Professional Documents
Culture Documents
Abstract - This study analyzes about the cause of the leak in KM Nusantara Akbar’s engine room. However, this
research is focus on leakage caused by shaft deflection. From the data found the cause of the leakage was packing driven by
a shaft deflection. Analysis was done by a review of the technical and non-technical factors. The first step was analyzing the
vessel document.Then the evidence that has been obtained from the documents related to the vessel would be used to make
the analysis using 5 whys method to look for the root cause. According to the analysis that has been done, the technical
cause of the engine room leakage caused by system shafting system was reconditioned the broken flange bolts and the
addition of flax on the bearing shaft without straightening axle deflection itself. Another fact from Autodesk Inventor 3D
modeling software obtained bolt broken because the load is 10782.31 N with shear stress 2.230 MPa, while the maximum
force in the normal load is 9.434,531.N with shear stress 1,951 MPa. Then, from non-technical factors are equipment to
overcome the failure system is very less, the workplace is dirty and uncomfortable and happened miss communication
between the crews.
I. INTRODUCTION
This research will analyze the causes of
the water that flow into the engine room KM.
Leakage is the water entered into one of Nusantara Akbar, but which became the focus
the rooms or compartments of the vessel caused by point of this research is leakage caused by shaft
the leaking of the room or anything else that causes deflection because of the field data provided by the
the water can run into the compartements of the KNKT, known causes of leaks in the engine room
vessel. This should be avoided as much as possible is packing driven by shaft deflection so that
because it may cause harm to the captain and crew, packing can not withstand the rate of water
vessel owners, marine environment and disruption This research will be conducted on the
of seabed ecosysem. Leaks in the vessel can occur two factors, the technical factors and the non-
because the vessel ran aground, fire, vessel plate is technical factors. Technical factors is a factor based
corrosion or internal factors such as failure of on the workings of the existing system in the
shafting system. Emergency situation will be came engine room, especially the shaft system and its
when the water enter quickly into a room or components, while for the non-technical factors are
compartment of the vessel, but in the other side's the other factors that affect the workings of the
ability to overcome the leakage is limited. Even if systems that exist in the engine room, especially for
this is allowed then the vessel will be sloping till shafting systems such as crew, workplace
sink. More complicated situation will come when conditions and others. At the beginning of each of
the decision-making and implementation is not technical and non-technical factors will be
fully supported by crew. performed using the fault tree. Analysis of the fault
The engine room is a very vital tree is a troubleshooting step to seek the cause of
compartment in a vessel, can sail or not a vessel an effect. This method is a technique to identify all
will be affected by the condition in the engine the problems in a given situation and to
room, because in the engine room there are many demonstrate this information as a series of causal
systems that support vessel. Such as main engine relation vessel. In the next step to do technical
systems that generates trust power for vessels, factors and non-technical factors is using the 5
auxiliary machinery systems to move the steering whys method. 5 whys method is the question and
system, power generation system / electric answer technique to investigate the causal relation
generator that provides electricity supply for untill the root of a problem. This technique is the
vessels and shafting sytem that the function is practice of asking why five times to determine the
deliver the trust power from the main engine to the root cause of a defect or problem. Then for the
propeller as a driver. technical factors aided by modeling using
Rachmat Gunawan, Department of Marine Engineering, Autodesk Inventor 3D and confirm with BKI rules
Institut Teknologi Sepuluh Nopember, Surabaya 60111,
Indonesia, Email : rachmat.gunawan@ymail.com
related shating systems.
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 2
Table 1.
The Example of 5 Whys Question Table.
II.2. BKI VOLUME III CHAPTER 4 diameter in way of shrink fitted couplings
Based on BKI rules volume III Rules For should be slightly increased, e.g. by 1 to 2 %.
Machiney Installations Chapter 4 of the Main k = 1,10 for intermediate shafts where the
shafting is stated that there is a standard material coupling flanges are mounted on the ends of
and size for each component. the shaft with the aid of keys. At a distance of
at least 0,2 · d from the end of the keyway,
A. Material such shafts can be reduced to a diameter
In general for the material, the minimum calculated with k = 1,0.
tensile strength for the system shafting (Shaft, k = 1,10 for intermediate shafts with radial
Flange couplings, bolts / fitted bolts) is between holes which diameter is not exceeding 0,3 · d.
400 N / mm2 to 800 N / mm2, specifically for Intersections between radial and eccentric axial
fitted bolts connections minimum tensile strength is holes require a special strength consideration.
more than 500 N / mm2. k = 1,15 for intermediate shafts designed
However, the value of Cm were used for the as multi-splined shafts where d is the outside
calculation of Rm must be less than: diameter of the splined shaft. Outside the
1. 600 N / mm2 for propeller shafts. splined section, the shafts can be reduced to a
2. 760 N / mm2 for shafts made of steel except diameter calculated with k = 1,0.
propeller shaft. k = 1,20 for intermediate shafts with
3. 800 N / mm2 for shafts made of stainless longitudinal slots within the following
staniless. limitations :
- slot length up to 0,8 d
B. Dimensioning / Size. - inner diameter up to 0,8 d
For the minimum diameter shaft size can - slot width e up to 0,1 d
be determined by the following formula: - end rounding at least 0,5 e
Pw - 1 slot or 2 slots at 180°or 3 slots at 120°
Da ≥d≥F.k. 3√ di 4 . Cw
n.[1−( ) ] Slots beyond these limitations require a special
da
strength consideration.
d = [mm] minimum required outer shaft
diameter b) Thrust shafts
da = [mm] actual outer shaft diameter k = 1,10 for thrust shafts external to
di = [mm] actual diameter of shaft bore. If engines near the plain bearings on both sides
the bore in the shaft is ≤ 0,4 . da, the of the thrust collar, or near the axial bearings
expression where a roller bearing is used.
di
1 − ( )4 may be taken as 1,0
da
Pw = [kW] rated power of propulsion motor, c) Propeller shafts
gear box and bearing losses are not to be k =1,22 for propeller shafts with flange
subtracted mounted or keyless taper fitted propellers,
N = [RPM] shaft speed at rated power applicable to the shaft part between the
F = factor for type of propulsion installation forward edge of the aftermost shaft bearing
a)Propeller shafts and the forward face of the propeller hub or
= 100 for all types of installations shaft flange, but not less than 2,5d.
b)Intermediate and thrust shafts In case of keyless taper fitting, the method of
= 95 for turbine installations, diesel engine connection has to be approved by BKI.
installations with hydraulic slip couplings, k =1,26 for propeller shafts in the area
electric propulsion installations specified for k= 1,22, if the propeller is keyed
= 100 for all other propulsion installations to the tapered propeller shaft.
Cw = material factor k =1,40 for propeller shafts in the area
specified for k = 1,22, if the shaft inside the
560 stern tube is lubricated with grease.
Rm+160 k =1,15 for propeller shafts between
Rm = [N/mm2] specified minimum tensile forward end of aftmost bearing and forward
strength of the shaft material (see also B.1) end of fore stern tube seal. The portion of the
k = factor for the type of shaft propeller shaft located forward of the stern
tube seal can gradually be reduced to the size
a. Intermediate shafts of the intermediate shaft.
k = 1,0 for plain sections of intermediate
shafts with integral forged coupling flanges or II.3. AUTODESK INVENTOR 3D
with shrink-fitted keyless coupling flanges. For Autodesk Inventor 3D is one of the
shafts with high vibratory torques, the software type of Computer Aided Drawing (CAD)
is more emphasis on solid modeling. This software
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 4
is one of the Autodesck Inc products. Autodesk based software, such as Catia, Solid Work, Pro-E
Inventor 3D is more devoted to the depiction of and others. In the Figure 2 below is one example of
mechanical engineering, which provides a Autodesk Inventor 3D using associated with this
complete facility to visualize the model in 3D, the analysis is the depiction of a shaft that has been
amenities offered assembly and working drawings. resized.
The software is made to compete with other CAD-
III. RESULTS AND DISCUSSION several parts according to its main components,
such as:
III.1. IDENTIFICATION AND ANALYSIS 1. Intermediate shaft
DATA. 2. Bearing
Shafting system is a system that the 3. Clutch
function is deliver trust power from the main 4. Stern tube
engine (prime mover) to the propeller so that the 5. Packing
vessel can get a thrust in accordance with the 6. Propeller shaft
expected. In this case, KM. Nusantara Akbar 7. Propeller
shafting use sea water lubrication system.
To facilitate the identification system While the field data obtained from the KNKT after
shafting KM. Nusantara Akbar will be divided into the accidents is as shown like on Figure 3 below
1. 1 piece coupling bolts are not in place (A). 6. Seeing fastening bolt on the clutch shaft, it is
2. 1 piece of broken coupling bolts (B) likely not a fitted bolt.
3. 2 pieces almost detached, the possibility is 7. When the intermediate shaft is rotating,
breaking up the middle intermediate shaft bearings going to sway. To
4. 2 bolts still attached but there is an additional reduce the sway then mounted a tackle block
ring, it should not be. as in Figure 4 (in this picture chain fastened to
5. 2 pieces bolts that are at the bottom is not the foundation bearing tackle)
visible in this image.
that the condition of the vessel is dirty and there are 1.1.1.1. Because there were misscommunication
mice. between crew
III.2. CAUSE ANALYSIS 1.1.1.2. Because the crew less competent
1.1.1.3. Beacause the crew physical and
(1). Technical Factors psychological conditions unfavorable
1.1.3. Why the working environment was dirty?
(a) 5 Whys 1.1.3.1. Because the crew is slovenly
After doing the analysis and identification of 1.1.3.2. Because operator ignore the vessel
the data that have been obtained, the next step is condition
analyze the causes of failure of the propeller shaft 1.2.1. Why the shaft deflection
deflection. 1.2.1.1. Because related components less support
In the first step is to choose the top event, (Flange and Bearing)
according to the guide, the top event is choosen from 1.2.1.2. Because the shaft could not accept the
events or incidents that have occurred. Engine room load.
leak incident at KM Nusantara Akbar is choosen as the 1.2.2. Why the packing could not resist the water rate?
top event. 1.2.2.1. Because Encouraged / disturbed by shaft
In the second step continued with the question deflection
of why. This question covers of technical and non- 1.2.2.2. Beacuse an error in the installation.
technical factors. Then the answer for the first why
question there is a leak in the engine room are as In the fifth step is giving why question to the
follows: fourth step answer. The answer of each question is:
1.1. Unpreparedness to face the damage / failure of 1.1.1.2. Why the crew standard of competence is less?
the system. 1.1.1.2.1. Because the crew did not renew the
1.2. Damage / failure of internal systems (shafting certificate of membervessel.
system). 1.1.1.2.1. Because there is no facility from vessel
operators
In the third step is giving the question why in every 1.2.1.1. Why the associated components was not
answer in second two. The answer of each question is: supported (flange and bearing)
1.1. Why happened the unpreparedness to face the 1.2.1.1.1. Beacause the maintenance of flange and
damage /failure of the system? bearing are not in accordance with the
1.1.1. Because crew is not responsive to face the standards
failure of the system. 1.2.1.1.2. Because the components are less well
1.1.2. Because the equipment was insufficient to 1.2.1.2. Why the shaft can’t accept the load?
handle failure 1.2.1.2.1. Because the load is too heavy
1.1.3. Because working environments conditions In the sixth step is giving why question to the fifth
are dirty step answer. The answer of each question is:
1.2. Why there is damage / failure of internal systems 1.2.1.1.1. Why the maintenance of flange and bearing
(shafting system)? are not compliant?
1.2.1. The shaft deflection (Deflection) 1.2.1.1.1.1. Because when the bolts is broken not
1.2.2. Failure on Packing and Seal (could not resist replaced but reconditioned.(welded)
the rate of water) 1.2.1.1.1.2. Because the addition of flax on the
bearings to handle deflection shaf.
In the fourth step is giving why question to the Then on the Figure 5 below is the result of why
third step answer. The answer of each question is: tree which has been described from the above process:
1.1.1. Why the crew not responsive to face the failure
of the system?
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 7
KEBOCORAN PADA
KAMAR MESIN
1
PERALATAN UNTUK
Poros mengalami KEGAGALAN PADA
ABK TIDAK TANGGAP MENANGANI 1.2.1
RUANG KERJA
1.1.3 defleksi SISTEM PERPOROSAN 1.2.2
MENGHADAPI 1.1.1 KEGAGALAN KURANG
KOTOR (DEFLEKSI)
KEGAGALAN SISTEM MENCUKUPI
1.1.2
KOMPONEN KURANG
KONDISI FISIK DAN OPERTOR
MISSKOMUNIKASI ABK KURANG ABK JOROK MENGABAIKAN
MENDUKUNG (FLANGE 1.2.1.1 Poros tidak sanggup TERDORONG OLEH KESALAHAN
PSIKOLOGI ABK DAN BAUT) menerima beban POROS YANG DEFLEKSI PEMASANGAN
ANTAR ABK BERKOMPETEN KONDISI KAPAL
KURANG BAIK
1.1.1.1 1.1.1.3 1.1.3.1 1.1.3.2 1.2.1.2 1.2.2.1 1.2.2.2
1.1.1.2
PERAWATAN FLANGE
ABK TIDAK KONDISI KOMPONEN MENERIMA BEBAN
TIDAK ADA FASILITAS DAN BEARING TIDAK KONDISI DAN DIMENSI
MEMPERPANJANG BURUK
SESUAI PROSEDUR TERLALU BESAR POROS KURANG BAIK
DARI OPERATOR
SERTIFIKAT
1.1.1.2.1 1.1.1.2.2 1.2.1.1.2 1.2.1.1.1 1.2.1.2.1 1.2.1.2.2
PENAMBAHAN
LENAPADA BEARING BAUT FLANGE YANG
TERKAIT POROS YANG RUSAK TIDAK DIGANTI
SUDAH DEFLEKSI
1.2.1.1.1.3&4 1.2.1.1.1.1&2
Figure 5. Why Tree of Leakage in the engine room of KM. Nusantara Akbar case
After the analysis of the why tree is into the table 5 whys question are events which
complete then the matrixs inserted into the 5 whys have been reinforced by the evidence above, so we
question table as in table 2. The events are entered will get the right solution.
Table 2.
5 Whys Question Table for Technical Factors
5 Whys Question Table
Problem Statement: Vessels leak in the engine room
Recommended Solution: Perform maintenance according to the procedure: replacing the flange bolts if damaged and then adjust
the straightening shaft bearing depend on the shaft
Latent Issues: Not treated maintenance in accordance with the procedure when in dock
No. Why Questions Answer Evidence Solution
1. Why there is a leak in Beacause damage / Leakage in the engine room
the engine room of failure of internal systems of KM. Nusantara Akbar
KM. Nusantara Akbar (shafting system).. (1.2)
?
2. Why there is damage / Because there is failure packing driven by shaft Prepare the spare parts/tools to
failure of internal on shafting system deflection so that packing can face the failure.
systems (shafting (Deflection) (1.2.1) not withstand the rate of
system)?(1) water
3. Why there was a Because related Flange bolts is broken and Regularly check the shaft
failure in the shafting components less support bearing is sway deflection and maintain the
system(deflection)? (Flange and permitted limit
(1.2.1) Bearing)(1.2.1.1)
4. Why the associated Beacause the Flange bolts is broken and Check the size and strength of
components was not maintenance of flange bearing is sway bearing and flange
supported (flange and and bearing are not in
bearing)?(1.2.1.1) accordance with the
standards. (1.2.1.1.1)
5. Why the maintenance Because when the bolts is Welding flange bolts perform appropriate
of flange and bearing broken not replaced but maintenance procedures:
are not compliant? reconditioned.(welded) replacing the flange bolts if
(1.2.1.1.1) (1.2.1.1.1.1) damaged and adjust the shaft
Because the addition of The addition of flax on the then straightening shaft bearing
flax on the bearings to bearings
handle deflection shaft
(1.2.1.1.1.2)
(b). Calculate the minimum diameter of shaft From the data, known,
according to the BKI rules P m/e : 3850 kW
Material : Stainlees Steel
Rm : 480 N/mm2
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 8
Explanation : Tm : 19827,4 Nm
Ơ: shear force from the main engine and propeller Tp : 19430,86 Nm
torque to the flange bolts
Tm: Main Engine Torque Once modeled as in Figure 7. and 9,
Tp: Propeller Torque obtained bolt broken because the act force is
g : gravity 10782.31 N with shear stress 2.230 MPa, while the
maximum force in the normal load is 9.434,531.N
The force known as : with shear stress 1,951 Mpa.
Ơ : 1,951 Mpa
(2). Non Technical Factors Analysis technical factors analysis. Then for the matrix that
The first step is to create Why tree to has been reinforced by the evidence to be inserted
analyze the cause before use 5 whys Table. Why into the 5 whys table in Table 3 below
tree used is why tree similar to that used for
Table 3
5 Whys Table for Non-Technical Factors
5 Whys Question Table
Problem Statement: Vessels leak in the engine room
Recommended Solution: prepare the spare parts/tolls related to overcome the failure, increase communication system
Latent Issues: Not preparing spare parts / equipment safety to prevent shafting system failures.
No. Why Questions Answer Evidence Solution
1. why there is a leak in the Because unpreparedness Leakage in the engine room
engine room of KM. to face the damage / of KM. Nusantara Akbar
Nusantara Akbar ? failure of the system.(1.1)
2. Why happened the Because crew is not Prevention of leaks using prepare the spare parts/tolls related
unpreparedness to face the responsive to face the makeshift tools. to overcome the failure
damage /failure of the failure of the system
system?(1.1) (1.1.1)
Because the equipment
was insufficient to handle
failure. (1.1.2.)
Because the working
environtment is dirty
(1.1.3)
3. Why the crew not Because the lack of crew captain did not know the crew Train communication and team
responsive to face the competency was killed because of panic. work
failure of the standards.(1.1.1.2)
system?(1.1.1)
Misscommunication
between crew (1.1.1.1)
Why was the equipment to Because of the lack of Crew handle leaks using Ask the operator to conduct the
deal the failure is procurement from the boards and clothes wearpack procurement of spare parts
insufficient? (3.2) operator. (3.2.A)
Why the working Because the crew is The work space is dirty and Clean the work space after and
environmrnt is dirty? slovenly (1.1.3.1) there are mices before shift changes
(1.1.3)
Beacause operator ignore get warning from the health Mempersiapkan koordinasi dan
the vessel condition department team work yang baik sebelum
(1.1.3.2) memulai pekerjaan
4 Why the crew standard of Because the crew did not There are crew certificates Make clear rules on the cleanliness
competence is less? (3.3.A) renew the certificate of was expired. of the vessel.
membervessel. (3.3.A)
broken. This should not be done, because it [13] P. Assi, "FE Analysis of Hollow Propeller Shaft Using
will change the character of the material that Steel and Composite Material then Compares it,"
Ahmedabad.
has received heat and the addition of different
[14] B. K. Indonesia, Volume III Rules for Machinery
materials.
Installations, 1st ed., BKI, 2015.
4. From docking report that has been analyzed,
[15] ABS, Guidance Notes on Vessel Vibration, 1st ed., New
found a mistake during the process of docking, York: ABS, 2015.
the addition of flax in the bearing to adjust the [16] A. Grzadziela, "Dynamic Problems of Propulsion System
shaft has a deflection. This should not be done, of Naval Vessels," Gdynia, 2007.
because the point of deflection will creep at
another point.
Non-Technical Factors:
1. From the data that has been analyzed, found
that the tools for system failure in the engine
room of KM. Nusantara Akbar is lacking, as
shown by the rate of water blockage using a
piece of board and crew wearpak. This should
not happen, because it will damage related
components and endanger the safety of the
crew.
2. From incidents reports that have been
analyzed, found that misscommunication
happened between crews, as shown by the
ignorance of the Master that one of crew
panicked and took the pump in Fresh Water
Tank, which later became one of the crew
killed in this incident. This should not happen,
because misscommunication will lead to a
decreased level of success in a team work.
3. From the vessel documents that has been
analyzed, found that the engine room
conditions of KM. Nusantara Akbar in dirty
conditions. This should not happen, because it
would interfere with the work of the crew.
REFERENCES