You are on page 1of 1

Report date: 19-Jan-10

DCPP 4x135 MW Unit-1 Daily Commissioning Report Status updated for: 18-Jan-10

S.No. Status of commissioning activities Remarks


1 Trial run of ACW pump motor # 3 completed
2 Trial run of N-pit transfer pump # 1 & 2 motors completed
3 Trial run of CT make up pump # 1 motor completed
4 TG lube oil flushing continued through filters
5 UST # 1 charged
6 UPCC and Boiler auxilliaries MCC charged
7
8

S.No. Planning for today Remarks


1 CT make up # 1 trial run
2 Test run of SA Fan # 1A & 1B
3 ACW Pump # 1 motor trial run
4 HPF Blower # 1B motor trial run
5 Charging of LT boards - BVDC, TVDC etc
6 Air flushing of LDO unloading lines
7
8

S.No. Exceptions (Delays, if any) Remarks


1
2
3
4
5
6
7
8

S.No. Critical concerns Remarks

1. Feed water line flushing to be


completed before commencement of dry
1 Refractory dry out out. Agency for pre boiler system
cleaning getting delayed.
2. Compressed air of 6kg/cm2 is required.
3. CCOE clearance for filling LDO in
tanks is required
2
3
4
5
6
7
8

You might also like