You are on page 1of 5

2013 IEEE 7th International Power Engineering and Optimization Conference (PEOC02013), Langkawi, Malaysia.

3-4 June
2013

Overcurrent Relays Coordination for


Commercial Building
2
10. Aliman, 1. Musirin

I
Faculty of Electrical & Electronics Engineering, Universiti Malaysia Pahang, Pekan, Pahang, Malaysia
2
Centre for Electrical Power Engineering, Universiti Teknologi Mara, Shah Alam, Selangor, Malaysia

l 2
omaraliman@ieee.org, ismailbml@gmail.com

algorithm for optimal coordination of overcurrent relays in a


Abstract- This paper presents an overcurrent relays loops distribution system is discussed in [1-4]. In this paper,
coordination study for an 11 kV commercial building in southern combination of primary and backup relay is chosen by using
Malaysia. Nevertheless, the actual study that covers the over­ graph theory, to avoid mal-operation of relays. A novel
current relays, earth fault relays and earth leakage relays were optimization technique based on evolutionary programming
executed by providing optimum and functionable relay settings
for overcurrent relay coordination in distribution networks is
prior to commissioning of the building. The calculated settings
presented in [5-6]. Evolutionary programming is a stochastic
and proposed adjustment settings have been verified and
multi-point searching optimization algorithm and is capable of
simulated by ETAP power tool for predictive sequence and
tripping time delay during fault. Based on the proven proposed escape from local optimum problems.
settings, the coordination study been accepted by the concerned In [7-9], intelligent relay coordination method have been
authority body and suggested for implementation accordingly. discussed based on the most widely used intelligent search
algorithms, called artificial bees colony (ABC) and particle
Index Terms-Radial power system, protection, over-current swarm optimization (PSO), for digital relaying, in which the
relays, ETAP, STAR view of relay curves, relay coordination. time-dial setting is appropriately adjusted in order to minimize
operating time while coordinated relays are also reliable.
I. INTRODUCTION Linear and non-linear programming optimizing techniques are
very frequently used for coordination of overcurrent relays. In
E
lectrical power system network consists of a series of
circuit breakers and relays which needed to protect one method of linear programming, the power supply system
expensive equipments. Significantly, the relays must be is divided into subsystems to give disabled diagonal matrix
coordinated so as to avoid mal-operation and also, to avoid structure connecting variables. Subsystem is solved using the
unnecessary downtime in other parts of the system. revised algorithm rare dual method of linear programming
Coordination of overcurrent relays in a meshed distribution [10-12]. Benders algorithm for linear programming is also
system is a challenge task for the protection engineers. Hence, used to coordinate solutions for each subsystem and system
it was initially done manually. master [13]. Method of linear programming is also used to
Generally, electricity demand increases more rapidly in coordinate distance relay zone-2 with overcurrent protection
developing countries in line with its economic development of [14].
the country. Impressed with the development, the networking Structured computer program that uses technically correct
of the power systems will also become more complex. In a models, uses a friendly interface, uses a common database and
case, analyzing streams load fault calculations and transfer user error trap are required to be a powerful tool that
primary and backup pairs will be very exhausting. Also, significantly improves the efficiency of engineering and
several iterations is needed to calculate the time multiplier performance. For that, ETAP is chosen that meets these
setting relay, so that the minimum margin discrimination as criteria. In addition, it performs numerical calculations with
required, is between relay and its entire backup relay in a large great speed and automatically applies accepted industry
electrical system. Therefore, in order to protect the entire standards.
system, the relays should be able to evaluate a wide range of In this paper, an industrial practice approach of overcurrent
parameters to determine what corrective action is needed relay coordination of 11 kV commercial building is presented.
responsive to any faults or abnormal conditions. This situation
is only possible and more accurate with reliance on computer IT. SYSTEM MODEL
capabilities.
An electrical power system model of a commercial
In present research development, artificial intelligence and building in southern Malaysia is shown in Figure 1. The 11 kV
optimization techniques are applied for optimal co-ordination incoming source has a three phase short current rating of 286
of overcurrent relays. For instance, application of genetic MV Asc. The step down 1110.415 kV transformer is 1.6 MYA
with 6% of transformer impedance is installed to connect to

978-1-4673-5074-7/13/$31.00 ©2013 IEEE 608


2013 IEEE 7th International Power Engineering and Optimization Conference (PEOC02013), Langkawi, Malaysia. 3-4 June
2013

2. Minimum Plug Setting (PS) for every relay calculated


based on maximum demand (MD) written in single line
diagram. In other words, the plug setting must not be less

I 286MVAsc
than the maximum normal load including permissible
continuous overload unless monitored by undervoltage

11 /0.415 kV relay, otherwise the relay will not allow the normal load
__ 1.6MVA
to be delivered.
MSB
3. Plug Setting value greater than minimum PS been chosen
to avoid tripping during normal operation and this PS
value also must be lower than upstream current setting.
MLl ML2 ML3 In estimating the plug setting, an allowance must be
1 made for the fact that the relay pick-up varies from 1 .05
------ to 1.3 times plug settings, as per standards.
2
..::.___
. - 1iI': �
�-- 4. Time Multiplier Setting (TMS) adjusted / grading based
1.0 MW on upstream relay curve. The time-multiplier setting
Stand by Gen.
must be chosen to give lowest possible time for the relay
EMSB
at the end of the radial feeder. Tn the preceding sections
towards the source, the time multiplier should be chosen
to give desire selective interval from the down-stream
ELl EL2 ELJ EL4 EL5 relay at maximum fault conditions.
5. The time multiplier setting should allow not only for the
Fig. I. II kV commercial building model. time of the breaker but also for the overshoot of the relay
and allowable time errors in the time of operation of
the MSB and EMSB feeders. Tn addition, a 1 MY A standby
successive relays. It is a common practice to use a fixed
power generator connected to 0. 415 kV bus acts a standby
selective interval of 0.25 second (considering 2cycle
power for EMSB. The total connected loads is 1,316.46 kW.
breakers) between the successive relays [15].
Out of the total connected load, EL3 bus carries the highest
loads of 407.54 kW.
TV. LOAD FLOW AND SHORT CIRC UlT ANALYSIS

m. METHOD IN COORDINATION ST UDY By performing the load flow analysis, the flow of current,
voltage and power, buses, transformers, switchgears, motors
Over the years, protection engineer use transparent template
and other equipment information can be determined. Thus,
that has been cut according to relay current-time characteristic
using this study as well plug relay settings can be solved. With
curve. By moving this template vertically will vary the time
the same work load flow, short circuit studies are important in
multiplier setting (T.M.S) and moving horizontally will vary finding the plug setting multiplier of relay. Therefore, load
the plug setting (PS) of relay. This traditional and flow and short circuit analysis should be required for the
conventional method which involves a lot of tedious and coordination of relays.
burdensome task in determine the plug and multiple setting for
each respective relay is adoptive and still considerable for a A. Loadflowanalysis
simple network. However, if the network is a bit large and has Load flow study plays an important role in the planning and
many layers of protective devices, the coordination works operation of electrical equipment. The results obtained in the
become intricate. study (in conjunction with the results of short-circuit) are used
With help of ETAP software, the protection engineer can to size capacitors, feeders, transformers and current-limiting
foresee the expected results from any possibilities of fault reactors, etc. Whether designing a new system or an existing
since from the initial stage. analysis, factors such as voltage drop, load capacity, power
Several options and techniques of relays coordination study factor constraints, steady-state stability limits, transformer tap
have been applied by engineers with ultimate goal of settings, and generator excitation levels should be considered.

providing optimum and functionable setting values. However, Analyzing the load flow study can determine the undervoJtage

the coordination procedure and consideration used in th is or overvoltage bus that can be severely affecting the efficient
study might be deferred and can be summarized as follow: operation of the machineries and loads.
1. Normally coordination study are doing by starting the
relay curve plot at lowest voltage level and largest load, B. Short circuit analysis
but in this case we will start from the power utility One of the major considerations in the design of a power
incomer since all the setting at this point has been system is adequate control of short circuits or faults as they are
decided by her. Grading from this point going to the commonly called. Uncontrolled short-circuits can cause
farthest relay at the lowers voltage level must be firstly service outage with accompanying production downtime and
done. Uniform grading time should be perform between associated inconvenience, interruption of essential facilities,
relays and if possible grading time of 0.3 second to 0.4 etc. Calculation of short-circuit currents for industrial power

second is recommended. systems are generally more complex, since a mixture of


sources that contributes to the current location of the fault. Tn a

609
2013 IEEE 7th International Power Engineering and Optimization Conference (PEOC02013), Langkawi, Malaysia. 3-4 June
2013

TC:': :l 3J.6. 4 6R.1A/


2:15. _ 9'9-:_
""'"
O . .:Ji1.5

� ��
) )

2 00/5 1400/5 _ "'00/5


><1<6 """ ?

-=-CL:130�
� ><K5
T-c:I...: J. OOKW
=CL; 1.4�. 62KH
l"!l:),: :!' .Q! 4.cef\ri

.r. __�BG�_'_4 ° O /_5__ �-�

I
4�
8'SO() IIdi
,STANBY GEN.

1400./5.
EMS .. �CL: 942 _ 85K""w
O_4�5 !<!!::.,: 716.9 9f\ri

..,,, h. ,""J-e
� MKlO ,""" 4h,
MKll ,"""�h,><KU �"�k.
MKla
� """9
TCL��75K""rl TCL�J.06'5- 24Krn' TCL�":::O? 54Kn' TCL�e:aHMir TCL:J.OE' .O"7KW

�: � 7 5 X--rl MD: J.<69.24KIii' MD: J. 9 2 . 0 D .2 .f K!ii' �: e :a RIM MD: 97 .'i5Kloi

Fig. 2. Single line diagram of 11 kY commercial building.

typical modem industrial system of the main sources of Setting Relay MK2 :
short-circuit currents are utilities, in-plant generation and
synchronous and induction motors. These sources contribute Maximum demand current
additional exponentially decaying currents which make fault 0.415
1773.94 x - - -
current magnitudes at various locations time dependent. 11
=

= 66.93 A
V. RELAY COORDINATION
[max
A. Manual calculation ofrelay setting PS> %
CT ratioxrelay current setting
The single line diagram of the commercial building is
illustrated in Figure 2 with all protective devices are placed 66.93
according to its original design. The initial calculation is PS>�%
started by focusing to the farthest and highest load at the x5
S
lowest voltage level. The first grading step is determining the PS> 89.24 %
grading relays for EL3as illustrated in Figure 3.
The parameters for relay MKI has been given by the power PS = 110% (adjusted based on relay MK 1 curve setting)
utility which the plug-setting is given as 82%, while the time­ TMS = 0.09
multiplier-setting is set as 0. 1.
Setting Relay MK3 :
Setting Relay MKI :
Maximum demand current is 1,773.94 A at 0.415 kV
Setting parameter for relay MKI has been provided by the
power utility supplier. 1773.94
PS> %
2000
-- x5
PS = 82% 5
TMS = 0.1 PS> 88.7 %

PS = 100% (adjusted based on relay MK2 curve setting)


TMS = 0.07

610
2013 IEEE 7th International Power Engineering and Optimization Conference (PEOC02013), Langkawi, Malaysia. 3-4 June
2013

Setting Relay MK6 : Setting Relay MKII :

Maximum demand current is 1,175.86 A at OA15 kV Maximum demand current


192.0034 kW
1175.86 v'3x415x0.85
PS> %
1400 314.25 A
--x5 =

5
PS> 84.0 % 314.25
PS> %
500
PS 100% (adjusted based on relay MIG curve setting) x5
=
T
TMS = 0.07 PS>62.85 %

PO'Mc.r UlI;ilitry PS = 75% (adjusted based on relay MK8 curve setting)


:2:86 �c:
TMS = 0.05
The above calculated and adjusted grading of relays is then be
150/5 translated into tripping curve as depicted in Figure 4.
!lK1.
CBIl-2
11 ""V 6aO A Amps X 100 EMSB (Nom. kV=0.415. Pial Ref. kV=0.415)
25 !<A CB:n.-4
6ao A

Ii I
500 500

JOO

>---.,---MK2·P
Mikro
I I fo.1I<2200 " .
CT RallO 75:5
) CB,-HS-8 lEe - Normal Inverse

2 00 A 50 Pickup::o 1.1 (0.5 - 2.5 xCT Sec) 50

Time Dial = 0.09


3x = 0.567 $, 5x == 0.385 $, 8x = 0.297 s
.M.5B. 50 "-'I. 2000/S JO
Inst == 8 (0.5 - 40 xCT Sec)
0..41.5 rt.V .!lK2 Time Delay = 0_05 s

1400/5
f:���li-H.'
!lK6

..
\ \ MK3-P
MJU.,E
�-----

,�A-�-----MK6-P
CB- 4 1 5- 1a ,����-----MK8-P
) H()() A
H.OO/;; MKJ.1..,J' -------',
Mikro
EH.:m, 50 kA !lK8 MK1000

O.·4H tV CT Ratio 500:5


IEC - Normal Inverse
Pickup = 0.75 (0.5 - 2.5 xCT Sec)
Time Dial = 0.09
3x == 0_567 s, 5x = 0.385 S, ax = 0.297 s
Ins! = 5 (0.5 - 40 xCT Sec)
Time Delay = 0_05 s

.. ...
5 'OK
"C'CL : 4 0"1. 5qK""ri'
¥.:J: 1 9 2.0Cii 3, ;Q illof Amps X 100 EMSB (Nom. kV=0.415. Plot Ref. kV=0.415)

Fig. 4. Overcurrent grading for relay MK!1.


Fig. 3. Grading of EL3.

Setting Relay MK8 :


TABLE!
ADJACENT RELAYS SETTING
Maximum demand current is 1,175.86 A at OA15 kV
Relay IMD. (A) PS(%) TMS

1175.86 MSB
PS> % 212.77 0.1
1400 MK4 90
--x5
5 MK5 163.67 100 0.1
PS> 84.0 % EMSB
MK9 286.40 80 0.05
PS = 90% (adjusted based on relay MK6 curve setting) MK10 277.00 100 0.1
TMS = 0.05 MK12 135.84 80 0.1

611
2013 IEEE 7th International Power Engineering and Optimization Conference (PEOC02013), Langkawi, Malaysia. 3-4 June
2013

Relays connected to MSB are graded base on the upstream [4] F. Razavi, H. A. Abyaneh, M. Al-Dabbagh, R. Mohammadi and H.
Torkaman, "A new comprehensive genetic algorithm method for
relay which is relay MK3. Whereas, relays connected to
optimal overcurrent relays coordination," Electric POlVer Systems
EMSB are graded base on the upstream relay which is relay Research. vol. 78,pp. 713-720,2008.
MK8. Table 1 shows the grading of the rest of the adjacent [5] I A Sueiro, E. Diaz-Dorado, E. Miguez and J. Cidnis, "Coordination
relays. of directional overcurrent relay using evolutionary algorithm and linear
programming," International Journal of Electrical Power & Energy
Systems. vol. 42, pp. 299-305, 2012.
B. Relay setting in ETAP: [6] C. W So and K. K. Li, "Overcurrent relay coordination by evolutionary
Consider that fault is occurred at bus EL3. Then near the programming," Electric POlVer Systems Research. vol. 53, pp. 83-90,
faulted bus, first relay MKII must be operated. In the ETAP 2000.
[7] D. Uthitsunthorn, P. Pao-La-Or and T. Kulworawanichpong, "Optimal
software, the star view feature is good to show the exact
overcurrent relay coordination using artificial bees colony algorithm,"
coordination of relays. in Electrical Engineering/Electronics. Computer. Telecommunications
Same way, if the relay MKll is failed, the relay MK8 must and Information Techno logy (ECTI-CON), 2011 8th International
be operated as back up relay. So as, if relay MK8 is failed, the Conference on, 2011,pp. 901-904.
relay MK6 must be operated. As above, if relay MK6 is failed,
[8] M. R. Asadi and S. M. Kouhsari, "Optimal Overcurrent relays
the next relay that should be operated is relay MK3. The same coordination using particle-swarm-optimization algorithm," in Power
will follow to relay MK2 and the last relay MKI. Systems Conference and Exposition. 2009. PSCE '09. IEEE/PES,2009,
Thus, the relay coordination from relay MKll to relay MKI pp. 1-7.
[9] H. H. Zeineldin, E. F. El-Saadany and M. M. A. Salama, "Optimal
is done by using ET AP software. The star views of all relays
coordination of overcurrent relays using a modified particle swarm
can be displayed to confirm complete coordination of all optimization," Electric Power Systems Research, vol. 76, pp. 988-995,
relays. 2006.
[10] P. P. Bedekar, S. R. Bhide and V. S. Kale, "Coordination of overcurrent
relays in distribution system using linear programming technique," in
VI. CONCLUSION
Contro l, Automation. Communication and Energy Conservation. 2009.
The overcurrent relays which dominate almost all types of INCACEC 2009. 2009 International Conference on, 2009,pp. 1-4.
[11] P. P. Bedekar, S. R. Bhide and V. S. Kale, "Optimum Coordination of
relays in the power system need to be coordinated properly so
Overcurrent Relays in Distribution System Using Dual Simplex
as to avoid mal-operation and also, to avoid unnecessary Method," in Emerging Trends in Engineering and Techno logy
downtime in other parts of the system. In this paper, normal (ICETET) , 2009 2nd International Conference on, 2009,pp. 555-559.
practice of coordination works of overcurrent relays by [12] P. P. Bedekar, S. R. Bhide and V. S. Kale, "Optimum coordination of
overcurrent relays in distribution system using genetic algorithm," in
manual calculation has been presented. However, since the
Power Systems, 2009. ICPS '09. International Conference on, 2009, pp.
network is very large and has many layers of protective 1-6.
devices, the coordination works become intricate. With help of [13] H. B. Elrefaie, M. R. Irving and S. Zitouni, "A parallel processing
ETAP software, the protection engineer can foresee the algorithm for co-ordination of directional overcurrent relays in
interconnected power systems," Generation. Transmission and
expected results from any possibilities of fault since from the
Distribution. lEE Proceedings-, vol. 141, pp. 514-520,1994.
initial stage. Therefore, the chances of mal-function operation [14] S. .Iamali and M. Pourtandorost, "New approach to coordination of
of the devices is very very minimal. Thus, the advantage of distance relay zone-2 with overcurrent protection using 1 inear
using software tool can efficiently provide and solve the programming methods," in Universities Power Engineering
Conference, 2004. UPEC 2004. 39th International, 2004, pp. 827-831
coordination problem of overcurrent relays in radial system.
vol. 1.
[15] B. Oza,N. Nair, R. Mehta and V. Makwana, Power System Protection
& Switchgear: Tata McGraw-Hill Education ( India) Pvt Limited, New
ACKNOWLEDGMENT Delhi,2010.

The authors would like to acknowledge The Research


Management Institute (RMT) UiTM, Shah Alam and Ministry
of Higher Education Malaysia (MOHE) for the financial Omar Aliman (M'07) received his Diploma in Electrical Power Engineering
support of this research. This research is supported by MOHE from University Teknologi Malaysia, graduated his BSc. from Hanyang
under the Research Acculturation Grant Scheme (RAGS) with University, Korea and obtained his MEng. from Universiti Teknologi
Malaysia. Currently, he is a PhD candidate at Universiti Teknologi MARA
project code: 600-RMIIRAGS 5/3(49/2012 ).
His special field of interest includes power distribution,distributed generation
and arc-flash analysis study.
REFERENCES
[I] .I. G. Singh, S. N. Singh and S. C. Srivastava, "An Approach for Associate Professor Dr. Ismail Musirin obtained his Diploma of Electrical
Optimal Placement of Static V Ar Compensators Based on Reactive Power Engineering in 1987, Bachelor of Electrical Engineering (Hons) in
Power Spot Price," IEEE Transactions on Power Systems, vol. 2 2, pp. 1990; both from Universiti Teknologi Malaysia, MSc in Pulsed Power
2021-2029,2007. Technology in 1992 from University of Strathclyde, United Kingdom and
[2] R. M. Chabanloo, H. A. Abyaneh, S. S. H. Kamangar and F. Razavi, PhD in Electrical Engineering from Universiti Teknologi MARA, Malaysia in
"A new genetic algorithm method for optimal coordination of 2004. His research interest includes power system stability, optimization
overcurrent and distance relays considering various characteristics for techniques,distributed generator and artificial intelligence.
overcurrent relays," in Power and Energy Conference, 2008. PECon
2008. IEEE 2nd International, 2008,pp. 569-573.
[3] R. M. Chabanloo, H. A. Abyaneh, S. S. H. Kamangar and F. Razavi,
"Optimal Combined Overcurrent and Distance Relays Coordination
Incorporating Intelligent Overcurrent Relays Characteristic Selection,"
Power Delivery, IEEE Transactions on, vol. 26, pp. 1381-1391,2011.

612

You might also like