Professional Documents
Culture Documents
Cement @ 150 kg/cum of concrete tonne 67.500 8100.00 546750.00 8320.00 561600.00
d) Overhead charges on (a+b+c) 5.00% 50478.17 59767.94
e) Contractor's profit on (a+b+c+d) 10.00% 106004.16 125512.67
Cost for 450 cum = a+b+c+d+e 1166045.73 1380639.32
Less: Cost of materials 791613.00 844209.00
374432.73 536430.32
Rate per cum = (a+b+c+d+e)/450 832.07 1192.07
say 832.00 say 1192.00
Note Quantity provided for aggregate is for estimating purpose.
Exact quantity shall be as per mix design.
Ref. to Plain Hill
Item
MoRTH Description Unit Quantity
No Rate ` Cost ` Rate ` Cost `
Spec.
6.02 602 Cement Concrete Pavement (laying with fixed form / slip
form paver)
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with min.
cement content @ 430 kg per cum, coarse and fine
aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a batching and
mixing plant as per approved mix design, transported to site,
laid with a fixed form or slip form paver, spread, compacted
and finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints,
joint filler, separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as
per
Unitdrawing
= cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 297.00 594.00 297.00 594.00
Mazdoor skilled day 15.000 297.00 4455.00 297.00 4455.00
Mazdoor day 35.000 245.00 8575.00 245.00 8575.00
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 360.00 1008.00 378.00 1058.40
Front end loader 1 cum bucket capacity hour 18.000 800.00 14400.00 840.00 15120.00
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 4433.00 26598.00 4654.65 27927.90
(effective output)
Electric generator 250 KVA hour 6.000 900.00 5400.00 945.00 5670.00
Slip form paver with electronic sensor hour 6.000 2700.00 16200.00 2835.00 17010.00
Water tanker6 KL capacity hour 36.000 150.00 5400.00 157.50 5670.00
Transit truck agitator 5 cum capacity. tonne.km 24150.000 3.00 72450.00 3.15 76072.50
Add 10 per cent of cost of carriage to cover cost of loading 7245.00 7607.25
and unloading
Concrete joint cutting machine . hour 12.000 150.00 1800.00 157.50 1890.00
Texturing machine . hour 12.000 154.00 1848.00 161.70 1940.40
c) Material
Crushed stone coarse aggregates of 25mm and 12.5mm cum 945.000 604.60 571347.00 697.80 659421.00
nominal size @ 0.90 cum/cum of concrete conforming to
clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 @ cum 473.000 627.92 297006.16 1263.64 597700.00
0.45 cum/cum of concrete
Cement 53 grade @ 430 kg/cum of concrete tonne 451.500 8320.00 3756480.00 8580.00 3873870.00
32 mm mild steel dowel bars of grade S 240 tonne 14.362 53900.00 774115.84 54900.00 788477.92
12 mm deformed steel tie bars of grade S 415 tonne 0.920 53900.00 49588.00 54900.00 50508.00
Separation Membrane of impermeable plastic sheeting sqm 3675.000 12.00 44100.00 12.00 44100.00
125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion joint. sqm 16.330 700.00 11431.00 700.00 11431.00
Joint sealant kg 875.000 387.00 338625.00 387.00 338625.00
Sealant primer kg 116.670 446.00 52034.82 446.00 52034.82
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 30.00 1400.10 30.00 1400.10
Curing compound liter 1850.000 60.00 111000.00 60.00 111000.00
Super plastisizer admixture IS marked as per 9103-1999 kg 2070.000 66.00 136620.00 66.00 136620.00
@ 0.5 per cent by weight of cement
Add 1 per cent of material for cost of miscellaneous 61437.48 66651.88
materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work bridges
for men to approach concrete surface without walking over it,
cutting blades and bites, minor equipments like scabbling
machine, threads, ropes, guide wires and any other
unforeseen items.
d) Overhead charges on (a+b+c) 5.00% 318557.92 345271.51
e) Contractor's profit on (a+b+c+d) 10.00% 668971.63 725070.17
Cost for 1050cum = a+b+c+d+e 7358687.95 7975771.84
Less: Cost of materials 5151530.84 5372276.92
2207157.11 2603494.92
Rate per cum = (a+b+c+d+e)/1050 2102.05 2479.52
say 2102.00 say 2480.00
Note The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will
be as per mix design.
Ref. to Plain Hill
Item
MoRTH Description Unit Quantity
No Rate ` Cost ` Rate ` Cost `
Spec.
6.02 A 1500 Cement Concrete Pavement (manual laying) [ ALTERNATE METHOD as per MORD]
of MORD Construction of un-reinforced, dowel jointed at expansion
and construction joint only, plain cement concrete pavement,
thickness as per design, over a prepared sub base, with min.
cement content @ 430 kg per cum, coarse and fine
aggregates conforming to IS:383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a batching &
mixing plant and appropriate weigh batcher using approved
mix design, laid in approved fixed side formwork (steel
channel, laying and fixing of 125 micron thick polythene film,
wedges, steel plates including levelling the formwork as per
drawing), spreading the concrete with shovels, rakes,
compacted using needle, screed and plate vibrators and
finished in continuous operation including provision of
contraction and expansion, construction joints, applying
debonding strips, primer, sealant, dowel bars, near
approaches to bridge/culvert and construction joints,
admixtures as approved, curing of concrete slabs for 14-
days, using curing compound (where specified) and water
finishing to lines and grade as per drawing and Technical
Specification
Unit = cum Clause 1501.
Taking output = 75 cum (172.5 tonne)
(100 x 3.75 x 0.200)
a) Labour
Mate day 2.000 297.00 594.00 297.00 594.00
Mazdoor (Unskilled) day 82.000 245.00 20090.00 245.00 20090.00
Mazdoor (Skilled) day 41.000 297.00 12177.00 297.00 12177.00
Blacksmith for cutting of dowel bars including removal of day 1.000 326.00 326.00 326.00 326.00
burrs, fabrications & fixing of dowel bars.
b) Machinery
Front end loader 1 cum bucket capacity hour 1.280 800.00 1024.00 840.00 1075.20
Cement concrete batch mix plant @ 75 cum per hour hour 0.430 2500.00 1075.00 2625.00 1128.75
(effective output)
Electric generator 250 KVA hour 0.430 900.00 387.00 945.00 406.35
Water tanker6 KL capacity hour 2.570 150.00 385.50 157.50 404.78
Transit truck agitator 5 cum capacity. tonne.km 1700.00 3.00 5100.00 3.15 5355.00
Needle vibrator hour 9.000 106.00 954.00 111.30 1001.70
Screed vibrator hour 9.000 106.00 954.00 111.30 1001.70
Plate vibrator hour 9.000 106.00 954.00 111.30 1001.70
Concrete joint cutting machine for initial & final cuts tonne.km 4.000 150.00 600.00 157.50 630.00
Air Compressor (1 hour initial + 1 hour final) hour 2.000 325.00 650.00 341.25 682.50
c) Material
Crushed stone coarse aggregates, grading will be as per cum 67.500 604.60 40810.50 697.80 47101.50
Clause 1501.2.4.1 (Table 1500.1) of specifications @
0.90 cum/cum of concrete
Sand as per IS:383 and conforming to Clause 1500.2.4.2 cum 33.750 627.92 21192.30 1263.64 42647.73
@ 0.45 cum/cum of concrete
Cement min @ 430 kg/cum of concrete tonne 32.250 8320.00 268320.00 8580.00 276705.00
Polythene sheet 125 micron sqm 412.500 12.00 4950.00 12.00 4950.00
32 mm mild steel dowel bars of grade S 240 & 12 mm t 1.090 53900.00 58751.00 54900.00 59841.00
deformed steel tie bars of grade S 415
Bitumen primer @ 200 ml per joint for 23 joints liter 4.600 200.00 920.00 200.00 920.00
Bituminous sealant 800 ml per joint for 23 joints liter 18.400 144.00 2649.60 144.00 2649.60
Jute rope 12 mm dia including 5 per cent wastage m 90.000 1.00 90.00 1.00 90.00
Debonding strips 3.75 m (length) x 10 mm (width) x 5 m 90.000 10.00 900.00 10.00 900.00
mm (thick) cut-out of rubber filler board or similar
material including 5 per cent wastage
Polythene sheathing, covering 2/3rd dowel bars (20x23) sqm 161.000 12.00 1932.00 12.00 1932.00
and tight fit including 5 per cent wastage
Plasticizer 0.5 per cent by weight of cement liter 122.000 66.00 8052.00 66.00 8052.00
Curing compound (if used) @ 0.33 litre per sqm liter 131.250 60.00 7875.00 60.00 7875.00
Water for curing kl 18.000 0.00 0.00 0.00 0.00
Joint filler board 20 mm thick as per IS:1838 sqm 3.000 700.00 2100.00 700.00 2100.00
(4 x 3.75 x 0.200 = 3 sqm)