You are on page 1of 2

Construction

Issues
discussion of construction
issues and techniques

R E
U
Soil nail wall construction. t
righ

T
y
Cop

W hen a line is drawn on paper, what does type of wall that is best suited

C
it mean? for a particular site. Choosing
Retaining walls are usually drafted as a simple the wrong type of wall may The Complexities of
e Line
U anSimple
line on plans by the architect or engineer, with not provide sufficient restraint,
little direction other than a note: “Retaining wall
i
may be impractical to construct,

R z
design and construction by others.” and may cause instability in the

T a
But retaining walls are more than just a simple existing geotechnical conditions.

ag
Considerations for

S
line. A range of decisions face the design and con- A decision has to be made at the beginning of
struction team when planning solutions for grade design: Is the site better suited for top-down
Retaining Wall Projects
separations with a retaining wall. Understanding
these decisions and accurately communicating
them to the client, as well as to each other, is
m
construction or bottom-up construction? Top-
down construction is appropriate for sites that
need to be excavated to achieve final grade,
By John H. Hart, P.E., D.GE.
essential for engineers, particularly as the use of while the bottom-up approach applies to sites
retaining walls in construction continues to grow. that need to be filled. Technologies for top-
As usable or “good” sites become scarcer, retaining down construction include soil nail walls,
walls are often the only option for optimizing secant drilled shafts, and soldier pile walls,
tight sites with hard-to-meet space requirements while technologies for bottom-up construction
or significant slopes. include mechanically stabilized earth (MSE)
John H. Hart, P.E., D.GE.
In short, that simple line can make or break walls, conventional gravity walls, and gabion
(JHart@ctlthompson.com),
a project. The key to designing and construct- walls. Each of these technologies has unique
is a practicing engineer at
ing a successful retaining wall – and avoiding applications that are dependent on the site
CTL|Thompson in Denver,
a “situation” – is careful consideration in the layout, the height of wall, soil conditions, the
Colorado. Specializing in the
initial design phases, including (1) the type of presence of nearby structures, underground
fields of deep foundations, earth
system to use, and (2) the contractual approach utilities, and the intended use of the areas near
retention design, and landslide/
to design and construction. the top and bottom of the wall.
stability analysis, Hart has led a
Too often, the wrong wall type is selected
broad spectrum of projects.
for a site, which results in two retaining walls
Type of System being constructed where only one is needed.
Engineers have several different options for the An example is when a design incorporates a
design and construction of retaining walls. At pres- bottom-up wall that requires excavation into an
ent, retaining walls can be built out of traditional existing slope. In order to provide the restraint
materials such as concrete and steel reinforcement, required, such as a heel for concrete walls or
or from new technological materials such as geo- geosynthetic length for MSE walls, a nearly
synthetics and lightweight concrete. Furthermore, vertical slope must be excavated behind these
in the last twenty years, pre-manufactured retain- elements. This requires an additional top-down
ing wall systems have become available that offer construction wall behind the proposed wall. If
reasonable factors of safety while providing multiple the designer is aware of all the retaining wall
aesthetic facing options. Typically, several condi- technologies, one top-down wall could be uti-
tions from the geotechnical, structural, civil, and lized in this situation, resulting in a substantial
construction perspectives have a bearing on the decrease in cost to the owner.
continued on next page
STRUCTURE magazine 13
Contractual Approach addition, if an engineer is well-versed in only one addition, the owner should be assured that a
engineering discipline, then aspects from other functioning final product will be produced.
to Design points of view may be overlooked.
Performance-Specified Design Approach
Top-down or bottom-up retaining walls Undeveloped properties may have unique
have advantages and disadvantages that are slopes or geotechnical issues that are yet undis- Another option for designing and building
specific to the site and situation. But who covered. This can lead to a difficult situation a retaining structure is the performance-
or what determines which retaining wall – especially if it is the contractor that recog- specified wall. In this approach, the design
system is the most appropriate, considering nizes the problem once the team is in the field. team provides basic criteria, such as desired
cost, resistance and constructability? Soil conditions may not be uniform, slopes wall length, height, etc. and the contractor,
There are generally two approaches to design may be steeper than expected, or the design with engineering support, designs and builds
and construction: the traditional approach, may not be adequate for the overall loads. the wall. In this scenario, an in-house engineer
where an engineer designs the system and the If the contractor must make these decisions or engineering consultant subcontracted to the
contractor builds it; and the performance- in the field, it may lead to change orders, contractor designs the wall considering the
specified approach, where the engineer which in turn lead to extra costs for the owner. basic criteria provided by the design team. The
provides the basic criteria such as length, Furthermore, if the designer is not in the contractor’s engineer decides which specific
height, and location, and the contractor field with the wall builder, there may be less system should be ® constructed and designs that

E
designs and builds the wall with engineering communication, which sets up the engineer system accordingly. Furthermore, the contrac-
support, either in-house or subcontracted. as an adversary and lessens the likelihood for tor’s engineer selects facing for the proposed

R
success. Lastly, the wall built by the low bidder wall, which may be block, something that
Traditional Design Approach
may not be the most aesthetically pleasing. matches the natural environment, or sculp-

U
In the traditional approach, the contrac- On the other hand, ht there are real benefits to tured shotcrete, which looks like natural rock.
yrig

T
tor constructs the wall in accordance with be derived from Cop the traditional approach. For There are several advantages to this approach: It
the plans and specifications developed by one thing, all of the contractors are bidding on could result in a lower cost to the owner because

C
the engineer. The owner hires an engineer the same design, which the engineer presumably it allows the engineering to be more innovative,

e
U
to design a retaining wall, and the engineer designed in full compliance with the governing enabling the designer to be more aggressive,
provides plans and specifications for contrac- codes. This results in economical construction
i n potentially offering more expertise as it relates to

R
tors to use in preparing competitive bids. because it is streamlined and consistent – if the specific conditions and wall types. This approach
z
T
If the features at the site and limitations of con- designer understands all engineering aspects of also lays the groundwork for better communi-
struction equipment are not fully understood, the a
the retaining wall. It also puts the contractors
g
cation between the engineer and contractor, so

S
proposed construction may not be achievable. In in competition from a bidding perspective. In modifications can be made on the fly.
a There are drawbacks as well. The per-
m formance of the wall may suffer because
quality control and quality assurance is left
in the contractor’s hands from both a design
and construction perspective. Furthermore,
the design may only be able to incorporate
wall systems that the contractor can build
and not truly evaluate different wall sys-
tems that may be appropriate for the site.
An example would be when the engineer
who is working for the contractor designs
an MSE wall to be built by an MSE wall
contractor; a soil nail wall system might
have been more appropriate for the site,
but the contractor does not have the equip-
ment to build it. Finally, with innovation in
design, codes may be pushed to the farthest
extent, which may result in deficiency in
Design/Build overall long-term performance of the wall.
Earth Retention
Foundation Support Conclusion
There are numerous approaches to design
Slope Stabilization
and many types of retaining systems, each
Ground Improvement with specialized applications that can be
used to retain soil and/or provide stability
Dewatering to slopes. Understanding what is involved
in each design approach, how the system is
constructed, and under what conditions they
800-562-8460 WWW.DBMCONTRACTORS.COM
Donald B. Murphy Contractors, Inc.
are constructed is imperative to successful
and economical design and construction.▪

STRUCTURE magazine 14 December 2013

You might also like