Professional Documents
Culture Documents
Description
1.0 DRIVEN PILING
1. Objective
To outline the sequence of activities method and resources needed for the operation of driving
the reinforced concrete pile
2. Scope
The work shall include all labor, material, equipment, permits and services necessary for the
execution of piling work.
Site survey: Setting out of pile points to be carried out in relation to the plinth position
of switchyard block or trench block
Platform preparation: The platform shall be leveled and cleared for piling frame to
move in for piling work
Move the piling frame over pile cap position at which the pile is to be driven in. Check
the verticality of the frame by vertical spirit level.
Check piling equipment including hydraulic power pack, hydraulic hoses, cooling
system and control panel.
Hoist pile by the mobile crane and shift near to the piling frame
Then pull the cable from the piling frame and hook on to the pile for positioning it to
the intended pile point. Check the pile vertically before starting driving with vertical
spirit level.
The equipment and machine shall be dismantled after completing work at the
particular location and then to mobilize & reinstall prior to continuing piling work at the
other bay.
Machine is assembled at site and the hydraulic system is checked for leakage.
Mobilize the machine to position over the intended pile point; adjust the machine to ensure
its leader is vertical
A length of pile is pitched by the service crane position centrally between the two main
jacks, the pile head is held within a cap at the upper drive-head, and supported about its
mid-section at the position of lower drive head.
The whole length of pile is pushed into the ground in two strokes.
An extension pile is nest pitched and jointed onto the previous pile by welding. The whole
operation is repeated.
The termination criteria are; the require pressure corresponding to the require force is
HG Power Transmission Sdn. Bhd.
Quality Plan
Inspection of the pile. All pile shall be free from defects.
Inspection of vertically of pile.
All sites welding of joint must be full bud-welding. Inspection on welding quality shall
be carried out before moving to the new pile.
Pile set. Check on penetration rate for pile set shall be carried out before moving to
the new pile position.
The test set up and relevant calibration certificates shall be submitted for verification
before test commences.
Safety Plan
Safety helmet and safety footwear must always be worn.
All soft spots or holes shall be identified and barricade if necessary.
The site shall be kept clear of unnecessary obstruction such as reinforcement rods,
timber with protruding nails, etc.
First aid box at site will be provided
Care should be taken to ensure that pile driving operation does not damage adjacent
properties and services.
1. Objective
The outline sequence of activities method and resources needed for the operation of driving the pre-
cast concrete piles.
2. Scope
The work shall include all labor, material, equipment, permits and services necessary for the
execution of piling work
Injection chamber/guide
Pre jack
Control panel and gauges