You are on page 1of 15

43 Nakpil v CA, L-47851, October 3, 1986 from liability by showing that the immediate cause of the damage

PARAS, J. was the act of God.


TOPIC: Fortuitous event • The negligence of the defendant and the third-party defendants
petitioners was established beyond dispute both in the lower court
DOCTRINE: To exempt the obligor from liability under Article 1174 of the Civil and in the Intermediate Appellate Court. Defendant United
Code, for a breach of an obligation due to an "act of God," the following must Construction Co., Inc. was found to have made substantial
concur: (a) the cause of the breach of the obligation must be independent of deviations from the plans and specifications. and to have failed to
the will of the debtor; (b) the event must be either unforseeable or observe the requisite workmanship in the construction as well as to
unavoidable; (c) the event must be such as to render it impossible for the exercise the requisite degree of supervision; while the third-party
debtor to fulfill his obligation in a normal manner; and (d) the debtor must be defendants were found to have inadequacies or defects in the plans
free from any participation in, or aggravation of the injury to the creditor. and specifications prepared by them. As correctly assessed by both
courts, the defects in the construction and in the plans and
specifications were the proximate causes that rendered the PBA
FACTS: building unable to withstand the earthquake of August 2, 1968. For
• The plaintiff, Philippine Bar Association, a civic-non-profit this reason the defendant and third-party defendants cannot claim
association, incorporated under the Corporation Law, decided to exemption from liability.
construct an office building on its 840 square meters lot located at • The records show that the lower court spared no effort in arriving at
the comer of Aduana and Arzobispo Streets, Intramuros, Manila. the correct appreciation of facts by the referral of technical issues to
The construction was undertaken by the United Construction, Inc. a Commissioner chosen by the parties whose findings and
on an "administration" basis, on the suggestion of Juan J. Carlos, the conclusions remained convincingly unrebutted by the
president and general manager of said corporation. The proposal intervenors/amicus curiae who were allowed to intervene in the
was approved by plaintiff's board of directors and signed by its Supreme Court.
president Roman Ozaeta, a third-party defendant in this case. The • In any event, the relevant and logical observations of the trial court
plans and specifications for the building were prepared by the other as affirmed by the Court of Appeals that "while it is not possible to
third-party defendants Juan F. Nakpil & Sons. The building was state with certainty that the building would not have collapsed were
completed in June, 1966. those defects not present, the fact remains that several buildings in
• In the early morning of August 2, 1968 an unusually strong the same area withstood the earthquake to which the building of
earthquake hit Manila and its environs and the building in question the plaintiff was similarly subjected," cannot be ignored.
sustained major damage. The front columns of the building buckled,
causing the building to tilt forward dangerously. The tenants 44 FIL ESTATE PROPERTIES INC V SPS RONQUILLO
vacated the building in view of its precarious condition. As a GR No. 185798 | January 13, 2014 | PEREZ
temporary remedial measure, the building was shored up by United
Construction, Inc. at the cost of P13,661.28. TOPIC: FORTUITOUS EVENT; NCC 1174
• On November 29, 1968, the plaintiff commenced this action for the
recovery of damages arising from the partial collapse of the building
against United Construction, Inc. and its President and General DOCTRINE:
Manager Juan J. Carlos as defendants. Plaintiff alleges that the
collapse of the building was accused by defects in the construction, Requisites of Fortuitous Event:
the failure of the contractors to follow plans and specifications and
violations by the defendants of the terms of the contract. (a) the cause of the breach of the obligation must be independent of
• Defendants in turn filed a third-party complaint against the the will of the debtor;
architects who prepared the plans and specifications, alleging in (b) the event must be either unforeseeable or unavoidable;
essence that the collapse of the building was due to the defects in (c) the event must be such as to render it impossible for the debtor to
the said plans and specifications. fulfill his obligation in a normal manner; and,
• The Commissioner eventually submitted his report on September (d) the debtor must be free from any participation in or aggravation of
25, 1970 with the findings that while the damage sustained by the the injury to the creditor.
PBA building was caused directly by the August 2, 1968 earthquake
whose magnitude was estimated at 7.3 they were also caused by
the defects in the plans and specifications prepared by the third- EMERGENCY RECIT: (short case)
party defendants' architects, deviations from said plans and
specifications by the defendant contractors and failure of the latter FACTS:
to observe the requisite workmanship in the construction of the
building and of the contractors, architects and even the owners to 1. Petitioner Fil Estate Properties Inc is the owner and developer of Central
exercise the requisite degree of supervision in the construction of Park Place Tower, its co petitioner Fil Estate Network is its authorized
subject building. marketing agent. Sps Ronquillo and Maria Ronquillo bought a
• Because of another earthquake on April 7, 1970, the trial court after condominium from them for P5.1M.
the needed consultations, authorized the total demolition of the
building 2. The Ronquillos executed a Reservation application agreement, agreeing
to deposit P200K as reservation fee. They paid the down payment and
ISSUE: W/N the defendants are liable for the damage monthly amortizations.
HELD: Yes
3. Upon learning that the construction has topped, the also stopped paying
RULING: the monthly amortization and demanded full refund of the amount they
• There is no dispute that the earthquake of August 2, 1968 is a already paid. Fil Estate refused so they filed a complaint for refund and
fortuitous event or an act of God. damages before HLURB.
• if upon the happening of a fortuitous event or an act of God, there
concurs a corresponding fraud, negligence, delay or violation or 4. The HLURB ordered Fil Estate Properties and Fil Estate Network solidary
contravention in any manner of the tenor of the obligation as jointly and severally liable. The Arbiter considered petitioners’ failure to
provided for in Article 1170 of the Civil Code, which results in loss or develop the condominium project as a substantial breach of their
damage, the obligor cannot escape liability. obligation which entitles respondent to seek for rescission with payment
• Thus it has been held that when the negligence of a person concurs of damages and that economic hardship is not an excuse for contractual
with an act of God in producing a loss, such person is not exempt and legal delay.
5. Petitioners appealed with OP and CA which were both denied. They claim rescission of the subject deeds of donation commence to run? From the
that the 1997 Asian financial crisis that caused the delay befalling the real moment the cause of action accrues. Petition DENIED.
estate industry constitutes as a fortuitous event.
Ratio:
ISSUE/S: • Article 1389 of the Civil Code simply provides that, "The action to claim
rescission must be commenced within four years." Since this provision of
WON Asian financial crisis constitute a fortuitous event which would justify law is silent as to when the prescriptive period would commence, the
delay by petitioners in the performance of their contractual obligation? - NO general rule, i.e., from the moment the cause of action accrues,
therefore, applies (Art. 1150).
HELD: • Article 1383 of the Civil Code provides as follows:

• The Court in the ase of Fil Estate v Spouses Go stated that the Asian
Art. 1383. An action for rescission is subsidiary; it cannot be
financial crisis is not an instance of caso fortuito. This case has the same
instituted except when the party suffering damage has no other
factual milieu as the instant case, which involves the same company but a
legal means to obtain reparation for the same.
different condominium project.

• The company’s failure to develop the condominium project despite • It is thus apparent that an action to rescind or an accion pauliana must be
substantial payment of the contract price amounts to breach of their of last resort, availed of only after all other legal remedies have been
obligation. exhausted and have been proven futile. For an accion pauliana to accrue,
the following requisites must concur: (SEE DOCTRINE)
• A real estate enterprise engaged in the pre-selling of condominium units • To count the 4 year prescriptive period to rescind an allegedly fraudulent
is concededly a master in projections on commodities and currency contract from the date of registration of the conveyance with the Register
movements and business risks. The fluctuating movement of the of Deeds, as alleged by the Cheng, would run counter to Article 1383 as
Philippine peso in the foreign exchange market and currency exchange well as settled jurisprudence. It would likewise violate the third requisite.
rate is an everyday occurrence. Thus the 1997 Asian financial crisis cannot • An accion pauliana thus presupposes the following: 1) A judgment; 2) the
be held as unforeseen and beyond the control of a business corporation issuance by the trial court of a writ of execution for the satisfaction of the
that will amount to a fortuitous event justifying the delay of the judgment, and 3) the failure of the sheriff to enforce and satisfy the
construction project. judgment of the court. It requires that the creditor has exhausted the
property of the debtor: The date of the decision of the trial court is
45 Cheng et.al. v CA and Philam Insurance immaterial. What is important is that the credit of the plaintiff antedates
G.R. No. 144169; 28 March 2001 that of the fraudulent alienation by the debtor of his property. After all,
Topic: Remedies of Creditors, Accion Pauliana | Ponente: J. Kapunan | Author: the decision of the trial court against the debtor will retroact to the time
Enriquez when the debtor became indebted to the creditor.
• Even if respondent Philam was aware, as of December 27, 1989, that
Doctrine: 1) That the plaintiff asking for rescission has a credit prior to, the petitioner Khe Hong Cheng had executed the deeds of donation in favor
alienation, although demandable later; 2) That the debtor has made a of his children, the complaint against Butuan Shipping Lines and/or
subsequent contract conveying a patrimonial benefit to a third person; 3) That petitioner Khe Hong Cheng was still pending before the trial court.
the creditor has no other legal remedy to satisfy his claim, but would benefit by • Had respondent Philam filed his complaint on December 27, 1989, such
rescission of the conveyance to the third person; 4) That the act being complaint would have been dismissed for being premature. Not only
impugned is fraudulent; 5) That the third person who received the property were all other legal remedies for the enforcement of respondent Philam's
conveyed, if by onerous title, has been an accomplice in the fraud. claims not yet exhausted at the time the needs of donation were
executed and registered. Respondent Philam would also not have been
able to prove then that petitioner Khe Hong Cheng had no more property.
Facts:
1. Petitioner Cheng is the owner of Butuan Shipping Lines. PH Agri Trading 46 SIGUAN v. LIM
Corp. shipped on board the vessel of Cheng 3,400 bags of copra. The said G.R. No. 134685 | November 19, 1999
shipment is covered by a marine insurance policy issued by American
Home Insurance Company (respondent Philam's assured).
2. However, it sank. Because of the loss, the insurer, American Home, paid Doctrine:
the amount of P354,000.00 (the value of the copra) to the consignee. The general rule is that rescission requires the existence of creditors at the time
3. Having been subrogated into the rights of the consignee, American Home of the alleged fraudulent alienation, and this must be proved as one of the
instituted a Civil Case to recover the money paid to the consignee, based bases of the judicial pronouncement setting aside the contract.
on breach of contract of carriage. While the case was still pending or on
1989, Cheng executed deeds of donations of parcels of land in favor of his
children, herein co-petitioners. Facts:
4. On Dec. 1993, the RTC ruled against Cheng and a writ of execution was ▪ August 1990 – Lim issued two Metrobank checks in the sums of
granted. When the sheriff, accompanied by counsel of respondent P300,000 and P241,668, respectively, payable to “cash.” Upon
Philam, went to Butuan City on Jan. 1997, to enforce the alias writ of presentment by Siguan with the drawee bank, the checks were
execution, they discovered that petitioner Khe Hong Cheng no longer had dishonored for the reason “account closed.” Demands to make good
any property and that he had conveyed the subject properties to his the checks proved futile.
children. ▪ A criminal case for violation of Batas Pambansa Blg. 22 was filed
5. Thus, Philam filed a complaint for the rescission of the deeds of donation. against Lim. RTC Cebu convicted him as charged. The case is pending
It alleged that Cheng executed the aforesaid deeds in fraud of his for review before the SC.
creditors, including respondent Philam. ▪ * It also appears that on July 1990, Lim was convicted of estafa but
6. Cheng filed a MTD on the ground that the action had already prescribed. eventually acquitted by SC but maintained the civil liability.
They posited that the registration of the deeds of donation on December ▪ July 2, 1991 – a Deed of Donation4conveying the following parcels of
27, 1989 constituted constructive notice and since the complaint a land and purportedly executed by LIM on August 10, 1989 in favor
quo was filed only on February 25, 1997, or more than four (4) years after of her children, Linde, Ingrid and Neil, was registered with the Office
said registration, the action was already barred by prescription. of the Register of Deeds of Cebu City.
7. RTC and CA ruled against Cheng. Hence, this petition. ▪ Siguan filed an accion pauliana against Lim and her children to
rescind the questioned Deed of Donation and to declare as null and
Issue/Held: When did the four (4) year prescriptive period as provided for in void the new transfer certificates of title issued for the lots covered
Article 1389 of the Civil Code for respondent Philam to file its action for by the questioned Deed.
▪ RTC ordered the recision but it was reversed by the CA 1. The fact that the consideration of the conveyance is fictitious or is
inadequate;
Issue/s: Whether the questioned Deed of Donation was made in fraud of 2. A transfer made by a debtor after suit has begun and while it is
petitioner and, therefore, rescissible. pending against him;
3. A sale upon credit by an insolvent debtor;
Held: No. Claim against LIM was constituted only in August 1990, or a year 4. Evidence of large indebtedness or complete insolvency;
after the questioned alienation. Thus, the first two requisites for the rescission 5. The transfer of all or nearly all of his property by a debtor, especially
of contracts are absent. when he is insolvent or greatly embarrassed financially;
6. The fact that the transfer is made between father and son, when
Ruling: there are present other of the above circumstances; and
The general rule is that rescission requires the existence of creditors at the time The failure of the vendee to take exclusive possession of all the property
of the alleged fraudulent alienation, and this must be proved as one of the
bases of the judicial pronouncement setting aside the contract. Without any 47 Gaite v. Fonacier
prior existing debt, there can neither be injury nor fraud. While it is necessary G.R. No. 123456 | 25 DECEMBER 2018 |J.B.L. Reyes| Mendoza
that the credit of the plaintiff in the accion pauliana must exist prior to the
fraudulent alienation, the date of the judgment enforcing it is immaterial. Even
if the judgment be subsequent to the alienation, it is merely declaratory, with Doctrine:
retroactive effect to the date when the credit was constituted. What characterizes a conditional obligation is the fact that its efficacy or
obligatory force is subordinated to the happening of a future and uncertain
The Court was not convinced with the allegation of Siguan that the questioned event; so that if the suspensive condition does not take place, the parties
deed was antedated to make it appear that it was made prior to Siguan’s would stand as if the conditional obligation had never existed.
credit. Notably, that deed is a public document, it having been acknowledged
before a notary public. As such, it is evidence of the fact which gave rise to its Facts:
execution and of its date. ▪ Fonacier owned 11 lode iron mineral claims, known as Dawahan Group, in
The fact that the questioned Deed was registered only on 2 July 1991 is not Jose Panganiban, Camarines Norte. He appointed Gaite as his attorney-
enough to overcome the presumption as to the truthfulness of the statement in-fact in the exploration and development of said mineral claims on a
of the date in the questioned deed, which is 10 August 1989. royalty basis of P0.50/ton of ore extracted therein.
Accion Pauliana ▪ Gaite assigned conveyance of the same to his solely-owned company
Requisites In this case Larap Iron Mines, subject to the same royalty basis required by Fonacier.
the plaintiff asking for rescission has Claim against Lim – August 1990 With the said venture, plaintiff caused development of the mining claims
a credit prior to the alienation, Alienation – August 1989 (e.g. construction of roads, mining facilities), and extracted ore.
although demandable later ▪ Fonacier then decided to rescind the power of attorney given to Gaite,
the debtor has made a subsequent Claim against Lim – August 1990 which the latter agreed to subject to P20,000 plus 10% royalties that
contract conveying a patrimonial Alienation – August 1989 Fonacier would receive for the mining claims.
benefit to a third person ▪ Gaite then transferred all his interests and rights over Larap Iron Mines,
Even assuming arguendo that petitioner became a creditor of LIM prior to the including all records and documents. In addition, plaintiff transferred to
celebration of the contract of donation defendant all his rights and interests over the “24,000 tons of iron ore,
the creditor has no other legal The term “subsidiary remedy” has more or less” in exchange for P75,000, P10,000 of which was paid upon
remedy to satisfy his claim been defined as “the exhaustion of all signing of the Revocation of Power of Attorney, with the balance of
remedies by the prejudiced creditor P65,000 to be paid from the first letter of credit covering the first
to collect claims due him before shipment of iron ores and from the first amount derived from the local
rescission is resorted to.” sale or iron ore made by Larap Mines.
Petitioner neither alleged nor proved ▪ For the remaining P65,000, defendant presented plaintiff a surety bond
that she did so with the former (Fonacier) as principal and Larap Mines and its
the act being impugned is fraudulent For presumption of fraud to apply, it stockholders as sureties. But plaintiff sought an additional bond
must be established that the donor underwritten by a bonding company. Thus defendant put up another
did not leave adequate properties bond with Far Eastern Surety and Insurance Co., but it provided that the
which creditors might have recourse liability
for the collection of their credits ▪ of the surety company would only have effect if there had been actual
existing before the execution of the sale of iron ore for an amount not less than P65,000, and that this liability
donation. would expire after one year, that is on December 8, 1955.
▪ On December 8, 1955, bond with Far Eastern had expired and was not
It was not sufficiently established that renewed, none of the 24,000 tons of iron ore had been sold and Fonacier
the properties left behind by LIM and the other sureties were unable to pay Gaite P65,000 upon his
were not sufficient to cover her debts demand. Gaite then brought action for the payment of P65,000.
existing before the donation was ▪ Defendants countered that payment of the P65,000 was conditioned on
made sale of iron ore by the company, which had not happened, rendering their
the third person who received the obligation to pay not yet demandable and that only 7,573 tons of the
property conveyed, if it is by onerous estimated 24,000 was actually delivered to them. Lower court ruled in
title, has been an accomplice in the favor of plaintiff.
fraud ▪

*Just in case: Issue/s:


With regard to estafa case: Whether the lower court erred in holding that the obligation of Fonacier to pay
Only the creditor who brought the action for rescission can benefit from the Gaite the P65K is one with a period or term and not one with a suspensive
rescission; those who are strangers to the action cannot benefit from its condition, and that the term expired on December 8, 1955.
effects. And the revocation is only to the extent of the plaintiff creditor’s Held: NO
unsatisfied credit; as to the excess, the alienation is maintained. Thus,
petitioner cannot invoke the credit of Suarez to justify rescission of the subject Ruling:
deed of donation
1. The SC affirmed the lower court’s decision that the shipment or local sale of
Badges of Fraud (Not Exclusive)
the iron ore is not a condition precedent (or suspensive) to the payment of the
balance of P65,000.00, but was only a suspensive period or term. respects with this Contract of Lease/Purchase insofar as the terms
What characterizes a conditional obligation is the fact that its efficacy or and conditions are concerned.”
obligatory force (as distinguished from its demandability) is subordinated to
the happening of a future and uncertain event; so that if the suspensive • Gonzales did not exercise his option to purchase the property
condition does not take place, the parties would stand as if the conditional immediately after the expiration of the 1-year lease. He remained in
obligation had never existed. possession of the property without paying the purchase price
provided for in the Contract and without paying any further rentals.
2. The words of the contract express no contingency in the buyers obligation to • The heirs sent a letter to Gonzales informing him of their decision to
pay: “The balance of P65K will be paid out of the first letter of credit covering rescind the Contract due to a breach committed by the latter.
the first shipment of iron ores x x x” etc. o Letter served as a demand to vacate the premises. But
Gonzales refused to vacate.
There is no uncertainty that the payment will have to be made sooner or later;
• Property subject of the Contract is currently the subject of an extra-
what is undetermined is merely the exact date at which it will be made. By the
judicial partition. Title to the property remains in the name of the
very terms of the contract, therefore, the existence of the obligation to pay is
plaintiffs’ predecessor-in-interest, Bernardino Calixto and Severo
recognized; only its maturity or demandability is deferred. 
 Cruz
3. To subordinate the obligation to pay the remaining P65,000.00 to the sale or • The heirs filed a complaint for recovery of possession of the
shipment of the ore as a condition precedent, would be tantamount to leaving property alleging that Gonzales has not purchased the property
the payment at the discretion of the debtor, for the sale or shipment could not after the lapse of 1 year, thus they seek to rescind the Contract and
be made unless the appellants took steps to sell the ore. recover the property. While Gonzales alleged breach of paragraph
nine.
4. The sale of the ore to Fonacier was a sale on credit, and not an aleatory
contract where the transferor, Gaite, would assume the risk of not being paid Issue/s: WON paragraph nine of the Contract is a condition precedent before
at all; and that the previous sale or shipment of the ore was not a suspensive Gonzales could exercise his option to buy the property.
condition for the payment of the balance of the agreed price, but was intended
merely to fix the future date of the payment. Held: Yes.

48 GONZALES v. HEIRS OF THOMAS AND PAULA CRUZ Ruling:


G.R. No. 131784; 16 September 1999 • The ninth provision was intended to ensure that respondents would
Topic: Conditional Obligations | Ponente: Panganiban, J. | Author: have a valid title over the specific portion they were selling to
Pagcaliwagan petitioner. Only after the title is assured, may the obligation to buy
the land and to pay the sums stated in the Contract be enforced
within the period stipulated. Verily, the petitioner’s obligation to
purchase has not yet ripened and cannot be enforced until and
Doctrine: When the obligation assumed by a party to a contract is expressly unless respondents can prove their title to the property subject of
subjected to a condition, the obligation cannot be enforced against him unless the Contract.
the condition is complied with. Furthermore, [t]he obligatory force of a • Because the ninth clause required respondents to obtain a separate
conditional obligation is subordinated to the happening of a future and and distinct TCT in their names and not in the name of petitioner, it
uncertain event, so that if that event does not take place, the parties would logically follows that such undertaking was a condition precedent to
stand as if the conditional obligation had never existed. the latter’s obligation to purchase and pay for the land. Put
differently, petitioner’s obligation to purchase the land is a
conditional one and is governed by Article 1181 of the Civil Code.
• Condition has been defined as every future and uncertain event
Emergency Recit: The heirs (LESSOR) and Gonzales (LESSEE) entered into a
upon which an obligation or provision is made to depend. It is a
Contract of Lease/Purchase. Gonzales did not exercise his option to purchase future and uncertain event upon which the acquisition or resolution
the property after the expiration of the 1-year lease and remained in of rights is made to depend by those who execute the juridical act.
possession of the land without paying. Paragraph 9 of the contract states that: Without it, the sale of the property under the Contract cannot be
“The LESSORS hereby commit themselves and shall undertake to obtain a perfected, and petitioner cannot be obliged to purchase the
separate and distinct T.C.T. over the herein leased portion to the LESSEE.” The property. When the consent of a party to a contract is given subject
heirs filed a complaint for recovery of possession. Gonzales argued that the to the fulfillment of a suspensive condition, the contract is not
heirs breached paragraph 9. The issue is WON paragraph 9 is a condition perfected unless that condition is first complied with.
precedent before Gonzales could exercise his option to buy the property. • The Court has held that [w]hen the obligation assumed by a party to
a contract is expressly subjected to a condition, the obligation
Facts: cannot be enforced against him unless the condition is complied
• Cruz and the heirs of Thomas and Paula Cruz (LESSORS) entered into with. Furthermore, [t]he obligatory force of a conditional obligation
is subordinated to the happening of a future and uncertain event, so
a Contract of Lease/Purchase with Gonzales (LESSEE) of a half-
that if that event does not take place, the parties would stand as if
portion of a parcel of land. The Contract of Lease/Purchase contains
the conditional obligation had never existed.
the following provisions:
• In this case, the obligation of the petitioner to buy the land cannot
be enforced unless respondents comply with the suspensive
“1. The terms of this Contract is for a period of one year upon the
condition that they acquire first a separate and distinct TCT in their
signing thereof. After the period of this Contract, the LESSEE shall
names. The suspensive condition not having been fulfilled, then the
purchase the property on the agreeable price of One Million Pesos obligation of the petitioner to purchase the land has not arisen.
(P1,000,000.00) payable within Two (2) Years period with an interest
of 12% per annum subject to the devalued amount of the Philippine 49 GONZALES v. HEIRS OF THOMAS AND PAULA CRUZ
Peso G.R. No. 131784; 16 September 1999
Topic: suspensive condition | Ponente: Panganiban, J. | Author: Pagcaliwagan /
9. The LESSORS hereby commit themselves and shall undertake to Pineda
obtain a separate and distinct T.C.T. over the herein leased portion
to the LESSEE within a reasonable period of time which shall not in
any case exceed four (4) years, after which a new Contract shall be
executed by the herein parties which shall be the same in all
Doctrine: When the consent of a party to a contract is given subject to the logically follows that such undertaking was a condition precedent to
fulfillment of a suspensive condition, the contract is not perfected unless that the latter’s obligation to purchase and pay for the land. Put
condition is first complied with. differently, petitioner’s obligation to purchase the land is a
conditional one and is governed by Article 1181 of the Civil Code.
• Condition has been defined as every future and uncertain event
upon which an obligation or provision is made to depend. It is a
Emergency Recit: The heirs (LESSOR) and Gonzales (LESSEE) entered into a future and uncertain event upon which the acquisition or resolution
Contract of Lease/Purchase. Gonzales did not exercise his option to purchase of rights is made to depend by those who execute the juridical act.
the property after the expiration of the 1-year lease and remained in Without it, the sale of the property under the Contract cannot be
possession of the land without paying. Paragraph 9 of the contract states that: perfected, and petitioner cannot be obliged to purchase the
“The LESSORS hereby commit themselves and shall undertake to obtain a property. When the consent of a party to a contract is given subject
separate and distinct T.C.T. over the herein leased portion to the LESSEE.” The to the fulfillment of a suspensive condition, the contract is not
heirs filed a complaint for recovery of possession. Gonzales argued that the perfected unless that condition is first complied with.
heirs breached paragraph 9. The issue is WON paragraph 9 is a condition • The Court has held that [w]hen the obligation assumed by a party to
precedent before Gonzales could exercise his option to buy the property. a contract is expressly subjected to a condition, the obligation
cannot be enforced against him unless the condition is complied
Facts: with. Furthermore, [t]he obligatory force of a conditional obligation
is subordinated to the happening of a future and uncertain event, so
• Cruz and the heirs of Thomas and Paula Cruz (LESSORS) entered into
that if that event does not take place, the parties would stand as if
a Contract of Lease/Purchase with Gonzales (LESSEE) of a half-
the conditional obligation had never existed.
portion of a parcel of land. The Contract of Lease/Purchase contains
• In this case, the obligation of the petitioner to buy the land cannot
the following provisions:
be enforced unless respondents comply with the suspensive
condition that they acquire first a separate and distinct TCT in their
“1. The terms of this Contract is for a period of one year upon the
names. The suspensive condition not having been fulfilled, then the
signing thereof. After the period of this Contract, the LESSEE shall
obligation of the petitioner to purchase the land has not arisen.
purchase the property on the agreeable price of One Million Pesos #50 Coronel v. CA
(P1,000,000.00) payable within Two (2) Years period with an interest G.R. No. 103577; October 7, 1996
of 12% per annum subject to the devalued amount of the Philippine Topic: Suspensive Condition | Ponente: J. MELO | Author: S A Y O.. Sorry
Peso complicated case

9. The LESSORS hereby commit themselves and shall undertake to


Doctrine:
obtain a separate and distinct T.C.T. over the herein leased portion
Art. 1181. In conditional obligations, the acquisition of rights, as well as the
to the LESSEE within a reasonable period of time which shall not in
extinguishment or loss of those already acquired, shall depend upon the
any case exceed four (4) years, after which a new Contract shall be
happening of the event which constitutes the condition.
executed by the herein parties which shall be the same in all
Art. 1186. The condition shall be deemed fulfilled when the obligor voluntarily
respects with this Contract of Lease/Purchase insofar as the terms
prevents its fulfillment.
and conditions are concerned.”
Art. 1187. The effects of conditional obligation to give, once the condition has
been fulfilled, shall retroact to the day of the constitution of the obligation .
• Gonzales did not exercise his option to purchase the property
Facts:
immediately after the expiration of the 1-year lease. He remained in
possession of the property without paying the purchase price 1. Defendants-appellants Romulo Coronel, et. al. (Coronels) executed a
provided for in the Contract and without paying any further rentals. document entitled Receipt of Down Payment in favor of plaintiff Ramona
Patricia Alcaraz (Ramona) which is reproduced hereunder:
• The heirs sent a letter to Gonzales informing him of their decision to
rescind the Contract due to a breach committed by the latter.
RECEIPT OF DOWN PAYMENT (DP)
o Letter served as a demand to vacate the premises. But
P1,240,000.00 - Total amount
Gonzales refused to vacate.
50,000.00 - Down payment
• Property subject of the Contract is currently the subject of an extra-
judicial partition. Title to the property remains in the name of the ------------------------------------------
plaintiffs’ predecessor-in-interest, Bernardino Calixto and Severo P1,190,000.00 - Balance
Cruz Received from Miss Ramona Patricia Alcaraz of 146
• The heirs filed a complaint for recovery of possession of the Timog, Quezon City, the sum of Fifty Thousand Pesos
property alleging that Gonzales has not purchased the property purchase price of our inherited house and lot, covered by
after the lapse of 1 year, thus they seek to rescind the Contract and TCT No. 119627 of the Registry of Deeds of Quezon City,
recover the property. While Gonzales alleged breach of paragraph in the total amount of P1,240,000.00.
nine. We bind ourselves to effect the transfer in our names
from our deceased father, Constancio P. Coronel, the
Issue/s: WON paragraph nine of the Contract is a condition precedent before transfer certificate of title immediately upon receipt of
Gonzales could exercise his option to buy the property. the down payment above-stated.
On our presentation of the TCT already in or name, We
Held: Yes. will immediately execute the deed of absolute sale of said
property and Miss Ramona Patricia Alcaraz shall
Ruling: immediately pay the balance of the P1,190,000.00.
• The ninth provision was intended to ensure that respondents would Clearly, the conditions appurtenant to the sale are the
have a valid title over the specific portion they were selling to following:
petitioner. Only after the title is assured, may the obligation to buy
the land and to pay the sums stated in the Contract be enforced a. Ramona will make a down payment of 50k pesos upon
within the period stipulated. Verily, the petitioner’s obligation to
execution of the document aforestated;
purchase has not yet ripened and cannot be enforced until and
b. The Coronels will cause the transfer in their names of
unless respondents can prove their title to the property subject of
the Contract. the title of the property registered in the name of their
• Because the ninth clause required respondents to obtain a separate deceased father upon receipt of the 50k DP
and distinct TCT in their names and not in the name of petitioner, it
c. Upon the transfer in their names of the subject certificate of title was still in the name of petitioners father, they
property, the Coronels will execute the deed of absolute could not fully effect such transfer although the buyer was then
sale in favor of Ramona and the latter will pay the former willing and able to immediately pay the purchase price.
the whole balance of 1.190M.
▪ Therefore, petitioners-sellers undertook upon receipt of the down
2. On the same date plaintiff-appellee Concepcion D. Alcaraz (Concepcion), payment from private respondent Ramona P. Alcaraz, to cause the
mother of Ramona, paid the DP of 50k issuance of a new certificate of title in their names from that of their
father, after which, they promised to present said title, now in their
3. On February 6, 1985, the property originally registered in the name of the names, to the latter and to execute the deed of absolute sale
Coronels father was transferred in their names. whereupon, the latter shall, in turn, pay the entire balance of the
purchase price.
4. On February 18, 1985, the Coronels sold the disputed property to
intervenor-appellant Catalina B. Mabanag (Catalina) ▪ The agreement could not have been a contract to sell because the
sellers herein made no express reservation of ownership or title to
5. For this reason, Coronels canceled and rescinded the contract with the subject parcel of land. Furthermore, the circumstance which
Ramona by depositing the down payment paid by Concepcion in the prevented the
bank in trust for Ramona Patricia Alcaraz.
parties from entering into an absolute contract of sale pertained to the sellers
6. On February 22, 1985, Concepcion, et. al., filed a complaint for a specific themselves (the certificate of title was not in their names) and not the full
performance against the Coronels. payment of the purchase price.

▪ Under the established facts and circumstances of the case, the Court may
Issue/s: safely presume that, had the certificate of title been in the names of
Was the contract a Conditional Contract of Sale or Contract to Sell?- petitioners-sellers at that time, there would have been no reason why an
Conditional Contract of Sale. absolute contract of sale could not have been executed and
WON the obligation became demandable due to the fulfillment of the consummated right there and then.
suspensive condition- YES
▪ Moreover, unlike in a contract to sell, petitioners in the case at bar did
Ruling: not merely promise to sell the property to private respondent upon the
fulfillment of the suspensive condition. On the contrary, having already
agreed to sell the subject property, they undertook to have the certificate
Contract To Sell
of title change to their names and immediately thereafter, to execute the
written deed of absolute sale.
A contract to sell as defined hereinabove, may not even be considered as a
conditional contract of sale where the seller may likewise reserve title to the ▪ Thus, the parties did not merely enter into a contract to sell where the
property subject of the sale until the fulfillment of a suspensive condition, sellers, after compliance by the buyer with certain terms and conditions,
because in a conditional contract of sale, the first element of consent is promised to sell the property to the latter. What may be perceived from
present, although it is conditioned upon the happening of a contingent event the respective undertakings of the parties to the contract is that
which may or may not occur. If the suspensive condition is not fulfilled, the petitioners had already agreed to sell the house and lot they inherited
perfection of the contract of sale is completely abated. from their father, completely willing to transfer ownership of the
subject house and lot to the buyer if the documents were then in order.
In a contract to sell, upon the fulfillment of the suspensive condition which is
the full payment of the purchase price, ownership will not automatically ▪ There is no doubt that unlike in a contract to sell which is most commonly
transfer to the buyer although the property may have been previously entered into so as to protect the seller against a buyer who intends to buy
delivered to him. The prospective seller still has to convey title to the the property in installment by withholding ownership over the property
until the buyer effects full payment therefor, in the contract entered into
prospective buyer by entering into a contract of absolute sale.
in the case at bar, the sellers were the ones who were unable to enter
into a contract of absolute sale by reason of the fact that the certificate
Conditional Contract of Sale
of title to the property was still in the name of their father.

In a conditional contract of sale, however, upon the fulfillment of the ▪ It was the sellers in this case who, as it were, had the impediment which
suspensive condition, the sale becomes absolute and this will definitely affect prevented, so to speak, the execution of a contract of absolute sale.
the seller’s title thereto. In fact, if there had been previous delivery of the
subject property, the seller’s ownership or title to the property is automatically ▪ What is clearly established by the plain language of the subject document
transferred to the buyer such that, the seller will no longer have any title to is that when the said Receipt of Down Payment was prepared and signed
transfer to any third person. Applying Article 1544 of the Civil Code, such by petitioners Romulo A. Coronel, et. al., the parties had agreed to a
second buyer of the property who may have had actual or constructive conditional contract of sale, consummation of which is subject only to
knowledge of such defect in the seller’s title, or at least was charged with the the successful transfer of the certificate of title from the name of
obligation to discover such defect, cannot be a registrant in good faith. Such petitioners father, Constancio P. Coronel, to their names.
second buyer cannot defeat the first buyer’s title. In case a title is issued to the
second buyer, the first buyer may seek reconveyance of the property subject of ▪ The Court significantly notes that this suspensive condition was, in fact,
the sale. fulfilled on February 6, 1985 (Exh. D; Exh. 4). Thus, on said date, the
conditional contract of sale between petitioners and private respondent
Ramona P. Alcaraz became obligatory, the only act required for the
So…
consummation thereof being the delivery of the property by means of the
execution of the deed of absolute sale in a public instrument, which
▪ With the above postulates as guidelines, we now proceed to the petitioners unequivocally committed themselves to do as evidenced by
task of deciphering the real nature of the contract entered into by the Receipt of Down Payment.
petitioners and private respondents.
▪ Since the condition contemplated by the parties which is the issuance of
▪ When the Receipt of Down payment is considered in its entirety, it a certificate of title in petitioners names was fulfilled on February 6,
becomes more manifest that there was a clear intent on the part of 1985, the respective obligations of the parties under the contract of sale
petitioners to transfer title to the buyer, but since the transfer
became mutually demandable, that is, petitioners, as sellers, were FACTS:
obliged to present the transfer certificate of title already in their names to 1. Cirer and Hill donated parcels of land to the Municipality of Tarlac
private respondent Ramona P. Alcaraz, the buyer, and to immediately on the condition that it be used absolutely and exclusively for the
execute the deed of absolute sale, while the buyer on her part, was erection of a school and public parks, which should commence
obliged to forthwith pay the balance of the purchase price amounting within six (6) months from the donation.
to P1,190,000.00. 2. The municipal president accepted and registered the donation.
3. Cirer and Hill later sold the same property to Parks.
▪ It is also significant to note that in the first paragraph in page 9 of their 4. Parks filed a complaint seeking the annulment of the earlier
petition, petitioners conclusively admitted that: donation to Tarlac. He further seeks that he be declared the
absolute owner of the property. Parks allege that the conditions of
3. The petitioners-sellers Coronel bound themselves to the donation were not complied with.
effect the transfer in our names from our deceased
father Constancio P. Coronel, the transfer certificate of ISSUE/S:
title immediately upon receipt of the downpayment W/N the conditions are conditions subsequent – YES
above-stated". The sale was still subject to this W/N the donation is effective – YES; furthermore, it can no longer be revoked
suspensive condition. (Emphasis supplied.) because it is barred by prescription.
(Rollo, p. 16)
HELD/RULING:
Petitioners themselves recognized that they entered
into a contract of sale subject to a suspensive It is true that the conditions have not been complied with, but these conditions
condition. Only, they contend, continuing in the same are not conditions precedent.
paragraph, that:
. . . Had petitioners-sellers not complied with this The characteristic of a condition precedent is that the acquisition of a right is
condition of first transferring the title to the property not effected while said condition is not complied with. Nothing is acquired,
under their names, there could be no perfected contract there is only an expectancy of a right.
of sale. (Emphasis supplied.)
(Ibid.) When a condition is imposed and the compliance of which cannot be effected
except when the right is deemed acquired, such condition cannot be a
▪ Besides, it should be stressed and emphasized that what is more condition precedent. Therefore, it is a condition subsequent.
controlling than these mere hypothetical arguments is the fact that
the condition herein referred to was actually and indisputably fulfilled In this case, the conditions that a public school and a park be made of the
on February 6, 1985, when a new title was issued in the names of donated land could not be complied with except after giving effect to the
petitioners as evidenced by TCT No. 327403. donation. The done could not do any work on the donated land if the donation
had not really been effected because it would be an invasion of another’s title.
▪ The inevitable conclusion is that on January 19, 1985, as evidenced by the These conditions are conditions subsequent.
document denominated as Receipt of Down Payment the parties entered
into a contract of sale subject to the suspensive condition that the sellers
Even in a condition subsequent, non-compliance with the condition is sufficient
shall effect
cause for the revocation of the donation. However, the period for bringing an
action for revocation has prescribed.
the issuance of new certificate title from that of their father’s name to their
names and that, on February 6, 1985, this condition was fulfilled.
The period of prescription of this class of action is ten (10) years. The action for
revocation arose on April 1911. The complaint in this action was presented only
▪ In obligations to do or not to do, the courts shall determine, in each case,
in July 1924, more than 10 years after the cause has accrued. Clearly, it has
the retroactive effect of the condition that has been complied with. The
rights and obligations of the parties with respect to the perfected prescribed.
contract of sale became mutually due and demandable as of the time of
fulfillment or occurrence of the suspensive condition on February 6, 52. Central Philippine University v CA
1985. As of that point in time, reciprocal obligations of both seller and
buyer arose. G.R. No. 112127 July 17, 1995
Topic: Resolutory (condition subsequent) | Ponente: J. Bellosillo| Author:
51 PARKS v PROVINCE OF TARLAC Valera
G.R. No. L-24190 | 13 July 1926| J. Avanceña| TIGLAO
TOPIC: Resolutory (Condition Subsequent)
Doctrine: Under Art. 1181, on conditional obligations, the acquisition of rights
DOCTRINE: When a condition is imposed and the compliance of which cannot as well the extinguishment or loss of those already acquired shall depend upon
be effected except when the right is deemed acquired, such condition cannot the happening of the event which constitutes the condition. Thus, when a
be a condition precedent. Therefore, it is a condition subsequent. person donates land to another on the condition that the latter would build
upon the land a school is such a resolutory one. The donation had to be valid
ER: Cirer and Hill donated a parcel of land with a condition that Tarlac should before the fulfillment of the condition. If there was no fulfillment with the
construct a school and a park on it within six months from the time of condition such as what obtains in the instant case, the donation may be
donation. After six months, it was not constructed. The prescriptive period to revoked & all rights which the donee may have acquired shall be deemed lost &
revoke the donation started from this moment. Since the complaint was only extinguished
filed more than 10 years from this time, the action is said to have prescribed.
Nonetheless, the donation was perfected at that time and was subject to a
condition subsequent because the property had to be donated to them before
Facts:
they can even possibly construct anything, subject only to the condition
▪ In 1939, Don Ramon Lopez Sr. executed a deed of donation in favor of
provided in this case.
the Central Philippine College(Central Philippine university) of parcel of
land. For which a new TCT was issued in the name of the done CPU with
the following annotations:
1. The land described shall be utilized by the CPU exclusively for
the establishment and use of a medical college with all its
buildings as part of the curriculum;
Doctrine: It has been ruled that when a person donates land to another on the
2. The said college shall not sell, transfer or convey to any third
condition that the latter would build upon the land a school, the condition
party nor in any way encumber said land;
imposed is not a condition precedent or a suspensive condition but a resolutory
3. The said land shall be called "RAMON LOPEZ CAMPUS", and
the said college shall be under obligation to erect a one.
cornerstone bearing that name. Any net income from the land
or any of its parks shall be put in a fund to be known as the
"RAMON LOPEZ CAMPUS FUND" to be used for improvements Facts:
of said campus and erection of a building thereon 1. Petitioners are the children of the late Trinidad Corvera Vda. de
• In 1989, private respondents(Heirs of Don Ramon Lopez Sr.) filed an Quijada. Trinidad was one of the heirs of the late Pedro Corvera and
annulmaent of donation, reconveyance and damges against CPU inherited from the latter the two-hectare parcel of land subject of
alleging that since 1939,up to the time of action was filed. CPU had the case, situated in the barrio of San Agustin, Talacogon, Agusan
not complied with the conditions of the donation. del Sur.
• On its answer CPU alleged that the right of private respondents to 2. On April 5, 1956, Trinidad Quijada together with her siblings
file the action had prescribed. that it did not violate any of the executed a conditional deed of donation of the parcel of land
conditions in the deed of donation because it never used the subject of the case in favor of the Municipality of Talacogon, the
donated property for any other purpose than that for which it was condition being that the parcel of land shall be used solely and
intended; and, that it did not sell, transfer or convey it to any third exclusively as part of the campus of the proposed provincial high
party. school in Talacogon. Apparently, Trinidad remained in possession of
• The Trial court ruled that CPU failed to comply with the conditions the parcel of land despite the donation.
of the donation and declared it null and void. 3. On July 29, 1962, Trinidad sold 1 hectare of the subject parcel of
• On appeal to the CA, the CA held that the annotations at the back of land to private respondent Regalado Mondejar. Eventually, the
petitioner's certificate of title were resolutory conditions breach of remaining 1 hectare was sold to Mondejar as well, verbally, without
which should terminate the rights of the donee thus making the the benefit of a written deed of sale and evidenced solely by
donation revocable receipts of payment.
➢ The CA also found that while the first condition mandated 4. In 1987, the proposed provincial high school having failed to
petitioner to utilize the donated property for the materialize, the Sangguniang Bayan of the municipality of Talacogon
establishment of a medical school, the donor did not fix a enacted a resolution reverting the 2 hectares of land donated back
period within which the condition must be fulfilled, hence, to the donors. In the meantime, Mondejar sold portions of the land
until a period was fixed for the fulfillment of the condition, to the other private respondents.
petitioner could not be considered as having failed to comply 5. On July 5, 1988, petitioners filed a complaint against private
with its part of the bargain thus it remanded the case to the respondents for quieting of title, recovery of possession, and
RTC to determine the period in which CPU should comply. ownership of parcels of land with claim for attorney's fees and
damages, claiming that at the time of the alleged sale to Regalado
Issue/s: WON petitioner failed to comply the resolutely conditions annotated Mondejar by Trinidad Quijada, the land still belonged to the
at the back of petitioner’s certificate of title without a fixed period when to Municipality of Talacogon, hence, the supposed sale was null and
comply with such conditions? void.
Held: Yes. Lorem ipsum dolor sit amet. 6. Trial court favored petitioners, but this was reversed by the CA,
ruling that the sale made by Trinidad Quijada to respondent
Ruling: Mondejar was valid as the former retained an inchoate interest on
the lots by virtue of the automatic reversion clause in the deed of
Under Art. 1181, on conditional obligations, the acquisition of rights as well the
donation.
extinguishment or loss of those already acquired shall depend upon the
happening of the event which constitutes the condition. Thus, when a person
Issue: Whether the sale of the subject property made by Trinidad Quijada to
donates land to another on the condition that the latter would build upon the
respondent Mondejar is void, considering that at that time, ownership was
land a school is such a resolutory one. The donation had to be valid before the
already transferred to the Municipality of Talacogon.
fulfillment of the condition. If there was no fulfillment with the condition such
as what obtains in the instant case, the donation may be revoked & all rights
Held: No, the sale is valid. CA decision affirmed.
which the donee may have acquired shall be deemed lost & extinguished.
Ruling:
More than a reasonable period of fifty (50) years has already been allowed 1. The donation made on April 5, 1956 by Trinidad Quijada and her
petitioner to avail of the opportunity to comply with the condition even if it be siblings was subject to the condition that the donated property shall
burdensome, to make the donation in its favor forever valid. But, be "used solely and exclusively as a part of the campus of the
unfortunately, it failed to do so. Hence, there is no more need to fix the proposed Provincial High School in Talacogon." The donation further
duration of a term of the obligation when such procedure would be a mere provides that should "the proposed Provincial High School be
technicality and formality and would serve no purpose than to delay or lead to discontinued or if the same shall be opened but for some reason or
an unnecessary and expensive multiplication of suits. another, the same may in the future be closed" the donated
property shall automatically revert to the donor. Such condition, not
Records are clear and facts are undisputed that since the execution of the deed being contrary to law, morals, good customs, public order or public
of donation up to the time of filing of the instant action, petitioner has failed to policy was validly imposed in the donation.
comply with its obligation as donee. Petitioner has slept on its obligation for an 2. When the Municipality's acceptance of the donation was made
known to the donor, the former became the new owner of the
unreasonable length of time. Hence, it is only just and equitable now to declare
donated property -- donation being a mode of acquiring and
the subject donation already ineffective and, for all purposes, revoked so that
transmitting ownership - notwithstanding the condition imposed by
petitioner as donee should now return the donated property to the heirs of the the donee. The donation is perfected once the acceptance by the
donor, private respondents herein, by means of reconveyance donee is made known to the donor. Accordingly, ownership is
53. ALFONSO QUIJADA, et al v. CA and REGALADO MONTEJAR, et al immediately transferred to the latter and that ownership will only
G.R. No. 126444. December 4, 1998 revert to the donor if the resolutory condition is not fulfilled.
Topic: Resolutory (Condition subsequent) | Ponente: Martinez, J. | Author: 3. In this case, that resolutory condition is the construction of the
Acido school. It has been ruled that when a person donates land to
another on the condition that the latter would build upon the land a 3. Lim advised Dy that he would no longer renew the contract
school, the condition imposed is not a condition precedent or a effecting October 1985. However, Dy wanted to renew the contract.
suspensive condition but a resolutory one. Thus, at the time of the
sales made in 1962 towards 1968, Trinidad could not have sold the 4. Lim did not agree to the renewal, hence, he filed another ejectment
lots since she had earlier transferred ownership thereof by virtue of suit against Dy. The MTC, RTC, and the CA all ruled that the
the deed of donation. So long as the resolutory condition subsists stipulation which allows the lessee to stay on the premises as long
and is capable of fulfillment, the donation remains effective and the as he needs it and can pay rents is valid.
donee continues to be the owner subject only to the rights of the
donor or his successors-in-interest under the deed of Issue: Whether the stipulation in the compromise agreement is valid
donation. Since no period was imposed by the donor on when must Held: No
the donee comply with the condition, the latter remains the owner
so long as he has tried to comply with the condition within a
Ruling:
reasonable period.
Contrary to the ruling of respondent court, the disputed stipulation “for as
4. Such period, however, became irrelevant herein when the donee-
long as the defendant needed the premises and can meet and pay said
Municipality manifested through a resolution that it cannot comply
with the condition of building a school and the same was made increases” is a purely potestative condition because it leaves the effectivity
known to the donor. Only then - when the non-fulfillment of the and enjoyment of leasehold rights to the sole and exclusive will of the lessee.
resolutory condition was brought to the donor's knowledge - that
ownership of the donated property reverted to the donor as The invalidity of a condition in a lease contract similar to the one at bar has
provided in the automatic reversion clause of the deed of donation. been resolved in Encarnacion vs. Baldomar, et al., where we ruled that in an
5. The donor may have an inchoate interest in the donated property action for ejectment, the defense interposed by the lessees that the contract of
during the time that ownership of the land has not reverted to lease authorized them to continue occupying the premises as long as they paid
her. Such inchoate interest may be the subject of contracts including the rents is untenable, because it would leave to the lessees the sole power to
a contract of sale. In this case, however, what the donor sold was determine whether the lease should continue or not. As stated therein, “(i)f
the land itself which she no longer owns. It would have been this defense were to be allowed, so long as defendants elected to continue the
different if the donor-seller sold her interests over the property
lease by continuing the payment of the rentals, the owner would never be able
under the deed of donation which is subject to the possibility of
to discontinue it; conversely, although the owner should desire the lease to
reversion of ownership arising from the non-fulfillment of the
continue, the lessees could effectively thwart his purpose if they should prefer
resolutory condition.
6. A perfected contract of sale cannot be challenged on the ground of to terminate the contract by the simple expedient of stopping payment of the
non-ownership on the part of the seller at the time of its perfection; rentals. This, of course, is prohibited by the aforesaid article of the Civil Code.
hence, the sale is still valid. The consummation, however, of the
perfected contract is another matter. It occurs upon the The continuance, effectivity and fulfillment of a contract of lease cannot be
constructive or actual delivery of the subject matter to the buyer made to depend exclusively upon the free and uncontrolled choice of the
when the seller or her successors-in-interest subsequently acquires lessee between continuing the payment of the rentals or not, completely
ownership thereof. Such circumstance happened in this case when depriving the owner of any say in the matter. Mutuality does not obtain in
petitioners -- who are Trinidad Quijada's heirs and successors-in- such a contract of lease and no equality exists between the lessor and the
interest -- became the owners of the subject property upon the lessee since the life of the contract is dictated solely by the lessee.
reversion of the ownership of the land to them. Consequently,
ownership is transferred to respondent Mondejar and those who
Resultantly, the contract of lease should be and is hereby construed as
claim their right from him. Article 1434 of the New Civil Code
providing for a definite period of three (3) years and that the automatic
supports the ruling that the seller's "title passes by operation of law
to the buyer." increase of the rentals by twenty percent (20%) will take effect only if the
parties decide to renew the lease. A contrary interpretation will result in a
54. LIM V. COURT OF APPEALS situation where the continuation and effectivity of the contract will depend
G.R. No. 87047 | 31 OCTOBER 1990 only upon the will of the lessee, in violation of Article 1308 of the Civil Code
Topic: Potestative| Ponente: Regalado, J. | Author: Castro and the aforesaid doctrine in Encarnacion.

It is likewise a suspensive condition because the renewal of the lease, which


gives rise to a new lease, depends upon said condition. It should be noted that
Doctrine: The disputed stipulation “for as long as the defendant needed the
a renewal constitutes a new contract of lease although with the same terms
premises and can meet and pay said increases” is a purely potestative
and conditions as those in the expired lease. It should also not be overlooked
condition because it leaves the effectivity and enjoyment of leasehold rights to
that said condition is not resolutory in nature because it is not a condition that
the sole and exclusive will of the lessee.
terminates the lease contract. The lease contract is for a definite period of
three (3) years upon the expiration of which the lease automatically
terminates.
Facts:
55 Silos v PNB, G.R. No. 181045, July 2, 2014
1. Benito Dy entered into a contract of lease with Francisco Lao Lim for DEL CASTILLO, J.
a period of 3 years (1976-1979). After the stipulated term expired,
TOPIC: Potestative
Dy refused to vacate the premises, so Lim filed an ejectment suit.
DOCTRINE: In loan agreements, it cannot be denied that the rate of interest is a
The suit was then terminated after the court approved their
principal condition, if not the most important component. Thus, any
compromise agreement.
modification thereof must be mutually agreed upon; otherwise, it has no
2. They stipulated “That the term of the lease shall be renewed every binding effect. Moreover, the Court cannot consider a stipulation granting a
three years retroacting from October 1979 to October 1982; after party the option to prepay the loan if said party is not agreeable to the
which the abovenamed rental shall be raised automatically by 20% arbitrary interest rates imposed. Premium may not be placed upon a
every three years for as long as defendant needed the premises and stipulation in a contract which grants one party the right to choose whether to
can meet and pay the said increases, the defendant to give notice of continue with or withdraw from the agreement if it discovers that what the
his intent to renew sixty (60) days before the expiration of the other party has been doing all along is improper or illegal.
term;”. The lease continued from 1979 to 1985.
FACTS: The unilateral action of the PNB in increasing the interest rate on the private
Spouses Eduardo and Lydia Silos (petitioners) have been in business for about respondent’s loan violated the mutuality of contracts ordained in Article 1308
two decades of operating a department store and buying and selling of ready- of the Civil Code:
to-wear apparel. Respondent Philippine National Bank (PNB) is a banking Art. 1308. The contract must bind both contracting parties; its
corporation organized and existing under Philippine laws. validity or compliance cannot be left to the will of one of them.
To secure a one-year revolving credit line of ₱150,000.00 obtained from PNB, Petitioners never agreed in writing to pay the increased interest rates
petitioners constituted in August 1987 a Real Estate Mortgage over a 370- demanded by respondent bank in contravention to the tenor of their credit
square meter lot in Kalibo, Aklan. In July 1988,the credit line was increased to agreement. Escalation clauses are not basically wrong or legally objectionable
₱1.8 million and the mortgage was correspondingly increased to ₱1.8 million. so long as they are not solely potestative but based on reasonable and valid
And in July 1989, a Supplement to the Existing Real Estate Mortgage was grounds. petitioners are correct in arguing that estoppel should not apply to
executed to cover the same credit line, which was increased to ₱2.5 million, them, for "estoppel cannot be predicated on an illegal act. As between the
and additional security was given in the form of a 134-square meter lot. In parties to a contract, validity cannot be given to it by estoppel if it is prohibited
addition, petitioners issued eight Promissory Notes and signed a Credit by law or is against public policy. PNB also violated Truth in lending Act.
Agreement.
The Credit Agreement contained stipulations including: 56 NAGA V CA
“The Borrower agrees that the Bank may modify the interest rate in GR No. 107112 | FEB 24, 1994| NOCON | DELFIN
the Loan depending on whatever policy the Bank may adopt in the TOPIC: CASUAL
future, including without limitation, the shifting from the floating
interest rate system to the fixed interest rate system, or vice versa.
Where the Bank has imposed on the Loan interest at a rate per DOCTRINE:
annum, which is equal to the Bank’s spread over the current floating A contract subject to mixed conditions, that is, they depend partly on the will of
interest rate, the Borrower hereby agrees that the Bank may, the debtor and partly on chance, hazard or the will of a third person, is valid.
without need of notice to the Borrower, increase or decrease its
spread over the floating interest rate at any time depending on
whatever policy it may adopt in the future.” EMERGENCY RECIT: (short case)
Respondent regularly renewed the line from 1990 up to 1997, and petitioners
made good on the promissory notes, religiously paying the interests without FACTS:
objection or fail. But in 1997, petitioners faltered when the interest rates
soared due to the Asian financial crisis. Petitioners’ sole outstanding 6. Petitioner Naga Telephone Co (NATELCO) renders local and long distance
promissory note for ₱2.5 million became past due, and despite repeated telephone service while Camarines Sur II Electric Cooperative (CASURECO
demands, petitioners failed to make good on the note. Thus, PNB foreclosed on II) is a private corporation operating electric service in Naga City.
the mortgage.
More than a year later, petitioners filed Civil Case, seeking annulment of the 7. They entered into a contract for the use by NATELCO in the operation of
foreclosure sale and an accounting of the PNB credit. Petitioners theorized that it’s telephone service the electric light posts CASURECO in Naga City. In
after the first promissory note where they agreed to pay 19.5% interest, the exchange, NATELCO agreed to install, free of charge, ten (10) telephone
succeeding stipulations for the payment of interest in their loan agreements connections for the use by CASURECO.
with PNB – which allegedly left to the latter the sole will to determine the
interest rate – became null and void. Petitioners added that because the 8. The contract provided:
interest rates were fixed by respondent without their prior consent or “the term or period of this contract shall be as long as the party of
the first part has need for the electric light posts of the party of the
agreement, these rates are void, and as a result, petitioners should only be
second part it being understood that this contract shall terminate
made liable for interest at the legal rate of 12%.
when for any reason whatsoever, the party of the second part is
forced to stop, abandoned [sic] its operation as a public service and
ISSUE: W/N the petitioners are correct it becomes necessary to remove the electric light post”
HELD: Yes
9. After being in effect for 10 yrs, CASURECO filed a reformation of contract
RULING: In a number of decided cases, the Court struck down provisions in with RTC Naga alleging the contract was one sided and in violation of
credit documents issued by PNB to, or required of, its borrowers which allow NEA guidelines for reasonable compensation for the use of posts.
the bank to increase or decrease interest rates "within the limits allowed by (P10/mo.
law at any time depending on whatever policy it may adopt in the future."
P.D. No. 1684 and C.B. Circular No. 905 no more than allow contracting parties 10. NATELCO files for MTD stating that:
to stipulate freely regarding any subsequent adjustment in the interest rate a. No COA for reformation of contract
that shall accrue on a loan or forbearance of money, goods or credits. In fine, b. Barred by prescription (filed more than 10yrs)
c. Estoppel
they can agree to adjust, upward or downward, the interest previously
stipulated. However, contrary to the stubborn insistence of petitioner bank, the
11. RTC ruled that the contract be reformed. It held that while the contract
said law and circular did not authorize either party to unilaterally raise the appeared to be fair to both parties when it was entered into, it had
interest rate without the other’s consent. become disadvantageous and unfair to CASURECO because of subsequent
There can be no contract in the true sense in the absence of the element of events and conditions (particularly the increase in the volume of the
agreement, or of mutual assent of the parties. If this assent is wanting on the subscribers of petitioners for more than ten (10) years without the
part of the one who contracts, his act has no more efficacy than if it had been corresponding increase in the number of telephone connections to
done under duress or by a person of unsound mind. private respondent free of charge.
Contract changes must be made with the consent of the contracting parties.
The minds of all the parties must meet as to the proposed modification, 12. It further held that the contract was subject to a potestative condition in
especially when it affects an important aspect of the agreement. In the case of favor if NATELCO.
loan contracts, it cannot be gainsaid that the rate of interest is always a vital
component, for it can make or break a capital venture. Thus, any change must ISSUE/S:
be mutually agreed upon, otherwise, it is bereft of any binding effect.
WON the court the contract was subject to a postestative condition making the
contract void? - NO
58 Smith, Bell & Co. v. Sotelo Matti
HELD: G.R. No. 16570 | October 14, 2015

• A potestative condition is a condition, the fulfillment of which depends


upon the sole will of the debtor, in which case, the conditional obligation Doctrine:
is void. Based on this definition, the finding that the provision in the Where the fulfillment of the condition does not depend on the will of the
contract, to wit:
obligor, but on that of a third person who can in no way be compelled to carry
That the term or period of this contract shall be as long as the party
it out, the obligor's part of the contract is complied with, if he does all that is in
of the first part (petitioner) has need for the electric light posts of
the party of the second part (private respondent) . . .. his power, and it then becomes incumbent upon the other contracting party to
comply with the terms of the contract.
is a potestative condition, is correct. However, it must have overlooked
the other conditions in the same provision, towit: ER: The Smith, Bell & Co. and Sotelo entered into contracts whereby Sotelo will
. . . it being understood that this contract shall terminate when for buy tanks, expellers, and motors from the company. The company allegedly
any reason whatsoever, the party of the second part (private failed to deliver the items on time (please see the table below for quick
respondent) is forced to stop, abandoned (sic) its operation as a reference). However, the SC said that there is no period that was actually
public servicevand it becomes necessary to remove the electric light agreed upon and the condition involved in this case is mixed because the
post (sic); fulfillment of such, is dependent on the will of the obligor and a third party (US
Government). Thus, (please see doctrine)
which are casual conditions since they depend on chance, hazard, or the
Facts:
will of a third person.
▪ August 1918 – Smith, Bell & Co. and Vicente Sotelo entered into contracts
whereby the company obligated itself to sell, and Sotelo to purchase from
• In sum, the contract is subject to mixed conditions, that is, they depend it, two steel tanks, for the total price P21,000, the same to be shipped
partly on the will of the debtor and partly on chance, hazard or the will of from New York and delivered at Manila "within three or four months;"
a third person, which do not invalidate the aforementioned provision. two expellers at the price of P25,000 each, which were to be shipped
from San Francisco in the month of September 1918 or as soon as
57 TOMAS OSMENA v CENORA RAMA possible; and two electric motors at the price of P2,000 each, as to the
G.R. No. 4437; 9 September 2018 delivery of which stipulation was made, couched in these words:
Topic: Conditional Obligations, Types of conditions, As to cause or origin, "Approximate delivery within ninety days.—This is not guaranteed."
Mixed| Ponente: J. Johnson | Author: Enriquez ▪ The tanks arrived at Manila on the 27th of April, 1919; the expellers on
the 26th of October, 1918; and the motors on the 27th of February, 1919
▪ The corporation notified the defendant, Mr. Sotelo, of the arrival of these
goods, but Mr. Sotelo refused to receive them and to pay the prices
Doctrine: A condition which depended upon her (debtor’s) exclusive will, and is
stipulated. The company brought suit against Sotelo.
void. Art. 1115 of the Civil Code.
Contract Arrival
Tanks Within 3 or 4 months (December April 1919
1918)
Facts: Expellers September 1918 or as soon as October 1918
▪ On Nov. 15, 1890, Rama entered into a contract (loan agreement) in the possible
amount of 200 pesos with Victoriano Osmena (Victoriano) wherein Rama Motors Approximate delivery within 90 Februray,
will pay in sugar in the following months. days (not guaranteed) 1919
▪ Rama then entered into another loan agreement with Victoriano.
▪ Victoriano then died. The said contracts become the property of his heir Issue/s: Whether or not the company is guilty of delay
Rafols. Rafols then ceded to Tomas Osmena (Tomas) all her right and
interest in the said contract. Held: No.
▪ Tomas then presented the contracts to Rama for payment and she
acknowledged her responsibility upon said contracts by an indorsement
Ruling:
upon them in the following language:
*just in case:
On this date I hereby promise, in the presence of two witness, that if
the house of strong materials in which I live in Pagina is sold, I will Stipulation in the Contract
pay my indebtedness to Don Tomas Osmeña as set forth in this Tanks To be delivered within 3 or 4 months—The promise or indication
document. (Signed Rama) of shipment carries with it absolutely no obligation on our part—
▪ Rama not having paid, Tomas commenced an action in the CFI of Cebu. Government regulations, railroad embargoes, lack of vessel
▪ Rama answered by filing a general denial and special defense of space, the exigencies of the requirements of the United States
prescription. Government, or a number of causes may act to entirely vitiate
▪ CFI ruled in favor of Tomas. the indication of shipment as stated. In other words, the order is
▪ Rama argued before the Court that in the acknowledgment above quoted accepted on the basis of shipment at Mill's convenience, time of
of the indebtedness made by Rama, she imposed the condition that she shipment being merely an indication of what we hope to
would pay the obligation if she sold her house. accomplish
Expellers The following articles, hereinbelow more particularly described,
Issue/Held: Whether the condition is valid? No, it is VOID. to be shipped at San Francisco within the month of September
/18, or as soon as possible.—Two Anderson oil expellers…
Ratio: Motors Approximate delivery within ninety days.—This is not
guaranteed.—This sale is subject to our being able to obtain
• The SC said that “If that statement found in her acknowledgment of the
Priority Certificate, subject to the United States Government
indebtedness should be regarded as a condition, it was a condition which
requirements and also subject to confirmation of
depended upon her exclusive will, and is therefore, void. (Art. 1115, Civil
manufacturers."
Code.)”
• The acknowledgment, therefore, was an absolute acknowledgment of the
obligation and was sufficient to prevent the statute of limitation from In all these contracts, there is a final clause as follows:
barring the action upon the original contract. "The sellers are not responsible for delays caused by fires, riots on
• CFI decision is affirmed. land or on the sea, strikes or other causes known as 'Force Majeure' entirely
beyond the control of the sellers or their representatives." Under these
stipulations, it cannot be said that any definite date was fixed for the delivery determined that its supply is sufficient, and will have the prerogative to
of the goods. have deliveries continue when raw materials become necessary, provided
The oral evidence falls short of fixing such period. that the seller is given sufficient notice.
These contracts were executed at the time of the world war when On Sept. 30, 1968, Vergara, Rustan’s Manager, sent a letter to Lluch informing
there existed rigid restrictions on the export from the United States of articles him that their supply had become sufficient and that they will not be needing
like the machinery in question, and maritime, as well as railroad, transportation further delivery.
was difficult, which fact was known to the parties. Lluch sought to clarify the contents of said letter, inquiring as to whether the
At the time of the execution of the contracts, the parties were not said requested stoppage was temporary or permanent, an inquiry which
unmindful of the contingency of the United States Government not allowing remained unanswered by Rustan.
the export of the goods, nor of the fact that the other foreseen circumstances Thus, Lluch resumed deliveries, which continued to be accepted by Rustan until
therein stated might prevent it. December 23, 1968. The petitioners also continued to accept deliveries of
Considering these contracts in the light of the civil law, we cannot supplies from other sellers.
but conclude that the term which the parties attempted to fix is so uncertain Because of those events, however, Lluch filed a complaint for contractual
that one cannot tell just whether, as a matter of fact, those articles could be breach against Rustan, which was dismissed. On appeal, however, they have
brought to Manila or not. If that is the case, as we think it is, the obligation raised the issues to the SC, hence, this case.
must be regarded as conditional. Issue/s:
Obligations for the performance of which a day certain has been Whether the contractual stipulations as to Rustan’s right to stop delivery of raw
fixed shall be demandable only when the day arrives. materials are valid. 

- "A day certain is understood to be one which must necessarily Held: NO
arrive, even though its date be unknown.
And as the export of the machinery in question was, as stated in Ruling:
the contract, contingent upon the sellers obtaining certificate of priority and Lluch is correctly apprehensive as to the conditions for delivery, considering
permission of the United States Government, subject to the rules and that the stipulated prerogative suggests a condition solely dependent upon the
regulations, as well as to railroad embargoes, then the delivery was subject to will of Rustan. Rustan can stop delivery of raw materials from Lluch if the
a condition the fulfillment of which depended not only upon the effort of the supply at the plant is sufficent, a fact which only petitioners can ascertain. The
herein plaintiff, but upon the will of third persons who could in no way be resumption of delivery is dependent as well on the will of Rustan, given that it
compelled to fulfill the condition. In cases like this, which are not expressly will happen only if according to the petitioners, supply is once more necessary.
provided for, but impliedly covered, by the Civil Code, The obligor will be Furthermore, given that the company still continued to accept supplies from
deemed to have sufficiently performed his part of the obligation, if he has Lluch and other sellers, it is doubtful that Rustan truly had sufficient supplies.
done all that was in his power, even if the condition has not been fulfilled in Rustan’s contentions that such actions were just an ‘act of generous
reality. accomodation’ are almost unbelievable; aside from being contrary to normal
business practices. So, why would any business continue to accept raw
The law implies, however, that if no time is fixed, delivery shall be materials which they do not need and which would result in losses just to be
made within a reasonable time, in the absence of anything to show that an accomodating?
immediate delivery is intended When the contract provides for delivery 'as Therefore, because of the purely potestative imposition, the stipulation must
soon as possible' the seller is entitled to a reasonable time, in view of all the be taken out without affecting the rest of the stipulations considering that the
circumstances, such as the necessities of manufacture, or of putting the goods condition relates to the fulfillment of an already existing obligation and not to
in condition for delivery. Delivery 'Shortly.'—In a contract for the sale of its inception. Of course, it is true that a condition which is both potestative and
personal property to be delivered 'shortly,' it is the duty of the seller to tender resolutory may be valid; however, that applies only at the birth, not the
delivery within a reasonable time and if he tenders delivery after such time the fulfillment, of an existing obligation.
buyer may reject. With regard to the claim of damages and attorney’s fees against Tantoco and
Vergara, the Court said that the Petitioner and Manager of a corporation who
The record shows, as we have stated, that the plaintiff did all within entered into and signed a contract in his official capacity cannot be made libale
its power to have the machinery arrive at Manila as soon as possible, and under his individual capacity in the absence of stipulations to that effect,
immediately upon its arrival it notified the purchaser of the fact and offered to because the personality of the corporation is separate and distinct from that of
deliver it to him. Taking these circumstances into account, we hold that the theirs.
said machinery was brought to Manila by the plaintiff within a reasonable time.
60 ROMERO v. COURT OF APPEALS
59. Rustan Pulp and Paper Mills v. IAC, Iligan Diversified Products, and Lluch G.R. No. 107207; 23 November 1995
G.R. No. 70789| 19 OCTOBER 1992| J. MELO Topic: Kinds of obligation; as to cause or origin; potestative; mixed | Ponente:
Vitug, J. | Author: Pagcaliwagan

Doctrine:
A condition which is both potestative (or facultative) and resolutory may be Doctrine: The undertaking required of private respondent is "mixed" condition
valid, even though the saving clause is left to the will of the obligor. "dependent not on the will of the vendor alone but also of third persons like
the squatters and government agencies and personnel concerned."

Facts:
Petitioner-Rustan Pulp had established a pulp and paper mill, and Respondent-
Lluch, a holder of a forest products license, sent a letter to negotiate with Emergency Recit:
Petitioner wherein in essence, the latter would supply raw materials to the Facts:
former. Such negotiations concluded in a contract of sale, subject to the ff. • Romero and his foreign partners decided to put up a central
Stipulations: warehouse in Metro Manila. After the announcement, Spouses
Flores, accompanied by a broker, offered a parcel of land.
▪ That Rustan has the option to buy from other sllers wo are equally qualified
• Romero visited the property and, except for the presence of
and holders of appropriate licenses; 

squatters in the area, he found the place suitable for a central
▪ That Rustan will not buy from sellers whose goods emanated from Lluch’s
warehouse.
concession; 

• Spouses Flores called on Romero with a proposal that he should
▪ That Lluch has priority in supplying materials to Rustan; and 

advance P50K which could be used in taking up an ejectment case
▪ That Rustan has the right to stop delivery of raw materials when it has
against the squatters, Spouses Flores would agree to sell the void the Deed of Donation. This would result in
property for only P800 per square meter. Thus, a Deed of automatic reversion of the property.
Conditional Sale was executed between the parties. • In 1980, within the prohibitive period, RCA executed a deed of sale
• Pursuant to agreement Spouses Flores filed a complaint against the in favor of Sps. Ignao. RCA sold the property to Sps. Ignao.
squatter families. A judgment was rendered ordering the • The Estate of Sps. De Castro filed a complaint for nullification of
defendants to vacate the premises. deed of donation, rescission of contract, and reconveyance of
• Spouses Flores sought to return the P50K since they could not get property with damages against RCA and Sps. Ignao.
rid of the squatters on the lot. But Romero refused the tender and o RCA and Sps. Ignao argue that the action has prescribed.
proposed that he shall take it upon himself to eject the squatters They invoke NCC 764: revocation prescribes four years
(expenses chargeable to purchase price of land). from non-compliance with the condition
• Romero was advised by Spouses’ counsel that the Deed of
Conditional Sale had been rendered null and void by virtue of his Issue/s:
client’s failure to evict the squatters from the premises within the
agreed period.
1. W/N the cause of action of Sps. De Castro has prescribed
• Spouses Flores prompted by Romero’s continued refusal to accept
2. W/N the revocation of donation could be granted
the return of P50K advance payment filed with the RTC for the
Held:
rescission of the deed of conditional sale.

Issue/s: WON Spouses Flores can demand the rescission of the contract. 1. NO.
2. NO.
Ruling: NO.
• From the moment the contract is perfected, the parties are bound Ruling:
not only to the fulfillment of what has been expressly stipulated but
also to all the consequences which, according to their nature, may 1. NO. NCC 764 not applicable as the Deed of Donation provides for automatic
be in keeping with good faith, usage and law. Under the agreement,
reversion in case of violation of the condition therein. The provision is valid, as
private respondent is obligated to evict the squatters on the
parties have the autonomy to agree on the terms of a contract. Hence, judicial
property. The ejectment of the squatters is a condition the
declaration not necessary.
operative act of which sets into motion the period of compliance by
petitioner of his own obligation, i.e., to pay the balance of the
purchase price. Private respondent's failure "to remove the • A judicial action for rescission of a contract is not necessary where
squatters from the property" within the stipulated period gives the contract provides that it may be revoked and cancelled for
petitioner the right to either refuse to proceed with the agreement violation of any of its terms and conditions. A judicial action is
or waive that condition in consonance with Article 1545 of the Civil proper only when there is absence of a special provision granting
Code. This option clearly belongs to petitioner and not to private the power of cancellation.
respondent. • The validity of such a stipulation in the deed of donation providing
• We share the opinion of the appellate court that the undertaking for the automatic reversion of the donated property to the donor
required of private respondent does not constitute a "potestative upon non-compliance of the condition was upheld in the recent case
condition dependent solely on his will" that might, otherwise, be of De Luna, et al. vs. Abrigo, et al. It was held therein that said
void in accordance with Article 1182 of the Civil Code but a "mixed" stipulation is in the nature of an agreement granting a party the
condition "dependent not on the will of the vendor alone but also of right to rescind a contract unilaterally in case of breach, without
third persons like the squatters and government agencies and need of going to court, and that, upon the happening of the
personnel concerned." We must hasten to add, however, that resolutory condition or non-compliance with the conditions of the
where the so-called "potestative condition" is imposed not on the contract, the donation is automatically revoked without need of a
birth of the obligation but on its fulfillment, only the obligation is judicial declaration to that effect.
avoided, leaving unaffected the obligation itself. • In contracts providing for automatic revocation, judicial intervention
• In contracts of sale particularly, Article 1545 of the Civil Code, is necessary not for purposes of obtaining a judicial declaration
aforementioned, allows the obligee to choose between proceeding rescinding a contract already deemed rescinded by virtue of an
with the agreement or waiving the performance of the condition. It agreement providing for rescission even without judicial
is this provision which is the pertinent rule in the case at bench. intervention, but in order to determine whether or not the
Here, evidently, petitioner has waived the performance of the rescission was proper.
condition imposed on private respondent to free the property from
squatters.
2. NO. Revocation relies on the condition against alienation for a 100-year
period. This condition, being unreasonable, it is considered impossible. As it is
61 ROMAN CATHOLIC ARCHBISHOP OF MANILA, SPS. IGNAO v. CA, ESTATE OF
impossible, pursuant to NCC 727, it is not considered imposed. Thus, RCA was
SPS. DE CASTRO
at liberty to sell the property to Sps. Ignao.
G.R. No. 77425; 19 June 1991
Topic: possible/impossible obligations | Ponente: J. Regalado | Author: Pineda
• The condition of the 100-year prohibitive period is an undue
restriction on the rights arising from ownership of RCA and Sps.
Ignao. It is, thus, contrary to public policy. Although the donor may
Doctrine:
impose certain conditions in the deed of donation, the same must
This condition, being unreasonable, it is considered impossible. As it is
not be contrary to law, morals, good customs, public order and
impossible, pursuant to NCC 727, it is not considered imposed. public policy.
• The prohibition in the deed of donation against the alienation of the
property for an entire century, being an unreasonable emasculation
Facts: and denial of an integral attribute of ownership, should be declared
• In 1930, Sps. De Castro executed a deed of donation in favor of as an illegal or impossible condition within the contemplation of
Roman Catholic Archbishop of Manila (RCA) covering a parcel of Article 727 of the Civil Code.
land in Cavite. o Consequently, as specifically stated in said statutory
o The Deed provides that the donee shall not dispose or provision, such condition shall be considered as not
sell the property within 100 years from the execution of imposed.
the Deed, otherwise a violation would render ipso facto
o The net result is that, absent said proscription, the deed was filed if it had passed, then the court should declare that
of sale supposedly constitutive of the cause of action for petitioner had breached the contract, as averred in the complaint,
the nullification of the deed of donation is not in truth and fix the resulting damages.
violative of the latter hence, for lack of cause of action, 4. On the other hand, if the reasonable time had not yet elapsed, the
the case for the Estate must fail. court perforce was bound to dismiss the action for being premature.
62. Araneta v. Phil Sugar 5. But in no case can it be logically held that under the allegations, the
G.R. No. L-22558 May 31, 1967 intervention of the court to fix the period for performance was
Topic: Source of period/term | Ponente: J. JBL Reyes | Author: Laureta warranted, for Article 1197 is precisely predicated on the absence of
any period fixed by the parties.
6. The complaint did not ask the court to set a period for the original
decision. It is clear that the complaint proceeded on the theory that
Doctrine: Article 1197 of the Civil Code involves a two-step process. the period for performance had already elapsed, that the contract
1. The Court must first determine that "the obligation does not fix a period" had been breached and defendant was already answerable in
(or that the period is made to depend upon the will of the debtor)," but from damages.
the nature and the circumstances it can be inferred that a period was 7. Article 1197 of the Civil Code involves a two-step process.
intended". 1. The Court must first determine that "the obligation does not
2. The Court must decide what period was "probably contemplated by the fix a period" (or that the period is made to depend upon the
parties". will of the debtor)," but from the nature and the
circumstances it can be inferred that a period was intended"
(Art. 1197, pars. 1 and 2).
2. Court must decide what period was "probably contemplated
Facts: by the parties".
1. JM Tuason & Co. (Tuason Co.) through Araneta Inc. sold a portion of 8. In this case, the trial Court appears to have pulled the two-year
its Sta. Mesa Heights property for sum of P430K to Philippine Sugar period set in its decision out of thin air, since no circumstances are
Estates Development Co., Ltd. (Phil Sugar) mentioned to support it. Plainly, this is not warranted by the Civil
2. The parties stipulated in the contract of purchase and sale with Code.
mortgage: 9. The contract shows that the parties were fully aware that the land
Buyer will: build the Sto. Domingo Church and Convent was occupied by squatters. Parties knew that they could not take
Seller will: construct streets on the NE and NW and SW sides of the the law into their own hand but must resort to legal processes in
land so it will be surrounded by streets on all four sides; and the evicting the squatters, the duration of which cannot be determined
street on the NE side shall be named "Sto. Domingo Avenue" in advance. In fact case against Abundo is still pending. Thus, the
3. The buyer, Phil Sugar finished the construction of Sto. Domingo parties must have intended to defer the performance of the
Church and Convent, but the seller, Araneta, Inc. is unable to finish obligations under the contract until the squatters were duly evicted.
the construction of Sto. Domingo Ave because a third-party - 35 Central Philippine University v. CA
Manuel Abundo, who has been physically occupying a middle part
thereof, refused to vacate the same. G.R. No. 112127 July 17, 1995
4. Phil Sugar filed its complaint against Tuason Co seeking to compel Topic: As to source - NCC Art. 1197 | Ponente: Bellosillo, J. | Author: Acido
the latter to comply with their obligation, as stipulated in the above-
mentioned deed of sale, and/or to pay damages in the event they
failed or refused to perform said obligation.
5. Araneta Inc & Tuazon Co. defense is that the action was premature Doctrine: When the obligation does not fix a period but from its nature and
since its obligation to construct the streets in question was without circumstances it can be inferred that a period was intended, the general rule
a definite period which needs to be fixed first by the court in a
provided in Art. 1197 of the Civil Code applies, which provides that the courts
proper suit for that purpose before a complaint for specific
may fix the duration thereof because the fulfillment of the obligation itself
performance will prosper.
6. The lower court, after finding that "the proven facts precisely cannot be demanded until after the court has fixed the period for compliance
warrants the fixing of such a period" fixed the period to 2 years from therewith and such period has arrived.
notice thereof.
7. In the CA, Araneta Inc argued that relief granted, i.e., fixing of a
period was not justified by the pleadings and not supported by the
facts submitted at the trial of the case in the court below and that Facts:
the relief granted in effect allowed a change of theory after the
submission of the case for decision. CA denied, hence this petition 1. In 1939, Don Ramon Lopez Sr. executed a deed of donation in favor
for certiorari. of the Central Philippine College (Central Philippine university) of
parcel of land. For which a new TCT was issued in the name of the
done CPU with the following annotations:
Issue/s: W/N lower court was correct in fixing the period/time for
a. The land described shall be utilized by the CPU
compliance? NO.
exclusively for the establishment and use of a medical
Held: Reversed. Obligations of petitioner Araneta, Inc. is fixed at the date that college with all its buildings as part of the curriculum;
all the squatters on affected areas are finally evicted therefrom. b. The said college shall not sell, transfer or convey to any
third party nor in any way encumber said land;
1. The fixing of a period by the courts under Article 1197 of the Civil c. The said land shall be called "RAMON LOPEZ CAMPUS",
Code is sought to be justified on the basis that Phil Sugar placed the and the said college shall be under obligation to erect a
absence of a period in issue by pleading in its answer that the cornerstone bearing that name. Any net income from the
contract with Phil Sugar gave petitioner Araneta, Inc. "reasonable land or any of its parks shall be put in a fund to be known
time within which to comply with its obligation to construct and as the "RAMON LOPEZ CAMPUS FUND" to be used for
complete the streets." improvements of said campus and erection of a building
2. The issue is not whether the court should fix the time of thereon
performance, but whether or not the parties agreed that the 2. In 1989, private respondents (Heirs of Don Ramon Lopez Sr.) filed an
petitioner should have reasonable time to perform its part of the annulmaent of donation, reconveyance, and damges against CPU
bargain. alleging that since 1939, up to the time of action was filed. CPU had
3. If the contract so provided, then there was a period fixed, a not complied with the conditions of the donation.
"reasonable time;" and all that the court should have done was to 3. In its answer CPU alleged that the right of private respondents to file
determine if that reasonable time had already elapsed when suit the action had prescribed. that it did not violate any of the
conditions in the deed of donation because it never used the Whether the defendant-appellant can rebuild the house burnt as a sufficient
donated property for any other purpose than that for which it was idemnity to the inured for the actual loss suffered by him.
intended; and, that it did not sell, transfer or convey it to any third
party.
APPLICABLE LAW:
4. The trial court ruled that CPU failed to comply with the conditions of
Article 1199:
the donation and declared it null and void.
A person alternatively bound by different prestations shall completely perform
5. On appeal, the CA found that while the first condition mandated
one of them.
petitioner to utilize the donated property for the establishment of a
The creditor cannot be compelled to receive part of one and part of the other
medical school, the donor did not fix a period within which the
undertaking. (1131)
condition must be fulfilled, hence, until a period was fixed for the
fulfillment of the condition, petitioner could not be considered as
having failed to comply with its part of the bargain thus it remanded HELD:
the case to the RTC to determine the period in which CPU should Yes. The defendant may build the house as an alternative prestation, freeing
comply. him from the payment of the sum in which the building was insured. This
conclusion is in line with The Civil Code’s Article 1131.
Issue: Whether the CA correctly remanded the case to the trial court for the Paying the sum in which the building was insured is one of the 2 prestations
fixing of the period within which petitioner would establish a medical college. provided in one of the clauses stipulating the conditions of the policies. Based
on the same Article of the Civil Code, the complete performance of one of
Held: No. RTC decision reinstated. them is sufficient to extinguish the obligation. While there are several
prestations, only one is due.
Ruling:

1. The period of time for the establishment of a medical college and


the necessary buildings and improvements on the property cannot
be quantified in a specific number of years because of the presence
of several factors and circumstances involved in the erection of an
educational institution, such as government laws and regulations
pertaining to education, building requirements and property
restrictions which are beyond the control of the donee.
2. Thus, when the obligation does not fix a period but from its nature
and circumstances it can be inferred that a period was intended, the
general rule provided in Art. 1197 of the Civil Code applies, which
provides that the courts may fix the duration thereof because the
fulfillment of the obligation itself cannot be demanded until after
the court has fixed the period for compliance therewith and such
period has arrived.
3. This general rule however cannot be applied considering the
different set of circumstances existing in the instant case. More than
a reasonable period of 50 years has already been allowed petitioner
to avail of the opportunity to comply with the condition even if it be
burdensome, to make the donation in its favor forever valid. But,
unfortunately, it failed to do so. Hence, there is no more need to fix
the duration of a term of the obligation when such procedure would
be a mere technicality and formality and would serve no purpose
than to delay or lead to an unnecessary and expensive
multiplication of suits.
Moreover, under Art. 1191 of the Civil Code, when one of the obligors
cannot comply with what is incumbent upon him, the obligee may seek
rescission and the court shall decree the same unless there is just cause
authorizing the fixing of a period. In the absence of any just cause for the
court to determine the period of the compliance, there is no more
obstacle for the court to decree the rescission claimed.

Ong Guan Can v. The Century Insurance Co. (46 PHIL. 592), December 2, 1924
FACTS:
PLAINTIFFS-APPELLEES: Ong Guan Can and the Bank of the Philippine Islands
DEFENDANT-APPELLANT: The Century Insurance Co., LTD.
PONENTE: Villamor, J.
The plaintiff owned a building that was insured against fire by the defendant in
the sum of Php 30,000, including the merchandise therein contained in the sum
of Php 15,000. Both the house and merchandise insured were burned in
February 28, 1923 while the policies issued by the defendant in favor of the
plaintiff were still in force.

The CFI of Iloilo granted the case in favor of the plaintiff that The Century
Insurance Co. should pay Ong Guan Can the sum of Php 45,000 as the total
value of the insured house and merchandise. The Insurance Company appealed
that the judgment be modified to permit it to rebuild the house and that they
be relieved from the payment of the sum in which the building was insured.

ISSUE:

You might also like