COSTO MANO DE OBRA y JORNALES


Costo de Mano de Obra
Operario Oficial Peon
Descripcion
S/. S/. S/.

Salario Basico 48.60 41.60 37.20


Bonificacion Unificada 15.55 12.48 11.16
Movilidad 7.20 7.20 7.20
Dominical 8.53 7.30 6.53
Liquidacion y utilidades 7.29 6.24 5.58
Vacaciones 5.60 4.80 4.29
Gratificaciones 10.80 9.25 8.27
Dias Feriados 1.82 1.56 1.40
Asignacion Escolar 12.15 10.40 9.30
Prestaciones de Salud 8.19 6.92 6.19
Accidentes de Trabajo 1.17 1.00 0.90
Overol 0.47 0.47 0.47

Costo Total 127.39 109.22 98.48

Costo por Hora 15.92 13.65 12.31

Instituto de Desarrollo e Investigación “Construir”


Tel: 263-7469 / Cel: 998718415 Lima – Perú
Web: www.institutoconstruir.org
0000FFINSTITUTO DE DESARROLLO E INVESTIGACION
“CONSTRUIR”
(IDIC)

PLANILLA DE JORNALES Elaborado con base al Acta de Negociacion Colectiva 2011-2012


CONSTRUCCION CIVIL Valido del 1 de Junio del 2011
I II III 1 2 3 4 A B 5 NETO
DESCANSO BONIFICACIONES 1+2+3 (4-3a) Ref(1+2) A+B A
Ocupacion y Equivalente Total de Importe REMUNERADO 3a 3b Importe DESCUENTO TRABAJADOR Total PAGAR
Remuneracion en dias Horas Semanal 2a 2b Movilidad BONIFICACION Semanal S.N.P. CONAFO Descuento 4-5
Basica laborados Laboradas Ordinario Jornal por Jornal por Acumulada UNIFICADA Ordinario .(13%) VICER
descanso feriado no Según RD DE + Ley 2%
Dominical laborado No.777-87 CONSTRUCCION Dominical No.26504 R.S. 001/95
DR-LIM BUC + MTC del
7/8/1987 Bonificacio- 1/5/1995
nes

S 5.5 33.41 5.57 7.20 10.69 56.87 6.46 0.78 7.24 49.64
1D 8.5 51.64 8.61 7.20 16.52 83.97 9.98 1.20 11.18 72.78
1D+S 14.0 85.05 14.18 14.40 27.22 140.84 16.44 1.98 18.42 122.42
OPERARIO 2D 17.0 103.28 17.21 14.40 33.05 167.94 19.96 2.41 22.37 145.57
2D+S 22.5 136.69 22.78 21.60 43.74 224.81 26.42 3.19 29.61 195.20
48.60 3D 25.5 154.91 25.82 21.60 49.57 251.90 29.94 3.61 33.55 218.35
3D+S 31.0 188.33 31.39 28.80 60.26 308.78 36.40 4.39 40.79 267.99
4D 34.0 206.55 34.43 28.80 66.10 335.87 39.92 4.82 44.74 291.13
4D+S 39.5 239.96 39.99 36.00 76.79 392.74 46.38 5.60 51.98 340.77
5D 42.5 258.19 43.03 36.00 82.62 419.84 49.90 6.02 55.92 363.92
6D (S.C.) 48.0 291.60 48.60 43.20 93.31 476.71 56.36 6.80 63.16 413.55
4D+F+S 39.5 239.96 48.60 51.64 36.00 76.79 452.99 54.21 5.77 59.98 393.01
5D+SF 42.5 258.19 48.60 33.41 36.00 82.62 458.82 54.97 6.14 61.10 397.72
S 5.5 28.60 4.77 7.20 8.58 49.15 5.45 0.67 6.12 43.03
1D 8.5 44.20 7.37 7.20 13.26 72.03 8.43 1.03 9.46 62.57
1D+S 14.0 72.80 12.13 14.40 21.84 121.17 13.88 1.70 15.58 105.59
OFICIAL 2D 17.0 88.40 14.73 14.40 26.52 144.05 16.85 2.06 18.92 125.14
2D+S 22.5 117.00 19.50 21.60 35.10 193.20 22.31 2.73 25.04 168.16
41.60 3D 25.5 132.60 22.10 21.60 39.78 216.08 25.28 3.09 28.38 187.70
3D+S 31.0 161.20 26.87 28.80 48.36 265.23 30.74 3.76 34.50 230.73
4D 34.0 176.80 29.47 28.80 53.04 288.11 33.71 4.13 37.84 250.27
4D+S 39.5 205.40 34.23 36.00 61.62 337.25 39.16 4.79 43.96 293.30
5D 42.5 221.00 36.83 36.00 66.30 360.13 42.14 5.16 47.29 312.84
6D (S.C.) 48.0 249.60 41.60 43.20 74.88 409.28 47.59 5.82 53.41 355.87
4D+F+S 39.5 205.40 41.60 44.20 36.00 61.62 388.82 45.87 4.94 50.81 338.01
5D+SF 42.5 221.00 41.60 28.60 36.00 66.30 393.50 46.48 5.25 51.73 341.77
S 5.5 25.58 4.26 7.20 7.67 44.71 4.88 0.60 5.47 39.24
1D 8.5 39.53 6.59 7.20 11.86 65.17 7.54 0.92 8.46 56.71

Instituto de Desarrollo e Investigación “Construir”


Tel: 263-7469 / Cel: 998718415 Lima – Perú
Web: www.institutoconstruir.org
0000FFINSTITUTO DE DESARROLLO E INVESTIGACION
“CONSTRUIR”
(IDIC)

1D+S 14.0 65.10 10.85 14.40 19.53 109.88 12.41 1.52 13.93 95.95
PEON 2D 17.0 79.05 13.18 14.40 23.72 130.34 15.07 1.84 16.92 113.42
2D+S 22.5 104.63 17.44 21.60 31.39 175.05 19.95 2.44 22.39 152.66
37.20 3D 25.5 118.58 19.76 21.60 35.57 195.51 22.61 2.77 25.38 170.13
3D+S 31.0 144.15 24.03 28.80 43.25 240.22 27.48 3.36 30.85 209.37
4D 34.0 158.10 26.35 28.80 47.43 260.68 30.14 3.69 33.83 226.85
4D+S 39.5 183.68 30.61 36.00 55.10 305.39 35.02 4.29 39.31 266.08
5D 42.5 197.63 32.94 36.00 59.29 325.85 37.68 4.61 42.29 283.56
6D (S.C.) 48.0 223.20 37.20 43.20 66.96 370.56 42.56 5.21 47.76 322.80
4D+F+S 39.5 183.68 37.20 39.53 36.00 55.10 351.50 41.02 4.42 45.43 306.07
5D+SF 42.5 197.63 37.20 25.58 36.00 59.29 355.69 41.56 4.70 46.26 309.43

Instituto de Desarrollo e Investigación “Construir”


Tel: 263-7469 / Cel: 998718415 Lima – Perú