BAC Secretariat 4. Schedule TWG meeting for bid opening and Schedule TWG meeting for
(Secretary II ) 1 day
evaluation bid opening and evaluation
BAC Secretariat
6. Prepare Abstract of Quotations (AOQ) for 2 hours
(AO III) Prepare AOQ for
signature of End user (EU) , TWG and BAC
members signature
EU, TWG and BAC 7. Sign the AOQ Sign the AOQ 1 day
Members
BAC Secretariat 9. Prepare Purchase of Order (PO) Prepare Purchase Order 2 hours
(AO III)
FD CAO, Concerned 10. Sign the PO Sign the Purchase Order 1 day
Service Director and
DED
BAC Secretariat 11. Forward the PO for conforme to Forward the PO for
conforme to 1 day
(AO III) supplier/provider
supplier/provider