The daily commissioning report for DCPP 4x135 MW Unit-1 provides the status of activities from January 18th. Trials were completed for various pump motors and flushing of the turbine lube oil continued. Critical concerns include completing feedwater line flushing before dryout and obtaining clearance to fill LDO tanks. Planned activities for January 19th include running additional equipment and charging control boards. No exceptions or delays were reported.
The daily commissioning report for DCPP 4x135 MW Unit-1 provides the status of activities from January 18th. Trials were completed for various pump motors and flushing of the turbine lube oil continued. Critical concerns include completing feedwater line flushing before dryout and obtaining clearance to fill LDO tanks. Planned activities for January 19th include running additional equipment and charging control boards. No exceptions or delays were reported.
The daily commissioning report for DCPP 4x135 MW Unit-1 provides the status of activities from January 18th. Trials were completed for various pump motors and flushing of the turbine lube oil continued. Critical concerns include completing feedwater line flushing before dryout and obtaining clearance to fill LDO tanks. Planned activities for January 19th include running additional equipment and charging control boards. No exceptions or delays were reported.
1 Trial run of ACW pump motor # 3 completed 2 Trial run of N-pit transfer pump # 1 & 2 motors completed 3 Trial run of CT make up pump # 1 motor completed 4 TG lube oil flushing continued through filters 5 UST # 1 charged 6 UPCC and Boiler auxilliaries MCC charged 7 8
S.No. Planning for today Remarks
1 CT make up # 1 trial run 2 Test run of SA Fan # 1A & 1B 3 ACW Pump # 1 motor trial run 4 HPF Blower # 1B motor trial run 5 Charging of LT boards - BVDC, TVDC etc 6 Air flushing of LDO unloading lines 7 8
S.No. Exceptions (Delays, if any) Remarks
1 2 3 4 5 6 7 8
S.No. Critical concerns Remarks
1. Feed water line flushing to be
completed before commencement of dry 1 Refractory dry out out. Agency for pre boiler system cleaning getting delayed. 2. Compressed air of 6kg/cm2 is required. 3. CCOE clearance for filling LDO in tanks is required 2 3 4 5 6 7 8