You are on page 1of 11

Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016.

26-30 (ISSN: 2541-5972) 1

LEAK CAUSES ANALYSIS IN THE


ENGINE ROOM OF KM. NUSANTARA
AKBAR
Rachmat Gunawan1, Trika Pitana2, Hari Prastowo3

Abstract - This study analyzes about the cause of the leak in KM Nusantara Akbar’s engine room. However, this
research is focus on leakage caused by shaft deflection. From the data found the cause of the leakage was packing driven by
a shaft deflection. Analysis was done by a review of the technical and non-technical factors. The first step was analyzing the
vessel document.Then the evidence that has been obtained from the documents related to the vessel would be used to make
the analysis using 5 whys method to look for the root cause. According to the analysis that has been done, the technical
cause of the engine room leakage caused by system shafting system was reconditioned the broken flange bolts and the
addition of flax on the bearing shaft without straightening axle deflection itself. Another fact from Autodesk Inventor 3D
modeling software obtained bolt broken because the load is 10782.31 N with shear stress 2.230 MPa, while the maximum
force in the normal load is 9.434,531.N with shear stress 1,951 MPa. Then, from non-technical factors are equipment to
overcome the failure system is very less, the workplace is dirty and uncomfortable and happened miss communication
between the crews.

Keywords: Leak, shafting system, deflection, crew, 5 whys.

I. INTRODUCTION
This research will analyze the causes of
the water that flow into the engine room KM.
Leakage is the water entered into one of Nusantara Akbar, but which became the focus
the rooms or compartments of the vessel caused by point of this research is leakage caused by shaft
the leaking of the room or anything else that causes deflection because of the field data provided by the
the water can run into the compartements of the KNKT, known causes of leaks in the engine room
vessel. This should be avoided as much as possible is packing driven by shaft deflection so that
because it may cause harm to the captain and crew, packing can not withstand the rate of water
vessel owners, marine environment and disruption This research will be conducted on the
of seabed ecosysem. Leaks in the vessel can occur two factors, the technical factors and the non-
because the vessel ran aground, fire, vessel plate is technical factors. Technical factors is a factor based
corrosion or internal factors such as failure of on the workings of the existing system in the
shafting system. Emergency situation will be came engine room, especially the shaft system and its
when the water enter quickly into a room or components, while for the non-technical factors are
compartment of the vessel, but in the other side's the other factors that affect the workings of the
ability to overcome the leakage is limited. Even if systems that exist in the engine room, especially for
this is allowed then the vessel will be sloping till shafting systems such as crew, workplace
sink. More complicated situation will come when conditions and others. At the beginning of each of
the decision-making and implementation is not technical and non-technical factors will be
fully supported by crew. performed using the fault tree. Analysis of the fault
The engine room is a very vital tree is a troubleshooting step to seek the cause of
compartment in a vessel, can sail or not a vessel an effect. This method is a technique to identify all
will be affected by the condition in the engine the problems in a given situation and to
room, because in the engine room there are many demonstrate this information as a series of causal
systems that support vessel. Such as main engine relation vessel. In the next step to do technical
systems that generates trust power for vessels, factors and non-technical factors is using the 5
auxiliary machinery systems to move the steering whys method. 5 whys method is the question and
system, power generation system / electric answer technique to investigate the causal relation
generator that provides electricity supply for untill the root of a problem. This technique is the
vessels and shafting sytem that the function is practice of asking why five times to determine the
deliver the trust power from the main engine to the root cause of a defect or problem. Then for the
propeller as a driver. technical factors aided by modeling using
Rachmat Gunawan, Department of Marine Engineering, Autodesk Inventor 3D and confirm with BKI rules
Institut Teknologi Sepuluh Nopember, Surabaya 60111,
Indonesia, Email : rachmat.gunawan@ymail.com
related shating systems.
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 2

question of why, then it will increase the chances


II. METHOD of finding the root cause of the underlying problem
or failure. Although this technique is called 'five
whys', five is the rule of thumb. In addition there is
II.1. 5 WHYS also the theory that 7 'why' is better and that the 5
5 whys method is a method to determine 'why' is not enough to looking for the real cause of
the cause-effect in trouble or failure events. It can the failure.
be used whenever there is a problem with the In the 5 whys analysis also implied a
system. Using the 5 whys is a simple way to try to method though not often stated openly, that the use
solve the problem without a detailed investigation of why tree like on Figure 1, this method is also
that requires a lot of resources. When the problem called Fault Tree Analysis. This method is one of
involves human factors, this method is the easiest the best ways to start the 5 whys method that
to use. This method is one of the simplest methods causes that may be visible. Why tree which was
of investigation that can easily be solved without originally just a simple matter to grow up with a
statistical analysis or also known as why tree, variety of causal branches.
where it is the simplest form of analysis of the root 5 whys method use tables to register
cause, by repeatedly asking the question, "Why?" it successive questions and answers. Table 1 is an
can peel the layers of problems and symptoms that example of the method 5 whys. At the table, each
can lead to the root cause. answer will be a question in the next process. It's
In the first step, begins with a statement important that each Why question is the answer
that is why it happened. The next step is to change before it, because it will create relation that clear
the answer from the first question as why for the and undeniable..
second question and so on. With emphasis on the

Figure 1. Example of Why Tree

Table 1.
The Example of 5 Whys Question Table.

5 whys Question Table


Problem Statement: On your way home from work your car stopped in the middle of the road.
Recommended Solution: Carry a credit card to access money when needed.
Latent Issues: Putting all the money into gambling shows lack of personal control and responsibility over money.
No. Why Questions Answer Evidence Solution
1. Why did the car stop? Because it ran out of gas in a back street Car stopped at side of
on the way home road
2. Why did gas run? Because I didn't put any gas into the car Fuel gauge showed Contact work
on my way to work this morning. empty and get someone
to pick you up
3. Why didn't you buy gas Because I didn't have any money on me Wallet was empty of Keep a credit
this morning? to buy petrol. money card in the wallet
4. Why didn't you have any Because last night I lost it in a poker Poker game is held Stop going to the
money? game I played with friends at my buddy’s every Tuesday night game
house
5. Why did you lose your Because I am not good at ‘bluffing’ when Has lost money in many Go to poker
money in last night's I don't have a good poker hand and the other poker games School and
poker game? other players jack-up the bets. become better at
‘bluffing’
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 3

II.2. BKI VOLUME III CHAPTER 4 diameter in way of shrink fitted couplings
Based on BKI rules volume III Rules For should be slightly increased, e.g. by 1 to 2 %.
Machiney Installations Chapter 4 of the Main k = 1,10 for intermediate shafts where the
shafting is stated that there is a standard material coupling flanges are mounted on the ends of
and size for each component. the shaft with the aid of keys. At a distance of
at least 0,2 · d from the end of the keyway,
A. Material such shafts can be reduced to a diameter
In general for the material, the minimum calculated with k = 1,0.
tensile strength for the system shafting (Shaft, k = 1,10 for intermediate shafts with radial
Flange couplings, bolts / fitted bolts) is between holes which diameter is not exceeding 0,3 · d.
400 N / mm2 to 800 N / mm2, specifically for Intersections between radial and eccentric axial
fitted bolts connections minimum tensile strength is holes require a special strength consideration.
more than 500 N / mm2. k = 1,15 for intermediate shafts designed
However, the value of Cm were used for the as multi-splined shafts where d is the outside
calculation of Rm must be less than: diameter of the splined shaft. Outside the
1. 600 N / mm2 for propeller shafts. splined section, the shafts can be reduced to a
2. 760 N / mm2 for shafts made of steel except diameter calculated with k = 1,0.
propeller shaft. k = 1,20 for intermediate shafts with
3. 800 N / mm2 for shafts made of stainless longitudinal slots within the following
staniless. limitations :
- slot length up to 0,8 d
B. Dimensioning / Size. - inner diameter up to 0,8 d
For the minimum diameter shaft size can - slot width e up to 0,1 d
be determined by the following formula: - end rounding at least 0,5 e
Pw - 1 slot or 2 slots at 180°or 3 slots at 120°
Da ≥d≥F.k. 3√ di 4 . Cw
n.[1−( ) ] Slots beyond these limitations require a special
da
strength consideration.
d = [mm] minimum required outer shaft
diameter b) Thrust shafts
da = [mm] actual outer shaft diameter k = 1,10 for thrust shafts external to
di = [mm] actual diameter of shaft bore. If engines near the plain bearings on both sides
the bore in the shaft is ≤ 0,4 . da, the of the thrust collar, or near the axial bearings
expression where a roller bearing is used.
di
1 − ( )4 may be taken as 1,0
da
Pw = [kW] rated power of propulsion motor, c) Propeller shafts
gear box and bearing losses are not to be k =1,22 for propeller shafts with flange
subtracted mounted or keyless taper fitted propellers,
N = [RPM] shaft speed at rated power applicable to the shaft part between the
F = factor for type of propulsion installation forward edge of the aftermost shaft bearing
a)Propeller shafts and the forward face of the propeller hub or
= 100 for all types of installations shaft flange, but not less than 2,5d.
b)Intermediate and thrust shafts In case of keyless taper fitting, the method of
= 95 for turbine installations, diesel engine connection has to be approved by BKI.
installations with hydraulic slip couplings, k =1,26 for propeller shafts in the area
electric propulsion installations specified for k= 1,22, if the propeller is keyed
= 100 for all other propulsion installations to the tapered propeller shaft.
Cw = material factor k =1,40 for propeller shafts in the area
specified for k = 1,22, if the shaft inside the
560 stern tube is lubricated with grease.
Rm+160 k =1,15 for propeller shafts between
Rm = [N/mm2] specified minimum tensile forward end of aftmost bearing and forward
strength of the shaft material (see also B.1) end of fore stern tube seal. The portion of the
k = factor for the type of shaft propeller shaft located forward of the stern
tube seal can gradually be reduced to the size
a. Intermediate shafts of the intermediate shaft.
k = 1,0 for plain sections of intermediate
shafts with integral forged coupling flanges or II.3. AUTODESK INVENTOR 3D
with shrink-fitted keyless coupling flanges. For Autodesk Inventor 3D is one of the
shafts with high vibratory torques, the software type of Computer Aided Drawing (CAD)
is more emphasis on solid modeling. This software
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 4

is one of the Autodesck Inc products. Autodesk based software, such as Catia, Solid Work, Pro-E
Inventor 3D is more devoted to the depiction of and others. In the Figure 2 below is one example of
mechanical engineering, which provides a Autodesk Inventor 3D using associated with this
complete facility to visualize the model in 3D, the analysis is the depiction of a shaft that has been
amenities offered assembly and working drawings. resized.
The software is made to compete with other CAD-

Figure 2. Example of using Autodesk Inventor 3D


.

III. RESULTS AND DISCUSSION several parts according to its main components,
such as:
III.1. IDENTIFICATION AND ANALYSIS 1. Intermediate shaft
DATA. 2. Bearing
Shafting system is a system that the 3. Clutch
function is deliver trust power from the main 4. Stern tube
engine (prime mover) to the propeller so that the 5. Packing
vessel can get a thrust in accordance with the 6. Propeller shaft
expected. In this case, KM. Nusantara Akbar 7. Propeller
shafting use sea water lubrication system.
To facilitate the identification system While the field data obtained from the KNKT after
shafting KM. Nusantara Akbar will be divided into the accidents is as shown like on Figure 3 below

Figure 3. Flange Condition After The Accidents


Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 5

1. 1 piece coupling bolts are not in place (A). 6. Seeing fastening bolt on the clutch shaft, it is
2. 1 piece of broken coupling bolts (B) likely not a fitted bolt.
3. 2 pieces almost detached, the possibility is 7. When the intermediate shaft is rotating,
breaking up the middle intermediate shaft bearings going to sway. To
4. 2 bolts still attached but there is an additional reduce the sway then mounted a tackle block
ring, it should not be. as in Figure 4 (in this picture chain fastened to
5. 2 pieces bolts that are at the bottom is not the foundation bearing tackle)
visible in this image.

Figure 4. Bearing Condition

1. The master didn’t know that one of his crew


(1). CERTIFICATES AND VESSEL DOCUMENTS panicked when the leak and immediately took
Certificates and vessel documents are letters the emergency pump in fresh water tank which
or other written evidence possessed indicating that the then lead to death.
vessel was seaworthy and ready to sail. These letters 2. When the leakage happened crew only cope with
also show that the vessel was in good condition crude equipment such as wearpak and pieces of
according to the rules applicable on the classification, wood.
in this case BKI, from the port state where the vessel
is anchored before sailing and from the flag state (3). DOCKING REPORTS
which is followed by the vessel. Docking report is a job report when the
vessel was being repaired on the dock from contracts
(2). INCIDENT REPORTS. repair, vessel goes up the dock till the vessel goes
Reports on the incidents is a report on an down from dock.
event or an accident which was written by someone in From the identification data related with docking
order to provide a detailed explanation in the form of a report, found that:
letter or writing, accompanied by evidence that has 1. The broken flange bolt was not replaced but
been found. reconditioned. (welded)
The sequence events of.KM Nusantara Akbar 2. There is no special treatment when carried out
accidents is as follows: repairs on the propeller.
3. Don’t do the alignment for shaft deflection but
1. The entry of water into the engine room through improved by setting flax to shrink deflection.
the propeller shaft stern tube.
2. Blockage use wearpak to reduce the flowrate of (4). CREW CERTIFICATES
water into the engine room. Crew certificates are the letters or written
3. Binding of retaining reamers packing but failed. evidence which contains crew profiles, level of
4. The seawater soaking up the engine room until expertise and skills possessed the crew. After
disturb on the rotating main engine flywheel. identification the crew certificates are finding that
5. The process of additional blockage by using the some of the crew certificate already expired.
board pieces at the stern tube propeller shaft in
the engine room. (5). OTHER DOCUMENTS RELATED TO
VESSEL.
From the identification data associated with the From the identification of relevant data
incident report contained findings that: supporting documents related to vessel are finding
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 6

that the condition of the vessel is dirty and there are 1.1.1.1. Because there were misscommunication
mice. between crew
III.2. CAUSE ANALYSIS 1.1.1.2. Because the crew less competent
1.1.1.3. Beacause the crew physical and
(1). Technical Factors psychological conditions unfavorable
1.1.3. Why the working environment was dirty?
(a) 5 Whys 1.1.3.1. Because the crew is slovenly
After doing the analysis and identification of 1.1.3.2. Because operator ignore the vessel
the data that have been obtained, the next step is condition
analyze the causes of failure of the propeller shaft 1.2.1. Why the shaft deflection
deflection. 1.2.1.1. Because related components less support
In the first step is to choose the top event, (Flange and Bearing)
according to the guide, the top event is choosen from 1.2.1.2. Because the shaft could not accept the
events or incidents that have occurred. Engine room load.
leak incident at KM Nusantara Akbar is choosen as the 1.2.2. Why the packing could not resist the water rate?
top event. 1.2.2.1. Because Encouraged / disturbed by shaft
In the second step continued with the question deflection
of why. This question covers of technical and non- 1.2.2.2. Beacuse an error in the installation.
technical factors. Then the answer for the first why
question there is a leak in the engine room are as In the fifth step is giving why question to the
follows: fourth step answer. The answer of each question is:
1.1. Unpreparedness to face the damage / failure of 1.1.1.2. Why the crew standard of competence is less?
the system. 1.1.1.2.1. Because the crew did not renew the
1.2. Damage / failure of internal systems (shafting certificate of membervessel.
system). 1.1.1.2.1. Because there is no facility from vessel
operators
In the third step is giving the question why in every 1.2.1.1. Why the associated components was not
answer in second two. The answer of each question is: supported (flange and bearing)
1.1. Why happened the unpreparedness to face the 1.2.1.1.1. Beacause the maintenance of flange and
damage /failure of the system? bearing are not in accordance with the
1.1.1. Because crew is not responsive to face the standards
failure of the system. 1.2.1.1.2. Because the components are less well
1.1.2. Because the equipment was insufficient to 1.2.1.2. Why the shaft can’t accept the load?
handle failure 1.2.1.2.1. Because the load is too heavy
1.1.3. Because working environments conditions In the sixth step is giving why question to the fifth
are dirty step answer. The answer of each question is:
1.2. Why there is damage / failure of internal systems 1.2.1.1.1. Why the maintenance of flange and bearing
(shafting system)? are not compliant?
1.2.1. The shaft deflection (Deflection) 1.2.1.1.1.1. Because when the bolts is broken not
1.2.2. Failure on Packing and Seal (could not resist replaced but reconditioned.(welded)
the rate of water) 1.2.1.1.1.2. Because the addition of flax on the
bearings to handle deflection shaf.
In the fourth step is giving why question to the Then on the Figure 5 below is the result of why
third step answer. The answer of each question is: tree which has been described from the above process:
1.1.1. Why the crew not responsive to face the failure
of the system?
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 7

KEBOCORAN PADA
KAMAR MESIN
1

TIDAK SIAP KERUSAKAN SISTEM


MENANGANI 1.1 INTERAL 1.2
KEGAGALAN SISTEM (PERPOROSAN)

PERALATAN UNTUK
Poros mengalami KEGAGALAN PADA
ABK TIDAK TANGGAP MENANGANI 1.2.1
RUANG KERJA
1.1.3 defleksi SISTEM PERPOROSAN 1.2.2
MENGHADAPI 1.1.1 KEGAGALAN KURANG
KOTOR (DEFLEKSI)
KEGAGALAN SISTEM MENCUKUPI
1.1.2
KOMPONEN KURANG
KONDISI FISIK DAN OPERTOR
MISSKOMUNIKASI ABK KURANG ABK JOROK MENGABAIKAN
MENDUKUNG (FLANGE 1.2.1.1 Poros tidak sanggup TERDORONG OLEH KESALAHAN
PSIKOLOGI ABK DAN BAUT) menerima beban POROS YANG DEFLEKSI PEMASANGAN
ANTAR ABK BERKOMPETEN KONDISI KAPAL
KURANG BAIK
1.1.1.1 1.1.1.3 1.1.3.1 1.1.3.2 1.2.1.2 1.2.2.1 1.2.2.2
1.1.1.2
PERAWATAN FLANGE
ABK TIDAK KONDISI KOMPONEN MENERIMA BEBAN
TIDAK ADA FASILITAS DAN BEARING TIDAK KONDISI DAN DIMENSI
MEMPERPANJANG BURUK
SESUAI PROSEDUR TERLALU BESAR POROS KURANG BAIK
DARI OPERATOR
SERTIFIKAT
1.1.1.2.1 1.1.1.2.2 1.2.1.1.2 1.2.1.1.1 1.2.1.2.1 1.2.1.2.2
PENAMBAHAN
LENAPADA BEARING BAUT FLANGE YANG
TERKAIT POROS YANG RUSAK TIDAK DIGANTI
SUDAH DEFLEKSI

1.2.1.1.1.3&4 1.2.1.1.1.1&2

TERDAPAT BUKTI DARI


DOKUMEN KAPAL

KEJADIAN YANG MENJADI


FOKUS DARI PENELITIAN

Figure 5. Why Tree of Leakage in the engine room of KM. Nusantara Akbar case

After the analysis of the why tree is into the table 5 whys question are events which
complete then the matrixs inserted into the 5 whys have been reinforced by the evidence above, so we
question table as in table 2. The events are entered will get the right solution.
Table 2.
5 Whys Question Table for Technical Factors
5 Whys Question Table
Problem Statement: Vessels leak in the engine room
Recommended Solution: Perform maintenance according to the procedure: replacing the flange bolts if damaged and then adjust
the straightening shaft bearing depend on the shaft
Latent Issues: Not treated maintenance in accordance with the procedure when in dock
No. Why Questions Answer Evidence Solution
1. Why there is a leak in Beacause damage / Leakage in the engine room
the engine room of failure of internal systems of KM. Nusantara Akbar
KM. Nusantara Akbar (shafting system).. (1.2)
?
2. Why there is damage / Because there is failure packing driven by shaft Prepare the spare parts/tools to
failure of internal on shafting system deflection so that packing can face the failure.
systems (shafting (Deflection) (1.2.1) not withstand the rate of
system)?(1) water
3. Why there was a Because related Flange bolts is broken and Regularly check the shaft
failure in the shafting components less support bearing is sway deflection and maintain the
system(deflection)? (Flange and permitted limit
(1.2.1) Bearing)(1.2.1.1)
4. Why the associated Beacause the Flange bolts is broken and Check the size and strength of
components was not maintenance of flange bearing is sway bearing and flange
supported (flange and and bearing are not in
bearing)?(1.2.1.1) accordance with the
standards. (1.2.1.1.1)
5. Why the maintenance Because when the bolts is Welding flange bolts perform appropriate
of flange and bearing broken not replaced but maintenance procedures:
are not compliant? reconditioned.(welded) replacing the flange bolts if
(1.2.1.1.1) (1.2.1.1.1.1) damaged and adjust the shaft
Because the addition of The addition of flax on the then straightening shaft bearing
flax on the bearings to bearings
handle deflection shaft
(1.2.1.1.1.2)

(b). Calculate the minimum diameter of shaft From the data, known,
according to the BKI rules P m/e : 3850 kW
Material : Stainlees Steel
Rm : 480 N/mm2
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 8

Intermediate shaft : Propeller shaft Calculation


L : 4000 mm
D : 275 mm Da ≥ d ≥ F . k . 3√
Pw
. Cw
di
n.[1−( )4 ]
da
Propeller/Tail Shaft
L : 3200 mm 320 ≥ d ≥ 100 . 1,15 . 3√
3850
.
560
di
D : 320 mm n.[1−( )4 ] 480+160
da

Intermediate shaft Calculation 320 mm ≥ d (mm) ≥ 302,45 mm

Pw The diameter of propeller shaft was fullfilled of


Da ≥d≥F . k . 3√ di . Cw
n.[1−( )4 ] BKI rules standard
da

3860 560 (c). Autodesk Inventor 3D


275 ≥d≥100 . 1 . 3√ di .
n.[1−( )4 ] 480+160
da
At this step, using Autodesk Inventor 3D
modeling to confirm the findings of the KNKT
275 mm ≥ d (mm) ≥ 263 mm field data Related broken bolts on the flange as in
Figure 3. The working forces on the shaft is on
The diameter of Intermediate shaft was fullfilled of Figure 6.
BKI rules standard.

Figure 6. Free Body Diagram.

Explanation : Tm : 19827,4 Nm
Ơ: shear force from the main engine and propeller Tp : 19430,86 Nm
torque to the flange bolts
Tm: Main Engine Torque Once modeled as in Figure 7. and 9,
Tp: Propeller Torque obtained bolt broken because the act force is
g : gravity 10782.31 N with shear stress 2.230 MPa, while the
maximum force in the normal load is 9.434,531.N
The force known as : with shear stress 1,951 Mpa.
Ơ : 1,951 Mpa

Figure 7. Shaft with 7 bolts condition.


Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 9

Figure 8. Calculating with 7 bolts.

Figure 9. Shaft with 8 bolts condition (normal condition).

Figure 10. Calculating with 8 bolts.


Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 10

(2). Non Technical Factors Analysis technical factors analysis. Then for the matrix that
The first step is to create Why tree to has been reinforced by the evidence to be inserted
analyze the cause before use 5 whys Table. Why into the 5 whys table in Table 3 below
tree used is why tree similar to that used for

Table 3
5 Whys Table for Non-Technical Factors
5 Whys Question Table
Problem Statement: Vessels leak in the engine room
Recommended Solution: prepare the spare parts/tolls related to overcome the failure, increase communication system
Latent Issues: Not preparing spare parts / equipment safety to prevent shafting system failures.
No. Why Questions Answer Evidence Solution
1. why there is a leak in the Because unpreparedness Leakage in the engine room
engine room of KM. to face the damage / of KM. Nusantara Akbar
Nusantara Akbar ? failure of the system.(1.1)
2. Why happened the Because crew is not Prevention of leaks using prepare the spare parts/tolls related
unpreparedness to face the responsive to face the makeshift tools. to overcome the failure
damage /failure of the failure of the system
system?(1.1) (1.1.1)
Because the equipment
was insufficient to handle
failure. (1.1.2.)
Because the working
environtment is dirty
(1.1.3)
3. Why the crew not Because the lack of crew captain did not know the crew Train communication and team
responsive to face the competency was killed because of panic. work
failure of the standards.(1.1.1.2)
system?(1.1.1)
Misscommunication
between crew (1.1.1.1)

Why was the equipment to Because of the lack of Crew handle leaks using Ask the operator to conduct the
deal the failure is procurement from the boards and clothes wearpack procurement of spare parts
insufficient? (3.2) operator. (3.2.A)

Why the working Because the crew is The work space is dirty and Clean the work space after and
environmrnt is dirty? slovenly (1.1.3.1) there are mices before shift changes
(1.1.3)

Beacause operator ignore get warning from the health Mempersiapkan koordinasi dan
the vessel condition department team work yang baik sebelum
(1.1.3.2) memulai pekerjaan

4 Why the crew standard of Because the crew did not There are crew certificates Make clear rules on the cleanliness
competence is less? (3.3.A) renew the certificate of was expired. of the vessel.
membervessel. (3.3.A)

IV. CONCLUSION diameter of the calculation according to the


BKI rules is 263 mm for intermediate shaft and
Based on the analysis that has been done, 302.45 mm for propeller shaft, which means it
through the evidence that obtained from the fulfilled the minimum standards of BKI.
docking report, certificate of classification entity, 2. From the data of the KNKT that there are
incident reports, crew certificates and others, some flange bolts were broken and loose, from
followed by analysis using five whys that the Autodesk Inventor 3D modeling software
confirmed with software Autodesk Inventor 3D and obtained bolt broken because the act force is
manual calculations using BKI rules. Found results 10782.31 N with the shear stress 2.230 MPa,
that: while the maximum force in the normal load is
9.434,531.N with shear force 1,951 Mpa.
Technical factors: 3. From docking report that has been analyzed,
1. The diameter size of KM. Nusantara Akbar is found a mistake during the process of docking,
275 mm for intermediate shaft and 320 mm such welding of flange bolts that have been
for propeller shaft, while the minimum
Int. J. of Marine Engineering Innovation and Research, Vol. 1(1), Dec. 2016. 26-30 (ISSN: 2541-5972) 11

broken. This should not be done, because it [13] P. Assi, "FE Analysis of Hollow Propeller Shaft Using
will change the character of the material that Steel and Composite Material then Compares it,"
Ahmedabad.
has received heat and the addition of different
[14] B. K. Indonesia, Volume III Rules for Machinery
materials.
Installations, 1st ed., BKI, 2015.
4. From docking report that has been analyzed,
[15] ABS, Guidance Notes on Vessel Vibration, 1st ed., New
found a mistake during the process of docking, York: ABS, 2015.
the addition of flax in the bearing to adjust the [16] A. Grzadziela, "Dynamic Problems of Propulsion System
shaft has a deflection. This should not be done, of Naval Vessels," Gdynia, 2007.
because the point of deflection will creep at
another point.

Non-Technical Factors:
1. From the data that has been analyzed, found
that the tools for system failure in the engine
room of KM. Nusantara Akbar is lacking, as
shown by the rate of water blockage using a
piece of board and crew wearpak. This should
not happen, because it will damage related
components and endanger the safety of the
crew.
2. From incidents reports that have been
analyzed, found that misscommunication
happened between crews, as shown by the
ignorance of the Master that one of crew
panicked and took the pump in Fresh Water
Tank, which later became one of the crew
killed in this incident. This should not happen,
because misscommunication will lead to a
decreased level of success in a team work.
3. From the vessel documents that has been
analyzed, found that the engine room
conditions of KM. Nusantara Akbar in dirty
conditions. This should not happen, because it
would interfere with the work of the crew.

REFERENCES

[1] S. Kristiansen, Maritime Transportation, 1st ed., Oxford:


Elsevier, 2005.
[2] M. Sondalini, How to Use 5 Whys for Root Cause
Analysis, 1st ed., lifetime-reliability.com.
[3] A. F. Molland, Vessel Resistance and Propulsion, 1st ed.,
Southampton: Cambridge University Press, 2007.
[4] H. Xing, "Elastohydrodynamic Lubrication Analysis of
Marine Sterntube Bearing Based on Multy-Body
Dynamics," Dalian, 2012.
[5] F. Zhao, "An Overall Vessel Propulsion Model for Fuel
Efficiency Study," Singapore, 2015.
[6] L. Qin, "Research on the Effect of Residual Stress to the
Measurement of Shaft Power," Wuhan, 2011.
[7] Y. Yang, "Optimal Design for a VLCC Propulsion System
Based on Torsional Vibration Analysis," Shanghai, 2011.
[8] A. Adekunle, "Development of CAD Software for Shaft
Under Various Loading Conditions," Ogun State, 2012.
[9] G. Yanlei, "Engine Vibration Certification," Beijing, 2013.
[10] Z. Gan-bo, "Reduced-order Modelling Method for
Longitudinal Vibration Control of Propulsion Shafting,"
Wuhan, 2012.
[11] D. E. Y. Seiji, "Advanced Technology of Propeller Shaft
Stern Tube Seal," Takasago.
[12] R. Praharaj, "Failure Prediction of Propeller Shaft
Prototype Using Finite Element Analysis," Mumbai.

You might also like