You are on page 1of 2

Doc No DSE/PGB/HEX/QAQC/IP/026

QA/QC PROCEDURE Rev 0


Date 14 Mar 2016
PGB/HO/19/2015/0094
Page 1 of 2

ENGINEERING, PROCUREMENT,
CONSTRUCTION AND COMMISSIONING (EPCC)
OF WATER COOLED HEAT EXCHANGERS INSTALLATION
AT GPP2, GPP3 & GPP4,
GAS PROCESSING KERTIH (GPK), TERENGGANU.

DOCUMENT TITLE:
INSPECTION & TEST PROCEDURE

DOCUMENT NO.:
DSE/PGB/HEX/QAQC/IP/026

Rev Date Status DIPETRO SYNERGY GPK


Prepared by: Checked by: Endorsed by: Checked by: Approved by:

SRA AY AFM
0 14/03/16 FOR
APPROVAL

DIPETRO SYNERGY ENG. SDN. BHD.


PT 12510 (A-13), Kawasan Perusahaan Chacar, Mukim Kuala Paka, 23100 Dungun, Terengganu
Doc No DSE/PGB/HEX/QAQC/IP/026
QA/QC PROCEDURE Rev 0
Date 14 Mar 2016
PGB/HO/19/2015/0094
Page 2 of 2

1.0 INTRODUCTION

This procedure applicable for project, especially for erected and fabricated by DiPETRO Synergy
Sdn Bhd for Engineering Procurement Construction and Commissioning (EPCC) of Water Cooled
Heat Exchangers Installation at GPP2, GPP3 & GPP4, at Gas Processing Kerteh (GPK).

2.0 SCOPE

This procedure shall be applied to inspect the butterfly valves at Valmatic Engineering Sdn. Bhd.
in accordance with project specification.

3.0 DEFINITION

3.1 Client : Petronas Gas Berhad


3.2 Contractor : DiPETRO Synergy Eng Sdn Bhd
3.3 Valve Supplier : Valmatic Engineering Sdn. Bhd.
3.4 Valve Manufacturing : CEPHAS PIPELINES CORP., LTD

4.0 ATTACHMENT

4.1 Attachment 1 : Inspection & Test Procedure rev.A

DIPETRO SYNERGY ENG. SDN. BHD.


PT 12510 (A-13), Kawasan Perusahaan Chacar, Mukim Kuala Paka, 23100 Dungun, Terengganu