You are on page 1of 14

DISTINGUISH

[ P-I 2018 ]
1 High Level Bridge Submersible Bridge
1 A bridge, which carries the roadway 1 A bridge in which road level of the
above H.F.L. of the channel channel is over topped during floods.
(including afflex), with appropriate
vertical clearance.
2 Higher cost as compared to 2 Lower cost as compared to High level
Submersible bridge. bridge.
3 Maintenance cost is less than 3 Required seasonal maintains before and
Submersible Bridge after monsoon, hence maintenance cost
is higher than High level Bridge.
4 Provided in Higher Category roads 4 Provided in lower category roads. i.e.
and for important routes. i.e. N.E., M.D.R., O.D.R. & V.R.
N.H., S.H.
5 It carries roadway above the highest 5 Its formation level should be fixed so as
flood level of the channel, so there is not to cause interruption to traffic for more
no case for interruption to traffic. than three days at a time nor for more
than six times in a year.

[ P -I 2018 ]
2 Friction Slab Approach Slab
1 A Friction slab is normally provided 1 An Approach slab is normally provided
when Reinforced Earth Wall is when Concrete wall (i.e. PCC, RCC) is
provided behind abutment. provided behind abutment.
2 A friction slab is used to transfer the 2 The approach slab is a transition slab of
lateral loads due to impact of reinforced concrete laid on immediate
vehicles on the barriers (i.e. Crash approaches to a bridge with one end
Barrier). resting on dirt wall /abutment.
3 It is necessary to make detailed 3 Approach slabs are designed to bridge
design for the friction slab taking over material that is prone to settlement.
care of adequate factor of safety
against sliding, overturning etc. in
addition to the structural design of
crash barrier.
4 Width of friction slab depends upon 4 Width of approach slab is normally kept
the design adequacy extending only same as width of Bridge.
for the part of the embankment
width.
5 Typically a friction slab varies from 5 Typically an approach slab varies from
1500 to 2500 mm width and 250 mm 8400 to 12000 mm width and 350 mm
thick depending on the type of crash thick depending on the width of bridge.
barrier provided.
6 6

7 It extended over a part of the width 7 It extended over full width of the approach
of the approach embankment of a embankment of a highway or River
highway bridge/flyover, to which the bridge, to which the dirt wall is anchored
crash barriers are anchored (doweled).
(doweled).

[ P – I 2018 ]
3 Friction Pile End Bearing Pile
1 These piles are used to transfer to a 1 These piles are used to transfer the load
depth of a friction load carrying through water or soft soil ground to a
material by mean of a skin friction suitable hard bearing stratum.
along the length of piles.
2 Friction piles are used to transfer 2 End bearing piles are used to transfer
loads to a depth of a friction-load- load through water or soft soil to a
carrying materials by means of skin suitable bearing stratum. Such piles are
friction along the length of the pile. used to carry heavy loads safely to hard
strata.
3 Such piles are generally used in 3 Such piles are generally used when hard
granular soil where the depth of hard strata is available at reasonable depth.
stratum is very great.
4 Preferable for Bridge foundations. 4 Multi-storeyed buildings are invariably
founded on end bearing piles, so that the
settlements are minimized.
5 5

[ P-I 02, ]
4 Nahni Trap Gully Trap
1 A nahni trap is used to collect wash 1 Gully trap disconnect sullage drain from
water from floor, kitchen and Bath the main drainage system
rooms.
2 It is made of cast Iron with a gravity 2 Gully trape made of cast iron or stone
at top to exclude the entry of big size ware. Stone ware gully trap is of square
solid. The cover can be removed section at top on which C.I. grating is
cleaning of trap fitted. It can also fitted in a masonry
chamber
3 Those type traps have small water 3 A water seal of 60 to 70 mm is usually
seal provided
4 Nahni trap is provided in side at the 4 Gully trap is provided out side at the
interior face of the wall in bath and external face of the wall. Thus receive
near kitchen. It forms the starting waste water from baths, kitchen s etc and
point of waste water flow. pass it on to the house drainage system
5 A nahni trap may serve two to three 5 A well design Gully trap may serve two to
connections three connections from nahni trap

[ P- I 03, ]
5 Major Bridge Minor Bridge
1 Bridge having a total length above 1 Bridge having a total length of 6.0 m to
60.0 m between the inner face of dirt 60.0 m between the inner face of dirt wall
wall for carrying traffic or other for carrying traffic or other moving loads
moving loads is termed as a Major is termed as a Major Bridge
Bridge

[ P- I 02, ]
6 Liquid Limit Plastic Limit
1 The water content at which the soil 1 The water content at which the soil
changes from liquid state to the changes from Plastic state to the semi
plastic stage is known as liquid limit solid state is known as plastic limit
2 Up to this limit the soil is in the liquid 2 Up to this limit the soil having plastic
form and can flow nature and deform in any shape
3 The shearing strength at this stage 3 It begins to crumble when rolled in to a
is the small value that can be thread of soil of 3.0 mm dia
measured in laboratory only
4 As the water content reduce the 4 As the water content reduce the volume
volume decreases decreases

[ P – II 03, 04,05,07, ]
7 King Post Truss Queen Post Truss
1 A King post Truss Consist of the 1 A Queen post Truss Consist of the
following component following component
[ i ] Lower Tie Beam [ i ] Lower Tie Beam
[ii ] Two inclined Principal Rafters [ii ] Two inclined Principal Rafters
[iii]Two struts [iii]Two struts
[iv ] King post [iv ] Two Queen post
[ v ] Straining Beam
[vi ] Straining sill
2 The lower horizontal Tie Beam 2 Two vertical Post rather than one in king
receives the ends of the Principal post are known as queen post member.
Rafters and prevent the wall from The queen post member is tension
spreading out due to thrust member , also support to the addition
The inclined principal rafter support purlins.
purlins The top of queen posts connected by
The strut connected to the tie beam horizontal member is known as straining
and principal rafter prevents the beam. This beams receives the thrust
sagging of principal rafter from the principal rafter and keep the
The King Post Prevents the tie beam junction in stable position.
from sagging at its centre of span The Bottom of queen posts connected
The Ridge Beam is provided at the by horizontal member is known as
apex of the roof to provide end straining sill. This beams counter acts the
support to the common rafter thrust from the inclined member known
The trusses are supported on the as strut.
bed block of stone or concrete
embedded in supporting wall so that
the load distributed to a greater area

3 The spacing of King post Limited to 3 The spacing of King post Limited to 5.0
3.0 meters c / c meters
c/c
4 The truss suitable for spans from 5.0 4 The truss suitable for spans from 8.0 to
to 8.0 meters 12.0 meters

[ P – II 04,08, ]
8 Plastering Pointing
1 A thin plastic covering that is applied 1 Finishing of mortar joints of stone
on the walls, columns, ceilings and masonry or brick masonry .
other building component to form a
smooth and durable surface is
known as plaster.
2 Plaster is applied on masonry wall 2 Pointing is applied in the Masonry joints
surface
3 It is done to protect the external 3 The external masonry joins are
surfaces against penetration of rain considered weakest and most
water and other atmospheric vulneranable sport from which rain water
agencies , give smooth surface and or dampness enter, to project against
decorative effect ,to protect against pointing is done
vermit. To conseal inferior material
or defective workmen ship
4 The mortar joints are racked up to 4 The masonry joints are racked up to
depth of 20 mm and surface is depth of 20 mm and surface is cleaned
cleaned and well wetted. The plaster and well wetted .The filling the joints with
layer of suitable mortar with required better quality mortar in the desired shape
thickness is applied.

[ P – II 03,04,06,07,08, ]
9 One way slab Two way slab
1 The slabs are supported 1 The slabs are supported continuously on
continuously on two opposite sides all four sides and have such dimension
so that loads are carried along one so that loads are carried along both
direction only direction
2 Most of Loads are transmitted along 2 Loads are transmitted along the both
the shorter span direction and the span direction as per span ratio ( Ly / Lx
and the slabs act as a one way slab ) and slabs act as a two way slab
3 Tendency of slab is to bends in one 3 Tendency of slab is to bends in both
direction only direction
4 The main reinforcement are 4 The main reinforcement are provided in
provided in the shorter span the both direction
direction
5 The steel is provided in the 5 For temperature and shrinkage effect No
transverse direction for temperature extra steel is required
and shrinkage effect called
distribution steel
6 In continuous slab at support due to 6 When slab simply supported on all four
negative moment extra steel is sides are loaded corners are corn and left
required up required extra steel at corner portion
7 The long span to short span ratio 7 The long span to short span ratio Less
greater than Two Ly / Lx > 2 than Two Ly / Lx < 2

[ P – II 03,06, ]
10 Short Column Long column
1 A Column may considered as short 1 A Column may considered as Long
column when both The slenderness column when both The slenderness
ratios ratios
( Lex / D and Ly / B ) are less than ( Lex / D and Ly / B ) are more than 12
12
2 Short column fails Primarily due to 2 Long column fails due to material Failure
material Failure as well as Buckling Failure
3 The Buckling effect within Limit 3 The Buckling effect may be predominant
value
4 Secondary moment has limited 4 Secondary moment has Considerable
value value
5 Generally designs based on the 5 A long column designed to resist the
strength of materials and applied applied loads and the additional bending
Load moment due to buckling effect

[ P – II 05,06, ]
12 Pier Abutment
1 Intermediate support of deck ( 1 The end support of deck ( Superstructure) of
Superstructure) of a bridge a bridge , which also retains earth fill of
approaches behind it

[ P – II 03,05,08 ]
13 GROUTING GUNNITING
1 Grouting Consists of injecting a 1 Most effective process of repairing
more or less pervious material with a concrete work which has damaged due to
pumpable liquid suspension inferior work or other reasons.
emulsion or mortar called grout.
2 The pervious material may be 2 It is used for providing an impervious
natural or man made ( masonary or layer.
concrete ) The grout is usually
injected through holes drilled in to
the material.
3 When grouting masonary or 3 The repairs are carried out in any
concrete the grout holes are usually situation in a short time.
left open. In most cases very thin
grout is injected in stages using an
inflamable packer Epoxy resin or
micro cement is often used.

[ P – II 05, ]
14 CURB KERB
1 1
2 2
3 3
4 4

[ P – I 08, ]
15 Dedo Skirting
1 Fixed on wall upto lintel level or full 1 Fixed on wall upto 7.5cm to 15cm height.
height as per requirement.
2 It gives pleasing appearance. 2 Purpose of skirting is to prevent walls to
be spoil during cleaning.
3 Walls easily cleaned. 3 Skirting prevents insect to enter through
gap between flooring & wall.
4 Effective registance against
absorption of oil and greese.
5 Sufficient resistance against
dampness so that healthy
environment is obtained.
6 Sufficient resistance to ware,
temperature change, disintegration
with time & decay so that long life is
obtained.
7 The wall surface shall be uniformly and 7 Skirting directly fixed with out backing coat
evenly covered with 10 mm thick
backing in cm 1:4
8 Generally provided on the walls in Bath 8 Generally provided on the walls in Living
,WC , Washing Place, where the wall is room ,BR Etc water effect is very less
offenly in contact with the water

[ P – I 08, ]
16 M25 M35
1 Means Concrete Having 1 Means Concrete Having compressive
compressive strength 25KN/m2 strength 35KN/m2
2 Cement consumption is decided by 2 Cement consumption is decided by mix
mix design & nearly @ 450 kg/m3 design & nearly @ 500 kg/m3
3 Permissible Bending Stress is 85 3 Permissible Bending Stress is 150
kg/cm2 kg/cm2
4 Direct Permissible Stress is 80 4 Direct Permissible Stress is 90 kg/cm2
kg/cm2

[ P – I 12, ]
17 Pre tentioning Post tentioning
1 The high strength steel tendons are 1 The concrete is casted with a provision of
pulled between Two ends prior to duct before high strength tendons are pulled
casting of concrete
2 The tendons are cuts after the concrete 2 The tendons are placed in duct, stressed and
attains the desired strength for the pre- cuts after the Harding the concrete
stressing
3 The pre-stress is transferred to the 3 The pre-compression is transmitted by the
concrete from the tendons by Bound anchorage devices
effect between them
4 A pre-stressing bed is required for the 4 The anchorage Devices and grouting
pre-tensioning operation. equipment is required for the post-
tensioning operation.
5 Pre-tensioning is suitable for the 5 Post-tensioning is suitable for heavy cast-in-
precast member produce in bulk. place members.
6 Minimum M35 grade of concrete is 6 Minimum M30 grade of concrete is required
required

[ P – I 12, ]
18 Warm Mix Asphalt Hot Mix asphalt
1 1
2 2
3 3
4 4
5 5

[ P – I 12, ]
19 Compaction Consolidation
1 1
2 2
3 3
4 4
5 5
6 6

[ P – I 12, ]
20 Grade-I GSB Grade-III GSB
1 1
2 2
3 3
4 4
[P–I ]
21 Ordinary Concrete Controlled Concrete
1 Selection of relative proportion of 1 Economical selection of the relative
cement, fine aggregate , coarse proportions of cement,fine aggregate ,
aggregate ,sand and water are coarse aggregate ,sand and water ( and
traditional , from past based on past admixture If specified ) to achieve
experience. compressive strength with a desired
workability in fresh state and impermeability
as well as durability in harden state.
2 Traditionally mixes were specified in 2 Concrete mix design is an involved process by
terms of fixed proportions of cement some expertise from the mix designer.
sand and coarse aggregate ( such as
1:2:4 means ,1 part of cement, 2 part
of sand and 4 part of coarse aggregate )
3 Relative proportion is generally 3 Relative proportion is measure by mass
measure by volume
4 The code provides “Nominal mix” 4 The code high light that design mix concrete
proportion for M5,M7.5,M15 and M20 based on principal of mix design is definitely
grade of concrete in term of total mass preferred than nominal mix.
of aggregate, proportion of fine
aggregate to coarse aggregate and
volume of water to be used for 50 kgs
mass of cement.
5 Nominal mix concrete is permitted in 5 Controlled concrete is permitted for higher
ordinary concrete construction , which grade up to M80
does not required concrete grade
higher than M20
6 Costly in compare to Controlled 6 The design mix found yields concrete of the
concrete desired quality and more economical than
nominal mix

[P–I ]
22 Shotcrete Gunniting
1 1
2 2
3 3
4 4

[P–I ]
23 Safe Bearing Capacity Allowable Bearing Pressure
1 Safe bearing capacity means 1 Allowable bearing pressure means net
maximum pressure which the soil loading intensity at which neither soil fails
can carry safely without risk of shear in shear nor there excessive settlement of
failure. the structure
2 SBC is higher than ABP. 2 ABP is lower than SBC.
3 3
4 4

[P–I ]
24 Mild Steel HYSD Bar
1 1
2 2
3 3
4 4

[P–I ]
25 LBM DBM
1 Lean Bituminous Macadam 1 Dense Bituminous Macadam
2 The work consists of construction in 2 The work consists of construction in a
a single course of a 37.5mm or in a single course of a 40 to 75 mm thick base
double course of 75 mm thick base / / binder course on a previously prepared
binder course on a previously base.
prepared base.
3 Coarser materials used in LBM are 3 Finner materials used in DBM are Binder,
Binder, Coarse agreegate & Fine Coarse agreegate, Fine aggregates &
aggregates. Filler.
4 4 The work should not be carried out during
rainy or foggy weather or when the base
course is damp or wet or during dust
storm or when the atmospheric
temperature in shade is 15 ̊ or less.

[P–I ]
26 Slab Culvert Pipe Culvert
1 Slab Culvert consist of RCC slab 1 Pipe Culverts are provided when
with or without beams or a stone discharge of stream is small or when
slab with or without girders to cover sufficient headway is not available.
the span across abutments & piers usually one or more pipes of diameter not
less than 60cm are placed side by side
2 The deck slab should be designed 2 Their exact number and diameter
as one way slab. depends upon the discharge & height of
bank.
3 The culvert on important highways 3 For economic reasons road culverts
should be designed for the work should have non pressNP3 confirming to
effect either one lane of IRC class IS 458-1961.
AA track vehicle or one lane of IRC
class AA wheeled loading.
Slab culvert is cross drainage whose Provide as a cross drainage where the
total length between inner side of dirt discharge is small & there is no defined
wall is up to 6.0 m channel
The deck-slab is rested by abutments The Hume pipes are provided to flow the
and wing-walls are provided to retain water and headwalls at u/s and d/s is
earth work of approaches on both side provided to support the earthwork
All Deck slab design as a one way slab to Hydraulic designs of vent way is required &
carry Dead load and Live Load with structural design of Hume pipe is decided on
impact factor class of pipe and Type of bedding
Approach slab is required on both side Approach slab is not required, but minimum
600mm fill over Hume pipe is provided . At
pipe joint CC credlt to be provided
Parapet is provided with a 750mm Above road level , the head hall portion is
height constructed to up to 750mm height with a
required thickness to serve as a parapet

[P–I ]
27 CPM PERT
1 Critical Path Method is activity oriented 1 Programme evaluation and review technique
method is Event oriented
2 Direct controlling factor is cost 2 Direct controlling factor is Time
3 The time estimate for completion of 3 The time estimate for completion of activities
activities with fair degree of accuracy not accurate and define
4 It is applicable in the construction 4 It is applicable in pioneering type of projects
project very effectively

[P–I ]
28 Activity Event
1 Activity is a performance of a task, 1 Av events represents begin or completion of
Between two Events. activity or group of activity
2 Each activity required time, money and 2 It consume neither time nor resources
resources and has definable begging
and ending.
3 Activity generally represented by an 3 An event generally represented by means of
arrow headings towards right circle, square or triangle with number
enclosed
4 No activity can start until its 4 No events can be considered complete until
predecessor events is occurs all activity leading to it has been completed

[P–I ]
29 OPC PPC
1 1
2 2
3 3
4 4

[P–I ]
30 Dead Load Live Load
1 1
2 2
3 3
4 4
[P–I ]
31 Toe Wall Dirt Wall
1 1
2 2
3 3
4 4

[P–I ]
32 Sub grade Sub base
1 1
2 2
3 3
4 4

[P–I ]
33 Total Float Free Float
1 1
2 2
3 3
4 4

[P–I ]
34 Pile Foundation Well Foundation
1 1
2 2
3 3
4 4

[P–I ]
35 Wind Load Seismic Load
1 1
2 2
3 3
4 4

[P–I ]
36 River Bridges Fly Overs
1 1
2 2
3 3
4 4

[P–I ]
37 R E Wall R C C Wall
1 1
2 2
3 3
4 4

[P–I ]
38 Cement Concrete Lime Concrete
1 1
2 2
3 3
4 4

[P–I ]
39 Reduced Rate Part Rate
1 1
2 2
3 3
4 4

[P–I ]
40 Percentage Rate Item Rate
1 1
2 2
3 3
4 4

[ P – I, 11 ]
41 Load Bearing Frame Structure
1 Generally used for Ground + Three 1 Generally used for above ground + Three
story multi story building
2 Load is taken by brick/stone 2 Load is taken by Footings + columns
masonary walls
3 Economical compared to frame 3 Costly compared to Load bearing
structure. structure.
4 Plaster is required for finishing. 4 Plaster may or may not required.
Exposed surfaces can achieve.
5 Depth of foundation is shallow 5 Depth of foundation is deep.
6 Field data like SBC not required for 6 Field data like SBC required for structural
design purpose. design.
7 Life span is less compared to frame 7 Life span is more compared to load
structure. bearing structure.

[P–I ]
42 B-1 Tender B-2 Tender
1 1
2 2
3 3
4 4
[P–I ]
43 Reduce Rate Part Rate
If the item executed is substandard ,but The majority activity of execution of item are
does not endanger safety of structure completed, but some minor activities are yet
or spoil architectural view of the to be complete ( eg. Curing period of RCC
structure and defect is minor and work). In this condition , only partly payment
tolerable and if divisional officer of the item ,except fraction of FR that
decided to accept the items, the rate is required to complete the same is propose for
paid is know the Reduce Rate payment . This Rate is known as Part Rate
The Reduce rate is permanent and final The part rate is raised to full rate when the
rate which can not be raised to Full remaining activity is completed
Rate in subsequent or final bill

[P–I ]
44 Ridge Pavement Flexible Pavement
Ridge Pavement have high flexural Flexible Pavement can resist only very small
strength tensile and can resist high tensile stress because of Limited Rigidity
tensile bending stress because of
Rigidity
Any small depression in the sub base Any deformation in the sub grade result in
resisted by bridging the depression of corresponding change in the surface of the
sub-base pavement
The Sub Base may not required as rigid A strong and firm sub base is required
pavement quite strong
Normally cement concrete base course Normally bituminous surfacing is used as
act as a wearing surface wearing surface

[P–I ]
45 WBM BBM

You might also like