Report date: 18-Jan-10

DCPP 4x135 MW Unit-1 Daily Commissioning Report Status updated for: 17-Jan-10

S.No. Status of commissioning activities Remarks


1 Water charging in CWST started
2 Trial run of ID fan # 1B motor
3 Trial run of PA fan # 1B motor
4 TG lube oil flushing continued through filters
5 DM Plant Trafo # 2 charged
6 DM Plant MCC charged
7 Station MCC charged
8 SST - 2nd transformer charged

S.No. Planning for today Remarks


1 Trial run of ACW pump # 3 motor
2 DM Plant - 2 Nos. transformer to be charged
3 CT make up pump # 1 motor trial run
4
5
6
7
8

S.No. Exceptions (Delays, if any) Remarks


1
2
3
4
5
6
7
8

S.No. Critical concerns Remarks

1. Feed water line flushing to be


completed before commencement of dry
1 Refractory dry out out. Agency for pre boiler system
cleaning getting delayed.
2. Compressed air of 6kg/cm2 is required.
3. CCOE clearance for filling LDO in
tanks is required
2
3
4
5
6
7
8