INSTALLATION OF NEW CLO2 PROJECT

Activity Duration September October Number December Jan-19


W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

Preparation of Machanical
1 20 Days
Package

2 PTFE Material Procurement 120 Days

2 Remaining Material Procurement 90 Days

3 Civil Work 15 Days

4 E&I Work 60 Days

5 Material shifting & sandblasting 5 Days

6 Pre fabrication of Piping 10 Days

7 installation of CLO2 Container 2 Days

Fabrication & Installation of


8 20 Days
piping & support
Hydrotesting, flushing&blowing
9 5 Days
of piping
Pre commissioning &
10 5 Days
commissioning activities