 A
CON24601 Removal of Scafolding & Formwork 0 100% 16/Feb/16 20/Feb/16 28/Feb/16 A 05/Mar/16 A 28/Feb/16 A 05/Mar/16 A
Tank Finishing Works
Wor 25 35.62% 20/Feb/16 24/Feb/16 14/Mar/16 A 12/Apr/16
CON24801 Waterprofing External Walls 2 95% 20/Feb/16 22/Feb/16 14/Mar/16 A 22/Mar/16 14/Mar/16 A 22/Mar/16
CON2485 Waterprofing Internal Walls 10 0% 20/Feb/16 22/Feb/16 21/Mar/16 29/Mar/16 21/Mar/16 29/Mar/16
CON2510 Ladder Mounting to Wall 1 0% 22/Feb/16 23/Feb/16 30/Mar/16 30/Mar/16 30/Mar/16 30/Mar/16
CON2482 Manhole Opening Frame Grouting 2 0% 22/Feb/16 24/Feb/16 11/Apr/16 12/Apr/16 11/Apr/16 12/Apr/16
Outdoor Foundation & Under Ground Tanks 62 41.18% 06/Feb/16 23/May/16 06/Feb/16 A 29/Jun/16
CON57420 ACCU Foundations Construction @ S/S #4 0 100% 06/Feb/16 15/Feb/16 06/Feb/16 A 16/Feb/16 A 06/Feb/16 A 16/Feb/16 A
CON57430 ACCU Foundations Construction @ S/S #5 0 100% 21/Feb/16 27/Feb/16 21/Feb/16 A 27/Feb/16 A 21/Feb/16 A 27/Feb/16 A
CON57440 Acid Neutralizing Tank Construction & Water Proofing @ SS/ #4 10 0% 09/Apr/16 18/Apr/16 03/May/16 12/May/16 03/May/16 12/May/16
CON57450 Acid Neutralizing Tank Construction & Water Proofing @ SS/ #5 10 0% 15/May/16 23/May/16 20/Jun/16 29/Jun/16 20/Jun/16 29/Jun/16
Rerouted Cables Tray
Tra Supports Foundations & Supports from S/S #5 to S/S #1 20 0% 30/May/16 18/Jun/16 27/Jun/16 21/Jul/16
CON70880 Excavation 2 0% 30/May/16 01/Jun/16 27/Jun/16 29/Jun/16 27/Jun/16 29/Jun/16
CON70890 REBARS & Formwork 6 0% 01/Jun/16 06/Jun/16 29/Jun/16 10/Jul/16 29/Jun/16 10/Jul/16
CON70900 Anchor Bolts Planting and Alignment 3 0% 06/Jun/16 08/Jun/16 10/Jul/16 12/Jul/16 10/Jul/16 12/Jul/16
CON70910 Check Before Casting 1 0% 08/Jun/16 09/Jun/16 12/Jul/16 13/Jul/16 12/Jul/16 13/Jul/16
CON70920 Casting 1 0% 09/Jun/16 11/Jun/16 13/Jul/16 13/Jul/16 13/Jul/16 13/Jul/16
CON70930 Curing 3 0% 11/Jun/16 13/Jun/16 14/Jul/16 17/Jul/16 14/Jul/16 17/Jul/16
CON70940 Water Proofing Works 2 0% 13/Jun/16 15/Jun/16 17/Jul/16 18/Jul/16 17/Jul/16 18/Jul/16
CON70950 Cable Bus Supports Installation & Alignment 4 0% 13/Jun/16 16/Jun/16 17/Jul/16 20/Jul/16 17/Jul/16 20/Jul/16
CON70960 Backfilling & Compacting 1 0% 15/Jun/16 16/Jun/16 19/Jul/16 19/Jul/16 19/Jul/16 19/Jul/16
CON70970 Conctrete Repair 2 0% 16/Jun/16 18/Jun/16 19/Jul/16 21/Jul/16 19/Jul/16 21/Jul/16
CON70980 Grouting 1 0% 16/Jun/16 18/Jun/16 20/Jul/16 21/Jul/16 20/Jul/16 21/Jul/16
Plumping Works 78 0% 20/Feb/16 05/Jun/16 30/Apr/16 18/Jul/16
Direct Burried Drainage
Drain Pipes Network 78 0% 20/Feb/16 05/Jun/16 30/Apr/16 18/Jul/16
CON2530 Pipes Laying from Power Transformer Foundation to Main Pipe Line Going to Tank 4 0% 20/Feb/16 23/Feb/16 30/Apr/16 03/May/16 30/Apr/16 03/May/16
CON2535 Gate Valves Installation @ Transformer Foundation Side 1 0% 22/Feb/16 23/Feb/16 03/May/16 03/May/16 03/May/16 03/May/16
CON2540 Pipes Laying from Battery Room ANT@ S/S #4 to Main Pipe Line Going to Tank 3 0% 18/Apr/16 21/Apr/16 12/May/16 15/May/16 12/May/16 15/May/16
CON2550 Pipes Laying from Mechanical Room @ S/S #4 to Main Pipe Line Going to Tank 3 0% 21/Apr/16 24/Apr/16 15/May/16 18/May/16 15/May/16 18/May/16
CON2560 Pipes Laying from Battery Room ANT @ S/S #5 to Main Pipe Line Going to Tank 4 0% 24/May/16 28/May/16 29/Jun/16 09/Jul/16 29/Jun/16 09/Jul/16
CON2515 Manholes RCC & Ground Clean Outs Casting 6 0% 24/May/16 29/May/16 29/Jun/16 11/Jul/16 29/Jun/16 11/Jul/16
CON2520 Excavation for Drainage Pipe Network 3 0% 24/May/16 28/May/16 30/Jun/16 09/Jul/16 30/Jun/16 09/Jul/16
CON25701 Pipes Laying from Mechanical Room @ S/S #5 to Main Pipe Line Going to Tank 4 0% 28/May/16 31/May/16 10/Jul/16 13/Jul/16 10/Jul/16 13/Jul/16
CON2575 Vents Connection Erection 3 0% 29/May/16 31/May/16 10/Jul/16 13/Jul/16 10/Jul/16 13/Jul/16
CON57410 Backfilling & Compaction 4 0% 01/Jun/16 05/Jun/16 14/Jul/16 18/Jul/16 14/Jul/16 18/Jul/16
Potable Water Supply
Supp 5 0% 21/Apr/16 26/Apr/16 15/May/16 19/May/16
CON57480 Excavation for Potable Water Pipes 1 0% 21/Apr/16 21/Apr/16 15/May/16 16/May/16 15/May/16 16/May/16
CON57490 Pipes Laying from Existing Connection Point to Battery Room @ S/S #4 2 0% 23/Apr/16 24/Apr/16 16/May/16 18/May/16 16/May/16 18/May/16
CON57500 Pipes Laying from Existing Connection Point to Battery Room @ S/S #5 2 0% 23/Apr/16 24/Apr/16 16/May/16 18/May/16 16/May/16 18/May/16
CON57560 Backfilling & Compaction 1 0% 25/Apr/16 26/Apr/16 19/May/16 19/May/16 19/May/16 19/May/16
Eye Wash Basins @ Battery Rooms Erection 47 0% 24/Apr/16 24/May/16 18/May/16 30/Jun/16
CON57570 Erection of Eye Wash @ S/S #4 Battery Room w/ Accessories 1 0% 24/Apr/16 25/Apr/16 18/May/16 19/May/16 18/May/16 19/May/16
CON57580 Erection of Eye Wash @ S/S #5 Battery Room w/ Accessories 1 0% 24/Apr/16 25/Apr/16 18/May/16 19/May/16 18/May/16 19/May/16
CON57590 Drainage Pipes to ANT @ S/S #4 1 0% 25/Apr/16 26/Apr/16 19/May/16 19/May/16 19/May/16 19/May/16
CON57600 Drainage Pipes to ANT @ S/S #5 1 0% 24/May/16 24/May/16 29/Jun/16 30/Jun/16 29/Jun/16 30/Jun/16
Fencing Works 29 0% 24/May/16 20/Jun/16 29/Jun/16 01/Aug/16
CON57020 Excavation 3 0% 24/May/16 26/May/16 29/Jun/16 09/Jul/16 29/Jun/16 09/Jul/16
CON57030 Lean Concrete 3 0% 26/May/16 29/May/16 09/Jul/16 11/Jul/16 09/Jul/16 11/Jul/16
CON57040 Water Proofing Below Fence Foundation 3 0% 29/May/16 01/Jun/16 11/Jul/16 13/Jul/16 11/Jul/16 13/Jul/16

Page 44 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON57050 REBARS 5 0% 01/Jun/16 06/Jun/16 14/Jul/16 18/Jul/16 14/Jul/16 18/Jul/16
CON57060 Formwork 5 0% 02/Jun/16 06/Jun/16 14/Jul/16 19/Jul/16 14/Jul/16 19/Jul/16
CON57070 Check Before Casting 1 0% 07/Jun/16 07/Jun/16 19/Jul/16 20/Jul/16 19/Jul/16 20/Jul/16
CON57080 Casting 1 0% 07/Jun/16 08/Jun/16 20/Jul/16 21/Jul/16 20/Jul/16 21/Jul/16
CON57090 Curing 3 0% 08/Jun/16 12/Jun/16 21/Jul/16 24/Jul/16 21/Jul/16 24/Jul/16
CON57110 Installation of Tention & Corner Poles 4 0% 11/Jun/16 14/Jun/16 24/Jul/16 27/Jul/16 24/Jul/16 27/Jul/16
CON57100 Formwork Removal 3 0% 12/Jun/16 14/Jun/16 24/Jul/16 27/Jul/16 24/Jul/16 27/Jul/16
CON57120 Fence Erection 3 0% 14/Jun/16 16/Jun/16 27/Jul/16 30/Jul/16 27/Jul/16 30/Jul/16
CON57105 Water Proofing 3 0% 14/Jun/16 16/Jun/16 27/Jul/16 30/Jul/16 27/Jul/16 30/Jul/16
CON57130 Doors Erection 2 0% 15/Jun/16 16/Jun/16 28/Jul/16 30/Jul/16 28/Jul/16 30/Jul/16
CON57107 Backfilling & Compaction 3 0% 16/Jun/16 20/Jun/16 30/Jul/16 01/Aug/16 30/Jul/16 01/Aug/16
Lighting Poles Found
Foundations 176 32.56% 21/Nov/15 22/Aug/16 21/Nov/15 A 07/Sep/16
CON2600 REBARS & Formwork 20 72% 21/Nov/15 05/Mar/16 21/Nov/15 A 07/Apr/16 21/Nov/15 A 07/Apr/16
CON2620 Check Before Casting 1 72% 19/Dec/15 05/Mar/16 19/Dec/15 A 07/Apr/16 19/Dec/15 A 07/Apr/16
CON2630 Casting 1 72% 20/Dec/15 05/Mar/16 20/Dec/15 A 07/Apr/16 20/Dec/15 A 07/Apr/16
CON2640 Curing 3 72% 20/Dec/15 05/Mar/16 20/Dec/15 A 07/Apr/16 20/Dec/15 A 07/Apr/16
CON2645 Formwork Removal 20 72% 20/Dec/15 08/Mar/16 20/Dec/15 A 11/Apr/16 20/Dec/15 A 11/Apr/16
CON2590 Excavation 4 0% 14/Aug/16 17/Aug/16 29/Aug/16 01/Sep/16 29/Aug/16 01/Sep/16
CON2610 Anchor Bolts Planting and Alignment 2 0% 18/Aug/16 20/Aug/16 01/Sep/16 04/Sep/16 01/Sep/16 04/Sep/16
CON2650 Water Proofing Works 2 0% 18/Aug/16 20/Aug/16 01/Sep/16 04/Sep/16 01/Sep/16 04/Sep/16
CON2660 Backfilling & Compacting 1 0% 20/Aug/16 21/Aug/16 04/Sep/16 05/Sep/16 04/Sep/16 05/Sep/16
CON2680 Conctrete Repair 2 0% 21/Aug/16 22/Aug/16 05/Sep/16 07/Sep/16 05/Sep/16 07/Sep/16
CON2670 Lighting Poles Erection 2 0% 21/Aug/16 22/Aug/16 05/Sep/16 07/Sep/16 05/Sep/16 07/Sep/16
Site Grading & Asphalting
Aspha 32 0% 21/Aug/16 21/Sep/16 05/Sep/16 08/Oct/16
CON57240 Backfilling & Grading 6 0% 21/Aug/16 27/Aug/16 05/Sep/16 11/Sep/16 05/Sep/16 11/Sep/16
CON57250 Compacting 6 0% 23/Aug/16 29/Aug/16 08/Sep/16 14/Sep/16 08/Sep/16 14/Sep/16
CON57260 Base Course Layer 5 0% 29/Aug/16 03/Sep/16 14/Sep/16 19/Sep/16 14/Sep/16 19/Sep/16
CON57270 Compacting 5 0% 31/Aug/16 05/Sep/16 17/Sep/16 21/Sep/16 17/Sep/16 21/Sep/16
CON57280 Sub-Base Course Layer 5 0% 05/Sep/16 10/Sep/16 21/Sep/16 27/Sep/16 21/Sep/16 27/Sep/16
CON57290 Compacting & Leveling 5 0% 08/Sep/16 13/Sep/16 25/Sep/16 29/Sep/16 25/Sep/16 29/Sep/16
CON57300 Asphalting 8 0% 13/Sep/16 21/Sep/16 29/Sep/16 08/Oct/16 29/Sep/16 08/Oct/16
General Painting & Finishing
F Works 100 0% 07/Jun/16 26/Sep/16 02/Jul/16 11/Oct/16
CON57135 Fire Retardant Filling of all Wall Crossings of Cable Trays & HVAC Ducts & Pipes. 5 0% 07/Jun/16 12/Jun/16 02/Jul/16 11/Jul/16 02/Jul/16 11/Jul/16
CON57140 Interior Touch up Painting of 230KV Building S/S #4 1 0% 10/Aug/16 11/Aug/16 06/Sep/16 06/Sep/16 06/Sep/16 06/Sep/16
CON57150 Interior Painting 2nd Coat of 13.8KV Building S/S #5 4 0% 16/Aug/16 20/Aug/16 22/Sep/16 27/Sep/16 22/Sep/16 27/Sep/16
CON57160 Final Painting Stairs , Hand Rails , Doors , Roof Access & Supports S/S #4 5 0% 20/Aug/16 24/Aug/16 27/Sep/16 02/Oct/16 27/Sep/16 02/Oct/16
CON57170 Final Painting Stairs , Hand Rails , Doors , Roof Access & Supports S/S #5 3 0% 20/Aug/16 23/Aug/16 27/Sep/16 29/Sep/16 27/Sep/16 29/Sep/16
CON57180 Final Painting of Steel Supports & Fence @ Transformer Yard 3 0% 24/Aug/16 28/Aug/16 02/Oct/16 04/Oct/16 02/Oct/16 04/Oct/16
CON57190 Grouting of PVC Duct Banks MH/HH of Cover Frames& Final Painting 3 0% 28/Aug/16 30/Aug/16 04/Oct/16 08/Oct/16 04/Oct/16 08/Oct/16
CON57210 Road Sign Boards Fixation 1 0% 21/Sep/16 22/Sep/16 08/Oct/16 09/Oct/16 08/Oct/16 09/Oct/16
CON57220 Roads Marking 2 0% 22/Sep/16 25/Sep/16 09/Oct/16 10/Oct/16 09/Oct/16 10/Oct/16
CON57230 Substation Boards Fixation 1 0% 25/Sep/16 26/Sep/16 10/Oct/16 11/Oct/16 10/Oct/16 11/Oct/16
General Outdoor - Electromechanical
Ele 138 0% 01/May/16 01/Sep/16 24/May/16 09/Oct/16
Hydrant System 31 0% 29/May/16 27/Jun/16 18/Jun/16 21/Jul/16
CON57310 Excavation 6 0% 29/May/16 04/Jun/16 18/Jun/16 22/Jun/16 18/Jun/16 22/Jun/16
CON57330 Laying of Pipes & Pipe Fitting Front of Transformer Yard 6 0% 31/May/16 06/Jun/16 19/Jun/16 25/Jun/16 19/Jun/16 25/Jun/16
CON57340 Contiue Laying & Fitting to around S/S #4 6 0% 06/Jun/16 12/Jun/16 25/Jun/16 30/Jun/16 25/Jun/16 30/Jun/16
CON57350 Continue Laying & Fitting to in-between of S/S #5 & Oily Water Tank 6 0% 12/Jun/16 16/Jun/16 30/Jun/16 12/Jul/16 30/Jun/16 12/Jul/16
CON57390 Hydrants Erection 6 0% 12/Jun/16 18/Jun/16 02/Jul/16 12/Jul/16 02/Jul/16 12/Jul/16
CON57355 Valve Box Placing and & Tie-in With Existing Pipe Line 6 0% 16/Jun/16 22/Jun/16 12/Jul/16 17/Jul/16 12/Jul/16 17/Jul/16
CON57360 Thrust Blocks Placing 3 0% 21/Jun/16 23/Jun/16 16/Jul/16 18/Jul/16 16/Jul/16 18/Jul/16

Page 45 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
CON57400 Backfilling & Compacting 4 0% 23/Jun/16 27/Jun/16 18/Jul/16 21/Jul/16 18/Jul/16 21/Jul/16
CON57370 Fire Monitor Connection 2 0% 23/Jun/16 26/Jun/16 18/Jul/16 20/Jul/16 18/Jul/16 20/Jul/16
Rerouted Cables Tray
Tra Installation from S/S #5 to S/S #1 5 0% 18/Jun/16 22/Jun/16 21/Jul/16 26/Jul/16
CON70990 Cabul Tray Erection from S/S#5 to S/S #1 for Rerouted Cables 5 0% 18/Jun/16 22/Jun/16 21/Jul/16 26/Jul/16 21/Jul/16 26/Jul/16
Outdoor Lighting 7 0% 20/Aug/16 27/Aug/16 04/Sep/16 11/Sep/16
CON57610 Wires Pulling to Lighting Panels 4 0% 20/Aug/16 23/Aug/16 04/Sep/16 08/Sep/16 04/Sep/16 08/Sep/16
CON57620 Installation of Lighting Fixtures on Poles 3 0% 23/Aug/16 27/Aug/16 08/Sep/16 11/Sep/16 08/Sep/16 11/Sep/16
Outdoor Earthing & Grounding
G 79 0% 25/Jun/16 01/Sep/16 25/Jul/16 09/Oct/16
CON57630 Completion of Main Grid @ S/S#4 & Connection to Existing Grid 15 0% 25/Jun/16 14/Jul/16 25/Jul/16 08/Aug/16 25/Jul/16 08/Aug/16
CON57640 Backfilling S/S #4 Side Completion 15 0% 27/Jun/16 17/Jul/16 27/Jul/16 10/Aug/16 27/Jul/16 10/Aug/16
CON57730 Lightening Arrestors (Bldg. #4) Connection to Earthing Grid S/S #4 1 0% 29/Jun/16 29/Jun/16 28/Jul/16 30/Jul/16 28/Jul/16 30/Jul/16
CON57650 Completion of Main Grid @ S/S#5 Connection to S/S #4 & Existing Grid S/S #1 15 0% 02/Jul/16 21/Jul/16 01/Aug/16 15/Aug/16 01/Aug/16 15/Aug/16
CON57660 Backfilling S/S #4 Side Completion 15 0% 10/Jul/16 24/Jul/16 02/Aug/16 16/Aug/16 02/Aug/16 16/Aug/16
CON57760 Lightening Arrestors (Bldg. #5) Connection to Earthing Grid S/S #5 1 0% 11/Jul/16 12/Jul/16 04/Aug/16 06/Aug/16 04/Aug/16 06/Aug/16
CON57790 Lightening Arrestors ( Transformer Yard ) Connection to Earthing Grid S/S #5 1 0% 14/Jul/16 14/Jul/16 07/Aug/16 08/Aug/16 07/Aug/16 08/Aug/16
CON57680 Earthing of Fence 1 0% 23/Jul/16 24/Jul/16 15/Aug/16 16/Aug/16 15/Aug/16 16/Aug/16
CON57670 Earthing of Lighting Poles 3 0% 27/Aug/16 29/Aug/16 11/Sep/16 14/Sep/16 11/Sep/16 14/Sep/16
CON57690 Earthing of all Steel Supports 2 0% 29/Aug/16 31/Aug/16 14/Sep/16 17/Sep/16 14/Sep/16 17/Sep/16
CON57700 Earthing of all Exposed Pipes 2 0% 31/Aug/16 01/Sep/16 17/Sep/16 18/Sep/16 17/Sep/16 18/Sep/16
CON7630 Earthing of Doors, Windows, Handrails & All St Supports Completion 2 0% 30/Aug/16 01/Sep/16 08/Oct/16 09/Oct/16 08/Oct/16 09/Oct/16
Lightening Protection System Installation 43 0% 01/May/16 28/May/16 24/May/16 09/Jul/16
CON57720 Bare Cupper Strips Fixing to External Wall of S/S #4 5 0% 01/May/16 05/May/16 24/May/16 29/May/16 24/May/16 29/May/16
CON57740 Installation of Lightening Arrester Rod Above S/S #4 Building Roof Parapet 1 0% 05/May/16 05/May/16 29/May/16 30/May/16 29/May/16 30/May/16
CON57750 Bare Cupper Strips Fixing to External Wall of S/S #5 5 0% 19/May/16 23/May/16 25/Jun/16 29/Jun/16 25/Jun/16 29/Jun/16
CON57770 Installation of Lightening Arrester Rod Above S/S #5 Building Roof Parapet 1 0% 24/May/16 24/May/16 29/Jun/16 30/Jun/16 29/Jun/16 30/Jun/16
CON57780 Bare Cupper Strips Fixing to Transformer Fire Walls 2 0% 24/May/16 26/May/16 30/Jun/16 09/Jul/16 30/Jun/16 09/Jul/16
CON57800 Installation of Lightening Arrester Rod Above Transformer Fire Walls 1 0% 26/May/16 28/May/16 09/Jul/16 09/Jul/16 09/Jul/16 09/Jul/16
Paging System @ S/S #4 & 5 80 0% 16/Jun/16 05/Sep/16 19/Jul/16 04/Oct/16
S/S #4- Paging System
Syste Installation 35 0% 16/Jun/16 25/Jul/16 19/Jul/16 21/Aug/16
CON60180 S/S #4 Indoor Paging System Conduits & JB Installation 5 0% 16/Jun/16 21/Jun/16 19/Jul/16 24/Jul/16 19/Jul/16 24/Jul/16
CON60190 S/S #4 Outdoor Paging System Conduits & JB Installation 10 0% 21/Jun/16 30/Jun/16 24/Jul/16 02/Aug/16 24/Jul/16 02/Aug/16
CON60200 S/S #4 Paging System Wire Pulling 10 0% 30/Jun/16 16/Jul/16 02/Aug/16 11/Aug/16 02/Aug/16 11/Aug/16
CON60210 S/S #4 Erection of Indoor Amplifiers & Loud Speakers 5 0% 16/Jul/16 20/Jul/16 11/Aug/16 16/Aug/16 11/Aug/16 16/Aug/16
CON60220 S/S #4 Erection of Outdoor Handsets & Loud Speakers 5 0% 20/Jul/16 25/Jul/16 16/Aug/16 21/Aug/16 16/Aug/16 21/Aug/16
S/S #5- Paging System
Syste Installation 45 0% 25/Jul/16 05/Sep/16 21/Aug/16 04/Oct/16
CON60230 S/S #5 Indoor Paging System Conduits & JB Installation 5 0% 25/Jul/16 30/Jul/16 21/Aug/16 25/Aug/16 21/Aug/16 25/Aug/16
CON60240 S/S #5 Outdoor Paging System Conduits & JB Installation 10 0% 30/Jul/16 08/Aug/16 25/Aug/16 04/Sep/16 25/Aug/16 04/Sep/16
CON60250 S/S #5 Paging System Wire Pulling 10 0% 08/Aug/16 17/Aug/16 04/Sep/16 14/Sep/16 04/Sep/16 14/Sep/16
CON60260 S/S #5 Erection of Indoor Amplifiers & Loud Speakers 5 0% 17/Aug/16 22/Aug/16 14/Sep/16 19/Sep/16 14/Sep/16 19/Sep/16
CON60270 S/S #5 Erection of Outdoor Handsets & Loud Speakers 5 0% 22/Aug/16 27/Aug/16 20/Sep/16 25/Sep/16 20/Sep/16 25/Sep/16
CON60280 S/S #5 Paging System Connection to S/S #4 Paging System 5 0% 27/Aug/16 31/Aug/16 25/Sep/16 29/Sep/16 25/Sep/16 29/Sep/16
CON60290 S/S #5 Paging System Connection to Existing S/S #1 Paging System 5 0% 31/Aug/16 05/Sep/16 29/Sep/16 04/Oct/16 29/Sep/16 04/Oct/16
General Testing. 34 0% 23/Aug/16 10/Sep/16 07/Sep/16 11/Oct/16
CON73420 Lighting System Testing 2 0% 23/Aug/16 24/Aug/16 07/Sep/16 08/Sep/16 07/Sep/16 08/Sep/16
CON73430 Paging System Testing 5 0% 05/Sep/16 10/Sep/16 04/Oct/16 09/Oct/16 04/Oct/16 09/Oct/16
CON73410 Earthing & Shielding System Testing 2 0% 01/Sep/16 04/Sep/16 09/Oct/16 11/Oct/16 09/Oct/16 11/Oct/16
Punch List Work 183 0% 18/Aug/16 07/Feb/17 12/Sep/16 04/Mar/17
CON73450 SS # 4 Punch List Work 25 0% 18/Aug/16 11/Sep/16 12/Sep/16 08/Oct/16 12/Sep/16 08/Oct/16
CON73455 SS # 5 Punch List Work 25 0% 01/Oct/16 24/Oct/16 25/Oct/16 17/Nov/16 25/Oct/16 17/Nov/16
CON73460 General Punch List Work 25 0% 15/Jan/17 07/Feb/17 08/Feb/17 04/Mar/17 08/Feb/17 04/Mar/17
Demolishing Work & De
Demobilization 18 0% 07/Feb/17 25/Feb/17 04/Mar/17 21/Mar/17

Page 46 of 47 TASK filter: All Activities


© Oracle Corporation
Replace Power Supply to Abu Ali Plants Construction Works 21/Mar/16 27/Mar/16 13:35

Activity ID Activity Name Remaining Units % BL Project Start BL Project Finish Start Finish 2014 2015 2016 2017
Duration Complete
M J J A S ON D J F MA M J J A SO N D J F MA M J J A S ON D J F MA M J J
Demolishing Work 10 0% 07/Feb/17 16/Feb/17 04/Mar/17 13/Mar/17
CLP0990 Removal of Existing Transformers 10 0% 07/Feb/17 16/Feb/17 04/Mar/17 13/Mar/17 04/Mar/17 13/Mar/1
CLP0993 Demolishing of Existing 115KV Lines 10 0% 07/Feb/17 16/Feb/17 04/Mar/17 13/Mar/17 04/Mar/17 13/Mar/1
Demobilization from Site
Si & Project Close Out 18 0% 07/Feb/17 25/Feb/17 04/Mar/17 21/Mar/17
CLP1000 Complete Energize S/S 0 0% 07/Feb/17 04/Mar/17 Complete
CLP1010 Contractor Demoblization 8 0% 16/Feb/17 25/Feb/17 13/Mar/17 21/Mar/17 13/Mar/17 21/Mar/1

Page 47 of 47 TASK filter: All Activities