Professional Documents
Culture Documents
Cash and Marketable Securities 142 197 552 759 1,138 1,121
Market Value of Common Equity 3,205 6,716 9,159 14,091 14,135 17,858
79 75 141 277
2.3 2 2 2.3
2.72 3.57 4.81 4.65
0.7 0.9 1.35 1.35
21 16 13 14
Exhibit 3 Cash Flow Estimation with t
a Mining costs were assumed to go up in steps. During the first half of the mining operations, costs were
b Of the original $200 million investment in capital for the project, $20 million was budgeted for working
ash Flow Estimation with the South African Investment Opportunity (in millions of dollars)
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
160 160 160 160 160 160 160 160 160 160
28.8 30.4 30.4 30.4 33.6 33.6 33.6 38.4 38.4 38.4
48 48 48 48 48 48 48 48 48 48
83.2 81.6 81.6 81.6 78.4 78.4 78.4 73.6 73.6 73.6
12 12 12 12 12 12 12 12 12 12
71.2 69.6 69.6 69.6 66.4 66.4 66.4 61.6 61.6 61.6
24.9 24.4 24.4 24.4 23.2 23.2 23.2 21.6 21.6 21.6
46.3 45.2 45.2 45.2 43.2 43.2 43.2 40 40 40
58.3 57.2 57.2 57.2 55.2 55.2 55.2 52 52 52
0 0 0 0 0 0 0 0 0 0
58.3 57.2 57.2 57.2 55.2 55.2 55.2 52 52 52
200 200 200 200 200 200 200 200 200 200
28.8 30.4 30.4 30.4 33.6 33.6 33.6 38.4 38.4 38.4
48 48 48 48 48 48 48 48 48 48
123.2 121.6 121.6 121.6 118.4 118.4 118.4 113.6 113.6 113.6
12 12 12 12 12 12 12 12 12 12
111.2 109.6 109.6 109.6 106.4 106.4 106.4 101.6 101.6 101.6
38.9 38.4 38.4 38.4 37.2 37.2 37.2 35.6 35.6 35.6
72.3 71.2 71.2 71.2 69.2 69.2 69.2 66 66 66
84.3 83.2 83.2 83.2 81.2 81.2 81.2 78 78 78
0 0 0 0 0 0 0 0 0 0
84.3 83.2 83.2 83.2 81.2 81.2 81.2 78 78 78
ning operations, costs were expected to be relatively low as a large portion of the iron ore was covered with little overburden. More expen
n was budgeted for working capital.
2027 2028 2029 Total
overburden. More expensive mining would not be necessary until the later years of mine operation.
Exhibit 4 Sensitivity of NPV (in millions of dollars) to
Ore Prices versus Various Discount Rates
5% $336.64 $581.42
6% 294.51 519.25
7% 256.97 463.8
8% 223.43 414.23
9% 193.41 369.81
10% 166.46 329.9
11% 142.23 293.97
12% 120.39 261.56
13% 100.66 232.24
14% 82.8 205.68
15% 66.61 181.57
16% 51.89 159.63
17% 38.5 139.63
18% 26.29 121.36
19% 15.13 104.66
20% 4.93 89.34
21% -4.43 75.29
22% -13.01 62.37
23% -20.91 50.46
24% -28.17 39.49
25% -34.87 29.35
26% -41.05 19.97
27% -46.77 11.28
28% -52.05 3.22
29% -56.95 -4.26
30% -61.5 -11.21
Exhibit 5 : World Top 10 Countries in Iron Production, Consumption, and Steel
Production (Million Tons)
a Capital was to be supplied at the beginning of the year and repaid at the end of the year.
Exhibit 6 : Tentative Capital Takedown Plan and Loan Principal Repayment Schedule (in millions of dollars)
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
60
40
60
40
200
0 0 0 0 0 60
2.2 2.3 0 0 0 40
8 8 8 8 4 60
10.2 10.3 8 8 4 160
Exhibit 7 Projected Cash Flows f
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
71.2 69.6 69.6 69.6 66.4 66.4 66.4 61.6 61.6 61.6
13.3 0 0 0 0 0 0 0 0 0
19.9 27 27.7 2 0 0 0 0 0 0
0 0 0 58.8
61.6 61.6 61.6 932.4
21.6 21.6 21.6 326.3
40 40 40 606.1
12 12 12 180
52 52 52 786.1
0 0 20 20
52 52 72 806.1
0 0 0 27.2
0 0 0 132.8
52 52 72 646.1
0 0 0 40
Exhibit 8 Schedule of Debt Amortization
Loan Principal
Line 2015 2016 2017 2018 2019
Payment Schedule
Senior subordinated
debt —Chinese steel
makers
9 Contractual repayment 0 0 0 0 0
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
60 60 60 60 60 60 60 60 60 60
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
40 40 40 40 40 40 40 40 40 40
0 0 0 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0 0 0
60 60 60 60 60 60 60 60 60 60
0 0 0 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0 0 0
Total
16.6
43.4
60
10.6
29.4
40
60
60
27.2
132.8
160