You are on page 1of 2

LISTE PRIX UNITAIRES MAIN D'OEUVRE

(COUTS SECS EN GOURDES)


Sept. 2018

DESCRIPTION UNITE PRIX BAS PRIX MOYEN PRIX HAUT

FOUILLES TERRE MEUBLE m3 HTG 250.00 HTG 325.00 HTG 390.00

FOUILLES ROCHES CARRIAN m3 HTG 500.00 HTG 650.00 HTG 780.00

FONCAGE A SEC m3 HTG 300.00 HTG 390.00 HTG 468.00

FONCAGE A SEC m2 HTG 100.00 HTG 130.00 HTG 156.00

NIVELAGE m2 HTG 50.00 HTG 65.00 HTG 78.00

REMBLAI m3 HTG 150.00 HTG 195.00 HTG 234.00

DEBLAI m3 HTG 150.00 HTG 195.00 HTG 234.00

FERAILLAGE livre HTG 5.00 HTG 6.50 HTG 7.80

FERAILLAGE QUADRILLAGE FER 1/4 (ACIER #2) m2 HTG 50.00 HTG 65.00 HTG 78.00

COFFRAGE LINEAIRE HORIZONTAL ml HTG 25.00 HTG 32.50 HTG 39.00

COFFRAGE LINEAIRE VERTICAL ml HTG 35.00 HTG 45.50 HTG 54.60

COFFRAGE SURFACE HORIZONTALE m2 HTG 225.00 HTG 325.00 HTG 390.00

COFFRAGE SURFACE VERTICALE m2 HTG 350.00 HTG 455.00 HTG 546.00

BETON DE PROPRETE m2 HTG 50.00 HTG 65.00 HTG 78.00

BETON PARQUET m3 HTG 1,000.00 HTG 1,300.00 HTG 1,560.00

BETON POTEAUX m3 HTG 1,250.00 HTG 1,625.00 HTG 1,950.00

BETON CHAINAGES ml HTG 75.00 HTG 97.50 HTG 117.00

BETON POUTRES ml HTG 100.00 HTG 130.00 HTG 156.00

BETON DALLE m3 HTG 1,250.00 HTG 1,625.00 HTG 1,950.00

BETON PANNEAUX VERTICAUX m3 HTG 1,500.00 HTG 1,950.00 HTG 2,340.00

POSE ROCHES m3 HTG 750.00 HTG 1,000.00 HTG 1,250.00

POSE BLOC 10 unite HTG 12.50 HTG 16.25 HTG 19.50

POSE BLOC 15 unite HTG 15.00 HTG 19.50 HTG 23.40

Liste Prix Main d'Oeuvre Page 1 de 2


DESCRIPTION UNITE PRIX BAS PRIX MOYEN PRIX HAUT

POSE BLOC 20 unite HTG 20.00 HTG 26.00 HTG 31.20

POSEE BLOC 30 unite HTG 25.00 HTG 32.50 HTG 39.00

CREPI m2 HTG 75.00 HTG 97.50 HTG 117.00

ENDUIT m2 HTG 75.00 HTG 97.50 HTG 117.00

FLOTTAGE m2 HTG 75.00 HTG 97.50 HTG 117.00

CIRAGE m2 HTG 75.00 HTG 97.50 HTG 117.00

REJOINTOIEMENT ROCHES m2 HTG 75.00 HTG 97.50 HTG 117.00

REJOINTOIEMENT BLOCS m2 HTG 75.00 HTG 97.50 HTG 117.00

Liste Prix Main d'Oeuvre Page 2 de 2