QUOTATION OF SOFT SOIL IMPROVEMENT WORK

PROJECT: JOTUN VIETNAM-GREEN FIELD PROJECT


ADD.: HIEP PHUOC INDUSTRIAL PARK, NHA BE COMMUNE, HCMC, VIETNAM.
No. Work item Unit Quantity Price (VNĐ) Amount (VNĐ) Remark
A Earth work
1 Supply sand for filling up to F.G + 2.9m, Compaction K90 m3 46,748 195,000 9,115,825,599
B Soil improvement work
I Prefabricated vertical drain board construction:
1 Supply and Installation material (include frequence testing) m 795,990 5,900 4,696,338,758 A7 type
II SB drain and horizontal dranage system
Supply, Installation material SB T200 (include frequence
1 m 23,386 33,500 783,420,716
testing)
Installation underground conllected canel (with UPVC
3 m 991 350,000 346,909,850
filtration pipe covered by geotextile and gravel)
Installation collected well (included well and pump) and
4 set 6 80,267,000 481,602,000
operation (12 months)
5 Side ditch m3 1,749 27,600 48,272,400
III Sand filling for Soil improvement work
1 Supply and Compact K90 sand for compensation m3 54,015 195,000 10,532,843,149
2 Supply and Compact K90 sand for surcharge preloading m3 62,405 195,000 12,169,072,073
4 Remove surcharge sand after SIW complete m3 62,405 23,000 1,435,326,450
5 Supply and Installation Woven Geotextile 200/200 kN/m m2 47,696 39,600 1,888,780,039
C Monitoring and post soil investigation
I Monitoring work Ls 1 800,000,000 800,000,000
1 Supply material, install Surface settlement plate set 24
Supply material, install Piezometer (at middle depth of
2 set 4
treated soil)
3 Supply material, install Inclinometer (40m of depth) set 2
4 Supply material, install Observation well (depth 20m) set 2
5 Monitoring and report month 12
Total not include VAT 42,298,391,033
VAT 10% 4,229,839,103
Total not include VAT 46,528,230,136